The present invention relates to one or more methods of constructing tensionless concrete pier foundations used to support tall, heavy and/or large towers and the like, and to tensionless concrete pier foundations constructed by such methods.
Concrete foundation structures of various kinds have been developed to support commercial signs, traffic signs, light poles and the like. To support larger structures including tall and heavy towers and wind turbines that exert significant overturning force on the foundation, Applicant developed and commercialized a tensionless pier foundation which is described in U.S. Pat. No. 5,586,417 (“the '417 patent”). The '417 patent is hereby expressly incorporated by reference as if fully set forth in its entirety herein.
The tensionless pier foundation described in the '417 patent includes a concrete foundation formed as a cylinder having an outer boundary shell defined by a corrugated metal pipe (CMP) and an inner boundary formed by a second CMP of smaller diameter, with the upper ends of both CMPs being below the top of the foundation. Elongated high strength steel bolts run from an anchor flange near the bottom of the concrete cylinder vertically up through the concrete to extend above the upper end of the foundation and through a connecting flange for the supported structure to be connected on top of the foundation. The bolts are encased in sleeves or hollow tubes over a substantial portion of their vertical extent in the concrete to allow the encased portion of the bolts to be stretched and thus tensioned. With such tensioning of the bolts, the concrete is kept under constant compression while the bolts are always in static tension. Thus, the pier foundation in the '417 patent is referred to as “tensionless” due to the absence of tensile stress on the concrete.
The '417 patent construction was a significant improvement over previously known concrete foundations that incorporated a reinforcing steel bar matrix and were subject to repeatedly alternating tensile and compressive loads on the steel bar matrix, leading to fatigue and, in many cases, premature failure. Additional improvements in tensionless concrete foundations are shown in Applicant's other U.S. Pat. No. 8,720,139 (“the '139 patent”) and U.S. Pat. No. 9,340,947 (“the '947 patent”), among others. The complete disclosures of the '139 and '947 patents are hereby expressly incorporated by reference as if fully set forth in their entirety herein.
While the tower-supporting tensionless concrete pier foundation disclosed in the '417 patent is strong and long lasting in use, the method of constructing the pier foundation required the construction of a form plate and also often involved sequential steps for the concrete pour and subsequent grouting associated with leveling of the tower support surface and placement of the tower on the foundation. Having to perform these steps sequentially increased the time required for construction and in some cases incurred significant costs particularly as related to the amount of time that heavy equipment such as cranes had to remain on site waiting for concrete and/or grout cure before the tower could be set and/or before the tower anchor bolts could be fully tensioned.
Therefore, it would be beneficial to have a method of constructing a tensionless pier foundation that reduces the overall cost of the foundation through various improvements, including elimination of the need for a separate form plate as well as the tower placement delays associated with waiting for grout cure, among others, while still obtaining and even improving the strength, operational effectiveness and structural integrity of the foundation over the life thereof.
In view of the foregoing, the present invention is directed to a method of constructing a tensionless concrete pier foundation having a plurality of elongated tower anchor bolts embedded within sleeves in a concrete pier and secured at their lower ends to an anchor or embedment ring. The upper ends of the anchor bolts extend above the top of the concrete so that the bolts, which bear the tensile load, can be post-tensioned to keep the concrete pier under constant compression in like manner to the tensionless concrete pier foundation construction described in the '417 patent. And like the pier foundation in the '417 patent, the concrete pier foundation according to the present invention is also referred to as a “tensionless” pier foundation due to the absence of tensile stress on the concrete.
The tower anchor bolts and embedment ring are received within an annular space formed between an outer corrugated metal pipe (CMP) and an inner CMP having a smaller diameter than the outer CMP. The upper end of at least the outer CMP extends vertically to be flush with the top of the foundation and, according to a preferred embodiment, the upper ends of both the inner and outer CMPs are flush with the top of the foundation. By having the upper ends of the CMPs flush with the top of the foundation, the upper surface of the concrete that is poured into the annular space between the CMPs forms the support surface for the lower base flange of the tower. This annular space can be filled with concrete and pre-grouted in virtually a single step, producing a level surface and allowing both the concrete and the grout to cure simultaneously instead of having a multi-step sequence of concrete pour, waiting for concrete cure, leveling of the support surface with additional grout and then waiting for grout cure before the tower can be fully assembled. As a result, the amount of time that a crane used to mount the tower has to spend on site can be reduced to a single day, saving in construction costs. In addition, once the tower is installed, the area around the lower base flange of the tower can then be post-grouted up to the top of the foundation to prevent the pooling of water and the like in the annular space. The post-grouting provides a filler and sealer of the space between the CMPs and the tower base flange above the pre-grouting and can be done at anytime, allowing the contractor flexibility in both material utilized and time of placement.
The present invention is also directed to a method of constructing a tensionless concrete pier foundation in which the positioning and spacing of the inner and outer CMPs within an excavation is reinforced with a plurality of lateral steel reinforcement and spacing members that extend through the two CMPs, spanning the annular space between the CMPs. The lateral steel reinforcement and spacing members may be embodied as bolts that are nutted both outside the outer CMP and inside the inner CMP. These lateral steel members can include an upper set of lateral reinforcement and spacing members used to facilitate leveling of the tower anchor bolt cage during construction. In the completed foundation, the lateral steel members provide bursting steel resistance and also allow for CMP location eccentricity adjustment. The lateral steel members can further be used for lifting lug bolt connections, while ends of the bolt members that extend beyond the inner and outer CMPs can be used for future retrofit and repowering additions, while also providing for electrical grounding connection to the CMPs.
Preferably, the lateral steel members include the upper set of spacing members near the top of the CMPs and a lower set of spacing members near the bottom of the CMPs. Additional sets of lateral spacing members may be placed in spaced relationship between the upper and lower sets to provide lateral shear strength and to increase stiffness and buckling resistance, if desired. During construction of the foundation, the upper lateral steel reinforcement and spacing members are used to support a bolt alignment ring which is placed within the annular space between the inner and outer CMPs and on top of the upper lateral steel members. Upper ends of the tower anchor bolts are secured within holes in the bolt alignment ring to suspend the tower anchor bolts and create the spacing for coupling the bolt lower ends to the embedment ring to complete a “tower anchor bolt cage”. Once the tower anchor bolts are secured at their upper ends to the bolt alignment ring, the bolts are lifted out of the annular space by the bolt alignment ring and the embedment ring is secured to the lower ends of the tower anchor bolts. The upper lateral spacing members are then removed to allow the tower anchor bolt cage to be lowered into the excavation. The upper lateral spacing members are then re-bolted to the CMPs, with the bolt alignment ring being supported on the spacing members, and the bolt alignment ring is leveled, using shims if necessary, to plumb the bolt cage. Following concrete pour in the annular space, the bolt alignment ring is removed from the upper ends of the tower anchor bolts and can be reused in constructing another foundation.
Also included within the present invention is the placement of a safety protection element such as a guard or padded member over the upper edges of the CMPs to reduce the safety risk to workers who, due to the height of the CMPs in extending to the top of the foundation, may be in direct proximity to the exposed edges. The guard or padded member may be a flexible tubing material, such as a split garden hose, that is fitted over the exposed upper edge(s).
A further feature of the present invention is replacement of the traditional concrete floor formed in the center of the foundation, i.e., the region surrounded by the inner CMP, with steel mesh, rubber mat, diamond plate, plastic sheet and the like to expedite construction and reduce material cost and labor. By replacing traditional concrete with one of these alternate materials, additional cost savings can be realized.
The floor is preferably placed atop a soil backfill. The upper portion of the soil backfill, on the order of about the upper 5 feet of the backfill, is preferably wetted and compacted to improve thermal conductivity and electrical conduction heat dissipation. Finally, approximately the top one foot of concrete poured into the annular space between the CMPs, which spreads the tower base load across the pier, is poured with greater compressive strength concrete (approximately 150% greater strength) than the recommended foundation concrete. By adding this additional compressive strength in the upper twelve inch layer of concrete and spreading the compressive load, the remainder of the pier concrete is subjected to a lesser compressive load making it possible to reduce the cement content below the top foot by at least one sack per cubic yard of concrete, yielding further cost savings in construction.
Further, the bolt alignment ring according to the present invention, in conjunction with the upper lateral spacing members, facilitates leveling of the tower anchor bolt cage to expedite construction and reduce construction expense by eliminating costly delays associated with the traditional steps of concrete pour using a lower chamfered template ring that contacts the concrete, waiting for cure and then subsequent leveling of the tower base flange support surface by adding shims and more cementitious material under the tower base flange and waiting for cure thereof. According to a preferred embodiment of the present invention, the bolt alignment ring does not need to contact the concrete but is supported on the upper lateral members which are at or above the upper surface of the high strength concrete pour and inside the annular space between the CMPs. As supported on the lateral members, the bolt alignment can be confirmed to be level and the tower anchor bolt cage plumb or, if necessary, made level by shimming the lateral members on the low side to raise that part of the bolt alignment ring to level. Following concrete pour, the upper surface of the concrete will then be level and the tower anchor bolt cage plumb all in one step.
Accordingly, it is an object of the present invention to provide a tensionless concrete pier foundation, including a concrete pier for supporting a tower and a method of constructing the same, that saves both time and money as compared with traditional tensionless concrete pier foundation constructions and methods.
Another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with the preceding object in which the outer and inner CMPs extend upwardly so that the upper edges thereof are flush with the top of the foundation, the “top of the foundation” being defined as the upper surface of the concrete in the annular space between the CMPs when fully grouted to be level with the upper edges of the inner and outer CMPs after the tower has been installed on the concrete pier.
Yet another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with the preceding object in which the upper portion of the outer CMP near the top edge thereof serves as a form plate defining the outer perimeter of the above-ground portion of the concrete foundation.
Still another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with the preceding objects in which the upper edges of the inner and outer CMPs create a grout trough in the annular space between the CMPs that can be pre-grouted in virtually a single step with the concrete pour of the annular space to form a level support surface for the tower base flange, allowing both the concrete and the grout to cure simultaneously instead of having a multi-step sequence of concrete pour, waiting for concrete cure, leveling of the support surface with additional grout and then waiting for grout cure before the tower anchor bolts can be fully tensioned, the pre-grouting in the annular space resulting in significant cost savings over earlier methods that often required heavy equipment to remain on site while waiting for concrete cure in order to install the tower.
A further object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which the inner and outer CMPs are coupled by a plurality of lateral steel reinforcement and spacing members that span the annular space and are nutted both outside the outer CMP and inside the inner CMP to ensure desired positioning and spacing of the CMPs within an excavation, the lateral steel reinforcement and spacing members facilitating plumb placement of the tower anchor bolt cage during construction while also thereafter providing bursting steel resistance as well as CMP location eccentricity adjustment, lifting lug bolt connections, bolt extensions beyond the inner and outer CMPs for future retrofit and repowering additions, and electrical grounding connection to the CMPs.
Yet a further object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least the preceding object in which a reusable bolt alignment ring is used to create the spacing for the tower anchor bolts and to facilitate plumbing of the tower anchor bolt cage during construction, the bolt alignment ring preferably being supported on an upper set of lateral steel reinforcement and spacing members within the annular space between the inner and outer CMPs, and upper ends of the tower anchor bolts being secured within holes in the bolt alignment ring, after which an embedment ring is secured to the lower ends of the tower anchor bolts to complete the tower anchor bolt cage, the upper lateral members being removed to allow the cage to be lowered into the excavation and then re-bolted to the CMPs with the bolt alignment ring supported and leveled on the upper lateral members for plumbing the bolt cage as suspended on the bolt alignment ring and, following concrete pour, the bolt alignment ring being removed and available for reuse in construction of another foundation.
A still further object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which the method includes placing a safety protection element such as a guard or padded member over the upper edges of the CMPs to reduce the safety risk to workers who, due to the height of the CMPs in extending to the top of the foundation, may be in direct proximity to the exposed edges.
Another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which the traditional concrete floor formed in the center of the foundation, i.e., in the region surrounded by the inner CMP and atop a soil backfill, is replaced with steel mesh, rubber mat, diamond plate, plastic sheet and the like to expedite construction and reduce material cost and labor.
Yet another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which an upper portion of the soil backfill in the center of the foundation, on the order of about the upper 5 feet of the backfill, is wetted to the approximate optimum moisture content (plus or minus 2%) for the soil and compacted to improve thermal conductivity and electrical conduction heat dissipation. As is known in the geotechnical engineering field, “optimum moisture content” is a term of art that refers to the moisture content of any soil at its maximum density.
Another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which about a bottom third of the excavated central region of the foundation is filled with concrete to enhance the lateral shear resistance of the foundation and to allow for the height of the inner CMP to be reduced by about one-third.
Still another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in accordance with at least one of the preceding objects in which about the top layer (1 ft.) of concrete in the annular space between the CMPs, which spreads the tower base load across the pier, is poured with greater compressive strength concrete (approximately 150% greater) than the recommended foundation concrete, the additional compressive strength in the top foot of concrete reducing the compressive load to which the remainder of the pier concrete is subjected and thereby making it possible to reduce the cement content below the top foot by at least one sack per cubic yard of concrete.
Yet another object of the present invention is to provide a method of constructing a tensionless concrete pier foundation in which a floor thereof is poured with concrete and only the outer CMP extends upwardly so that the upper edge thereof is flush with the upper surface of the concrete forming the concrete floor, a reusable bolt alignment ring having chamfered sides being used to create the spacing for the anchor bolts and to hold the upper ends of the bolts while concrete is poured up to the top of the bolt alignment ring to form the floor, the bolt alignment ring thereafter being removed with the chamfered sides having created a grout trough that can be pre-grouted to reduce on-site time for the heavy equipment used to mount the tower on the foundation.
Still another object of the present invention is to provide a tensionless concrete pier foundation including an outer CMP and an inner CMP that define an annular space between them, the annular space being filled with concrete to create a support surface for the base flange of a tower to be mounted on the concrete pier foundation, at least the outer CMP having an upper edge that is flush with the upper surface of the foundation, the upper surface of the foundation being defined by the upper surface of the concrete, either in the annular space between the CMPs when the upper edges of both CMPs are flush with the top of the foundation, or across the upper surface of a concrete floor poured inside the perimeter of the outer CMP when only the outer CMP upper edge is flush with the top of the foundation, once the tower has been installed and both pre-grouting and post-grouting have been completed.
A further object of the present invention is to provide a tensionless concrete pier foundation in accordance with the preceding object in which the upper edges of both the outer CMP and the inner CMP extend to the top of the foundation, the upper surface of the concrete in the annular space between the CMPs being level with the CMP upper edges once the annular space has been fully grouted after the tower has been installed on the concrete pier.
A still further object of the present invention is to provide a tensionless concrete pier foundation in accordance with the object before the preceding object in which only the outer CMP has an upper edge that extends to the upper surface of the foundation, the upper edge of the inner CMP being about one foot lower than the outer CMP upper edge, the upper surface of the foundation being defined by the upper surface of the concrete poured to form a floor defined by the perimeter of the outer CMP and after both pre-grouting and post-grouting have been completed.
Another object of the present invention is to provide a tensionless concrete pier foundation including an outer CMP and an inner CMP that define an annular space between them, the annular space being filled with concrete and supporting the base flange of a tower to be mounted on the concrete pier foundation, the upper edges of both the outer CMP and the inner CMP extending to the top of the foundation, the top of the foundation being defined as the upper surface of the concrete in the annular space between the CMPs once the annular space has been fully grouted to be level with the upper edges of the CMPs after the tower has been installed on the concrete pier, the annular space being spanned by a plurality of radially extending lateral reinforcement and spacing members that are bolted to the outer and inner CMPs to provide bursting steel resistance as well as CMP location eccentricity adjustment, lifting lug bolt connections, bolt extensions beyond the inner and outer CMPs for future retrofit and repowering additions, and electrical grounding connection to the CMPs.
Yet another object of the present invention is to provide a tensionless concrete pier foundation in accordance with the preceding object in which an upper set of lateral steel reinforcement and spacing members is used to support a bolt alignment ring which is placed within the annular space between the inner and outer CMPs and on top of the upper lateral members during construction, upper ends of the tower anchor bolts being secured within holes in the bolt alignment ring to create the spacing for the anchor bolts to be secured at their lower ends to an embedment ring to form the tower anchor bolt cage which is lowered into an excavation and secured with concrete, the bolt alignment ring thereafter being removed and available for reuse on another foundation.
A further object of the present invention is to provide a tensionless concrete pier foundation in accordance with the preceding two objects in which the floor of the foundation is formed with steel mesh, rubber mat, diamond plate, plastic sheet and the like to expedite construction and reduce material cost and labor.
A still further object of the present invention is to provide a tensionless concrete pier foundation in accordance with at least one of the preceding three objects in which the upper edges of the CMPs are covered with a safety protection element such as a guard or padded member to reduce the safety risk to workers who, due to the height of the CMPs in extending to the top of the foundation, may be in direct proximity to the exposed edges.
These together with other objects and advantages which will become subsequently apparent reside in the details of construction and operation as more fully hereinafter described and claimed, reference being had to the accompanying drawings forming a part hereof, wherein like numerals refer to like parts throughout.
It is to be understood that the embodiments described herein are disclosed by way of illustration only. It is not intended that the invention be limited in its scope to the details of construction and arrangement of components set forth in the following description or illustrated in the drawings. Also, in describing the preferred embodiments, specific terminology will be resorted to for the sake of clarity. It is to be understood that each specific term includes all technical equivalents which operate in a similar manner to accomplish a similar purpose.
A tensionless concrete pier foundation like that disclosed in the '417 patent, in which the soil backfill in the center of the foundation is complete below the surface of the ground 18, is shown in
The upper ends of the bolts 20, 21 are supported from a template referred to generally by the reference numeral 32. The template 32 includes upper and lower ring sections 34 and 36 secured together and operative with associated blockout bodies 64 as further described in the '417 patent. Upwardly opening radial channel members 38 and mounting blocks 40 received in the channel members 38 are clamped between the ring sections 34, 36 by upper and lower nuts 42 and 44 threaded on the bolts 20, 21. The inner ends of the radial channel members 38 are joined by a center plate 46, and the inner portions of the channel members 38 include lateral stabilizers 45 that engage with upper edge portions of the inner CMP 12. The outer ends of the channel members 38 include threadingly adjustable channel member feet 50 abuttingly engageable with the ground 18 for leveling of the ring 32, and a cylindrical form plate 52 is clamped about the upper end of the outer CMP 14. As shown in
After the concrete 68 is poured between the CMPs, the upper ends of the tower anchor bolts 20, 21 extend upwardly to project above the top of the concrete for post-tensioning thereof. As shown in
According to a first embodiment shown in
The bolts 20, 21 are secured at their lower ends to an anchor or embedment ring 122 to form a tower anchor bolt cage generally designated by reference numeral 218. During the construction sequence, a bolt alignment ring 152 is part of the tower anchor bolt cage (see
The tower anchor bolt cage 218 is embedded within an annular space, generally designated by reference numeral 228, formed between the inner corrugated metal pipe (CMP) 112 and the outer CMP 114. Unlike in the '417 patent, the upper edge 214 of at least the outer CMP 114 extends vertically to be flush with the top of the foundation, which is generally designated by reference numeral 120. According to a preferred embodiment shown in
By having the upper edges of the CMPs 112, 114 flush with the top surface of the foundation 120, the annular space 228 created between the CMPs can be effectively pre-grouted with high strength grout to form a level support surface for the lower base flange 300 of the tower 310. As used herein, “grout” is intended to refer to any mixture of fine aggregate, such as sand, mixed with a cementitious material and water, the mixture hardening over time in like manner as with concrete.
The high strength grout spreads load concentration and reduces compression stress on the underlying concrete and, because the grout can be placed and allowed to set ahead of time, i.e., before the tower sections are brought in, the pre-set grout allows the tower anchor bolts to be fully tensioned immediately after setting the tower base sections. This is in contrast to having to wait 24 hours for the grout to set before tensioning the tower anchor bolts and setting additional sections of the tower as can occur when using prior known techniques in which the tower support surface must be first leveled and then grouted. As a result, the amount of time that a crane used to mount the tower has to spend on site can be reduced to a single day.
Once the tower is installed, the lower base flange 300 of the tower and the top of the foundation 120 can then be post-grouted at 77 (see
According to a preferred embodiment, the present invention further includes reinforcing the positioning and spacing of the inner and outer CMPs within the excavation using a plurality of lateral steel reinforcement and spacing members generally designated by reference numeral 150. The lateral steel reinforcement and spacing members 150 are positioned horizontally and extend radially through the two CMPs, spanning the annular space 228 between the CMPs. The members 150 are typically embodied as bolts which are nutted both outside the outer CMP 114 and inside the inner CMP 112 as shown in
As shown in
According to one preferred construction sequence for the start of the foundation, the inner and outer CMPs 112, 114 are placed into an excavation 116 after which the upper ends of the two CMPs are bolted together with the upper set of spacing members 151. The CMPs 112, 114 are then lifted from the excavation 116 and the lower ends of the two CMPs are bolted to one another with the lower set of spacing members 149. The two CMPs, now bolted at their upper and lower ends by the upper and lower reinforcement and spacing members 151, 149, respectively, are then lowered back into the excavation centered and plumb. The annular space 227 between the outer CMP and the perimeter of the excavation 116 is then filled, preferably with a slurry of aggregate and cementitious material forming concrete, preferably to about four feet below pad grade, i.e., below the top of the excavation, and a concrete plug 80 is poured at the bottom of the inner CMP 112. If desired, a concrete plug 82 may be poured between the inner and outer CMPs to provide additional bolt cage support but this is optional. The inner CMP 112 is then backfilled to about five feet from the top of the foundation with uncompacted soil 229. As used herein in connection with the depth of backfilled soil and poured concrete, “about” is intended to refer to the stated value and variances of plus or minus 20% to 25%. Therefore, a soil backfill of “about five feet” is intended to refer to a soil backfill depth of between approximately 4-6 feet.
With the inner and outer CMPs secured to one another and positioned in the excavation as just described, the construction sequence continues by using the upper set of spacing members 151 to support the bolt alignment ring 152 (see
Once all the tower anchor bolts 20, 21 have been nutted atop the bolt alignment ring 152, the bolt alignment ring and the attached bolts are lifted from between the CMPs. The embedment ring is then secured flush and level to the bottom of the half nut 217 and secured in place by a full nut 117 that is snugged against the underneath side of the embedment ring 122 on each bolt to complete the bolt cage 218 (see
Once the embedment ring 122 is secured to the lower ends of the tower anchor bolts to form the tower anchor bolt cage 218, the upper spacing members 151 are removed to allow the cage to be lowered into the excavation and then reinstalled (see
The concrete in the annular space 228 between the CMPs spreads the tower base load across the pier. According to the present invention, lower strength concrete is poured into the annular space to within 1 ft. of the upper lateral spacer members or bolts 151. The upper layer of concrete 131 in the annular space is then poured with greater compressive strength concrete (approximately 150% greater) than the recommended foundation concrete (see
After the concrete is poured, including the top layer 131 with higher strength concrete, the annular space 228 is then pre-grouted at 75 (see
The central region surrounded by the inner CMP and generally designated by reference numeral 158 (see
As a modification of the construction shown in
Traditionally, a concrete floor 319 is formed on top of the soil backfill in the center of the foundation as shown in
To protect workers from possible injury arising from contact with the upper edges 212, 214 of the CMPs, the present invention further includes a safety protection element generally designated by reference numeral 315, such as a guard or padded member 162, placed over the upper edges of the CMPs as shown in
A second embodiment of the present invention is shown in
Because the inner CMP 112 in the second embodiment has a reduced height, the grout trough 321 used for pre-grouting 75 is formed by the chamfered sides of the bolt alignment ring. In particular, during concrete pour in the annular space between the CMPs, the concrete is brought up to top of the bolt alignment ring to form the floor. Upon removal of the bolt alignment ring, the chamfered sides thereof will have created a grout trough 321 that can be pre-grouted 75 in like manner to the pre-grouting of the annular space 228 as described in connection with the first embodiment. The space between the pre-grouting 75 and the tower base flange 300 is thereafter post-grouted 77 as in the first embodiment, with the upper edge 214 of the outer CMP 114 being flush with the top of the foundation 120 with the tower in place. Further, the upper edge 214 of the outer CMP is preferably covered with a safety protection element 315.
A preferred sequence of the method steps for construction of a tensionless concrete pier foundation in accordance with the present invention may be summarized as follows:
The foregoing descriptions and drawings should be considered as illustrative only of the principles of the invention. The invention may be configured in a variety of shapes and sizes and is not limited by the dimensions of the preferred embodiment. Numerous applications of the present invention will readily occur to those skilled in the art. Therefore, it is not desired to limit the invention to the specific examples disclosed or the exact construction and operation shown and described. Rather, all suitable modifications and equivalents may be resorted to, falling within the scope of the invention.
This application claims priority from U.S. provisional application Ser. No. 62/760,433, filed Nov. 13, 2018.
Number | Date | Country | |
---|---|---|---|
62760433 | Nov 2018 | US |