The present invention relates to a wind turbine foundation and substructure and method of installation. More particularly, the present invention relates to a two-piece design for an offshore wind turbine steel substructure and foundation and method of installation.
The present invention relates to a wind turbine foundation and substructure and method of installation. More particularly, the present invention relates to a two-piece design for an offshore wind turbine steel substructure and foundation and method of installation.
Present jacket installation practice in Europe involves a structural steel template used to drive four pin piles at each jacket location. Once the pin piles are driven into place, the template is removed, at which point a serially fabricated jacket substructure can be simply stabbed into the pin piles and subsequently grouted in place. This current practice of jacket installation in Europe was the inspiration behind a new design (the present invention).
For information about suction cassions, see for example http://www.sptoffshore.com/
The following patent documents are incorporated herein by reference:
The present invention relates to a wind turbine foundation and substructure and method of installation. More particularly, the present invention relates to a two-piece design for an offshore wind turbine steel substructure and foundation and method of installation that could afford a step-change reduction in the levelized cost of offshore wind energy at suitable locations world-wide.
For a further understanding of the nature, objects, and advantages of the present invention, reference should be made to the following detailed description, read in conjunction with the following drawings, wherein like reference numerals denote like elements and wherein:
The present invention relates to a wind turbine foundation and substructure and method of installation. More particularly, the present invention relates to a uniquely configured design for an offshore wind turbine steel substructure and foundation and method of installation that could afford a step-change reduction in the levelized cost of offshore wind energy at suitable locations world-wide. In
In one embodiment, the wind turbine foundation apparatus 10 of the present invention is preferably comprised of two structures (lower foundation 11 and tower or upper foundation 12) when assembled. The two structures, or pieces, preferably include an upper tower structure 12 and a lower foundation structure 11 that receives and connects to the upper structure 12. Upper foundation 12 supports wind turbine 60 preferably upon pedestal, mounting plate or upper frame 35.
In one embodiment, the present invention is preferably comprised of a plurality of upper towers, space-framed lattice structures or upper foundations 12, each received in a foundation structure 11, wherein the upper structures 12 can preferably be interchangeable and of a substantially uniform size (e.g., for mounting on a selected foundation 11).
Rather than driven pin piles that are present in the prior art, one embodiment of the present invention preferably has a lower foundation structure 11 with multiple (preferably three) footings 15 (see
In one embodiment of the present invention, the lower foundation structure 11 preferably has vertical legs 13 of variable height emerging from each support 15 to account for the natural variability of seafloor depth, such that after all the supports 15 have been installed (see
By having an adjustable height lower structure 11, 23, 33 (see
By varying the height of the lower foundations 11, 23, 33 the crane 41 height can be lower thus saving costs. A crane 41 need only be large enough to lift the upper foundation or tower 12 up above deck 43 of barge 40 or water surface 50. For shallower water depth, the same lift equipment 40 could lift the tower 12 while the lower foundation would be the shorter lower foundation 11.
In an example of a preferred installation, there are modular towers 12 of a fixed size, three different modular transition members of a fixed size, and modular footings or suction caissons 15 of a fixed size (or perhaps multiple fixed sizes, depending upon the underwater terrain and/or water depth) (see
Preferably, the height of the supporting deck of the foundation above mean sea level will be dictated by wave climate and tidal variation of the specific location. The distance from mean sea level to the support deck will preferably be as uniform as is practical, likely on the order of less than one-meter variability across the installation, but it might be as much as three meters in some situations.
The basic plan of the present invention is to capture manufacturing efficiencies with a design that has a high degree of standardization. In a preferred embodiment of the present invention, the variability of soil type and water depth will be accommodated by a two-part foundation. The lower section 11, 23, 33 will preferably be the suction caissons 15, connected by either struts or trusses, for example, to make a structure which can be easily fabricated, transported and lifted in to place by smaller marine equipment than has been customarily done. This lower section 11, 23, 33 is preferably designed to adjust for water depth and soil strength, as dictated by the physical location of each tower in the offshore wind farm.
The upper space-frame tower section 12 is preferably designed as a standard height component, such that multiple identical units can be built in an “assembly line” fashion using, for example, identical pieces of structure such as legs 20, horizontal braces 29, diagonal braces 28, deck sections, cathodic protection anodes, grout lines, and possibly access ladders, boat bumpers or other appurtenances. In a preferred embodiment of the present invention, the upper section 12 of each foundation 10 can be built and transported in either a horizontal or vertical position, or both, depending on the preference of the fabricator (see
In a preferred embodiment of the present invention, the present invention can have the following advantages:
1) The caissons 15 and lower sections 11, 23, 33 can be built in one yard, and the upper sections 12 can be built in another. The yard selected for the upper section 12 may require vertical clearance for those sections to be built and transported in a vertical position (see
2) The lower sections 11, 23, 33 of each foundation 10 can be installed months ahead of the delivery of the upper section 12, again leading to schedule improvement.
The following is a list of parts and materials suitable for use in the present invention and short-hand designations used herein:
All measurements disclosed herein are at standard temperature and pressure, at sea level on Earth, unless indicated otherwise.
The foregoing embodiments are presented by way of example only; the scope of the present invention is to be limited only by the following claims.
The following related patent applications are hereby incorporated herein by reference: U.S. Provisional Patent Application Ser. No. 62/443,430, filed 6 Jan. 2017; U.S. Provisional Patent Application Ser. No. 62/542,650, filed 8 Aug. 2017; and priority of these applications is hereby claimed.
Number | Date | Country | |
---|---|---|---|
62542650 | Aug 2017 | US | |
62443430 | Jan 2017 | US |