The present invention relates to an operational information managing apparatus for a construction machine. More particularly, the present invention relates to an operational information managing apparatus for a construction machine, the apparatus being able to supply a supervisor, etc. with top priority data among plural kinds of operational data of a hydraulic excavator, which may bring the hydraulic excavator into rest, and also relates to an operational information managing system for a construction machine equipped with the apparatus.
A construction machine, particularly a large-sized hydraulic excavator or the like, is used, e.g., for excavation of earth and rocks in a large work site. Generally, such a large-sized hydraulic excavator is continuously operated in many cases for the purpose of increasing productivity. If there occurs an abnormality, it is required to stop the operation of the hydraulic excavator and repair it. Depending on the severity of the abnormality, the operation must be stopped for a long period. In that case, because production work with the hydraulic excavator is suspended, scheduling of a production plan must be changed.
In view of that background, to prevent the occurrence of failures, an information presenting system for construction machines is already known which, by utilizing the recent information communication technology, transmits information, such as operational data of construction machines all over the world, to one place, and collects operational information regarding all of the construction machines based on the transmitted data, thereby managing the operational information in a centralized manner (see, e.g., Patent Reference 1). According to that known related art, in each construction machine, the operating status of the construction machine is detected as operational data by operation sensors, and the operational data is periodically transported to a support center by an operational information managing apparatus (operational data communication apparatus). The support center receives the transmitted operational data, records the received data in a main database, and predicts the presence/absence of failures for each construction machine based on the operational data, thereby automatically outputting a report. Such a system configuration enables the failure prediction to be always made with a constant level of accuracy.
Patent Reference 1: JP,A 2000-259729
Generally, in the field of construction machines, a method for performing maintenance and management of the construction machines is primarily divided into two. According to one method, the maintenance and management are consigned to a construction machine maker (in practice, a selling company (so-called dealer), and according to the other method, the maintenance and management are performed by customers themselves.
In the case employing the former method, since the customer is not engaged in the maintenance and management of the construction machine, there is a need, for example, that the customer wants to know whether the construction machine is operated everyday in a remote site. On the other hand, in the case employing the latter method, since the customer is engaged in the maintenance and management, there is a need, for example, that the customer wants to confirm trends of various kinds of operational data and, upon the occurrence of an alarm, to know detailed data in respective periods before and after the occurrence of the alarm for the purpose of clarifying the cause of the alarm occurrence. Thus, the kinds of operational data demanded by the customer regarding the construction machine operating in the remote site differ depending on the customer's intentions.
However, because the large-sized hydraulic excavator is required to continuously operate for the purpose of increasing productivity as described above, it is an essential demand common to both the aforesaid methods that the downtime caused by the failure must be minimized. It is therefore important to provide information, which may bring a hydraulic excavator into rest because of the necessity of repair, maintenance, etc., to the maker (dealer) or the customer of the hydraulic excavator in an accurate way.
From that point of view, according to the above-mentioned Patent Reference 1, the support center takes in items regarding the detailed operating status, such as the exhaust temperature, the exhaust pressure, the lubricant temperature, the temperature and pressure of working oil, the cooling water temperature, and the engine revolution speed, and then makes diagnosis of operating situations of the hydraulic excavator. When trying to manage operating situations of the hydraulic excavator, however, the disclosed method takes a very long processing time for the diagnosis, and the hydraulic excavator may be brought into rest during work while the processing is executed. Particularly, in the case managing a plurality of hydraulic excavators, such a potential risk is increased, and the management equipment and cost required for the diagnosis are also increased.
For that reason, as described above, it is required to provide the most important item of the operational data, which may bring the hydraulic excavator into rest, to the supervisor, etc. in a prompt and accurate way. Up to now, however, a sufficient consideration has not been paid to that point.
The present invention has been made in view of the above-mentioned state of the art, and its object is to provide an operational information managing apparatus for a construction machine, the apparatus being able to supply a supervisor, etc. with top priority data among plural kinds of operational data of a hydraulic excavator, which may bring the hydraulic excavator into rest, and to an operational information managing system for a construction machine equipped with the apparatus.
In the operational information managing apparatus of the present invention, the plural kinds of operational information regarding the construction machine are stored as operational data in the storage means, and the top priority operational data selected, for example, by the supervising side (i.e., a customer and a maker, etc.) from among the plural kinds of operational data stored in the storage means is extracted and transmitted to the supervising side by the control means.
With that feature, unlike the related art wherein detailed operational data regarding the operating status are all transmitted to the supervising side from the viewpoint of reducing the downtime, the top priority operational data which may bring the construction machine into rest and is truly required by the supervising side can be selectively presented to the supervising side. As a result, it is possible to eliminate the drawback experienced with the related art, i.e., the disadvantage that a very long processing time is required to make diagnosis on a large amount of the operational data and the hydraulic excavator may be brought into rest during work while the processing is executed, and to suppress a reduction of productivity caused by the rest of the construction machine. In addition, the management equipment and cost required for the diagnosis can be reduced.
Generally, in the field of construction machines, a method for performing maintenance and management of the construction machines is primarily divided into two. According to one method, the maintenance and management are consigned to a construction machine maker (in practice, a selling company (so-called dealer), and according to the other method, the maintenance and management are performed by customers themselves.
In the case employing the former method, since the customer is not engaged in the maintenance and management of the construction machine, there is a need, for example, that the customer wants to know whether the construction machine is operated everyday in a remote site.
In view of that need, with the present invention, by selecting an item of cumulative engine run time on the customer side, for example, the operational information managing apparatus can operate such that the computing means computes the cumulative run time of the engine based on the operational data stored in the storage means, and then transmits the computed run time data. Therefore, the customer can confirm from the cumulative engine run time data whether the hydraulic excavator is operated everyday in a remote site, and the need on the customer side can be satisfied with the least necessary operational data.
With that feature, the operational information managing apparatus is adaptable for such a need on the supervising side as wanting to know only production information (i.e., the operating time per 30 minutes or the average engine load factor) without requiring detailed operational information.
For example, when an alarm occurs in the construction machine operating in a remote site, there is a need that the supervising side wants to know the occurrence of the alarm in an as close as possible real-time way. With the present invention, upon the occurrence of the alarm, the computing means computes the alarm information and the snapshot information regarding the relevant alarm based on the operational data stored in the storage means, and then transmits the computed data to the supervising side. As a result, it is possible to satisfy the need of wanting to know the occurrence of the alarm in real time on the supervising side, and to analyze the cause of the alarm occurrence based on the transmitted snapshot data.
With that feature, the operational information managing apparatus is adaptable for such a need on the supervising side that the operational data (daily report) provided, e.g., everyday per 24 hours is not sufficient and the supervising side wants to more finely confirm the operating situation of the construction machine. Conversely, the operational information managing apparatus is also adaptable for such a customer's need as caused when the daily report is not necessary and the supervising side is just required to confirm the operating situation at intervals of several days and wants to cut the communication cost correspondingly.
1 hydraulic excavator (construction machine)
2 controller network (operational information managing system)
2A first network (first communication network)
2B second network (second communication network)
51L, 51R engine monitor unit
52 machine body control unit
53 electric lever control unit
54 display (display means)
55 display control unit (display control means)
60 data recording unit (operational information managing apparatus)
65 CPU (control means; processing means; control unit)
67 RAM (storage means)
One embodiment of an operational information managing apparatus for a construction machine according to the present invention and an operational information managing system for a construction machine equipped with the apparatus will be described below with reference to the drawings. This embodiment represents the case where the operational information managing apparatus for the construction machine according to the present invention and the operational information managing system for the construction machine equipped with the apparatus are applied to the so-called super-large-sized hydraulic excavator including two engines and belonging to a class with the body weight of several hundreds tons, which is employed in, e.g., overseas mines in many cases.
Further, numeral 12 denotes a travel body, and 13 denotes a swing body mounted on the travel body 12 in a swingable manner. Numeral 14 denotes a cab provided in a front left portion of the swing body 13, and 15 denotes a front operating mechanism (excavating device) mounted to a front central portion of the swing body 13 in a vertically angularly movable manner. Those components constitute the hydraulic excavator 1. Numeral 16 denotes a boom rotatably mounted to the swing body 13, 17 denotes an arm rotatably mounted to a fore end of the boom 16, and 18 denotes a bucket rotatably mounted to a fore end of the arm 17. The front operating mechanism 15 is made up of the boom 16, the arm 17, and the bucket 18.
In
The hydraulic pumps 21a, 21b are driven for rotation by an engine 32 (in fact, the hydraulic excavator 1 includes a pair of left- and right-side engines 32L, 32R, but only one engine 32 is shown in
Numeral 33, 34, 35 and 36 denote control lever devices disposed corresponding to the control valves 22a, 22b-26a, 26b. Though not shown for the sake of avoiding intricacy, the control lever devices 33, 34, 35 and 36 are each made up of an electric lever and a proportional solenoid valve. An electric signal from each electric lever is inputted to the controller network 2 (more specifically, to an electric lever control unit 53 described later), and an electric signal depending on a control input applied with the manipulation of the electric lever is outputted from the controller network 2 to each corresponding proportional solenoid valve. Then, an original pilot pressure is reduced by the proportional solenoid valve depending on the control input applied with the manipulation of the electric lever, and the produced pilot pressure is outputted from corresponding one of the control lever devices 33, 34, 35 and 36. More specifically, for example, when a control lever of the control lever device 33 is manipulated in one X1 of two crossed directions, an arm-crowding pilot pressure or an arm-dumping pilot pressure is produced and applied to the arm control valve 23. When the control lever of the control lever device 33 is manipulated in the other X2 of the two crossed directions, a rightward-swing pilot pressure or a leftward-swing pilot pressure is produced and applied to the swing control valve 25.
On the other hand, when a control lever of the control lever device 34 is manipulated in one X3 of two crossed directions, a boom-raising pilot pressure or a boom-lowering pilot pressure is produced and applied to the boom control valves 22a, 22b. When the control lever of the control lever device 34 is manipulated in the other X4 of the two crossed directions, a bucket-crowding pilot pressure or a bucket-dumping pilot pressure is produced and applied to the bucket control valve 24. Further, when control levers of the control lever devices 35, 36 are manipulated, a left-travel pilot pressure and a right-travel pilot pressure are produced and applied to the travel control valves 26a, 26b. The control lever devices 33 to 36 are disposed in the cab 14 along with the controller network system 2.
Numerals 40-49 denote various sensors disposed in the hydraulic system 20 described above. The sensor 40 is a pressure sensor for detecting, as an operation signal of the front operating mechanism 15, the arm-crowding pilot pressure in this embodiment, and the sensor 41 is a pressure sensor for detecting, as a swing operation signal, the swing pilot pressure taken out through a shuttle valve 41a. The sensor 42 is a pressure sensor for detecting, as a travel operation signal, the travel pilot pressure taken out through shuttle valves 42a, 42b and 42c.
The sensor 43 is a sensor for detecting an ON/OFF state of a key switch for the engine 32, the sensor 44 is a pressure sensor for detecting the delivery pressure of the hydraulic pumps 21a, 21b, i.e., the pump pressure, taken out through a shuttle valve 44a, and the sensor 45 is an oil temperature sensor for detecting the temperature of working oil (i.e., the oil temperature) in the hydraulic system 20. The sensor 46 is a revolution speed sensor for detecting the revolution speed of the engine 32. The sensor 47a is a fuel sensor for detecting the amount of fuel injected by the fuel injection device (not shown) of the engine 32 (i.e., the fuel consumption), the sensor 47b is a pressure sensor for detecting the blowby pressure in a cylinder of the engine 32, and the sensor 47c is a temperature sensor for detecting the temperature of a cooling water (radiator water) for cooling the engine 32 (in fact, the above-mentioned sensors 46, 47a, 47b and 47c are disposed for each of the left- and right-side engines 32L, 32R, but they are each shown as one sensor in
The sensor 48 is a pressure sensor for detecting, as a digging pressure applied from the front operating mechanism 15, the pressure on the bottom side of the bucket cylinder 29 in this embodiment (or on the bottom side of the arm cylinder 28). The sensor 49a is a pressure sensor for detecting the travel pressure, i.e., the pressure of the travel motor 31a or 31b (for example, a maximum one of the pressures of both the travel motors may be taken out through a shuttle valve not shown), and the sensor 49b is a pressure sensor for detecting the swing pressure, i.e., the pressure of the swing motor 30. Detected signals from those sensors 40 to 49 are all sent to and collected in the controller network 2.
The controller network 2 collects data regarding the machine operating status for each part of the hydraulic excavator 1 (hereinafter referred to simply as “operational data”).
In
The engine monitor units 51L, 51R are connected to a later-described data recording unit (operational information managing apparatus) 60 via a first network (first communication network) 2A. The operational data (hereinafter referred to also as “engine related data (first kind of operational data; third kind of operational data” as required)) regarding the respective run statuses of the engines 32L, 32R, which are detected by the sensors and inputted to the engine control units 50L, 50R and the engine monitor units 51L, 51R, are inputted to the data recording unit 60 via the first network 2A. Moreover, numerals 58a, 58b denote terminating resistors disposed at terminal ends of the first network 2A.
Also, numeral 52 denotes a machine body control unit for executing control related to a body of the hydraulic excavator 1 and detecting the operational data regarding the machine body. For example, the machine body control unit 52 receives the delivery pressure of the hydraulic pumps 21a, 21b detected by the pressure sensor 44, and controls respective delivery rates of the hydraulic pumps 21a, 21b through a regulator unit (not shown) in accordance with the received delivery pressure so that a total of input torques of the hydraulic pumps 21a, 21b is held not larger than an output torque of the engines 32, thereby executing the so-called total horsepower control. Further, the machine body control unit 52 receives the working oil temperature in the hydraulic system 20 detected by the oil temperature sensor 45 and executes control of, e.g., an oil cooler fan motor (not shown) so that the working oil temperature is held constant. In addition, the key switch ON/OFF signal for each engine 32, which is outputted from the sensor 43, is also inputted to the machine body control unit 52.
Numeral 53 denotes an electric lever control unit for executing control related to the electric levers and detecting the operational data regarding respective operating statuses of the electric levers. The electric lever control unit 53 receives the arm-crowding pilot pressure detected by the pressure sensor 40, the swing pilot pressure detected by the pressure sensor 41, the travel pilot pressure detected by the pressure sensor 42, the travel pressure detected by the pressure sensor 49a, the swing pressure detected by the pressure sensor 49b, etc. Further, as described above, the electric lever control unit 53 controls the proportional solenoid valve depending on the control input applied with the manipulation of the electric lever for each of the control lever devices 33, 34, 35 and 36, and reduces the original pilot pressure by the proportional solenoid valve, and produces the pilot pressure depending on the control input applied with the manipulation of the electric lever.
Numeral 54 denotes a display (display means) disposed in the cab 14 and displaying various kinds of operational information regarding the hydraulic excavator 1, alarm information, etc. for presentation to the operator. Numeral 55 denotes a display control unit (display control means) for executing control related to display made on the display 54. Further, numeral 56 denotes a keypad connected to the display control unit 55 and used for making, e.g., various kinds of data settings and changing screens with the input operation of the operator.
Additionally, numeral 57 denotes an option unit related to other monitor functions, such as a contamination sensing unit for detecting the contaminated state of a drain of each hydraulic motor.
The machine body control unit 52, the electric lever control unit 53, the display control unit 55, and the option unit 57 are connected to the later-described data recording unit (operational information managing apparatus) 60 via a second network (second communication network) 2B. With such an arrangement, the operational data (hereinafter referred to also as “machine body related data (second kind of operational data; fourth kind of operational data”) as required) regarding the body of the hydraulic excavator 1, which are detected by the sensors and inputted to the machine body control unit 52, the electric lever control unit 53 and the option unit 57, etc. are inputted to the data recording unit 60 and the display control unit 55 via the second network 2B. Moreover, numerals 58c, 58d denote terminating resistors disposed at terminal ends of the second network 2B.
Numeral 60 denotes the data recording unit connected to the first network 2A and the second network 2B to take in respectively the engine related data from the first network 2A and the machine body related data the second network 2B. Further, the data recording unit 60 executes recording and processing to transmit the engine related data and the machine body related data via the satellite communication terminal 3, or to download those data in a portable terminal 71.
In
The various kinds of operational information regarding the hydraulic excavator 1 are inputted to the CPU 65 from the first and second networks 2A, 2B, the pressure sensor 48, etc. via the interfaces 61, 62 and 63 per unit time (e.g., 1 second). Then, as described above, the CPU 65 processes the inputted various kinds of operational information regarding the hydraulic excavator 1 into the predetermined data structure in accordance with the control programs read out of the ROM 66, and stores the processed data in the RAM 67.
In
If it is determined that the engine 32 is under run, the CPU proceeds to step 2 and reads data regarding the detected signals of the respective pilot pressures for the front operating mechanism, the swing and the travel from the sensors 40, 41 and 42 (step 2). Then, for each of the respective pilot pressures for the front operating mechanism, the swing and the travel, the CPU calculates a time during which the pilot pressure exceeds a predetermined pressure (i.e., a level of the pilot pressure at which the front operating mechanism, the swing or the travel can be regarded as being operated), and stores and accumulates the calculated time in the RAM 67 in correspondence to the date and the time-of-day (step 3) by using time information from the timer 64. Instead of detecting the operating statuses of the front operating mechanism, the swing and the travel in the above-mentioned manner, those operating statuses may be detected based on the respective control inputs (electric signals) applied with the manipulation of the electric levers of the control lever devices 34, 35 and 36.
Thereafter, in step 4, the CPU reads data regarding the detected signal of the pump delivery pressure from the sensor 44, data regarding the detected signal of the working oil temperature from the sensor 45, data regarding the detected signal of the engine revolution speed from the sensor 46, data regarding the detected signal of the fuel consumption from the sensor 47a, data regarding the detected signal of the engine blowby pressure from the sensor 47b, data regarding the detected signal of the engine cooling water temperature from the sensor 47c, data regarding the detected signal of the digging pressure from the sensor 48, data regarding the detected signal of the travel pressure from the sensor 49a, and data regarding the detected signal of the swing pressure from the sensor 49b. Further, the CPU stores and accumulates those read data in the RAM 67 in correspondence to the date and the time-of-day by using the time information from the timer 64.
Then, while it is determined in step 1 that the engine 32 is under run, the CPU calculates an engine run time and stores and accumulates the calculated time in the RAM 67 in correspondence to the date and the time-of-day by using time information from the timer 64 (step 5).
During a period in which the controller network 2 is powered on, the CPU 65 executes the above-described process from step 1 to 5 in units (=cycle) of a predetermined time (e.g., 30 minutes). As a result, the RAM 67 accumulates therein the front operating time, the swing operating time and the travel lever operating time in each predetermined cycle which are obtained in step 3, and an average pump delivery pressure, an average oil temperature, an average engine revolution speed, an average fuel consumption, an average engine blowby pressure, an average cooling water temperature, an average digging pressure and an average travel pressure in each predetermined cycle which are obtained in step 4, as well as an average engine run time which is obtained in step 5 (see
In addition, for the time data among the above-mentioned data, respective cumulative values totalized with the lapse of each cycle, i.e., a cumulative front operating time, a cumulative swing operating time, a cumulative travel lever operating time, and a cumulative engine run time, are calculated separately and stored in the RAM 67 with updating of the previous data (see
Further, though not described in detail here, various kinds of event data, such as turning-on/off of the engine and turning-on/off of the key switch, various kinds of alarm data, automatic snapshot data (described in detail later) in the event of issuance of an alarm, etc. are also time-serially stored in the RAM 67 (see
The most important feature of this embodiment resides in that, in the data recording unit 60, the CPU 65 extracts or computes, from among the operational data stored in the RAM 67, the top priority operational data selected by the supervising side (i.e., the user and the maker, etc.), and transmits the extracted or computed operational data to the supervising side via satellite communication. This feature will be described in more detail below.
As shown in
Further, the data extracting program 110 is made up of five programs, i.e., a program 120 for extracting the cumulative engine run time from among the operational data stored in the RAM 67; a program 130 for extracting the predetermined data from among the operational data stored in the RAM 67 and computing daily data (described later); a program 140 for extracting the predetermined data from among the operational data stored in the RAM 67 to prepare life data (described later) and computing daily data; a program 150 for extracting the per-part operating time per unit time (30 minutes in this embodiment) from among the operational data stored in the RAM 67 and computing an average engine load factor (so-called production information); and a program 160 for extracting alarm data and snapshot data regarding the relevant alarm from among the operational data stored in the RAM 67. Those data extracting programs 120 to 160 correspond respectively to options 1 to 5 for an item of extracting the operational data (i.e., a top priority operational data item).
While the option of the top priority operational data item is usually changed in this embodiment with an input applied by the operator from the keypad 56, the present invention is not limited to such a manner. For example, the option may be changed with an input applied from the portable terminal 71 connected to the data recording unit 60. As an alternative, the option may be changed with a remote operation made from the supervising side (i.e., the user and the maker, etc.) via satellite communication. The change of the option with the remote operation is performed, for example, by inputting a selection command signal, which corresponds to the desired option and is inputted from the user-side personal computer 7 or the server 6 on the side of the maker, etc., to the CPU 65 of the data recording unit 60 via the Internet 8, the base station 5, the communication satellite 4, the satellite communication terminal 3, and the communication interface 68.
Corresponding to the option inputted from the keypad 56 or the portable terminal 71, or inputted with the remote operation, the CPU 65 reads the data extracting program out of the ROM 66. More specifically, for example, when the operational data is outputted in the state of the option 1 being selected, the CPU 65 reads the program 120 out of the ROM 66, extracts the cumulative engine run time from among the cumulative data in the operational data stored in the RAM 67, shown in
The option 1 is selected in the following situation. Generally, in the field of construction machines, a method for performing maintenance and management of the construction machines is primarily divided into two. According to one method, the maintenance and management are consigned to the maker, etc., and according to the other method, the maintenance and management are performed by customers themselves. In the case employing the former method, since the customer is not engaged in the maintenance and management of the construction machine, there is a need, for example, that the customer wants to know whether the construction machine is operated everyday in a remote site.
In such a case, by selecting the option 1 in this embodiment, the customer can confirm whether the hydraulic excavator 1 is operated everyday, while looking at the cumulative engine run time data transmitted per, e.g., 24 hours, and therefore the need on the customer side can be satisfied. Further, in the case of the option 1 being selected, because the transmitted data is only the cumulative engine run time, it is possible to greatly reduce the data capacity and to greatly cut the communication cost.
On the other hand, when the operational data is transmitted in the state of the option 2 being selected, the CPU 65 reads the program 130 out of the ROM 66, extracts each set of time unit data from among the operational data stored in the RAM 67 in accordance with the program 130, and computes the daily data. Here, the term “daily data” means various kinds of operational data representing detailed behaviors over the range of 1 day, i.e., 24 hours. In other words, the daily data means average data of time unit data 1 to n (n=48 in this embodiment) prepared per unit time (e.g., 30 minutes), shown in
The option 2 is selected, for example, in the situation where the supervising side (i.e., the customer and the maker, etc.) wants to know fairly detailed operational information everyday for the purpose of maintenance and management. In such a case, by selecting the option 2 in this embodiment, the maker, etc. or the customer can obtain the daily data everyday, confirm a trend of the various kinds of operational data in units of day, and can perform effective diagnosis.
When the operational data is transmitted in the state of the option 3 being selected, the CPU 65 reads the program 140 out of the ROM 66, extracts the life data from among the operational data stored in the RAM 67 in accordance with the program 140, and computes the daily data. Here, the term “life data” means various kinds of cumulative operational data, such as cumulative engine run time and the cumulative per-part operating time, during a period from the start of operation after manufacturing of the hydraulic excavator 1 (e.g., from the time of delivery of the hydraulic excavator). The life data corresponds to the cumulative data in the operational data stored in the RAM 67. Accordingly, the CPU 65 extracts the cumulative data from among the operational data stored in the RAM 67 to obtain the life data, also extracts the time unit data to compute the daily data, and outputs the thus-produced life data and daily data to the satellite communication terminal 3 via the communication interface 68.
The option 3 is selected, for example, in the situation where the supervising side wants to not only confirm a trend of the operational data, but also to perform life management of various components and devices. In such a case, by selecting the option 3 in this embodiment, the supervising side can confirm the various kinds of cumulative data, such as the cumulative operating time, and can predict the life of each of the various components and devices.
When the operational data is transmitted in the state of the option 4 being selected, the CPU 65 reads the program 150 out of the ROM 66, extracts the per-part operating time per unit time (e.g., 30 minutes) from among the operational data stored in the RAM 67 in accordance with the program 150, and computes the average engine load factor. Here, the term “average engine load factor” means a value calculated based on the following formula:
average engine load factor (%)=(fuel consumption per unit time)−(fuel consumption per unit time in no-load state)/({(fuel consumption per unit time in full-load state)−(fuel consumption per unit time in no-load state)}×100
An average fuel consumption in the no-load state and an average fuel consumption in the full-load state in the range of the unit time (e.g., 30 minutes) are stored, for example, in the ROM 66 beforehand (or they may be inputted as the occasion requires). The CPU 65 reads those average fuel consumptions out of the ROM 66, extracts the average fuel consumption in the time unit data from among the operational data stored in the RAM 67, and computes the average engine load factor in accordance with the above formula. Then, the extracted operating time and the computed average engine load factor are outputted to the satellite communication terminal 3 via the communication interface 68.
The option 4 is selected, for example, in the situation where the supervising side wants to know the so-called production information (i.e., the operating time and the average engine load factor per unit time).
When the operational data is transmitted in the state of the option 5 being selected, the CPU 65 reads the program 160 out of the ROM 66, extracts the alarm data from among the event/alarm and other data in the operational data stored in the RAM 67 in accordance with the program 160, and also extracts the snapshot data. The extracted alarm data and snapshot data are both outputted to the satellite communication terminal 3 via the communication interface 68. Considering the case where the same alarm is frequently issued in the same day, the operational data corresponding to the option 5 is outputted only once per day for each type of alarm. Also, when the automatic snapshot is performed, the data recording unit 60 stores, in the RAM 67, the snapshot data for a period of, e.g., 6 minutes (5 minutes and 1 minute respectively before and after the occurrence of the alarm). This however results in a large data capacity. In this embodiment, therefore, the snapshot data for a period, e.g., 10 seconds after the occurrence of the alarm, is extracted from among the stored snapshot data and then outputted.
The option 5 is selected, for example, in the situation where, upon the occurrence of an alarm in the hydraulic excavator 1, the supervising side wants to know the occurrence of the alarm in an as close as possible real-time way. With this embodiment, when the option 5 is selected, the alarm data and the snapshot data regarding the relevant alarm are transmitted to the supervising side in the next transmission step after the occurrence of the alarm. As a result, the occurrence of the alarm can be informed to the supervising side in a nearly real-time way, and the supervising side can analyze the cause of the alarm occurrence based on diagnosis of the transmitted snapshot data.
When the operational data corresponding to each option is outputted from the CPU 65 to the satellite communication terminal 3 as described above, each set of operational data is prepared in the form of a file for each transmission. More specifically, by way of example, a file header is placed at the beginning of the file. The file header includes machine body data, such as the machine number of the relevant hydraulic excavator 1, and the transmission time-of-day (indicated on the basis of any standard time, for example, along with time lag information when the relevant hydraulic excavator is operated oversea). Further, the position data of the relevant hydraulic excavator 1 is added in, e.g., the file header by the GPS module 72.
The operational data thus prepared in the form of a transmission file is transmitted from the satellite communication terminal 3 and is received by the base station 5 via the satellite 4. The operational data received by the base station 5 is sent as, e.g., E-mail to each of the server 6 on the side of the maker, etc. and the user-side personal computer 7 via the communication line 8. Instead of directly sending the operational data from the base station 5 to the user-side personal computer 7 as mentioned above, the operational data may be sent to only the server 6 on the side of the maker, etc. from the base station 5 and then sent to the user-side personal computer 7 from the server 6 on the side of the maker, etc.
While the data transmission made by the CPU 65 to the supervising side via satellite communication may be performed, e.g., everyday as a daily report per 24 hours, the transmission cycle is optionally changeable as required in this embodiment. More specifically, the transmission cycle can be changed, for example, in response to an input applied from the keypad 56 by the operator, etc., or an input applied from the portable terminal 71 connected to the data recording unit 60, or an input applied with the remote operation from the supervising side via satellite communication.
The operational data received by the server 6 on the side of the maker, etc. or the user-side personal computer 7 is processed by an application program previously installed in the server 6 or the personal computer 7, and is displayed in a predetermined format as service information that represents the operating situation.
In the example of
Additionally, respective values of a non-operation time percentage (a %), a travel lever operating time percentage (b %), an operation lever operating time percentage (c %), and a cumulative engine run time percentage (d %=100%) are also displayed as numerals on condition that the cumulative engine run time is 100[%]. This display enables data comparison to be easily made among a plurality of hydraulic excavators 1 differing in engine run time from one another.
Furthermore, on the right side of the bar graphs, a “Note” space is prepared so that the operator can write a memo therein. Thus, the operator can report, as a memo, even the matter that cannot be expressed in the form of a graph.
At an upper left corner of the screen, two tags “Graph” and “Report” are displayed in a selectable manner allowing the operator to select the data of the same contents in the form of a graph or a list with numerical values (
In
In the example of
Further, in the example of
The controller network 2 described above is constructed such that networks separated into two lines, i.e., the first and second networks 2A, 2B, are connected to each other by the data recording unit 60. The data recording unit 60 serves to transfer the operational data between the first and second networks 2A, 2B.
As shown in
Another feature of this embodiment resides in that the snapshot function is given in each of the data recording unit 60 and the display control unit 55. This feature will be described below. The snapshot function used herein is divided into two types depending on a trigger to start the snapshot, i.e., automatic snapshot and manual snapshot.
More specifically, in the controller network 2, the engine related data on the first and second networks 2A, 2B and the machine body related data on the second network 2B flow over the networks while being updated per certain period (e.g., 1 second). The data recording unit 60 and the display control unit 55 record, for each certain time (e.g., 5 minutes), the engine related data and the machine body related data both flowing over the networks at all times with updating of the previous data.
When an alarm occurs in that condition, the data recording unit 60 and the display control unit 55 extract and store, from among the engine related data and the machine body related data both recorded for the certain time as mentioned above, predetermined operational data regarding the occurred alarm (items of the predetermined operational data are stored in, e.g., the ROM 66 of the data recording unit 60 or a ROM (not shown) of the display control unit 55). In addition, the units 60, 55 extract and store, from among the engine related data and the machine body related data in the range of a certain time (e.g., 1 minute) after the occurrence of the alarm, predetermined operational data regarding the occurred alarm. Stated another way, the predetermined operational data regarding the occurred alarm and falling in a period of 5 minutes before the occurrence of the alarm and 1 minute after the occurrence of the alarm is stored as the snapshot data. This is the automatic snapshot function.
On the other hand, the manual snapshot function is the function of manually starting the snapshot with the manipulation of, e.g., the keypad 56 when the operator feels awkward by intuition during the operation, for example, and of executing the snapshot continuously within the range of a memory-allowable maximum time (e.g., 30 minutes) until an end command is inputted from the keypad 56. Data items collected with the manual snapshot function can be selected, for example, with the manipulation of the keypad 56 by the operator looking at the display.
Thus, for example, when the operator wants to look the snapshot data recorded with the automatic snapshot function or the manual snapshot function in the cab 14, the snapshot data stored in the display control unit 55 is displayed on the display 54 with the manipulation of the keypad 56 by the operator. Meanwhile, when the option 5 is selected to transmit the snapshot data via satellite communication, or when the snapshot data is to be downloaded in the portable terminal 71, etc., the snapshot data stored in the data recording unit 60 (e.g., the RAM 67) is transmitted. In any of the case displaying the snapshot data on the display 54 and the case transmitting it via satellite communication, therefore, the snapshot data having a large capacity is avoided from flowing between the data recording unit 60 and the display control unit 55 over the second network 2B. As a result, it is possible to prevent an adverse influence from acting on the engine related data and the machine body related data, which flow over the second network 2B at all times while being updated.
When the snapshot is performed in both of the data recording unit 60 and the display control unit 55 as in this embodiment, the timings of starting the snapshot must be matched with each other. A manner of making the start timings matched with each other will be described below with reference to
In the case of the automatic snapshot, the data recording unit 60 first determines whether an alarm has occurred. Then, if the occurrence of the alarm is detected, the data recording unit 60 sends a snapshot start signal (indicated by a broken-line arrow 75 in
In the case of the manual snapshot, the display control unit 55 first determines whether a command to start the snapshot is inputted from the keypad 56. Then, if the command is inputted, the display control unit 55 sends a snapshot start signal (indicated by a chain-line arrow 77 in
While the above-mentioned signals 75 to 78 are transferred between the data recording unit 60 and the display control unit 55 via the second network 2B in this embodiment, a separate signal line solely dedicated for those signals may be provided as another example.
Advantageous effects obtained with one embodiment of the thus-constructed operational information managing apparatus according to the present invention and the operational information managing system for the construction machine equipped with the apparatus will be described below for each item of the effects.
(1) Effect of Suppressing Reduction of Productivity by Presenting Top Priority Data
With this embodiment, as described above, plural kinds of operational data (i.e., the engine related data and the machine body related data) regarding the operating status of the hydraulic excavator 1 are transmitted to the supervising side (i.e., the user and the maker, etc.) via satellite communication.
With the related art wherein detailed operational data regarding the operating status of the hydraulic excavator are all transmitted to the supervising side from the viewpoint of reducing the downtime, a very long processing time is required to make diagnosis of the operating situation on the supervising side, and the hydraulic excavator may be brought into rest during work while the processing is executed. In particular, when managing a plurality of hydraulic excavators, such a potential risk is increased, and the management equipment and cost required for the diagnosis are also increased.
In contrast, according to this embodiment, among the operational data (i.e., the engine related data and the machine body related data) regarding the operating status of the hydraulic excavator 1, only the operational data corresponding to one of the options 1-5 selected on the supervising side is transmitted satellite communication. This enables selective presentation of the top priority operational data, which may bring the hydraulic excavator 1 into rest and is truly required by the supervising side. As a result, it is possible to eliminate the drawback experienced with the related art, i.e., to avoid the hydraulic excavator from being brought into rest during work while the operational data is processed for diagnosis, and to suppress a reduction of productivity caused by the rest of the hydraulic excavator. In addition, the management equipment and cost required for the diagnosis can be reduced.
(2) Effect of Further Suppressing Reduction of Productivity with Capability of Optionally Changing of Transmission Cycle
With this embodiment, as described above, the cycle of transmitting the operational data from the hydraulic excavator 1 to the supervising side can be optionally changed, as required, from the keypad, the portable terminal, or with the remote operation, etc. Therefore, for example, when the operational data (daily report) provided everyday per 24 hours is not sufficient and the supervising side wants to more finely confirm the operating situation of the hydraulic excavator 1 at a shorter cycle (e.g., per several hours), such a demand can be coped with by setting the transmission cycle to a shorter one. Conversely, for example, when the daily report is not necessary and the supervising side is just required to confirm the operating situation at intervals of several days and wants to cut the communication cost correspondingly, such a demand can be coped with by setting the transmission cycle to a longer one. Thus, according to this embodiment, the top priority operational data can be provided flexibly in responsive to the need on the supervising side. It is hence possible to make soundness diagnosis of the hydraulic excavator 1 in a more effective manner, and to further suppress a reduction of productivity caused by the rest of the hydraulic excavator.
(3) Effect of Increasing Extensibility with Unit-Distributed and Two-Line-Separated Structure of Network
In this embodiment, the controller network 2 has a unit-distributed structure in which control units are separately disposed depending on individual functions. This makes the network flexibly adaptable, for example, such that when a new function is added to the controller network 2, a control unit for the new function is added, and when a predetermined function is not required, a control unit for the predetermined function is removed. As compared with a structure in which a plurality of functions are provided in a single unit, not only function extensibility, but also versatility can be improved. Further, control units for performing control and monitoring with regards to the engine are disposed in the first network 2A in a concentrated way, and other control units for performing control and monitoring with regards to the machine body of the hydraulic excavator 1 are disposed in the second network 2B in a concentrated way, thus resulting in a network configuration separated into two systems. Then, by setting, e.g., data communication methods for the respective networks in different modes from each other, it is possible to take in respective data based on the different communication methods, and to improve the data extensibility. Further, with this embodiment, since the machine body related data is not transmitted from the second network 2B to the first network 2A, the bus occupancy rate of the first network 2A can be reduced.
(4) Effect of Reducing Bus Occupancy Rate with Doubling of Snapshot Function
In this embodiment, as described above, the snapshot function is given in each of the data recording unit 60 and the display control unit 55. More specifically, when the snapshot data is displayed on the display 54, the snapshot data stored in the display control unit 55 is used. When the snapshot data is transmitted to the supervising side via satellite communication, or when the snapshot data is downloaded in the portable terminal 71, etc., the snapshot data stored in the data recording unit 60 is used. In any of the case displaying the snapshot data on the display 54 or the case transmitting it via satellite communication or downloading it, therefore, the snapshot data having a large capacity can be avoided from flowing between the data recording unit 60 and the display control unit 55 over the second network 2B. As a result, it is possible to prevent an adverse influence on the engine related data and the machine body related data, which flow over the second network 2B at all times while being updated. Hence, the transmission, the downloading, etc. of the snapshot can be performed without impairing display of the operating status, etc. on the display 54 during ordinary work.
While, in the first embodiment of the present invention described above, the top priority operational data regarding the hydraulic excavator 1 is decided with selection of one of the preset options 1-5 made from the supervising side, the present invention is not limited to that embodiment. For example, the item of the top priority operational data may be optionally selected, for example, with an input from the keypad 56 or the portable terminal 71, or with the remote operation via satellite communication from the supervising side.
Further, while the hydraulic excavator 1 has been described in one embodiment of the present invention, taking as an example the so-called large-sized excavator or super-large-sized excavator including two engines and belonging to a class with the body weight of several hundreds tons, applications of the present invention are not limited to such an example. As a matter of course, the large-sized hydraulic excavator may be of the type including one engine. Further, the present invention is also applicable to not only the so-called medium-sized excavator in a class with the body weight of several tens tons, which is most popularly employed in various kinds of construction work sites, etc. in Japan, but also the so-called mini-excavator which has a smaller size and is employed in small-scaled construction work sites.
According to the present invention, plural kinds of operational information regarding a construction machine are taken in as operational data in storage means, and from among the plural kinds of operational data stored in the storage means, top priority operational data is extracted and transmitted to the supervising side by control means. Unlike the related art wherein detailed operational data regarding the operating status are all transmitted to the supervising side from the viewpoint of reducing the downtime, the top priority operational data which may bring the hydraulic excavator into rest and is truly required by the supervising side can be selectively presented to the supervising side. As a result, it is possible to eliminate the drawback experienced with the related art, i.e., the disadvantage that a very long processing time is required to make diagnosis on a large amount of the operational data and the hydraulic excavator may be brought into rest during work while the processing is executed, and to suppress a reduction of productivity caused by the rest of the construction machine. In addition, the management equipment and cost required for the diagnosis can be reduced.
Number | Date | Country | Kind |
---|---|---|---|
2003-388342 | Nov 2003 | JP | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/JP2004/013348 | 9/14/2004 | WO | 00 | 12/23/2005 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2005/049927 | 6/2/2005 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
4838835 | Takano et al. | Jun 1989 | A |
6349252 | Imanishi et al. | Feb 2002 | B1 |
6546363 | Hagenbuch | Apr 2003 | B1 |
7039507 | Hagenbuch | May 2006 | B2 |
Number | Date | Country |
---|---|---|
2000-259729 | Sep 2000 | JP |
2000-297443 | Oct 2000 | JP |
2002-180502 | Jun 2002 | JP |
2003-34954 | Feb 2003 | JP |
Number | Date | Country | |
---|---|---|---|
20060212203 A1 | Sep 2006 | US |