This invention relates generally to concrete reinforcing steel construction and, more specifically, to the efficient prefabrication and non-structural welding of rebar panels for use in concrete structures. This invention further relates to the fabrication of welded rebar panels on site as well as off site, thereby reducing the cost associated with time, material and labor.
Currently, rebar panels are constructed by wire tying, mechanical couplers, and occasionally by a combination of welding and wire tying. All of these processes are costly because they are labor intensive and time consuming. Further, inherent weaknesses within each method limits the size and shape of panel that can be produced, thereby increasing the steps and thus costs in the overall construction process. As a result, conventional reinforcement steel bars (rebar) assembly methods require more steps with increased costs, resulting in the construction of structurally compromised rebar panels.
Tie wire constructed rebar panels often structurally fail for several reasons. Firstly, the connection resulting from the tying process is subject to human inconsistencies. For example, the tie wire connection is only as strong as the individual person making the tie. Thus, structural inconsistencies often exist in panels where more than one person is constructing a panel, or a single person becomes fatigued while doing so.
Even if tied correctly, tied rebar connections severely limit panel size due to wire strength and overall rebar intersection rigidity. Typically, the panels are assembled and tied with the assembly laid out on the ground near the job site. Upon completion of the tying process, a crane or other machine is used to place the panel in the concrete form. Wire tied panels are often incapable of supporting the panel's weight during their placement, often yielding a displacement of the tied rebar members known as “raking.” As the spacing of the rebar must be made within the tolerances specified by the engineer, the displaced rebar must be retied in its specified location increasing labor costs.
Not too different from the tied rebar panels are panels constructed with mechanical rebar couplers. Here, a great variety of mechanical couplers are applied to intersections of the rebar panel in place of wire ties. The couplers are more time consuming to use than the wire tie method discussed above. Generally, however, a more consistent rebar connection is attained when using the mechanical coupler over the tie wire panel construction technique. Thus, when the mechanical coupling is done properly a more consistent panel construction is achieved. However, panels constructed with mechanical couplers are very costly with regards to the multiple steps required to assemble them and the price of the couplers themselves.
Finally, attempts have been made to produce a welded rebar panel. Historically, these attempts have yielded a sub-standard product. All prior welding techniques have not achieved metallurgical properties meeting the requirements for reinforced concrete. Rebar in concrete is designed to support tensile loads; therefore, welds must not compromise the ability of the steel to support such loading. Consequently, a rebar panel constructed with welds not having appropriate metallurgical properties is not desirable and may increase the likelihood of a structural failure.
The present invention is directed to a system and method for the construction of weld-stabilized rebar panels that overcomes the above-mentioned problems.
The present invention comprises a system for the construction of weld-stabilized rebar panels using a plurality of spot fusion welds made by a unique gas metal arc welding (GMAW) process. The system and method includes rapidly welding rebar sections using GMAW to obtain a fusion weld joint. The system includes a rebar shear used to cut the rebar to predetermined lengths, a rebar bender used to impart required curvature to the rebar, a welding jig used to align the rebar in the desired rebar panel configuration, a rebar welder, preferably a gas metal arc welder, a power source, and one or more rolling tables facilitating the movement of the rebar from the rebar shear to the rebar bender and ultimately to the welding jig. In operation, the rebar starts at the rebar shear, where the rebar is cut, as necessary, to predetermined lengths. The rebar then travels along the rolling tables to rebar bender, where any required curvature is imparted to the rebar. The rebar is then forwarded along rolling table to the welding jig, where is comes to a stop aligned within the jig to facilitate intersection with other rebar in the panel assembly. Once the rebar is properly aligned in the welding jig, the rebar welder, powered by the power source, is used to fusion weld the rebar intersections.
Specific settings are used on the welder and the power source in order to achieve a flare bevel groove weld that meets the grade A706 requirements. The use of shielding gas in the method contains not only heat, but also helps create the fusion between the rebar and consumable electrode of the welder without causing any carbon breakdown in the heat-affected zone of the rebar, thus maintaining the rebar ductility and the specific advantages of the present invention.
The preferred and alternative embodiments of the present invention are described in detail below with reference to the following drawings.
The present invention provides a system and method for construction of weld-stabilized rebar panels. By way of overview and with reference to
Welding jig 16 is described in more detail with reference to
Critical to the ability of the rebar to function as a tensional load-bearing member is the maintenance of the rebar metallurgical properties. A specific welding process to achieve a flare bevel groove weld of grade A706 must be carried out to ensure that the metallurgical properties of the rebar is not compromised during the fusion weld. After extensive experimentation, its was determined that this welding process is accomplished as follows.
In the preferred embodiment, specific settings are used on welder 18 and power source 20 in order to achieve a flare bevel groove weld that meets the grade A706 requirements. With respect to welder 18, initially the shielding gas supply hose of the welder (not shown) must be disconnected and a flow filter with manual adjustment attached. This results in diffusing the typical narrow flow pattern to a more open spray pattern. The gas flow rate is set to approximately 35 cubic feet per hour. The spot time on the welder is set to approximately 0.02 seconds, and the voltage to approximately 26 volts. A 0.046 inch diameter or equivalent I.E. Murimatic D2-ER80s-D2 electrode wire is fed into the welding area at a feed rate of 350 inches per minute. Additional adjustments are likewise made with respect to power supply 20, preferably an electrical power generator. Specifically, the cover of the electrical generator is removed, after which the main feed cable is removed from the internal breaker. Next, a voltage booster is inserted where the main feed cable was previously attached. Following the insertion of a voltage booster, the main feed cable is attached to the voltage booster in a manner understood by those skilled in the relevant art, or as specifically indicated on the junction plate of a Lincoln Power Source 400. In the preferred embodiment, and as applied using an electrical generator, the selected arrangement is Red=Black, 0=Green, B=White. In this manner, the required voltage (optimally 25-volts) is achieved at an even ratio in order to create the desired weld without affecting the metallurgical properties of the rebar.
In operation of the GMAW rebar welder upon rebar sections in the welding jig, the weld area is flooded with an Argon-Carbon Dioxide shielding gas (approximately 90% Argon, 10% CO2). The Argon/CO2 shielding gas pours at approximately 35 cubic feet per hour (CFH). Filler weld material grade LA90 or Murematic D2—single shield or dual shield consumable electrode—is placed near the rebar intersection areas. In a preferred embodiment, an arc is struck for two or three seconds, resulting in a molecular fusion weld approximately ¼ to ⅝ inches long. It will be appreciated that longer or shorter welds may also be made. By American Welding Society standard, a flare bevel groove weld is produced. This welding process is repeated at all or a desired subset of rebar intersections of a panel.
The shielding gas contains not only heat, but also helps create the fusion between the rebar and consumable electrode without causing any carbon breakdown in the heat-affected zone of the rebar, thus maintaining the rebar ductility. Based on experimentation, using Argon/CO2 shielding gas with the 90/10% ratio and at approximately 35 CFH flow rate obtains the strongest fusion rebar weld. A rebar panel containing a plurality of such fusion welds is inherently strong and self-stabilizing. Thus, the fusion welded rebar panels do not require any additional stabilizing structure to maintain panel integrity. An independent testing facility was employed to examine the strength value of the weld and to examine the overall effect of the weld on the structural integrity of the rebar. The conclusions reached by researchers at the independent testing facility are presented in Appendix A and incorporated by reference herein.
The present invention anticipates a variety of alternative embodiments of the welded rebar manufacturing center without deviating from the scope of the present invention.
An alternative embodiment is shown with reference to
While the preferred embodiment of the invention has been illustrated and described, as noted above, many changes can be made without departing from the spirit and scope of the invention. Accordingly, the scope of the invention is not limited by the disclosure of the preferred embodiment. Instead, the invention should be determined entirely by reference to the claims that follow.
This application is a Continuation of U.S. Ser. No. 09/823,037, filed on Mar. 29, 2001, now U.S. Pat. No. 6,627,832 which claims priority to U.S. Provisional Application Ser. No. 60/193,408, entitled Modular Steel Concrete Reinforcement System, filed Mar. 29, 2000. All above named applications are incorporated by reference.
Number | Name | Date | Kind |
---|---|---|---|
2504868 | Muller et al. | Apr 1950 | A |
3143630 | Sohn et al. | Aug 1964 | A |
3364711 | Nordgren | Jan 1968 | A |
3370150 | Nordgren | Feb 1968 | A |
4221951 | Connolly | Sep 1980 | A |
4911209 | Smith et al. | Mar 1990 | A |
6029880 | Primot | Feb 2000 | A |
6627832 | Vittone | Sep 2003 | B2 |
Number | Date | Country |
---|---|---|
3324678 | Jan 1985 | DE |
29501318 | Jun 1995 | DE |
5-169261 | Jul 1993 | JP |
Number | Date | Country | |
---|---|---|---|
20040056002 A1 | Mar 2004 | US |
Number | Date | Country | |
---|---|---|---|
60193408 | Mar 2000 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 09823037 | Mar 2001 | US |
Child | 10624977 | US |