The disclosure refers to a novel system of manufacture and construction of decks of bridges or viaducts with two tracks for light railways or metros, to be used in urban areas, with the particularity of having an open cross-section, in the shape of a U, being the two tracks located inside the deck.
It has special application in the field of industry related to the construction of decks for railway tracks.
In the current state of the art the construction of elevated metros and light railways is being carried out through the execution of viaducts. This is replacing the traditional underground construction, mainly due to construction and maintenance costs. Within this type of construction, it is a common solution to make bridge or viaduct decks with a U-shaped cross section in which the railway circulates inside the structure. In the case of double-track railways, there are two possible alternatives. The first consists in the realization of two independent decks, one for each track. The second alternative consists of the realization of a single deck that houses the two tracks.
In this kind of construction, the usual structural typologies consist of concrete decks, concreted structures, whose execution can be carried out in situ, that is, on site, or by prefabrication of segments, prefabricated structures, which are subsequently transported to the site for assembly.
The structures concreted in situ can be executed on formwork supported on the ground by means of scaffolding or using steel girders that are supported on the piers to span the complete span between piers, called MSS (Movable Scaffolding System).
The precast structures are usually formed by segments, elements that are built in a precast yard and then transported to the construction site and placed by different processes that, in general, require the use of auxiliary means and impose an execution span by span, in order, following the railway line defined by the piers.
The current technology of complete precast decks is focused on construction for its use in one-way track decks. The construction of the deck consists of a U-beam of the same length as the complete span between piers. This structure is transported to the site in a special transport that can circulate on the roads or streets of the cities, as its size does not exceed the permitted limits. Subsequently, by using cranes, this kind of U-beams are lifted and placed over the spans delimited by the piers that define the different sections of track.
However, the use of this technique is not possible for the decks that house two tracks. The reason is that the width of this kind of structures, which is not less than 10 meters, is greater than the maximum allowed to be transported by road or through the streets of a city. In this way, when the possibility of being transported is discarded, the option of executing the full span in situ, on site, could be considered. However, this solution would not be profitable either because it is not possible to start with the deck until the substructure was executed and a solution in situ is much slower than the assembly of a precast solution.
For this reason, the manufacture of double-track decks is considered unviable through this type of solution. On the other hand, for this kind of structures, the method used consists of a solution based on the transversal segmentation of the deck in segments of a width compatible with their transport by road to the construction site. To assemble them in their definitive position, auxiliary means specially constructed for this purpose are used. These auxiliary means consist of steel girders that rest on the piers, equipped with a lifting system that allows to lift all the segments of a span to join them later by longitudinal prestressing.
However, this construction method, despite being frequently used, presents a series of inconveniences such as those described below.
First, the manufacture of the segments is very complex and involves not only the need for large manufacturing facilities, but also the employment of a large number of personnel. In addition, the segments are manufactured in conjugate form so each segment has a unique position. If a segment breaks during any phase of the process or any unexpected altercation occurs, the assembly is paralyzed until another identical segment to the one that has been broken is built.
On the other hand, the necessary auxiliary means on site for the lifting and subsequent placement and joining together of the different segments also implies a high cost in terms of assembly and disassembly.
In addition, the use of this method of construction involves a chain assembly, so that the reception on site of segments must be well coordinated with the assembly and it is essential that the complete infrastructure (foundations and piers) is completed in advance for that stoppages do not occur with the auxiliary means. If for some reason, such as a diversion of a utility that is complicated, a break of a segment, etc., the assembly can be paralyzed and to continue in another part of the viaduct it is necessary to disassemble and reassemble the auxiliary means. This triggers assembly costs and deadlines.
The disclosure comes to solve the aforementioned problems, which are not resolved in the present state of the art, by the construction of precast beams that are subsequently transported on site for assembly, completing a span with two longitudinal beams and a series of transverse slabs that are located between the beams. This implies a reduction in the following aspects:
To complete the description of the invention and in order to help a better understanding of its characteristics, according to a preferred example of realization of the same, there is attached a set of drawings in which, for illustrative purposes and without limitation, it has been represented the following FIGS.:
Considering the numbering adopted in the FIGS., the disclosed invention consists in the development of a novel system for the manufacture and construction of bridge deck structures (3) for bridges or viaducts for double-track installations for the circulation of urban railways, either metro or light rail, with the particularity that the structure is open with a U-shaped cross section so that the double track is housed inside.
The structures of the decks (3) are intended to be located on a series of piers (4) that define spans, or free length between piers (4), which must be spanned by the decks (3), as shown in
The contact of the longitudinal beams (1) on the piers (4) is made by bearings (7,8), typically made of rubber, neoprene or similar material, to absorb movements and prevent both elements from contacting directly. In this way, between the piers (4) and the longitudinal beams (1) there is a permanent bearing (7) and also a temporary bearing (8), the latter being intended for stability during the construction of the decks (3), provisional support can be replaced by another provisional system that performs the same function.
The longitudinal beams (1) are prefabricated and have a similar length to the span between two consecutive piers (4) where they are supported, also joining longitudinally to the previous longitudinal beam (1). The longitudinal beams (1) are located on each side of the cross section of the piers (4). The transverse slabs (2) are assembled on the bottom flanges (1a) of the longitudinal beams (1), so that the interior space between the longitudinal beams (1) and the transverse slabs (2), configured in a “U” shape”, is destined to the location of the two tracks through which the railways will circulate.
The transverse slabs (2) are fixed to the ends of the bottom flanges (1a) of the longitudinal beams (1), resting on them to form a monolithic and stable element in its final state by means of specific joints. On these transversal slabs (2) is located the railway platform which, due to this form of construction, is called ballastless or ballasted tracks.
In this way, as shown in
The main features of the disclosure are those described below.
First, the deck (3) is not manufactured by transverse segments, as has been done in the state of the art, but by longitudinal beams (1) of a length similar to the span defined by the distance between two piers (4) of the viaduct destined to accommodate the double-track. These longitudinal beams (1) constitute the lateral sections of the deck (3).
Secondly, transverse slabs (2) are used, supported between the longitudinal beams (1) by their bottom flanges (1a) and connected so that the final set in the form of U being pursued is monolithic. A representation of this configuration is shown in
Third, the deck (3) is configured in a “U” shape, focused on housing a double railway track inside. This differs from another very usual current technique consisting of the construction of two longitudinal beams, located between piers, above them a slab is located on which a double railway track runs. In this case, each of the beams may have a “U” shaped cross section, being separated or joined together in the form of a “W”, which presents a great disadvantage with respect to the disclosed invention, especially as regards to manufacturing and assembly costs, since a longitudinal “U” beam and a slab, although shared, are needed for each of the two railway tracks.
The assembly of the structure of the deck (3) of the modular system of the invention is represented in the sequence defined by
The longitudinal beams (1) are transported in trucks (6), as will be commented below, which are parked between the two piers (4) between which the longitudinal beam (1) will be located to facilitate its later collection and erection up to the pier (4) by a crane (5).
As shown in
It must be taken into account that, for the support of the longitudinal beams (1) on the piers (4), bearings (7, 8) are placed on the piers (4) that define the position of the longitudinal beams (1) and avoid direct contact between the two elements.
Finally, transverse slabs (2) are collected with the crane (5) to position them between the longitudinal beams (1), as shown in
The construction of the deck (3) is defined in
Subsequently, both the absolute position of the longitudinal beams (1) on the piers (4) and the relative position between the longitudinal beams (1), it is convenient that are controlled by means of a bracing of those known in the state of the art , as it can be by incorporating auxiliary beams that connect the upper flanges (1c) of the longitudinal beams (1) so that, both the separation distance between the longitudinal beams (1) and the parallelism between them, is defined and also the stability against overturning of the longitudinal beams (1) is guaranteed.
Other means of bracing can be by placing mechanical stops that indicate without question the position of each of the longitudinal beams (1) or by fixing the beams (1) by wiring.
Subsequently, as shown in
Subsequently, to ensure that all the elements form a monolithic structure, the longitudinal beams (1) and the transverse slabs (2) are fixed firmly, as shown in
Finally, the transverse slabs (2) are joined together, either by threading and prestressing tendons or steel bars, or by leaving a separation between the transverse slabs (2) that are filled with concrete once they are all positioned for guarantee to convert the independent slabs (2) into a monolithic slab.
Once it has been ensured that the joining method between beams (1) and transverse slabs (2) used has been completed, either by hardening the concrete or mortar of the joints, or any other method used, the provisional bracings that could have been placed in an earlier stage are removed and the construction of the deck is being completed (3).
The advantages of the disclosure with respect to the state of the art are based on three concepts:
Regarding the production needs, consider that, by means of this construction process, all the structural elements, both the longitudinal beams (1) and the transverse slabs (2), require manufacturing conditions that are quite small in terms of facilities. Facilities for a production of three beams (1) per week per cast and considering a total of two casts, can consist of a shed of 180 meters in length and 25 meters in width. For the collection of components and finished elements would require an esplanade of 200×60 m2. Since the production depends mainly on the number of casts available, the way to increase it is achieved mainly with the increase in the number of casts.
Regarding the transportation of the construction elements, consider that the longitudinal beams (1) can be transported to the site in conventional transports, such as trucks (6), appropriately adapted for the displacement of elements of great length, where two trailers are used with a single tractor, as shown in
Finally, regarding the needs on site for the placement of the construction elements, the longitudinal beams (1) can be erected by conventional cranes (5), without great technical requirements, so that, for example, two cranes (5) LTM 1500 can be used. The transverse slabs (2) can be erected in the same way, for example by using a crane (5) LTM 1160 or, even, by gantry cranes (5) supported on the longitudinal beams (1). In this way, the raising and subsequent installation of the prefabricated elements is quite simple. In
The savings in execution time due to the lower complexity of the manufacturing plant, the lower cost of transport and savings in erection and assembly of elements can exceed 37% compared to the traditional way of building by erecting transverse segments. This, without counting the losses due to delays caused by lack of synchronization or errors in the delivery of material on site or stops due to delays in the construction of the piers (4) where the launching gantry that raises the segments is supported. In addition, this prefabrication methodology reduces the increasing of schedule associated with the problems that occur in a span built by segments, as it is independent the execution and assembly of a span of its location (does not need that the launching gantry has reached that span) and as many spans as desired can be executed simultaneously depending on the disposition of a greater number of automobile cranes, of great availability in the market and with easy mobilization period.
The advantages of the construction method allowed by the disclosure are therefore based on the flexibility to prefabricate, on the viability of transport with conventional means, on the ease and speed in the arrangement of the cranes necessary for the assembly of construction elements, in the flexibility in the assembly of elements along the railway, because they can be assembled alternately, by not depending on the supply of certain elements and by the speed in the assembly of stations, as it is possible to build the spans before and after the station at the same time than the station itself.
This manufacturing configuration using precast longitudinal beams (1) and transverse slabs (2) located over the longitudinal beams (1) is known in the state of the art, as it has been mentioned above, although for the construction of closed structures where the railway circulates above the structure, or for the construction of beams on which a slab is subsequently placed above, on which the railway circulates, without having been able to develop effectively for the construction of open structures for the location of a double railway track where the railway circulates through its interior, a requirement that is essential in the type of constructions to which the disclosure is dedicated, that is to say, the circulation of railways inside the deck (3).
Anyway, it must be taken into account that the disclosure should not be limited to the way of realization described here. Other configurations may be made by those skilled in the art in view of the present disclosure. Accordingly, the scope of the invention is defined by the following claims.
This application is the United States National Phase of International Application No. PCT/ES2018/070639 filed Oct. 3, 2018, the disclosure of which is hereby incorporated by reference in its entirety.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/ES2018/070639 | 10/3/2018 | WO | 00 |