The world is using extensive amounts of fossil fuels for electrical power generation, and, despite the advances and increasing use of renewable power sources (wind, solar, tides, etc.), it will be using fossil fuels for many decades at least. A main disadvantage of fossil fuel plants is that they emit copious quantities of carbon dioxide gas (CO2), which is a carbon burden to the ecology and contributes to climate warming and its well-known disadvantages. Rapid conversion of coal burning plants to cleaner burning natural gas in countries such as the U.S. that have stores of natural gas can bring a large reduction of CO2 emissions in those countries. But coal will continue to be the main source of power in many large economies, such as China and India. Oil will dominate as a source of power in the Middle East until they can convert to natural gas and/or nuclear. That is certainly decades away. In the meantime, major reductions in CO2 worldwide, beyond natural gas conversion, will have to be made by other means if climate warming is to be reduced.
The greatest, immediate reduction in climate warming can be accomplished by replacing coal with natural gas in existing and future power plants that must use fossil fuel. Natural gas produces less than half the air pollution of coal. The next big reduction can be accomplished by building natural gas or oil burning Fuel-Localized-Power (FLP) plants since these emit almost no CO2 into the atmosphere.
At the very least, the increase in the carbon burden is harmful to the ecology, population health, and atmospheric cleanliness and clarity. It is not possible to halt or reduce this increase unless we can at least stop the increase of CO2 from new fossil fuel plants. Increased demand for power from fossil fuels beyond present levels must be met by carbon neutral schemes.
See “Carbon Dioxide Enhanced Oil Recovery”, National Energy Recovery Laboratory, US Dept of Energy (www.netl.doe.gov) and (http://en.wikipedia.org/wiki/Enhanced_oil_recovery).
Accordingly one or more advantages of various aspects of the present system are to reduce the carbon burden and CO2 emissions from power plants. Another advantage is to be able to continue to utilize fossil fuel power sources while producing a decreased amount of CO2 pollution. Further advantages of various aspects will be apparent from a consideration of the ensuing description and accompanying drawings.
A plant is provided that can provide increased power from fossil fuels with reduced increase of the carbon burden. The plant is made moveable and is located in a fossil fuel field, either in a new field or a “depleted” field.” The CO2 generated from the plant is re-injected into the underground strata from which the fossil fuel is extracted. This provides a double benefit in that the CO2 emissions from the plant are reduced or eliminated and the re-injected CO2 can be used to enhance production from the fossil fuel field. Enormous amounts of oil and natural gas can be recovered in this manner from fields considered “depleted.” The infrastructure required to build and operate such carbon neutral moveable power plants can use known components. For “depleted” fields enhanced oil (or gas) recovery (EOR) procedures are highly developed and used throughout the world.
EOR Enhanced Oil (or Gas) Recovery
FLP Fuel Localized Power
Plant 100 is connected to a track-mounted exhaust gas pump unit 120 by conduit 110 that transmits the exhaust gases 110a to a pump unit 120. Pump unit 120 compresses the exhaust gases 130a to some desirable pressure for re-injection into a nearby depleted or “companion” well 30 via an injection conduit 130. Injection conduit 130 is connected to a well pipe 140, which extends down into ground 80. Alternatively the exhaust gases can be sent to an on-site liquefier (
Well pipe 140 is surrounded by a protective well casing 30 that is closed and sealed by pressure seals 150 so that compressed exhaust gases 130a injected into the bottom 160 of well 30 cannot escape back up the annular space between casing 30 and pipe 140.
The compressed exhaust gases 130a injected into well 30 at bottom 160 create a pressure Pe in the area surrounding the bottom of well 30. A pressure profile 170 depicts the pressure drop Pe down to Pe′ from well 30 back to the area around well 20. The induced pressure Pe′ can enhance the production of well 20 by pushing fossil fuel products into well 20.
Power plant 100 produces electricity and transmits it over power lines 210a, 210b, and 210c that are connected to a transmission tower 200 mounted on power plant 100. These power lines are supported by moveable (portable) power line towers 220 that are connected to and pulled along by power plant 100 when it is moved on the track 40. Multiple track mounted towers 220 may follow power plant 100 such that the power lines reach back to and are connected to fixed transmission lines some distance from plant 100.
The FLP concept, in its most effective form, turns fossil fuel, considered the most environmentally “dirty” energy, into green energy in the sense that no carbon is injected into the atmosphere by the burning of fossil fuels in an FLP power plant. The FLP power plant also opens up enormous new supplies of fossil fuel in “depleted” oil-gas fields by providing a local supply of CO2 that can be used to enhance the recovery of fossil fuels from the depleted fields.
The FLP concept alleviates many of the major problems created by fixed-location power plants that are the main sources of air pollution and the increasing amounts of CO2 in the atmosphere. The thousands of existing coal, natural gas and oil burning power plants will not be replaced in less than many decades, so there is ample use for the FLP. The important first step to reducing climate warming is to at least reduce the increase of CO2 injection into the atmosphere as electrical energy demands increase worldwide. That means stopping the building of new conventional fossil fuel power plants that inject CO2 into the atmosphere.
The FLP concept described allows the use of enormous supplies of fossil fuels still in the ground as well as the use of new supplies of natural gas to produce carbon-free power plants that compete with the best of the “green” energy sources being developed at much greater cost per unit of electricity produced.
The entire infrastructure needed to build an FLP exists today with available components. All the major components needed are being used for a variety of other purposes. No new groundbreaking research results are necessary. An FLP can be built and installed in most any fossil fuel field in less than a year. Compare this to the hundreds of millions being spent to test just a few CO2 sequestration schemes that could, at best, serve only a small percentage of the fixed-site power plants in the world.
An FLP can alternatively be used to re-inject its exhaust gases into “sequester wells” surrounding nearby production wells that supply fuel to the power plants. The CO2 injected into nearby “sequester wells” can be used to create Enhanced Oil Recovery (EOR) to force trapped oil to the surface for use by the FLP. Thus, FLPs can be carbon neutral in the ideal case, or they can approach this goal. They can compete with other much more expensive “green” energy supplies as far a low impact on climate warming.
The FLP concept accomplishes several important objectives and exploits existing infrastructure that is already highly developed for the following reasons
In Canada, a CO2-EOR project has been established by CenovusEnergy (see at the Weyburn Oil Field in southern Saskatchewan. The project is expected to inject a net 18 million tons of CO2 and recover an additional 130 million barrels (21,000,000 m3) of oil, extending the life of the oil field by 25 years. There is a projected 26+ million tonnes (net of production) of CO2 to be stored in Weyburn, plus another 8.5 million tonnes (net of production) stored at the Weyburn-Midale Carbon Dioxide Project, resulting in a significant net reduction in atmospheric CO2. That's the equivalent of taking nearly 7 million cars off the road for a year. Since CO2 injection began in late 2000, the EOR project has performed largely as predicted. Currently, some 1600 m3 (10,063 barrels) per day of incremental oil is being produced from the field.
The US has been using EOR for several decades. For over 30 years, oil fields in the Permian Basin have implemented CO2 EOR using naturally sourced CO2 from New Mexico and Colorado. The Department of Energy (DOE) has estimated that full use of “next generation” CO2-EOR in United States could generate an additional 240 billion barrels (38 km3) of recoverable oil resources. Developing this potential would depend on the availability of commercial CO2 in large volumes, which could be made possible by widespread use of carbon capture and storage. For comparison, the total undeveloped US domestic oil resources still in the ground total more than 1 trillion barrels (160 km3), most of it remaining unrecoverable. The DOE estimates that if the EOR potential were to be fully realized, state and local treasuries would gain $280 billion in revenues from future royalties, severance taxes, and state income taxes on oil production, aside from other economic benefits.
Liquid Carbon Dioxide Superfluids
Carbon dioxide is particularly effective in reservoirs deeper than 2,000 ft., where the injected CO2 will be in a supercritical state. In high-pressure applications with lighter oils, CO2 is miscible with the oil, with resultant swelling of the oil, and reduction in viscosity, and possibly also with a reduction in the surface tension with the reservoir rock. In the case of low-pressure reservoirs or heavy oils, CO2 will form an immiscible fluid, or will only partially mix with the oil. Some oil swelling may occur, and oil viscosity can still be significantly reduced.
In these applications, between one-half and two-thirds of the injected CO2 returns with the produced oil and is usually re-injected into the reservoir to minimize operating costs. The remainder is trapped in the oil reservoir by various means. Carbon dioxide as a solvent has the benefit of being more economical than other similarly miscible fluids such as propane and butane.
The thousands of existing coal, natural gas and oil burning power plants will not be replaced in less than many decades. The important first step to reducing climate warming is to at least stop the increase of CO2 injection into the atmosphere as electrical energy demands are increasing worldwide. That means stopping the building of new conventional fossil fuel power plants that inject CO2 into the atmosphere.
The FLP concept described allows the use of enormous supplies of fossil fuels still in the ground in “depleted fields” as well as new supplies of natural gas to produce carbon-free power plants that compete with the best of the “green” energy sources being developed at much greater cost per unit of electricity produced.
Fortunately, enormous supplies of natural gas are being developed close to major urban centers in the northeast of the U.S. Here, FLP's can be built in the middle of the fossil fuel fields. The FLP's will also be close to the power demand locations and electrical transmission lines that fed these areas.
The recoverable oil and natural gas in the depleted fields of the U.S. alone can supply the power needs of the country for many decades. These depleted fields have most of the transportation infrastructure in place (and, in many cases, the electrical power transmission) that is required to construct and operate moveable power plants at minimal expense and in short time.
The additional cost for new power transmission lines and moveable power plant equipment is more than offset by the savings in cost for carbon sequestration that is otherwise out of the question of most fixed-base power plants.
The ideal way to reduce atmospheric CO2 from burning fossil fuels extracted from the ground is to return the carbon to where it came from. Put the CO2 back in the ground. However, that is simply not possible at reasonable expense for the vast majority of land-based power plants burning fossil fuels. The biggest impediment to carbon sequestration is the mere fact that most fixed-base power plants are located in urban and industrialized areas, near the demand for power. These are generally not the areas that are best suited for sequestration of the CO2 produced by the power plants. The obvious path to CO2 reduction is to locate new fossil fuel plants near the fuel sources that are good sequestration sites.
Accordingly the reader will see that, according to one or more aspects, I have provided a power plant that can produce liquid CO2 for EOR (Enhanced Oil Recovery), without the need to transport the CO2 to the wells or to produce CO2 in central facilities and deliver it over long pipelines or by truck/train. Power plants that can sequester CO2 can be provided adjacent the locations best suited for CO2 sequestration, such as ocean areas and oil/gas fields. The present FLP system can be located at the site of fossil fuel recovery. This provides fuel for a power plant close to the plant and CO2 from the power plant that can be used for EOR by be re-injecting the exhaust CO2 into the depleted oil or gas wells that supplied the fuel to the power plant as the power plant moves forward to new wells.
While the above description contains many specificities, these should not be construed as limitations on the scope, but as exemplifications of some present embodiments. Many other ramifications and variations are possible within the teachings. For example the power plant can be mounted on rubber or other resilient wheels without tracks so that it can be easily moved on flat ground without tracks. The power plant can be mounted on a floating watercraft (barge or ship) to facilitate movement thereof.
Thus the scope should be determined by the appended claims and their legal equivalents, and not by the examples given.
Number | Date | Country | |
---|---|---|---|
61773408 | Mar 2013 | US |