Information
-
Patent Grant
-
6412132
-
Patent Number
6,412,132
-
Date Filed
Wednesday, August 2, 200024 years ago
-
Date Issued
Tuesday, July 2, 200222 years ago
-
Inventors
-
-
Examiners
Agents
- Renner, Kenner, Greive, Bobak, Taylor & Weber
-
CPC
-
US Classifications
Field of Search
US
- 014 6
- 014 73
- 014 771
- 014 773
- 052 7411
- 052 74214
- 052 74215
- 052 319
- 052 320
- 052 321
- 052 324
- 249 207
-
International Classifications
-
Abstract
A method for constructing a bridge includes the steps of disposing a bridge form and a connected support structure over an area to be spanned by the bridge. Next, concrete is poured into the bridge form. Finally, the support structure is disconnected and removed from the bridge form. The bridge forms are carried or supported by beams positioned over the area to be spanned. The forms may be carried directly by the beams or by support assemblies suspended from the beams may carry the bridge forms. Trolleys may be used to position portions of the forms between or below the beams.
Description
TECHNICAL FIELD
The invention herein resides generally in the art of bridge construction. More particularly, the present invention relates to bridges constructed from forms that are carried by or suspended from temporarily positioned beams.
BACKGROUND ART
There are two commonly-used methods for forming long-span concrete structures such as bridges, parking decks, building floors, structures within stadiums, and the like. These structures may be made by either using pre-cast pieces which are manufactured off-site, and then transported to the construction site and assembled. Alternatively, these structures can be manufactured by building the forms on site, pouring concrete into the forms and then removing the forms.
The pre-cast method utilizes standard or special forms which receive concrete or other structural building-type material. After an appropriate curing time, the form is opened and the piece is removed. Reinforcing members may be included in the form if desired. Utilizing such forms allows the manufacturer to efficiently build a large number of building components to a particular specification depending upon end-use. Although this method is effective, there are high costs involved in shipping and erecting the pre-cast pieces. Additionally, craning the large weight of pre-cast pieces into place adds significant extra cost to high-rise structures.
The other common method for forming long-span concrete structures is where the forms are assembled on site with the desired reinforcing structure. In some instances, significant site preparations are required. Next, the concrete is poured into the form, and after it has set, the forms are removed. This method is also costly inasmuch as the site must be properly prepared to accommodate the form and supporting structure and then the supporting structure must be torn down, cleaned and removed or reinstalled after completion of the concrete pour and setting thereof. Forming the concrete members in place is quite expensive for highly-engineered structures such as bridges, stadiums, and high-rise structures.
One method, which is disclosed in U.S. patent application Ser. No. 09/467,703, filed Dec. 20, 1999, which is incorporated herein by reference, discloses a method for constructing long-span concrete structures utilizing a unique method of pre-stressing the concrete used to form the bridge. This method discloses utilizing beams as supports for forming a beam form upon which a bridge surface is later disposed. Although this method is effective, additional preparation work for preparing the bridge surface is needed. This is especially cumbersome when the span is over water and the support structure must be placed along the length of the beam form.
Therefore, there is still a need to provide a method for in-situ bridge forming which is fast, reliable, and structurally sound.
DISCLOSURE OF INVENTION
In light of the foregoing, it is a first aspect of the present invention to provide a method for constructing a bridge utilizing in-situ forms carried by or suspended from I-beams.
It is thus an aspect of the present invention to provide a method for constructing a bridge in which a bridge form and a connected support structure are disposed over an area to be spanned by the bridge.
It is another aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein concrete is poured into the bridge forms and after setting, the support structure may be disconnected and removed from the bridge forms.
It is a further aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein variations of the bridge form and connected support structure are provided. In one variation, at least two beams may be placed in a substantially parallel relationship over the area and decking is placed between the beams to provide a bottom form between the beams. Concrete is then poured into the forms between the beams and after setting, the beams are removed. The formed concrete slabs may then be laterally moved together to complete the bridge structure. In a second variation of the present invention, cribbing may be placed on both sides of the area to be spanned and a cross-beam is set on the cribbing. At least two hanger beams are then placed in a parallel relationship on the cross-beams and over the area. These hanger beams carry support assemblies which carry the bridge forms used to receive the concrete. After the concrete has set, the support structure and hanger beams are removed to provide the desired bridge structure. In a third variation of the present invention, a bottom form may be placed across the abutments prior to placement of the at least two beams which are placed in a substantially parallel relationship over the area. The beams are then secured to the bottom form such that they remain parallel with one another, whereupon end forms may be attached to the bottom form and side forms may be detachably secured to the beams and extend beyond a peripheral edge provided thereby. Concrete is then poured into the formed cavities and, after it has set, the end forms and side forms are removed. Next, the beams are detached from the bottom forms and removed to leave a side cavity which is then filled with concrete to complete the bridge structure.
It is yet another aspect of the present invention to provide a method for constructing a bridge according to the first variation, wherein the parallel beams may be placed upon an abutment which may have notches for receiving the beams.
It is yet another aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein for the first variation shims are provided to support the beams upon the abutments, and wherein after the concrete has set, the shims are removed so as to transfer weight of the concrete from the beams to the abutments and allow removal of the beams.
It is still another aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein for the first variation each beam may be provided with a deflection shim along the length of its bottom cross-piece to compensate for the weight of the poured concrete and to facilitate withdrawal of the beams after the poured concrete has set.
It is still a further aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein for the first variation, the beams may be provided with a plurality of cross-holes that are alignable with the cross-holes of the other beams such that a cross-tie may be inserted therethrough and allow for lateral movement of the slabs after the beams are removed to enhance the structural strength of the completed bridge.
It is an additional aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein cross-braces may be installed across the beams as part of the support structure to stabilize the beams during pouring of the concrete.
It is still yet another aspect of the present invention to provide a method for constructing a bridge, wherein for the second variation, the hanger beams may be placed in a substantially parallel relationship over the area and may be supported by the cross-beams.
Yet a further aspect of the present invention is to provide a method for constructing a bridge, as set forth above, wherein for the second variation a plurality of support assemblies extend from the hanger beams.
It is another aspect of the present invention for the support assemblies to carry decking and end and side forms that receive the poured concrete. Additionally, the support assemblies include an inverted T-section, wherein one end of a J-hanger is connected to the hanger beam and the other end carries the inverted T-section.
It is still a further aspect of the present invention to allow for length adjustment of the hangers to selectively position the completed deck with respect to the abutments.
It is still yet a further aspect of the present invention to provide a method for constructing a bridge according to the second variation, wherein a trolley may be positionable between adjacent beams for the purpose of carrying decking to a desired position along the length of the beams and wherein use of the trolley may be repeated until the decking extends between the abutments.
It is another aspect of the present invention to provide a method for constructing a bridge according to the second variation, wherein after the decking and forms have been filled with concrete and the concrete has set, the shafts of the hangers are cut to allow removal of the hanger beams.
It is still an additional aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein the second variation may use a support assembly that includes a member with hangers connected thereto that is positioned substantially parallel with the cross-beams.
It is yet an additional aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein a trolley assembly may be used to put the members in place and then to use another trolley assembly to place decking and other form materials on the members. As in the other variation, after the concrete has been poured and set, the hanger shafts are cut so as to allow for removal of the hanger beams.
Another aspect of the present invention is to provide a method for constructing a bridge, as set forth above, wherein any of the variations may be pre-assembled near their final location to be spanned and wherein the connected support structure and the pre-assembled bridge structure may be coupled to a moveable counterweight which is then moved to a position over the area.
It is yet another aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein the movable counterweight is de-coupled from the preassembled bridge structure to allow for pouring of concrete into the forms. The support structure is then disconnected and removed.
It is an additional aspect of the present invention to provide a method for constructing a bridge, as set forth above, wherein the preassembled bridge form and support structure may be formed in half sections in either side of the area to be spanned. Each half section is then connected to a moveable counterweight and then positioned in place and connected to one another.
The foregoing and other aspects of the present invention, which shall become apparent as the detailed description proceeds, are achieved by a method for constructing a bridge, comprising the steps of disposing a bridge form and a connected support structure over an area to be spanned by the bridge, pouring concrete into the bridge form, and disconnecting and removing the support structure from the bridge form.
These and other aspects of the present invention, as well as the advantages thereof over existing prior art forms, which will become apparent from the description to follow, are accomplished by the improvements hereinafter described and claimed.
BRIEF DESCRIPTION OF THE DRAWINGS
For a complete understanding of the objects, techniques and structure of the invention, reference should be made to the following detailed description and accompanying drawings, wherein:
FIG. 1
is a perspective view of a bridge form and supporting structure used according to the methods of the present invention;
FIG. 2
is a fragmentary elevational view, in partial cross-section, of an abutment supporting a beam used in the bridge form shown in
FIG. 1
;
FIG. 3
is a fragmentary end view of two parallel beams supported by the abutment;
FIG. 4
is an end view, in partial cross-section, of an alternative bridge form and supporting structure used according to the methods of the present invention;
FIG. 5
is a fragmentary perspective view, in partial cross-section, of a plurality of hanger beams and support assemblies used in a variation of the method for constructing a bridge according to the present invention;
FIG. 5A
is a fragmentary perspective view of a support assembly utilized in the bridge construction method of the present invention;
FIG. 6
is a perspective view showing a plurality of cross-beams and hanger beams utilized in constructing a bridge according to the present invention;
FIG. 7
is an end view of a trolley assembly employed in construction of the bridge shown in
FIGS. 5 and 6
;
FIG. 8
is a fragmentary perspective view of another method for constructing a bridge according to the present invention;
FIG. 9
is an end view of a trolley assembly employed in the construction of the bridge shown in
FIG. 8
;
FIGS. 10A-C
show a method for constructing a bridge form and connecting structure off-site and employing a moveable counterweight to place the bridge over an area to be spanned; and
FIGS. 11A-C
show a similar methodology for constructing a bridge form and connecting structure off-site and moving it over into the area to be spanned, wherein the bridge form and connecting structure is divided in half and moved over the span from either side thereof.
BEST MODE FOR CARRYING OUT THE INVENTION
Referring now to the drawings and, more particularly, to
FIGS. 1-3
, it can be seen that a method for constructing abridge utilizing beams for supporting in-situ forms is designated generally by the numeral
20
. It is envisioned that bridges made with this construction will be used to cross streams, small valleys, and the like. Generally, the bridge
20
is supported by a pair of opposed abutments
22
. The abutments are employed to support the bridge forms, the bridge, and the related supporting structure as needed for the final construction. As shown in the drawings, the abutments
22
are vertically oriented concrete slabs, but those skilled in the art will appreciate that the abutments may be other constructed or natural structures that are strong enough to support the weight of a completed bridge.
The abutments
22
may be provided with a plurality of notches
24
which are uniformly spaced and accommodate portions of a bridge form, generally designated by the numeral
26
, as needed to facilitate construction of the bridge.
The bridge form
26
includes at least two uniformly spaced beams
28
which may be placed across the abutments
22
by a crane or set in place by a counterweight device. Although this embodiment shows the beams set in corresponding notches
24
, it will be appreciated that use of the notches is not required. A pair of triangularly-shaped shim blocks
30
may be interposed between a bottom surface of the beam and the abutment
22
. The shim blocks
30
are employed to support the beams upon the abutment and are later removed to transfer the weight of the completed bridge from the beams to the abutments.
The beams
28
each include a bottom cross-piece
34
which rests upon the abutment
22
. The beams also include a top cross-piece
36
that is connected to the bottom cross-piece
34
by a rib
38
. The beam may be provided with a hole
40
at either end to allow for grasping of the beam as needed. It will be appreciated that the beam
28
may be an American Standard beam, a beam, a truss, or any structural member that can support or carry a heavy load such as wet concrete.
A deflection shim
42
is disposed on the top surface of the bottom cross-piece
34
on both sides of the rib
38
. As best seen in
FIG. 2
, the deflection shim
42
gradually tapers from a minimum height at an end of the beam
28
to a maximum height somewhere about a mid-portion of the length of the beam
28
. From the maximum height, the deflection shim then tapers downwardly to a minimal height at the opposite end of the beam. The taper angle and maximum height of the deflection shim is determined based upon several variables in the bridge construction. Factors in determining the final shape of the deflection shim will become apparent as the description proceeds.
Once all of the beams
28
are placed upon the abutments
22
in a substantially parallel relationship, a plurality of bottom forms
44
are placed upon the deflection shims
42
so as to span the openings between the beams
28
. The bottom forms
44
extend between each abutment
22
so as to preclude any openings therebetween. A plurality of side forms
46
may then be placed in an adjacent parallel relationship with the ribs
38
. Alternatively, the ribs
38
could be used as the side forms as long as provisions are made so that the concrete to be received in the form does not bond to the ribs
38
. This may be done with grease or other appropriate material. It will be appreciated that the side forms
46
are dimensionally sized so as to leave a gap
48
between a bottom surface of the top cross-piece
36
and a top of the side form
46
. A plurality of end forms
50
are then extended from the bottom forms
44
and the side forms
46
so as to complete the forming structure between each beam
28
. A plurality of cross-holes
52
may be provided in each beam
28
. The cross-holes
52
are strategically placed and aligned with the cross-holes
52
of other beams so as to provide a path through the completed bridge construction. A plurality of temporary cross-ties
54
are then threaded through each of the aligned cross-holes
52
. A plurality of lateral braces
56
may then be connected to the tops of each beam in a substantially perpendicular or angular configuration. The lateral braces
56
function to maintain the spacing of the beams and ensure that their positioning is essentially perpendicular with that of the abutments
22
. Reinforcing steel
58
or the like may then be set within the forms
44
,
46
, and
50
. The steel
58
may be supported by the end forms
50
as shown. All of the forms described in this embodiment may be manufactured from reinforced polymeric material. All forms, in this embodiment and the others to follow, may be made by pultrusion, extrusion, or any process which forms polymeric pieces with the need structural strength characteristics.
Concrete, generally designated by the numeral
60
, is then poured into the forms up to the top edge of the side forms
46
. As the concrete is poured into these forms, its weight causes the beams to deflect. The amount of deflection is determined by the weight of the particular type of concrete used, the length of the span, the area of the form to be filled, and other related factors. Accordingly, the taper of the deflection shim
42
is calculated to accommodate the weight of the concrete so that the deflection shim is essentially flat or planar from abutment to abutment upon setting of the concrete. Once the concrete has set, the braces
54
are removed and the temporary cross-ties
54
are withdrawn from their respective positions. Once this step is complete, the shims
30
, if provided, are removed from their support of the beams
28
. The shims
30
may not be required if the depth of the notches
24
allow for the abutments
22
to support the weight of the poured concrete. Accordingly, the weight of the formed slabs
64
is supported by the abutments
22
. It will be appreciated that the dimension of the gap
48
is calculated such that the deflection of the beams is compensated for and the beams can be easily withdrawn without interference from the formed slabs. The beams
28
are withdrawn by connecting the appropriate piece of equipment to the holes
40
and pulling the beam outward. Once this step has been completed for all of the beams used in the bridge form
26
, a permanent cross-tie may be inserted into each of the aligned cross-holes
52
and the slabs
64
are laterally moved toward one another so as to create a uniform bridge surface. Appropriate filling material may be disposed between the gaps of the slabs and into the cross-holes to preclude entry of moisture between the concrete slabs. Fill material may be placed on either side of the abutment so as to provide the necessary ramping to allow access to the bridge.
Based upon the foregoing, it can be seen that the bridge
20
is easily constructed and significantly reduces the need for unnecessary supporting structure while constructing the bridge. Use of this method reduces construction costs and significantly reduces the amount of time needed to construct the span. Whereas previous methods of construction typically take three to four months, use of the method described above is believed to reduce the construction time to five to six weeks, provided the abutments are in place. This shortened construction time is achieved by eliminating the need for false work and for later removal of the support forms. Moreover, this method reduces any adverse environmental impact, as no support work is required to be placed in the stream or stream bed.
Referring now to
FIG. 4
, an alternative bridge construction method, designated generally by the numeral
300
, is shown. In this embodiment, a bridge form
302
is assembled to facilitate forming the span, then later removed upon completion thereof. This embodiment is constructed by placing a bottom form
303
across the span and attaching it to each abutment
22
. At least two beams
304
are placed on top of the bottom form
303
and positioned over the span. The beams
304
are substantially parallel with one another and, depending upon the width of the bridge, additional beams may be placed in a substantially parallel relationship within the outer two beams. Each beam
304
includes a bottom cross-piece
306
, a top cross-piece
308
, and a rib
310
connecting the cross-pieces to one another. The bottom cross-piece
306
is bolted to the bottom form
303
by bolts
312
or the like on either or both edges of the bottom cross-piece
306
.
Side forms
314
are placed between the bottom cross-pieces and top cross-pieces
306
,
308
in such a manner that they extend at least beyond the peripheral edge of the cross-pieces. The side forms
314
may be provided with outwardly extending ribs
316
. The forms
314
may be laterally supported by horizontal bars
317
. The bars
317
may be hinged, or not, to the top edge of the form
314
. In either case, the bar
317
is deflectable to allow installation and removal thereof. Once the side forms
314
are installed, end forms
318
are placed at each end of the span to complete the form
302
. Reinforcing bars
320
may be placed within the cavity formed by the side forms
314
, the end forms
318
, and the bottom form
303
. Once everything is in position, concrete
322
is poured into the cavities so as to form slabs
324
. After the appropriate curing time for the concrete
322
, the side forms
314
, that bars
317
, and the end forms
318
are removed. Removal of the side forms
314
results in the formation of side cavities
326
. At this time, the bolts
312
are removed from the beams
304
and the bottom form
303
. Preferably, the beams
304
are lifted out by crane, although they could be slid out along the length of the span. Once this is complete, cavity end forms
330
are installed between each formed slab
324
at their respective ends. This encloses the side cavities. Concrete
322
is then poured into these cavities to form a medial slab
334
. The medial slabs
334
have outwardly extending ridges
335
as a result of the ribs
316
used in forming the slab
324
. After this concrete has set, the end forms
330
are removed. It will be appreciated that the ridges
335
stabilize the entire structure as it spans an area. Upon completion of the medial slabs
334
, a wearing surface
338
, a curb
340
, and a railing
342
may be installed in a manner well known in the art.
It will be appreciated that the embodiment shown in
FIG. 4
provides several advantages over the previously discussed embodiments. Primarily, this embodiment does not require the use of shims or other labor-intensive methods for forming the slab. Additionally, the beams
304
may be more easily removed from the formed structure by a lifting crane instead of pulling. Additionally, by not providing the shims along the bottom cross-pieces, a thicker slab may be constructed.
Referring now to
FIGS. 5-7
, another alternative bridge construction method is shown. As in the previous embodiment, the abutments
22
vertically extend adjacent the area to be spanned. Cribbing, designated generally by the numeral
104
, is placed at the outer ends of the abutments, usually higher than the bridge level desired. Cribbing, as understood by those skilled in the art, are timbers or the like used to support other materials.
A bridge form
110
is then constructed over the area to be spanned as follows. First, a cross-beam
112
is set on the cribbing
104
in a substantially parallel relationship with the area to be spanned. A plurality of hanger beams
114
are then disposed in a substantially parallel relationship with one another over the area and are supported by the cross-beams
112
. As in the previous embodiment, the hanger beams
114
include a bottom cross-piece
116
.
A plurality of support assemblies
120
are then attached to and suspended from the length of each hanger beam
114
. As best seen in
FIG. 5A
, each support assembly
120
includes an inverted T-section
122
that provides a hanger flange
124
which has a substantially perpendicular form flange
126
. A bracket
128
is attached or bolted to the hanger flange
124
and is provided in a substantially triangular shape with a portion extending outwardly therefrom. The bracket
128
includes a hole
130
extending through the extending portion.
A J-hanger
132
carries the T-section
122
. In particular, the J-hanger
132
includes a hook
124
that extends from a shaft
136
which may be threaded. The hook
134
is received within the hole
130
while the threaded shaft
136
is connected to and/or through the bottom cross-piece
116
by a nut
138
. It will be appreciated that the nuts
138
allow for selective positional adjustment of the T-section
122
with respect to the hanger beam
114
. Ideally, ends of the form flange
126
are positioned to rest upon the respective abutment
22
. As the T-sections span along the length of the hanger beam
114
, it will be appreciated that a slight angle may be imparted to the T-section
122
so as to allow for imparting of a camber to the completed bridge construction. In any event, after the support assemblies
120
are connected and placed into their desired position, a plurality of deck pieces
140
are placed upon the form flanges
126
. In other words, the decking
140
is placed such that it is carried by the form flanges
26
between the abutments
22
.
To install the decking
140
, a trolley, such as shown in
FIG. 7
, may be employed. The trolley, designated generally by the numeral
150
, includes a pair of opposed carriers
152
. Each carrier
152
includes a roller
154
that is rotatable upon an axle
156
. An opposite end of the axle
156
is connected to an arm
158
. The roller
154
, as shown in
FIG. 7
, is moveable upon the bottom cross-piece
116
. Although not shown, each carrier
152
may employ a second roller that is supported by the bottom cross-piece on the other side of the rib
38
. The opposed carrier
152
is placed upon an adjacent beam
114
. The arms
158
include a pivot finger
162
or, in the alternative, a nut construction
164
that carries the decking
140
. A plurality of pull wires
166
may be connected to the arms
158
to allow for movement of the trolley
150
along the length of the beams
114
. The trolley
150
carries the decking
140
to a position along the length of the beams
114
. At the appropriate time, the pivot fingers
162
release the decking
140
so that it rests on the form flanges
126
in the desired position. After the decking has been put in place, the pull wires
166
are used to retrieve the trolley to allow for installation of other decking pieces.
Once the decking is installed, a side form
170
and end forms
172
are secured to the decking and the T-sections
122
. Once all of the forms are in place, concrete
174
is poured and allowed to set. Once the concrete has set, the shafts
136
are cut flush with the surface of the concrete and the beams
112
and
114
are removed along with the cribbing
104
.
This method of bridge construction is advantageous inasmuch as a single slab is formed instead of multiple slabs. Accordingly, the cross-ties are not required in this embodiment. This embodiment provides at least all of the advantages of the previous embodiment. Moreover, the support beams used in this embodiment are easily removed by a crane or a counterweight, without having to slide the beams lengthwise from the formed slabs.
Referring now to
FIGS. 8 and 9
, yet another method for constructing a bridge is presented. In this embodiment, a bridge, designated generally by the numeral
200
, utilizes the abutments
22
and the cribbing
104
as set forth in the previous embodiment. The bridge
200
includes a bridge form
210
which employs cross-beams
212
supported by the cribbing
104
on each side of the area to be spanned. A plurality of substantially parallel positioned hanger beams
214
are placed upon the cross beams
212
.
A support assembly
216
is utilized to carry the concrete forms from the cross beams
212
. In particular, the support assemblies
216
are suspended across the hanger beams
214
in a manner similar to that shown in the previous Figs. In particular, the support assembly
216
includes a member
218
which may be a square tube, a rod, or the like. A hanger
220
is connected to at least each end of the member
218
for the purpose of carrying the member. The hanger
220
includes a threaded shaft
222
and the appropriate connection devices
224
such as nuts, hooks, and the like. Along with the required hangers
220
at each end of the member
218
, the member
218
may include additional hangers along its length so as to connect with hanger beams
214
disposed in between the outermost hanger beams
214
.
A plurality of decking forms
228
are then disposed on and supported by the members
218
. The decking
228
may be one continuous sheet of material or may be a plurality of sheets positioned to rest upon the members
218
.
A trolley, as best seen in
FIG. 9
, is designated generally by the numeral
230
, may be employed to carry the members
218
to the appropriate position along the length of the bridge form
210
. The trolley
230
includes a pair of carriers
232
, each having a roller
234
connected to an axle
236
. Although not shown, each carrier
232
may have a second roller that is supported by the bottom cross-piece on the other side of the rib
38
. An arm
238
extends from the axle
236
and carries the hanger
220
for carrying the member
218
. The hanger
220
is connected at one end of the tube or member
218
and the threaded shaft
222
is then later connected to the bottom cross-piece
215
when in the desired position. Any means known in the art may be employed to connect the shaft
222
to the beams
212
. A pull wire
242
may be employed to move the trolley
230
from one end of the bridge form
210
to the other. It will be appreciated that the underside of the decking is supported by at least the top surface of the abutments
22
. Once all of the decking is in place, side forms
244
and end forms
248
are employed to complete formation of the bridge form
210
. Concrete
250
is then poured into the form and allowed to set. Once the concrete is set, the shafts
222
are cut flush with the top surface of the concrete. Next, the cross-beams
212
, hanger beams
214
, and any extraneous-forming material that is not retained by the formed concrete piece, is removed. Those skilled in the art will appreciate that this embodiment has the advantage of utilizing much simpler pieces to create the concrete form. Moreover, this embodiment provides the advantages of the previously discussed embodiment.
As an alternative to forming the bridge forms over the span, with their attendant difficulties in aligning the forms, the members, and related materials, it will be appreciated that the forms may be assembled at a location somewhat removed from the area to be spanned.
Referring now to
FIGS. 10A-C
, it can be seen that a bridge form with truss supports, designated generally by the numeral
260
, may be constructed at one side of the area to be spanned. A truck
262
with an attached harness
264
is then connected to the truss
260
. The connection between the truss support
260
and the truck
262
includes a plurality of wheels
266
so as to allow slight pivoting of the truss support
260
. Those skilled in the art will appreciate that the truck
262
is a counterweight to the truss support
260
so as to allow for movement of the truss support
260
. The truss support
260
is then positioned over the span and connections are made to the adjoining abutments. Once the truss support is put in place with the appropriate forms, concrete is poured and the bridge construction is completed upon setting of the concrete.
A similar construction or methodology of constructing a bridge is shown in
FIGS. 11A-C
, wherein a first truss
280
is connected to a first truck
282
with a harness assembly
281
. Likewise, on the other side of the area to be spanned, a second truss assembly
290
is connected by harness
291
to a second truck
292
. These trusses are then placed over the span and connected to one another at their ends. The harnesses are then disconnected from their respective trusses. Concrete is poured into the appropriate forms and allowed to set. The harnesses and trucks are removed from the trusses and upon the concrete setting, the bridge is ready for use.
The embodiments shown in
FIGS. 10 and 11
allow for off-site construction of the bridge truss and forms which is much easier and more cost effective than constructing the bridge and forms over the area to be spanned. In addition to the benefits of the other embodiments, these constructions are inherently safer to build as they are formed in a safe area as opposed to being formed over the span.
Thus, it can be seen that the objects of the invention have been satisfied by the structure and its method for use presented above. While in accordance with the Patent Statutes, only the best mode and preferred embodiment has been presented and described in detail, it is to be understood that the invention is not limited thereto or thereby. Accordingly, for an appreciation of true scope and breadth of the invention, reference should be made to the following claims.
Claims
- 1. A method for constructing a bridge, comprising the steps of:disposing at least one bridge form and a connected support structure, over an area to be spanned by the bridge by placing at least two supported beams in a substantially parallel relationship over the area, each of the beams having at least a bottom cross-piece and a rib extending substantially perpendicularly from said bottom cross-piece and placing a bottom form between adjacent beams so that said bottom form is carried by said corresponding bottom cross-pieces; pouring concrete into said at least one bridge form; and disconnecting and removing support structure from said at least one bridge form.
- 2. The method according to claim 1, wherein said disposing step further comprises the step of preparing an abutment at both sides of the area to be spanned.
- 3. The method according to claim 2, wherein said disposing step further comprises the steps of:supporting said two beams with said abutments; and assembling end forms at each end of said bottom from prior to said pouring step, said at least two beams forming said support structure.
- 4. The method according to claim 3, wherein said disposing step further comprises the steps of:placing at least a third beam in a substantially parallel relationship with said other beams over the area; installing side forms on said beams, wherein said side forms extend further than said bottom cross-pieces; and removing said side forms and said beams after said concrete has set to form slabs with side cavities therebetween.
- 5. The method according to claim 4, further comprising the steps of:installing cavity end forms at the end of each said slab to partially enclose said side cavities; and pouring concrete into said side cavities to form median slabs between said slabs.
- 6. The method according to claim 5, further comprising the steps of:providing said side forms with outwardly extending indentations at said installing side forms step; and removing said cavity end forms.
- 7. The method according to claim 3 further comprising the steps of:installing a deflection shim along the length of said bottom cross-pieces to compensate for the weight of said poured concrete; transferring the weight of said poured concrete from said beams to said abutments; and withdrawing said at least two beams, such that said concrete slabs span said abutments.
- 8. The method according to claim 7, wherein said disposing step further comprises the steps of:providing each said beam with a plurality of cross-holes that are alignable with said plurality of cross-holes of adjacent beams; inserting temporary cross-tie forms through said plurality of aligned cross-holes prior to said pouring step; and pulling said concrete slabs together after withdrawal of said beams.
- 9. The method according to claim 8, further comprising the steps of:removing said temporary cross-tie forms prior to withdrawal of said beams; and installing permanent cross-ties through said plurality of aligned cross-holes after withdrawal of said beams.
- 10. The method according to claim 7, wherein said disposing step further comprises the step of installing cross-braces across said beams as a part of said support structure.
- 11. A The method according to claim 7, wherein said disposing step further comprises the steps of:disposing a shim between said abutment and said beams at each end prior to said pouring step; and removing said shims after said concrete has set to transfer weight from said beams to said abutments.
- 12. The method according to claim 7, wherein said disposing step further comprises the steps of:notching said abutments to a depth sufficient to receive said bottom cross-piece; disposing a shim between said abutment and said beams at each end prior to said pouring step; and removing said shims after said concrete has set to transfer weight of the concrete from said beams to said abutments.
- 13. The method according to claim 7, further comprising the step of notching said abutments to a depth sufficient to receive said bottom cross-piece such that said bottom cross-piece is at least flush with said abutment, wherein said bottom form and the weight of said concrete are supported by a top surface of said abutment.
- 14. A method for constructing a bridge, comprising the steps of:disposing at least one bridge form and a connected support structure, over an area to be spanned by the bridge, wherein said disposing step further comprises the steps of: preparing an abutment at both sides of the area to be spanned; placing cribbing on the sides of said abutments away from the area: setting cross-beams on said cribbing substantially parallel with the area; placing at least two hanger beams in a substantially parallel relationship over the area, each of said hanger beams having at least a bottom cross-piece supported by said cross-beams and a rib extending substantially perpendicularly from said bottom cross-piece, said cross-beams and said hanger beam forming said support structure; pouring concrete into said at least one bridge form; and disconnecting and removing support structure from said at least one bridge form.
- 15. The method according to claim 14, wherein said disposing step further comprises the steps of:suspending a plurality of support assemblies from said hanger beams; and installing decking and end forms carried by said plurality of support assemblies prior to said pouring step.
- 16. The method according to claim 15, wherein each said support assembly comprises:an inverted T-section having form flanges extending from a hanger flange; a bracket connected to said hanger flange, said bracket having a hole therethrough; a J-hanger having a hook receivable in said hole, said J-hanger having a shaft from which said hook extends; wherein said disposing step further comprises the steps of: connecting said shaft of each said support assembly to said bottom cross-pieces; and selectively adjusting the length of each said shaft such that said form flanges are supported by said abutment.
- 17. The method according to claim 16, wherein said disposing step further comprises the steps of:positioning a trolley between adjacent beams after said suspending step; carrying said decking to a desired position for placement by said trolley; and repeating said positioning step until said decking extends from one said abutment to the other said abutment.
- 18. The method according to claim 17, wherein said disconnecting step further comprises the steps of:cutting said shafts after the concrete has set; and removing said hanger beams and said cross-beams.
- 19. The method according to claim 15, wherein each said support assembly comprises:a member; and at least two hangers connected to said member; wherein said disposing step further comprises the step of: adjustably connecting the hangers to said bottom cross-pieces, such that said member is substantially at the same level as said abutments.
- 20. The method according to claim 19, wherein said disposing step further comprises the steps of:positioning a trolley upon said hanger beams; temporarily securing said member to said trolley; and positioning said member with said trolley and then performing said adjustably connecting step.
- 21. The method according to claim 20, wherein said disposing step further comprises the steps of:positioning another trolley upon said hanger beams after said suspending step; carrying said decking to a desired position for placement by said another trolley; and repeating said positioning step until said decking extends from one said abutment to the other said abutment.
- 22. A method for constructing a bridge, comprising the steps of:disposing at least one bridge form and a connected support structure, over an area to be spanned by the bridge, wherein said disposing step comprises the steps of: pre-assembling said bridge form and said connected support structure to form a preassembled bridge structure; coupling a movable counterweight to said pre-assembled bridge structure; and moving said moveable counterweight so that said pre-assembled bridge structure spans the area; pouring concrete into said at least one bridge form; and disconnecting and removing support structure from said at least one bridge form.
- 23. The method according to claim 22, further comprising the step of de-coupling said moveable counterweight from said pre-assembled bridge structure.
- 24. A method for constructing a bridge, comprising the steps of:disposing at least one bridge form and a connected support structure, over an area to be spanned by the bridge, wherein said disposing step further comprises the steps of: pre-assembling a first portion of said bridge form and said connected support structure to form a first pre-assembled bridge structure on one side of the area to be spanned; pre-assembling a second portion of said bridge form and said connected support structure to form a second pre-assembled bridge structure on another side of the area to be spanned; coupling corresponding moveable counterweights to said first and second preassembled bridge structures; moving said moveable counterweights so that said first and second pre-assembled bridge structures together to span the area; and connecting said first and second pre-assembled bridge structures to one another; pouring concrete into said at least one bridge form; and disconnecting and removing support structure from said at least one bridge form.
- 25. The method according to claim 24, further comprising the step of de-coupling said moveable counterweights from said pre-assembled bridge structures.
US Referenced Citations (20)
Foreign Referenced Citations (2)
Number |
Date |
Country |
1030462 |
Jul 1983 |
SU |
1030463 |
Oct 1983 |
SU |