Offshore deck installation

Information

  • Patent Grant
  • 6210076
  • Patent Number
    6,210,076
  • Date Filed
    Thursday, March 11, 1999
    25 years ago
  • Date Issued
    Tuesday, April 3, 2001
    23 years ago
Abstract
A method and apparatus that eliminates the need for a derrick barge to lift the deck into place on a floating offshore structure. A connector is used to connect the transport barge to the floating offshore structure. The connector is a type that allows only relative pitch motions between the transport barge and floating offshore structure in response to sea states acting on the barge and floating offshore structure. The connector is also a type that allows disconnection while large forces are acting on the connector. One or more skidding girders attached to the legs of the deck support the legs of the deck above the skidding surface of the transport barge. A skidding surface on the girders, and complementary skidding surface on the surface of the transport barge and floating offshore structure, allow the deck to be skidded from the barge to the floating offshore structure. Once the deck is in the proper position on the floating offshore structure, the deck legs are lowered into contact with the floating offshore structure by removing spacers provided in the girders. The girders are then detached from the legs of the deck and removed. The deck may also be transferred from the transport barge to the floating offshore structure in a manner where relative pitch between the transport barge and floating offshore structure is not allowed. This is accomplished by also using a knee brace that is attached between a submerged portion of the floating offshore structure and the transport barge.
Description




BACKGROUND OF THE INVENTION




1. Field of the Invention




The invention is generally related to the load out, transportation, and installation of offshore platform decks and more particularly to the installation of a deck onto a floating offshore structure.




2. General Background




There are several methods for installing decks on offshore platforms that are well known in the industry. By far, the most common method is to build the deck onshore in a fabrication yard, lift or skid the deck onto a transport barge, transport the deck to the site on a transport barge, and lift the deck from the transport barge onto the platform substructure using a derrick barge. This is the only method that has been used to install a deck onto a spar type structure. A spar type structure may be a deep draft caisson such as that described in U.S. Pat. No. 4,702,321 or an open or truss framework such as that described in U.S. Pat. No. 5,558,467. A derrick barge is a barge with a revolving crane built into its hull. Ideally, the derrick barge that is available can make a one piece lift of the deck, so that costly hook up work offshore can be avoided. Hook up involves the connection between two or more deck units of structural, piping, electrical, and control systems. If the deck is too heavy for available equipment to lift it from the fabrication yard onto the transport barge, then the deck will be skidded along skid ways onto the transport barge in an operation know as a skidded load out.




In an effort to avoid offshore hook up work, the industry has developed methods other than lifting to install one piece decks. One or more of the alternative methods may be considered whenever a derrick barge of sufficient capacity is not available to make a one piece deck lift.




One of these methods, disclosed in U.S. Pat. No. 5,403,124, includes using a vessel having one end that is U-shaped in plan view. The deck is supported on the vessel over the U-shaped end. The vessel is then moved into position such that the U-shaped end surrounds the platform and the deck is over the offshore platform. The vessel is then ballasted down to transfer the deck onto the floating offshore platform. The width of the U-shape at the end of the vessel limits the maximum size offshore platform on which a deck can be installed by this method. Such a vessel has not been built and this method has not been used.




For a TLP (tension leg platform), the shallow draft of the structure allows it to be brought inshore to relatively shallow and protected water. This allows the deck to be built on the structure and the structure then towed to the installation site after completion.




Spar structures are typically deep draft structures that are six hundred to seven hundred feet tall and thus are incapable of being brought inshore into shallow, protected waters.




It can be seen that for spar structures, there is a need for an alternate method and apparatus for deck installation to that presently available. This need also applies in situations where the floating offshore structure and deck structures are built at different locations and it would be impractical to transport one or both to the same inshore site for installation of the deck onto the floating offshore structure.




SUMMARY OF THE INVENTION




The invention addresses the above needs. What is provided is a method and apparatus that eliminates the need for a derrick barge to lift the deck into place on the floating offshore structure. A connector is used to connect the transport barge to the floating offshore structure. The connector allows only relative pitch motions between the transport barge and floating offshore structure in response to sea states acting on the barge and floating offshore structure. The connector also allows disconnection while large forces are acting on the connector. One or more skidding girders attached to the legs of the deck support the legs of the deck above the skidding surface of the transport barge. A skidding surface on the girders, and complementary skidding surface on the surface of the transport barge and floating offshore structure, allow the deck to be skidded from the barge to the floating offshore structure. Once the deck is in the proper position on the floating offshore structure, the deck legs are lowered into contact with the floating offshore structure by removing spacers provided below the skid girders. The girders are then detached from the legs of the deck and removed. The deck may also be transferred from the transport barge to the floating offshore structure in a manner where relative pitch between the transport barge and floating offshore structure is not allowed. This is accomplished by also using a removable knee brace between the floating offshore structure and the transport barge.











BRIEF DESCRIPTION OF THE DRAWINGS




For a further understanding of the nature and objects of the present invention reference should be made to the following description, taken in conjunction with the accompanying drawings in which like parts are given like reference numerals, and wherein:





FIG. 1

is an elevation view of a frame row of a typical four-legged deck.





FIG. 2

is a perspective view of an orthogonally framed, four legged deck.





FIG. 3

is a plan view of the four legged deck supported on a circular spar vessel.





FIG. 4

is an elevation of a transport barge connected to the spar vessel with the deck skidded to a position over the connector, with a downward kink of the skidding surface due to the relative pitch being emphasized.





FIG. 5

is an elevation of the transport barge connected to the spar vessel with the deck skidded to a position over the connector, with an upward kink of the skidding surface due to the relative pitch being emphasized.





FIG. 6

is a section view through the skid girder taken along lines


6





6


of FIG.


5


.





FIG. 7

is an elevation of the deck and its support system while being fabricated onshore.





FIG. 8

is an elevation of the deck in the fabrication yard after the skid girders have been installed between the deck legs.





FIG. 9

is an elevation view of the deck in the fabrication yard after the deck has been lowered onto the skid girders.





FIG. 10

is an elevation view of the deck during a skidded loadout showing the deck partially on the transport barge.





FIG. 11

is a plan view of the transport barge moored to the spar vessel in preparation for docking and connection.





FIG. 12

is a plan view of the transport barge and the spar vessel docked, just before connection.





FIGS. 13A

, B are elevation views detailing the lowering of the deck from its resilient skid girder runners onto the permanent deck leg supports built into the spar vessel.





FIG. 14

is an elevation view of an alternate embodiment of the invention.





FIG. 15

is a plan view of the alternate embodiment of the invention.





FIG. 16

is a section view through the axes of the swivel receiver for the swivel seen in FIG.


15


.





FIG. 17

is a section view through the axes of the swivel receiver and the swivel, showing the swivel seated in the receiver.





FIG. 18

is a plan view showing the rigging at the beginning of the brace installation onto the transport barge.





FIG. 19

is a plan view showing the rigging with the brace partly through its installation onto the transport barge.





FIG. 20

is a plan view of the brace installed on the transport barge.





FIG. 21

is an elevation of the brace attached to the transport barge at the swivels with the brace floating in a horizontal attitude.





FIG. 22

is an enlarged view of the area indicated by numeral


22


in FIG.


21


.





FIG. 23

is an elevation of the brace attached to the transport barge at the swivels with the brace lifted and supported near the stern in the tow attitude.





FIG. 24

is an elevation view of the transport barge approaching the spar vessel with the brace in an attitude too low for connection.





FIG. 25

is an elevation view of the transport barge joined to the spar vessel at the top connector.





FIG. 26

is an elevation view of the transport barge with the brace attached to the spar vessel.





FIGS. 27-29

illustrate an alternate embodiment of the invention wherein jacks are used instead of a wood runner.











DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT




Typical orthogonal framing for a four-legged deck


10


is shown in

FIGS. 1

, and


2


. The framing system for a spar vessel


12


delivers all of the deck load to four legs


14


located at the corners of a square


16


inscribed in the spar vessel


12


cylindrical shell as seen in FIG.


3


. Thus, the spar vessel diameter determines the deck leg spacing


17


.





FIGS. 4 and 5

show a transport barge


18


joined to a spar vessel


12


with a marine connector


20


such as that described in U.S. application filed on Jul. 31, 1997 and assigned Ser. No. 08/903,776. The transport barge


18


may be a launch barge and is provided with a wedge


23


on the stern rake that replaces the rocker arms normally present on a launch barge. The toggle nose


24


of the marine connector is built into the aft end of the wedge


23


. The toggle nose receiver


26


is attached to the spar vessel


12


with connection plates


28


. It should be understood that the toggle nose


24


may be mounted on the bow of the transport barge and that a launch barge is not necessarily indicated since any barge with sufficient stability and strength may be used.





FIG. 6

is a cross section through the skid girder


30


seen in

FIGS. 4 and 5

. Attached to the bottom of the skid girder


30


is a resilient runner


32


which may be formed from a piece of solid rubber


34


with steel plates


36


bonded to the top and bottom sides of the rubber. Sandwiched between the resilient runner


32


and the bottom of the skid girder bottom flange is a wood runner


38


. The function of the wood will be explained below. The bottom steel plate is the actual skidding surface.





FIGS. 4 and 5

show the deck


10


skidded partway between the transport barge


18


and the spar vessel


12


. As shown, the mid-span region of the skid girder


30


is located over the transverse pin of the marine connector


20


. Relative pitch between the vessels causes the top surface of the marine connector


20


to kink down, as seen in

FIG. 4

, and to kink up, as seen in FIG.


5


. The magnitude of the pitch is exaggerated to illustrate the problem solved by the resilient runner. The kinking would alternately crush the ends and then the middle of the skidding surface on the skid girder leading edge after a few cycles to failure. The resilient runner can distort to accommodate the cyclical kinking without damage.




The platform deck


10


is fabricated onshore in one piece as shown in FIG.


7


. The highly concentrated loading from the four deck legs


14


require a significant foundation system to fabricate and load out the deck


10


, indicated as pile supported caps


40


and load out ways


42


. During fabrication the deck legs


14


are supported on cups


44


that bear on the pile caps


40


. “Cups” are a term of art in the offshore construction industry used to indicate short sections of steel pipe with a diameter approximately equal to the deck legs


14


. The cups


44


support the deck


10


during most of the fabrication period. Near the end of the fabrication period, cambered skid girders


30


with the timber and resilient runners already attached beneath the skid girders


30


, are welded to the deck legs


14


as shown in

FIG. 8. A

predetermined gap less than the height of the cups


44


is left between the resilient runners


32


on the bottom of the skid girders


30


.




As seen in

FIG. 9

, immediately prior to load out onto a transport barge, the cups


44


are removed to lower the deck


10


onto the skid girders


30


, which are preferably cambered. The cups


44


are cut with a cutting torch in repeated circumferential passes. Each pass causes the cup to be shortened and the deck lowered by the kerf of the cut. The weight of the deck will straighten the cambered skid girder


30


, resulting in a uniform compression of the resilient runners


32


along their lengths. After the cups


44


are removed, a predetermined gap is left between the bottom of the deck legs and the top of the load out ways


42


.





FIG. 10

illustrates the transport barge


18


in position next to the load out ways


42


, with the deck


10


partly skidded onto the barge. The stern of the transport barge


18


may be grounded as shown so that only barge trim needs to be considered during the skid transfer to the barge. Alternately, a floating load out can be utilized.





FIG. 11

shows the transport barge


18


rigged to the spar vessel


12


with mooring lines


46


in preparation for docking.

FIG. 12

shows the transport barge


18


and the spar vessel


12


docked, just before connection. The marine connector is engaged as described in the co-pending application referred to above. This illustrates that conventional mooring systems can be utilized to dock the marine connector


20


without any special effort.




Once the transport barge


18


and spar vessel


12


are connected, the platform deck


10


is skidded on the spar vessel


12


. After it is skidded to its final location the deck legs are located over receiving legs


48


that are built into the spar vessel


12


.

FIG. 13A

illustrates the situation before the lowering of the deck


10


. In order to lower the deck


10


onto the spar legs


48


and to recover the resilient runners


32


, the wood runner


38


is cut away in a series of passes with a beam chain saw or a hydro-blaster. A hydro-blaster is a device that produces a fine, high-pressure jet of water that is able to cut through steel plate or pipe. After several passes the wood will be reduced enough in thickness to unload the resilient runner


32


, let the camber back into the skid girders


30


, and lower the deck


10


by the gap thickness.

FIG. 13B

illustrates the situation after the lowering of the deck


10


. The resilient runner


32


may be recovered after the deck


10


has been lowered onto the spar vessel.





FIGS. 14 and 15

illustrate an alternate embodiment of the invention where a brace


50


is installed between the transport barge


18


and the spar vessel


12


to eliminate relative pitch between the two vessels. The brace


50


has two arms that extend from midship of the transport barge


18


to about mid depth on the spar vessel


12


. Since the spar vessel depth is about six hundred feet and the transport barge length is also about six hundred feet, the brace


50


is a large structure that requires special features for transport and connection.




The brace


50


has a first end


52


adapted to be connected to the spar vessel


12


and a second end


54


with each arm adapted to be connected to the transport barge


18


. Connectors are provided on the spar vessel


12


and transport barge


18


and will be described below.




The first end


52


tapers to a closed end having a T-shaped connector


53


constructed of large diameter pipes as seen in FIG.


15


. The transverse pipe forms the toggle nose for a marine connector such as that described in U.S. application filed Jul. 31, 1997 and assigned Ser. No. 08/903,776. The transverse pins, toggle mechanism, and hydraulic ram of the marine connector fit inside the “T”. The toggle nose receiver


55


of the marine connector is joined to the spar vessel


12


while the vessel is under construction in the shipyard.




The end of each arm of the second end


54


of the brace


50


is connected to a swivel


56


mounted in a swivel receiver


58


in the transport barge


18


, seen in

FIGS. 15-17

. The swivel receiver


58


is built into the side shell and one of the longitudinal bulkheads of the transport barge


18


. Each swivel


56


is provided with a reduced diameter or saddle-shaped section


57


. The swivels are readily attached and removed to allow normal barge operation when the swivels are not needed.





FIGS. 27-29

illustrate an alternate embodiment of the invention where a jack


66


is provided in each leg


14


of the deck


10


. This eliminates the need for the wood runner


38


described above. In this embodiment, the deck


10


is skidded into its final position on the spar vessel


12


on resilient runners


32


as described above. As seen in

FIG. 27

, jacks


66


, seen in the cutaway section of the deck leg


14


, are mounted on support plates


68


in the legs


14


so that the axes of the jacks and deck legs are coincident. As seen in

FIG. 28

, the jacks


66


are actuated to cause the jack rams


70


to lift the deck high enough to unload the resilient runner


32


and open a gap


72


between the bottom of the resilient runner


32


and the spar vessel


12


. The resilient runner


32


and skid girder


30


are removed and then the jacks


66


are used to lower the deck onto the spar vessel


12


, as shown in FIG.


29


. The jacks


66


are not recovered.




In operation, the deck


10


is skidded onto the transport barge


18


and tied down. If the brace


50


is to be used, the transport barge


18


travels to protected water for installation of the brace.

FIGS. 18 and 19

illustrate the installation of the brace


50


on the transport barge


18


. The brace


50


is designed to float horizontally at the waterline. Winches pull the brace into position while tugs maintain back tension on the lines.

FIG. 18

shows the brace in position to be pulled along side the transport barge.

FIG. 19

shows the brace partway along side the transport barge.

FIGS. 20 and 21

show the horseshoe shaped brace connector


60


received around the saddle-shaped section


57


on the swivel


56


.

FIG. 22

shows the brace docked on the swivels and connected by lowering a stake


59


through the eyes on the ends of the horseshoe shaped brace connector


60


.




After the brace


50


is connected to the swivels


56


and is still floating horizontally, winch lines


62


are rigged to the brace


50


from the cantilever


64


provided on the barge


18


, as seen in

FIGS. 21 and 23

. The winch lines


62


are used to lift the brace


50


until it seats on the bottom of the cantilever


64


. Once lifted, a support


65


(one on each side of the barge) is swung out, and the winches lower the brace


50


a short distance onto the supports as seen in FIG.


23


. The brace


50


is then tied down on the supports


65


to secure it for transport to the installation site.




Once at the installation site the brace


50


is lifted slightly by the winches, the brace supports


65


are swung out of the way, and the winches lower the brace


50


into the water. Flooding chambers in the brace


50


are opened to cause the buoyancy of the brace


50


to change from neutral to slightly negative. As seen in

FIG. 24

, the winches and winch lines


62


then lower the brace


50


to a position lower than the position at which it will be connected to the spar vessel


12


. With the brace


50


in this out of the way position the top connection at the water line is made as seen in FIG.


25


. The top connection is made using the same procedures described above for the relative pitch option. The winches and winch lines


62


are used to pull the brace


50


upward until the T-shaped connector, which forms the toggle nose of the marine connector, docks in the toggle nose receiver


55


on the spar vessel


12


as seen in FIG.


26


. The connection is made by operating the toggle with hydraulic lines running up the brace


50


to the transport barge


18


. After the connection is made the winch lines


62


can be slacked off, leaving the configuration ready for skid on operations, as seen in FIG.


26


.




The skid on operation and deck lowering operation using the brace


50


are essentially the same as the operation conducted without the brace


50


where relative pitch is allowed between the transport barge


18


and the spar vessel


12


. After the skid on is completed, the brace


50


and barge


18


are disconnected by reversing the operations described above.




Although the description above refers to a spar vessel for installing a deck, it should be understood that the spar vessel is merely used as an example of a floating offshore structure and that the invention is applicable to other floating offshore structures.




Because many varying and differing embodiments may be made within the scope of the inventive concept herein taught and because many modifications may be made in the embodiment herein detailed in accordance with the descriptive requirement of the law, it is to be understood that the details herein are to be interpreted as illustrative and not in a limiting sense.



Claims
  • 1. A method for transferring a deck having a plurality of legs from a barge to a floating offshore structure, comprising the steps of:a. connecting one end of the barge to the floating offshore structure using a connector that allows only relative pitch between the barge and floating offshore structure; b. skidding the deck from the barge to the floating offshore structure on a resilient runner; and c. disengaging the connection between the barge and the floating offshore structure.
  • 2. The method of claim 1, wherein:a. the legs of the deck are supported a predetermined distance above the surface of the barge by a skid girder welded to the legs of the deck; and b. a removable runner is provided on the skid girder and positioned above the resilient runner for lowering the deck legs to the surface of the floating offshore structure once the transfer is complete.
  • 3. A method for loading a deck having a plurality of legs onto a barge and transferring the deck from the barge to a floating offshore structure, comprising the steps of:a. providing removable cups on the bottom of each leg of the deck; b. attaching a skid girder to the legs of the deck such that, with said skid girder having a removable runner attached to the bottom surface of the skid girder and a resilient runner attached to the bottom surface of the removable runner, and said skid girder being positioned such that said resilient runner is a predetermined distance above the surface on which the removable cups rest; c. removing the removable cups such that the skid girder and resilient runner support the deck and the deck legs are at a predetermined distance above the surface on which the skid girder rests; d. skidding the deck onto the barge; e. transporting the barge adjacent a floating offshore structure and connecting the barge to the floating offshore structure using a connector that allows only relative pitch between the barge and floating offshore structure; and f. skidding the deck onto the floating offshore structure; g. removing the removable runner from the skid girder such that the deck legs support the deck on the floating offshore structure.
  • 4. The method of claim 3, wherein the removable runner is formed from wood.
  • 5. The method of claim 3, wherein the resilient runner is formed from rubber sandwiched between steel plates.
  • 6. A method for transferring a deck having a plurality of legs from a barge to a floating offshore structure, comprising the steps of:a. connecting one end of the barge to the floating offshore structure using a connector that allows only relative pitch between the barge and floating offshore structure; b. connecting a brace from the barge to the floating offshore structure at a predetermined depth on the floating offshore structure such that the two-point connection formed by the connector and brace prevents relative pitch between the barge and the floating offshore structure; c. skidding the deck from the barge to the floating offshore structure; and d. disengaging the connections between the barge and the floating offshore structure.
  • 7. The method of claim 6, wherein:a. the legs of the deck are supported a predetermined distance above the surface of the barge by a skid girder welded to the legs of the deck; b. a removable runner is provided on the skid girder for lowering the deck legs to the surface of the floating offshore structure once the transfer is complete.
  • 8. The method of claim 6, wherein the brace attaches to the barge using a swivel connection.
  • 9. A method for loading a deck having a plurality of legs onto a barge and transferring the deck from the barge to a floating offshore structure, comprising the steps of:a. providing removable cups on the bottom of each leg of the deck; b. attaching a skid girder to the legs of the deck, with said skid girder having a removable runner attached to the bottom surface of the skid girder and a resilient runner attached to the bottom surface of the removable runner, and said skid girder being positioned such that said resilient runner is a predetermined distance above the surface on which the removable cups rest; c. removing the removable cups such that the skid girder and resilient runner support the deck and the deck legs are at a predetermined distance above the surface on which the skid girder rests; d. skidding the deck onto the barge; e. transporting the barge adjacent a floating offshore structure; f. connecting the barge to the floating offshore structure using a connector that allows only relative pitch between the barge and floating offshore structure; g. connecting a brace from the barge to the floating offshore structure at a predetermined depth on the floating offshore structure such that the two-point connection formed by the connector and brace prevents relative pitch between the barge and the floating offshore structure; h. skidding the deck from the barge to the floating offshore structure; i. removing the removable runner from the skid girder such that the deck legs support the deck on the floating offshore structure; and j. disengaging the connections between the barge and the floating offshore structure.
  • 10. The method of claim 9, wherein the removable runner is formed from wood.
  • 11. The method of claim 9, wherein the brace attaches to the barge using a swivel connection.
Parent Case Info

This application is a continuation-in-part of U.S. application Ser. No. 08/903,776, filed Jul. 31, 1997, now U.S. Pat. No. 5,988,932.

US Referenced Citations (17)
Number Name Date Kind
H488 Rowan Jul 1988
2959015 Beck Nov 1960
4086777 Lai May 1978
4683832 Dysarz Aug 1987
4729695 Silvestri Mar 1988
4874269 Dysarz Oct 1989
5037241 Vaughn et al. Aug 1991
5097786 Sheffield Mar 1992
5183376 Aralt Feb 1993
5207534 Brasted et al. May 1993
5219451 Datta et al. Jun 1993
5403124 Kocaman et al. Apr 1995
5553977 Andersen et al. Sep 1996
5558468 Barentt, Jr. et al. Sep 1996
5829919 Heerema Nov 1998
5924822 Finn et al. Jul 1999
5988932 Haney et al. Nov 1999
Foreign Referenced Citations (2)
Number Date Country
2008652 Jun 1979 GB
1463849 Mar 1989 SU
Continuation in Parts (1)
Number Date Country
Parent 08/903776 Jul 1997 US
Child 09/266422 US