The present invention relates to the technical field of offshore rig construction and more particularly to the integration of the topside of a rig to its lower supporting hull structure for drilling or production operations. The topsides concerned substantially depend on the drilling and production requirements.
Two major parts of an offshore rig are: 1) a topside, which houses devices, equipment and crew accommodation unit needed for drilling or production of oil and gas; and 2) a lower hull which provides the necessary buoyancy to support the rig at an offshore site. The topside and hull of the rig are usually fabricated separately for many reasons (e.g. cost, schedule, capability and availability of fabrication facilities). The topside and the hull are transported to a mating site (usually required to be well protected from heavy traffic and weather environment) and integrated together through attachment of the topside onto the top of the hull. Traditionally, the topside integration with the hull is done either at the offshore site using lift vessel(s) or in smaller modules at a quay site.
Integration offshore is restricted by limited good weather window in which the environmental condition is mild enough to allow a safe operation and the availability of heavy lift vessels to lift the topside and place it on top of the hull. The offshore integration also requires a large logistic support including transportation barges, offshore tugs, supply vessels and anchor handling tugs (AHTs). Offshore integration is technically very challenging and the cost exposure is also very high. Integration in smaller modules at quay site is safer and less dependent on the weather condition, but requires sub-integrations (connections and hook ups among the modules) and commissioning works at height. The availability of quay site facilities is also very limited.
Five common basic types of topside integration methodologies have been used:
Offshore float-over. This operation involves submerging lower hull using ballast water at a pre-selected offshore location with sufficient water depth. When in position and ready to receive the topside, a heavy-lift barge carrying the topside is towed and maneuvered into position for the lower hull to be de-ballasted and mated with the topside. This is an intricate operation and highly dependent on the weather condition. It requires a large logistic support including heavy-lift transportation barges, offshore tugs, supply vessels, AHTs and a team of very experienced crew with specially trained skills. The cost of an offshore float-over operation is very high.
Use of offshore heavy lift vessel. This operation involves the use of an offshore heavy lift vessel which is basically a crane on a floating vessel (barge). The lower hull is usually brought to installation location either by dry or wet tow. The lower hull is first positioned at its final position. The topside is then lifted by the offshore heavy lift vessel and placed onto the lower hull. Depending on the total weight of the topside and the lift vessel's capacity, the integration of the topside to the hull may be done in one of the following manners:
If the lift capacity of a single lift vessel exceeds the weight of the whole topside, the whole topside is lifted by the single lift vessel and placed onto the lower hull.
If the weight of the whole topside exceeds the capacity of a single lift vessel, the topside is built and brought to the installation site in modules and each module is lifted using the single lift vessel. This operation requires connecting and hooking up the modules on site. The process takes a longer time than one single lift. Heavy lift vessels are usually hired at a fixed day rate; therefore, longer installation time means high cost.
If the weight of the whole topside exceeds the capacity of a single lift vessel, the whole topside is lifted by two or more lift vessels at the same time and placed onto the lower hull. The operation is very intricate and requires very large logistic support. The cost of this operation is also very high.
Other disadvantages of using offshore vessel lift vessels relate to the requirement that the lifting points be built into the topside structure. Also, due to limited heavy lift vessels in the world, vessels need to be pre-booked in advance, which makes the scheduling of the installation even more difficult in addition to the weather condition. Offshore lifting may be further limited by crane outreach and vessel stability, resulting in the lift vessels' maximum lifting capacity not being fully used and more lift vessels may be needed for the installation.
Integration using heave lift device at quay site. During the integration, heavy lift devices are usually huge cranes that stand on ground while the lower hull floats in water by the lift device. Depending on the weight and size of the topside, the heavy lift device can either make it in one lift or the topside has to be brought in several modules. The single lift is largely limited by the crane's outreach capacity and weight.
Integration on land with use of strand jacks. This method of integration requires a large open space with strong load bearing ground. The location requires a launching capacity. The construction of the topside and lower hull is done in the same location in pre-determined positions. Generally, the lower hull is assembled around the topside to minimize skidding distance. When all components are complete, the topside is raised off the ground with the use of strand jacks and the lower hull skidded underneath of the topside deck. Once in position, the deck is lowered to complete the integration. This method of integration requires a good load bearing ground and large land space since both the topside and the hull have to be constructed in the same location.
The use of specialty vessels. At the moment, there are several specialty vessels in construction in various parts of the world. They all have varying operation philosophy as compared to the heavy lift vessels. These specialty vessels all require certain level of offshore logistic support and are weather dependent while carrying out the installation offshore. Some of these vessels may have restriction on the footprint size of the deck, lift height and weight.
One common disadvantage of the above integration methodologies is that the weight of the mass structure is supported by a small/limited number of lift points. Each lift bears a very large load, which would result in high stress on the structure in an area around the lift point and strong structural reinforcement is needed to avoid damage during the lifting operation. If one of the lift points fails during the operation, the load it bears would transfer to other lift points. Because of the small number of lift points, the percentage of the load increase on the remaining lift points would be very significant and may cause another lift point to fail. The load on the remaining lift points would further increase, resulting in a chain reaction: all the lift points would fail one after another and the structure being lift would eventually fall causing a serious accident. To avoid the chain reaction, the lift points must be reinforced with very large safety margin. The cables/ropes used to lift the structure must also be chosen with a large safety margin. This means an inefficient use of the structural materials and high costs.
Integration with single lift using one single lift vessel/device in a protected area certainly has many advantages over multi-lift integration, especially because it requires a shorter time and simpler operation, and has lower probability of failure. As oil and gas exploration and production goes to deeper and deeper water and desired production rate increases, the weight and size of the topside of a rig (new-build or conversion) for deep water will significantly increase. The topside of such rig may weigh up to 24,000 tons or higher. Today, the largest offshore lift vessel in the world has a lift capacity of 14,000 tons (Meerema Thialf). The capacity of the largest existing heavy lift device for quay site integration available from Kiewit Offshore Services located at Ingleside, Tex. is 13,000 tons. At present, no single lift integration is possible to lift topside weighing more than 14,000 tons with the existing heavy lift vessel or device. New heavy lift device/systems with much larger lifting capacity are needed for single lift integrations. Building the new lift vessels/devices by simply scaling up the existing ones would not be economical because the size and weight of the new build would dramatically increase and require a larger operation space and a dramatically larger logistic support. Besides, building such a giant lift device itself is a challenge and very costly. Such larger lift vessels/devices would also be much more difficult to mobilize.
Accordingly, it is an objective of the present invention to provide a heavy lift system with lift capacity larger than the largest capacity of the existing heavy lift vessels/devices for topside integration for offshore rigs.
It is another object of the present invention to provide a single heavy lift system with high mobility and ease of assembling that can be erected on site on land or offshore.
It is a further objective of the present invention to provide a single heavy lift system whose lifting capacity can be increased relatively easy.
It is yet another object of the present invention to provide a method of assembling a floating structure using a single lift system capable of handling significant mass of a topside of the floating structure.
The objectives of the present invention are achieved through a provision of a heavy lift system comprised of modular units, each of which comprises a pair of supporting legs and a transverse beam secured to the legs through jackup device that allow the beam to be moved up and down along the legs. The heavy lift system is transported and erected on site where the heavy lifting task is to be performed, such a dry dock or an offshore location, for instance where the topside is to be combined with the hull of a floating structure.
The legs are positioned adjacent the hull and the topside is suspended from the transverse beams. With the transverse beams of each modular unit moving in unison, the topside is moved to rest on the hull, after which a topside attachment process can begin.
For a further understanding of the nature and objectives of the present invention, reference should be made to the following detailed description of the preferred embodiments thereof, taken in conjunction with accompanying drawings, in which like parts are given reference numerals and wherein:
In the following description, numerous details are set forth to provide an understanding of the present invention. However, it will be understood by those skilled in the art that the present invention may be practiced without these details and that numerous variations or modifications from the described embodiments may be possible.
In this description, an exemplary weight of the topside is assumed to be approximately 15,000 metric tons. This weight is presented for illustration purposes only, and it will be understood that the system of the present invention can be used for other topside weights, as well. It should be also noted that in this description, the following groups of words are used interchangeably: “system” and “structure”; “vessel” and “barge”; “platform” and “rig”; “horizontal beam,” “suspension beam”, and “crane beam”; “legs,” “supporting legs” and “jackup legs”; “jacking device,” “jacking system” and “jacking mechanism”; “fabricate,” “manufacture,” “construct,” and “build”; “fabrication” and “construction”; “modular units” and “modules.”
As can be seen in the drawings, the lift system of the present invention is designated by numeral 10. The lift system comprises one or more modular units, each of which comprises a pair of opposing spaced-apart supporting legs 12 and 14. A suspension beam 16 is supported by the legs 12 and 14. The horizontal beam 16 can be a box beam or a truss beam, depending on a particular application.
A jacking device 18 is secured at an end 20 of the horizontal beam 16, and a second jacking device 22 is secured to an end 24 of the beam 16. The jacking devices 18, 22 facilitate movement of the beam 16 vertically along the legs 12 and 14. A platform's topside 30 (or any other heavy lift article) is suspended from the beam 16 by suitable suspension means 32, which can be a wire rope and the like. When more than one modular unit is used, a plurality of connecting beams 34, 36, 38, and 39 connect the modular units and ensure that the system works in a synchronized manner.
One example of use of the lift system 10 is shown in
In case of the hull 52 being fabricated in a different location, the hull must be first transported from its construction site and waits outside the dry dock 50. When both are ready for integration, the topside 30 is lifted to the desired height using the jacking devices 18, 22 that move the suspension beam 16 up and down, as required. Then the dry dock 50 is flooded and the gate of the dock is open to allow the hull 52 to float in. After the hull 52 is brought to the position aligned with the topside 30, the topside is lowered onto the top of the hull 52 and integrated with the hull 52. Finally, the integrated structure is floated out of the dock 50 and transported to the offshore site.
In the above case illustrated in
The heavy lift system 10 can be transported to a location as a whole or in pieces.
Still another example of the system of the present invention is illustrated in
The jacking systems or devices 18, 22 used in the heavy lift system of this invention are well adapted to handling large loads; they can lift up to 20,000 tons, and it is relatively easy to increase the lift capacity without significant increase in cost and difficulty. Many jackup manufacturers, such as those yards of Keppel O&M, have already the ability to build larger jacking systems.
One of the particular advantages of the present invention is the use of modular structure concept for the single heavy lift system. The modular structure allows the system to be transported in modules to different locations and easily assembled them at a job site. The modular structure also allows easy change of the system's lift capacity by simply increasing or decreasing the number of modular units in the system.
The legs 12, 14 can stand on each side of a dry dock, or a wet bed, or a floating dock and support the beam 16 at the two ends. The beam is equipped with a jacking mechanism/system on each of its ends. The jacking system is similar to those of a jackup rig. The beam is supported by the legs through the jacking systems and can be moved up and down by the jacking systems. Two or more major modular units can be connected side by side using the supplemental modular units to form a single heavy lift system of a desired lifting capacity. A heavy structure, such as topside, attached/tied to the horizontal beams can be lifted by jacking up the beams. The system of the present invention may be built for use on land or offshore depending on where the integration will be conducted.
The space between the major modular units and the locations of the holding points where the suspension means 32 are secured to the beams 16 can be adjusted to accommodate particular topside for optimal load distribution so that the lifting capacity can be used as closely as possible to the fullest extent. Additional modular unit can be added to increase the lift capacity if needed.
The mobility of the heavy lift system 10 can be achieved in many ways:
If the horizontal beams 16 are made such that they can provide sufficient buoyancy to support the whole system, the whole system can be towed to different locations. The beams and legs can be transported separately and assembled at site. The beams may be towed (if buoyant) or transported on a barge. The legs can be transported on a barge. The beams and legs can further be made into smaller modules. These smaller modules are transported to the desired location and assembled at site. Transportation in smaller modules allows use of smaller transportation vessels, especially for land transportation in case there is no special road for heavy vehicles and heave cranes available.
The heavy lift system 10 of the present invention can also include a movable base on which the legs of the system stand on the moveable base so that the whole lift system can move on a horizontal plane. The movable base can be carts with wheels which can move along track rails on a solid foundation, or a floating dock or barges, even vessels with propulsion systems similar to those illustrated in
The heavy lift system of this invention has the following advantages but not limited to these:
Integration operation can be carried out during all seasons of the year with no weather window to follow, except in raw extreme conditions such hurricanes and strong storms;
Operation can be carried out in yard vicinity thus eliminating expensive mobilization cost of any logistical resources to support the operation;
Rig components can be constructed in different location giving flexibility and choice of construction location;
There are no outreach limitations as the system lifts the entire topside over and above the lower hull;
No expensive and relatively heavy ballasting operation on the lower hull is needed as the system will lift deck up to 300 ft overhead.
The heavy lift system 10 of the present invention also has a larger flexibility in choosing the number of the lift points and their locations along the suspension beams (16). The number of lift points of the system 10 can be significantly larger than those of existing lift devices and their locations can be optimized so that the reinforcement can be kept to a minimal or even unnecessary. A large number of the lift points would also significantly reduce the chance of chain-reaction type of failure and therefore require a smaller safety margin. This would imply a significant saving in the materials and construction cost.
The system of this invention is relatively smaller in size and weight compared to conventional heavy lift systems; thus lower cost, as compared to traditional swinging types of cranes for a same lifting capacity.
While the illustrative embodiments of the invention have been described with specific details, it is understood that various modifications can be readily made by those skilled in the art without departing from the spirit and scope of the invention. Accordingly, the scope of the claims appended hereto is not limited to the description provided herein but encompasses all the patentable features of the present invention, including all features which would be treated as equivalents thereof by those skilled in the art to which this invention pertains.
Number | Date | Country | Kind |
---|---|---|---|
200803846-5 | May 2008 | SG | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/SG09/00139 | 4/15/2009 | WO | 00 | 1/24/2011 |