Claims
- 1. A system for open hole drilling a borehole from an offshore platform and through a cased borehole at the seafloor, the system comprising:
a guide assembly extending from the platform to the seafloor and having a lower end extending into the cased borehole; and a bottomhole assembly disposed on a lightweight drill string extending through said guide assembly for drilling the borehole.
- 2. The system of claim 1 wherein said guide assembly is a pipe string.
- 3. The system of claim 1 wherein said guide assembly includes a casing.
- 4. The system of claim 1 wherein said guide assembly includes a riser.
- 5. The system of claim 1 wherein said guide assembly includes a casing and a riser attached to the casing by a head.
- 6. The system of claim 1 wherein said lightweight drill string includes metal coiled tubing.
- 7. The system of claim 1 wherein said lightweight drill string includes composite coiled tubing.
- 8. The system of claim 1 wherein said lightweight drill string includes lightweight jointed pipe.
- 9. The system of claim 1 wherein said bottomhole assembly includes a formation displacement member adapted to drill a borehole having a diameter greater than the diameter of the guide assembly.
- 10. The system of claim 9 wherein the formation displacement member includes a bi-center bit.
- 11. The system of claim 9 wherein said formation displacement member includes a conventional bit with an underreamer.
- 12. The system of claim 9 wherein said formation displacement member includes a conventional bit with a winged reamer.
- 13. The system of claim 1 further including a drilling fluid flowing through said drill string and said bottomhole assembly and flowing through a fluid passageway around the bottomhole assembly and between said lower end and the cased borehole into the sea.
- 14. The system of claim 1 further comprising a hoisting system capable of supporting the guide assembly.
- 15. The system of claim 1 wherein said bottomhole assembly enables drilling of a slim borehole.
- 16. The system of claim 4 wherein said riser comprises a conventional high-pressure riser.
- 17. The system of claim 4 wherein said riser comprises a small diameter low pressure riser.
- 18. A method for open hole drilling a new borehole from an offshore platform and through a cased borehole at the seafloor, the method comprising:
lowering a guide assembly from the platform to the seafloor; inserting the lower end of the guide assembly into the cased borehole and forming an annulus therearound; lowering a bottomhole assembly on a lightweight drill string through the guide assembly; flowing a drilling fluid through the drill string and bottomhole assembly to drill the new borehole; flowing the drilling fluid and cuttings up through another annulus formed by the drill string and new borehole and through the annulus formed by the lower end of the guide assembly and cased borehole into the sea water; removing the drill string and bottomhole assembly from the cased borehole and guide assembly; and lowering the guide assembly into the new borehole.
- 19. The method of claim 18 further including utilizing the guide assembly as a riser between the platform and seafloor in the drilling of subsequent boreholes.
- 20. The method of claim 18 further comprising:disposing a float valve at the lower end of the guide assembly;
cementing the guide assembly into the new borehole; extending the bottomhole assembly suspended on the drill string through the guide assembly; and drilling a subsea borehole below the guide assembly.
- 21. The method of claim 18 wherein the guide assembly comprises a conductor casing and a riser pipe.
- 22. The method of claim 18 wherein the drill string is composite coiled tubing.
- 23. The method of claim 18 wherein lowering the guide assembly into the new borehole comprises lowering a casing into the new borehole.
- 24. The method of claim 18 wherein lowering the guide assembly into the new borehole further comprises the formation of a subsea wellhead.
- 25. The method of claim 18 wherein the new borehole comprises a slim borehole.
- 26. The method of claim 18 wherein the new borehole is drilled and the guide assembly is lowered into the new borehole in one trip from the platform.
- 27. The method of claim 18 wherein lowering the guide assembly from the platform comprises lowering the guide assembly by a hoisting system on the platform.
- 28. The method of claim 20 wherein cementing the guide assembly into the new borehole comprises cementing a casing into the new borehole.
- 29. The method of claim 20 further comprising lowering a liner into the subsea borehole.
- 30. The method of claim 29 wherein the liner comprises expandable metal casing.
CROSS-REFERENCE TO RELATED APPLICATIONS
[0001] The present application is related to application Ser. No. ______, filed Oct. 4, 2002 and entitled Methods and Apparatus for Riserless Drilling, Attorney Docket No. 1391-35100, hereby incorporated herein by reference in its entirety.