Embodiments relate to a pick and carry crane having an articulated boom.
A pick and carry crane is a crane which is able to move (i.e. travel) while it has a load suspended from a boom of the crane. Some pick and carry cranes are able to drive on public roads at highway speeds where they are classified as special purpose vehicles. The design of pick and carry cranes can vary depending on the application of the crane. Some designs of pick and carry cranes are more maneuverable compared to other crane types. For example, when the pick and carry crane is articulated, the whole crane can fit within a turning circle of the crane. This design feature can enable articulated pick and carry cranes to be used in tight or confined spaces to lift and move loads, such as on the floor of a manufacturing facility.
Pick and carry cranes can also take the form of “taxi cranes”, i.e. cranes travelling with all equipment required to operate the crane through the full range of capability of that crane. Many cranes cannot operate as a taxi crane since they cannot transport all components required to operate, hence support vehicles are generally required to carry extra components, such as counterweights and rigging including slings & hooks.
In general, in pick and carry cranes, the same operator station is used to control the crane when travelling (such as on a public road) as when operating the crane at a facility. This “single cabin” arrangement helps to simplify crane configuration, and provides flexibility for the operator (i.e. by not having to move back and forth between a driver's cab and a crane cab).
Such pick and carry cranes have tipping lines defined by the points of contact between the crane and the ground (i.e. the tyres). So, when the moment about the tipping line is sufficient, the crane will tip, or fall, about the tipping line. There are many factors which can affect the extent of the moment about the tipping line (“tipping moment”) such as boom extension, boom luff, load weight and weight distribution, incline of the ground and orientation of the crane relative to that incline, extend of crane articulation, swing of the load, etc.
Since pick and carry cranes are generally dimensioned to fit public roads, tipping can be a significant concern. Not only does tipping of the crane damage the crane, but also poses a significant safety concern to the operator of the tipped crane as well as any personnel in the vicinity who may be placed at risk by a tipping crane.
With other mobile cranes outriggers can be used to minimise susceptibility to sideways tipping. However, such outriggers are used when the crane is operating at a stationary position. Since pick and carry cranes need to travel with a load, this means that outriggers typically cannot be used.
It is to be understood that references herein to the prior art do not constitute an admission that such art forms a part of the common general knowledge of a person of ordinary skill in the art, in Australia or any other country.
Embodiments relate to a mobile crane. The mobile crane may be a taxi crane. The mobile crane may be a pick and carry crane for operation on public roads. The mobile crane may lack outriggers. The mobile crane may be articulated. The mobile crane may have a single operator cabin for controlling the crane when travelling and for controlling the crane when lifting and/or moving a load.
An embodiment relates to a mobile crane having an articulated body and an elongate boom attached to the body, the boom being for carrying a load when the crane is stationary and while the crane is mobile, said boom being articulated to provide a movement for lifting and lowering an end of the boom, wherein the boom is further articulated to provide a movement of the boom laterally. The movement for lifting and lowering may provide a first degree of freedom for movement of the boom. The movement for lifting and lowering may be an up and down articulation. The lateral movement may provide a second degree of freedom for movement of the boom. The lateral movement may be a lateral articulation.
In an embodiment, the boom may be articulated about a first axis substantially perpendicular to a longitudinal axis of the crane. This articulation may correspond to the up and down articulation. The boom may be further articulated about an axis substantially parallel to a longitudinal axis of the crane. This articulation may correspond to the lateral articulation.
The mobile crane may have a first articulated joint for providing the lifting and lowering movement and a second articulated joint for providing the lateral movement.
The mobile crane may have an actuator for providing the lifting and lowering movement and the lateral movement. The actuator may be mechanical, pneumatic, hydraulic, electrical, or any combination thereof.
The actuator may comprise two rams, wherein the rams move to provide the lifting and lowering movement and/or the lateral movement.
The two rams may move in the same direction to provide the lifting and lowering movement, and wherein the two rams move in the same direction at different speeds, or in opposite directions, to provide the lateral movement.
The rams may be hydraulic.
In an embodiment, the two rams are symmetrically arranged with respect to the boom and the body of the crane.
In an alternative embodiment, the actuator may comprise two rams unsymmetrically arranged with respect to the boom and the body of the crane. A first ram may move to provide movement for lifting and lowering the end of the boom. A second ram may move to provide the movement of the boom laterally. When the boom is only lifted and lowered, the second ram may be stationary. When the boom is only moved laterally, the first ram may be stationary.
According to this embodiment, the control for lifting with the first ram may be independent from the control for lateral movement with the second ram therefore potentially being simpler to control each movement independently with just one ram for each movement. Other potential advantage may be that the second ram is positioned to one side of the boom (laterally) allowing space on the other side for a side cabin. The first ram may still be placed under the boom. This may also allow the boom to lower to a level below the height of the cabin.
The first ram may be attached to the boom at a medial line of the boom. The second ram may be attached to the boom at a side of the boom.
A further embodiment relates to a method of controlling a mobile crane, the mobile crane having an articulated body and an elongate boom attached to the body, the boom being for carrying a load when the crane is stationary and while the crane is mobile, said method comprising moving the boom for lifting and lowering an end of the boom and moving the boom laterally. The movement for lifting and lowering may provide a first degree of freedom for movement of the boom. The lateral movement may provide a second degree of freedom for movement of the boom.
The crane may comprise a first articulated joint for providing the lifting and lowering movement and a second articulated joint for providing the lateral movement.
The lifting and lowering movement and/or the lateral movement may be provided by an actuator. The actuator may be mechanical, pneumatic, hydraulic, electrical, or any combination thereof.
When the actuator comprises two rams, the method may comprise moving the rams to provide the lifting and lowering movement and the lateral movement.
The method may comprise moving both the rams in the same direction to provide the lifting and lowering movement, and moving the two rams in the same direction at different speeds, or in opposite directions, to provide the lateral movement.
A further embodiment relates to a method of controlling a tipping moment of a mobile crane, the mobile crane having an articulated body and an elongate boom attached to the body, the boom being for carrying a load when the crane is stationary and while the crane is mobile, said method comprising moving the boom laterally.
The method may further comprise lifting or lowering the boom to control the tipping moment.
The boom may be lifted or lowered at the same time as moving the boom laterally.
The boom may be lifted or lowered before or after moving the boom laterally.
A further embodiment relates to a method of controlling swing in a load, the load being borne by a mobile crane, the mobile crane having an articulated body and an elongate boom attached to the body, the boom being for carrying a load when the crane is stationary and while the crane is mobile, said method comprising moving the boom laterally in dependence on the swing.
The method may comprise measuring a swing of the load and moving the boom laterally in dependence on the measured swing.
A method for measuring swing could be via radar sensors, scanning the load in 3D, or motion sensors sensing dynamic movements and accelerations of the crane, boom, hook attachment/load. The boom would then be moved to counteract the momentum of the swinging load cancelling the swinging motion. This can be calculated with the known position and accelerations of the load and the known weights of the crane masses and the load mass which the crane measures via pressure transducers in the hydraulic rams lifting the boom.
Embodiments are herein described, with reference to the accompanying drawings in which:
A side tipping line 34 (see
In the embodiment of the pick and carry crane 10 as depicted in the Figures, the side tipping line 34 is an imaginary longitudinal axis that extends between a point at which the outer tyres T1 of the front body contact the ground, via wheel 20, and a point at which the outer tyre T3 of the rear body contacts the ground, via wheel 18. Thus, the tyres T1 and T3 of the wheels 20 and 18 define the points about which the crane may topple sideways. The crane 10 includes two sets of rear tyres T3 and T2. In this embodiment, the foremost set T3 is used to define the tipping line as the rearmost set T2 can be lifted during a taxi mode so that those tyres are no longer in contact with the road or other travel surface.
The pick and carry crane illustrated has three axles, but is to be realised that in different embodiments, the mobile crane may have two axles, or more than three axles.
Attached to the rear end of the front body 12 is a boom support arm 24. The boom support 24 may be a separate structure that is mounted e.g. welded or bolted to the front body 12. In an embodiment, the boom support arm 24 forms part of the chassis of the front body 12. The boom support arm 24 pivotally supports boom 26, where the boom 26 is raised and lowered about the pivot point, represented by pin 27 (
Provided on the underside of the boom 26 are two pins 80 and 82. In use, the pins 80 and 82 of boom 26 are engaged with the voids 56, 58, 64 and 66 of the brackets 52, 54, 60 and 62 of plate 42. The pins 80 and 82 allow the boom to pivot up and down relative to the plate 42.
As illustrated in
As illustrated in
In an alternate embodiment, the total lateral movement of the boom is restricted to 20°, 10° to either side of the vertical.
In alternate embodiments, the extent of the lateral movement may be set depending on a number of factors such as the maximum length of the boom when extended, the capacity of the crane, operating conditions etc.
The hydraulic rams 28A and 28B control both the up and down articulation of the boom 26 as well as the lateral articulation. For certain embodiments there may be an advantage to using hydraulic rams to control both up and down, and lateral articulation since known pick and carry cranes include such hydraulic rams. Therefore, it is not necessary to develop and install a new articulation mechanism to accommodate the lateral articulation in addition to the existing up and down articulation.
By controlling the directional control valves 102A and 102B, the control system 106 controls the movement of the rams 28A and 28B thereby controlling the articulation of the boom 26. By moving the rams in the same direction at the same speed at the same time, the boom 26 will articulate only up or down. By moving only one of the rams, or both of the rams at different speeds or in different directions, the control system 106 is able to control the lateral articulation of the boom 26.
The control system is further connected to a mode selector 108 whereby a user selects the mode of the crane as manual mode or automatic mode and a command input 110 which a user may use to control the boom. Various sensors are also connected to the control system: a boom lateral angle sensor 112, a chassis angle sensor 114, a wheel speed sensor 116 and an engine RPM sensor 118.
The control system 106 uses the input from the operator comments and the sensors to control the lateral boom angle. For example, if the mode selector is in automatic mode, and the chassis angle sensor detects a slant, the control system will tilt the boom laterally in the opposite direction to compensate for the slant in the chassis.
It is to be realised that other sensors may additionally be used. For example, a boom extension sensor; a boom up-down articulation sensor; crane articulation sensor, load height sensor, load swing sensor etc. The extent to which the boom is laterally articulated will take all of these factors into account to potentially improve the stability of the crane.
The embodiment illustrated in
Therefore, the rams 128A and 128B are attached asymmetrically between the boom 126 and the base plate 142. Therefore, the up and down movement of the boom 126 is controlled by the ram 128A and the side to side movement of the boom 126 is controlled by the ram 128B.
It is to be realised that it is not necessary to activate the rams 128A and 128B independently; they could be activated together to move the boom simultaneously up and down, and left and right. The control system illustrated in
A further embodiment relates to control of swing of the load. In this embodiment, the operator controls the lateral articulation of the boom to reduce or stop swinging in the load. By timing the lateral articulation of the boom, the operator is able to dampen the swing of the load which may improve the stability of the crane since load swing can induce tipping of the crane.
To determine the swing, various measurements of the position of the load relative to the boom are made. These measurements are made using radar sensors, scanning the load in 3D, or motion sensors sensing dynamic movements and accelerations of the crane, boom, hook attachment/load.
The boom is then moved to counteract the momentum of the swinging load cancelling the swinging motion. The amount of movement required can be calculated with the known position and accelerations of the load and the known weights of the crane and the load mass which the crane measures via pressure transducers in the hydraulic rams lifting the boom.
Features of pick and carry cranes relating to the control of tipping are described in PCT/AU2014/000261, PCT/AU2017/050999 and AU2018903904, the contents of which are incorporated herein. It is to be realised that the lateral articulation of the boom as herein described could be incorporated in the tipping prevention considerations and controls discussed in those applications.
Number | Date | Country | Kind |
---|---|---|---|
2019903890 | Oct 2019 | AU | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/AU2020/051103 | 10/14/2020 | WO |