Not applicable.
Not applicable.
This section is intended to introduce various aspects of the art, which may be associated with exemplary embodiments of the present disclosure. This discussion is believed to assist in providing a framework to facilitate a better understanding of particular aspects of the present disclosure. Accordingly, it should be understood that this section should be read in this light, and not necessarily as admissions of prior art.
The present disclosure relates to the field of hydrocarbon recovery operations. More specifically, the invention relates to the completion of a well for the production of oil and gas. More specifically still, the invention relates to a perforating gun assembly wherein the shots along the perforating guns may be radially aligned.
In the drilling of an oil and gas well, a near-vertical wellbore is formed through the earth using a drill bit urged downwardly at a lower end of a drill string. After drilling to a predetermined depth, the drill string and bit are removed and the wellbore is lined with a string of casing. An annular area is thus formed between the string of casing and the formation penetrated by the wellbore.
A cementing operation is conducted in order to fill or “squeeze” the annular volume with cement along part or all of the length of the wellbore. The combination of cement and casing strengthens the wellbore and facilitates the zonal isolation, and subsequent completion, of hydrocarbon-producing pay zones behind the casing.
In connection with the completion of the wellbore, several strings of casing having progressively smaller outer diameters will be cemented into the wellbore. These will include a string of surface casing, one or more strings of intermediate casing, and finally a production casing. The process of drilling and then cementing progressively smaller strings of casing is repeated until the well has reached total depth. In some instances, the final string of casing is a liner, that is, a string of casing that is not tied back to the surface.
Within the last two decades, advances in drilling technology have enabled oil and gas operators to economically “kick-off” and steer wellbore trajectories from a vertical orientation to a horizontal orientation. The horizontal “leg” of each of these wellbores now often exceeds a length of one mile, and sometimes two or even three miles. This significantly multiplies the wellbore exposure to a target hydrocarbon-bearing formation. The horizontal leg will typically include the production casing.
The wellbore 100 is completed with a first string of casing 120, sometimes referred to as surface casing. The wellbore 100 is further completed with a second string of casing 130, typically referred to as an intermediate casing. In deeper wells, that is wells completed below 7,500 feet, at least two intermediate strings of casing will be used. In
The wellbore 100 is finally completed with a string of production casing 150. In the view of
It is observed that the annular region around the surface casing 120 is filled with cement 125. The cement (or cement matrix) 125 serves to isolate the wellbore from fresh water zones and potentially porous formations around the casing string 120.
The annular regions around the intermediate casing strings 130, 140 are also filled with cement 135, 145. Similarly, the annular region around the production casing 150 is filled with cement 155. However, the cement 135, 145, 155 is optionally only placed behind the respective casing strings 130, 140, 150 up to the lowest joints of the immediately surrounding casing strings. Thus, for example, a non-cemented annular area 132 is typically preserved above the cement matrix 135, and a non-cemented annular area 152 is frequently preserved above the cement matrix 150.
In order to enhance the recovery of hydrocarbons, particularly in low-permeability formations 115, the casing 150 along the horizontal section 156 undergoes a process of perforating and fracturing (or in some cases perforating and acidizing). Due to the very long lengths of new horizontal wells, the perforating and formation treatment process is carried out in stages.
In one method, a perforating gun assembly 200 is pumped down towards the end of the horizontal leg 156 at the end of a wireline 240. The perforating gun assembly 200 will include a series of perforating guns (shown at 210 in
In operation, the perforating gun assembly 200 is pumped down towards the end 154 of the wellbore 100. The charges associated with one of the perforating guns are detonated and perforations are “shot” into the casing 150. Those of ordinary skill in the art will understand that a perforating gun has explosive charges, typically shaped, hollow or projectile charges, which are ignited to create holes in the casing (and, if present, the surrounding cement) 150 and to pass at least a few inches and possibly several feet into the formation 115. The perforations (not shown) create fluid communication with the surrounding formation 115 so that hydrocarbon fluids can flow into the casing 150 and up to the surface 105.
After perforating, the operator will fracture (or otherwise stimulate) the formation 115 through the perforations (not shown). This is done by pumping treatment fluids into the formation 115 at a pressure above a formation parting pressure.
After the fracturing operation is complete, the wireline 240 will be raised and the perforating gun assembly 200 will be positioned at a new location (or “depth”) along the horizontal wellbore 156. A plug (such as plug 112) is set below the perforating gun assembly 200 and new shots are fired in order to create a new set of perforations. Thereafter, treatment fluid is again pumping into the wellbore 100 and into the formation 115 at a pressure above the formation parting pressure. In this way, a second set of fractures is formed away from the wellbore.
The process of setting a plug, perforating the casing, and fracturing the formation is repeated in multiple stages until the wellbore has been completed, that is, it is ready for production. The shots create clusters of perforations to create fracture complexity and to enhance fluid communication with the formation.
In order to provide perforations for the multiple stages without having to pull the perforating gun after every detonation, the perforating gun assembly 200 employs multiple guns in series.
Each perforating gun 210 represents various components. These typically include a “gun barrel” 212 which serves as an outer tubular housing. An uppermost gun barrel 212 is supported by an electric wire (or “e-line”) 240 that extends from the surface 105 and that delivers electrical energy down to the tool string 200. Each perforating gun 210 also includes an explosive initiator, or “detonator” (not shown). The detonator is a small aluminum housing with a resistor inside surrounded by a sensitive explosive.
In addition, each perforating gun 210 comprises a detonating cord. The detonating cord contains an explosive compound that is detonated by the detonator. Thus, the detonator receives electrical energy and passes it along to the detonator cord. The detonator cord propagates an explosion down its length to a series of shape charges. The shaped charges are held in an inner tube, referred to as a carrier tube, for security. The shape charges are discharged through openings 215 in the selected gun barrel 212.
The perforating gun assembly 200 may include short centralizer subs 220. In addition, tandem subs 225 may be used to connect the gun barrels end-to-end. Each tandem sub 225 comprises a metal threaded connector placed between the gun barrels 210. Typically, the gun barrels 210 will have female-by-female threaded ends while the tandem sub 225 has opposing male threaded ends. Further, an insulated connection member 230 connects the e-line 240 to the uppermost gun barrel 210.
The perforating gun assembly 200 and its long string of gun barrels (the housings 212 of the perforating guns 210) is carefully assembled at the surface 105, and then lowered into the wellbore 10 at the end of e-line 240. After the casing 150 has been perforated and at least one plug 112 has been set, the setting tool 120 and the perforating gun assembly 200 are taken out of the wellbore 100 and a ball (not shown) is dropped into the wellbore 100 to close the plug 112. When the plug 112 is closed, a fluid (e.g., water, water and sand, fracturing fluid, etc.) is pumped by a pumping system down the wellbore (typically through coiled tubing) for fracturing purposes.
As noted, the above operations may be repeated multiple times for perforating and/or fracturing the casing 150 at multiple locations, corresponding to different stages of the well. Multiple plugs and balls may be used for isolating the respective stages from each other during each perf-and-frac stage. When all stages are completed, the plugs are drilled out and the wellbore is cleaned using a circulating tool.
As the perforating gun assembly 200 leaves the hands of the operator, the assembly 200 will rotate as it gravitationally falls into the wellbore and is pumped down the horizontal leg 156. However, the operating company may desire that shots be fired not only at selected depths, but also in a selected altitude (or angle relative to horizontal). Specifically, operators may prefer that the perforations be formed in a horizontal direction. This enables fractures to propagate outwardly from the wellbore at a 90° angle.
It will be appreciated by the petroleum engineer that the size and orientation of a fracture, and the amount of hydraulic pressure needed to part the rock along a fracture plane, are dictated by the formation's in situ stress field. This stress field can be defined by three principal compressive stresses which are oriented perpendicular to one another. These represent a vertical stress, a minimum horizontal stress, and a maximum horizontal stress. The magnitudes and orientations of these three principal stresses are determined by the geomechanics in the region and by the pore pressure, depth and rock properties.
According to principles of geo-mechanics, fracture planes will generally form in a direction that is perpendicular to the plane of least principal stress in a rock matrix. Stated more simply, in most wellbores, the rock matrix will part along vertical lines when the horizontal section of a wellbore resides below 3,000 feet, and sometimes as shallow as 1,500 feet, below the surface. In this instance, hydraulic fractures will tend to propagate from the wellbore's perforations in a vertical, elliptical plane perpendicular to the plane of least principle stress. If the orientation of the least principle stress plane is known, the longitudinal axis of the leg 156 of a horizontal wellbore 100 is ideally oriented parallel to it such that the multiple fracture planes will intersect the wellbore 100 at-or-near orthogonal to the horizontal leg 156 of the wellbore.
In any instance, the perforating gun assembly must be assembled at the surface in such a way that the shots are aligned along the length of the assembly 200. Currently, a threaded adjustment collar is used to adjust the radial point at which the gun barrel housing engages the collar relative to the tandem sub when they are tightened together. Such a system is undesirable as it adds considerable length to the tool string 200.
Therefore, a need exists for an orienting system for a perforating gun assembly. Further, a need exists for an improved method of aligning charges along a perforating gun assembly for use in a wellbore. Still further, a need exists for a method of avoiding frac hits by shooting aligned perforations in one horizontal direction only.
A perforating gun orienting system is provided herein. In one aspect, the perforating gun orienting system includes a first perforating gun and a second perforating gun. Each of the first and second perforating guns defines a tubular body serving as a gun barrel housing. The housings each have a first end and an opposing second end. Preferably, the first and second ends of each of the first and second perforating guns comprises female threads, forming a female-by-female tubular body.
The orienting system also includes a tandem sub. The tandem sub has first and second opposing ends. Each of these ends defines a male threaded connector. In addition, each of these ends includes a side port configured to receive a cap screw. Each cap screw serves as a threaded alignment screw.
A first slot is placed at the second end of the tubular housing of the first perforating gun. This first slot is configured to align with a first side port in the tandem sub upon rotation of the first perforating gun relative to the tandem sub. Similarly, a second slot is disposed at the first end of the tubular housing of the second perforating gun. The second slot is configured to align with a second side port in the tandem sub upon rotation of the second perforating gun relative to the tandem sub.
The perforating gun orienting system also includes a pair of alignment screws. Each alignment screw has a head for driving the screw into the respective first and second slots. Of interest, the first and second slots are configured to receive the alignment screws such that a head of the alignment screws clears an inner diameter of a perforating gun when threadedly run into its respective slot.
Each of the first and second slots includes a stepped surface along an inner diameter of the respective tubular housing. In one aspect, the head of each alignment screw comprises a tapered head that mates with the stepped surface. Thus, when an alignment screw is partially backed out of a tandem sub portal, it will land in the stepped surface, thereby rotationally locking the gun barrel housing relative to the tandem sub.
A method of aligning shots in a perforating gun assembly is also provided herein. In one embodiment, the method first comprises providing a first perforating gun. The first perforating gun has a tubular housing (known as a gun barrel housing) having a first end and a second opposing end.
The method also includes providing a second perforating gun. As with the first perforating gun, the second perforating gun also includes a tubular housing having a first end and a second opposing end.
The second end of the first perforating gun comprises a slot. Similarly, the first end of the second perforating gun also comprises a slot. Each slot includes a stepped surface along an inner diameter of the respective tubular housing.
The method further includes providing a tandem sub. The tandem sub has first and second opposing ends, with each end defining a male threaded connector. In other words, a male-by-male tubular body is provided. Each end of the tandem sub includes a side port. The side ports are configured to receive a threaded alignment screw.
The method additionally comprises running an alignment screw into each side port of the tandem sub such that a top of each alignment screw resides below an inner diameter of the tubular housing of the perforating guns. In one aspect, the operator simply runs the alignment screws all the way into the respective ports.
As a next step, the method includes threadedly connecting the second end of the first perforating gun with the first end of the second perforating gun. This is done using the tandem sub as a threaded intermediate. Preferably, each of the first and second ends of each of the perforating guns comprises female threads, forming a female-by-female tubular body. This allows the tandem sub to quickly and rotationally connect to the perforating guns. In one aspect, threadedly connecting the second end of the first perforating gun with the first end of the second perforating gun comprises threading each of the first and second perforating guns onto the tandem sub until a gun barrel shoulder is against a corresponding tandem sub shoulder.
The method further comprises rotationally unthreading each of the first and second perforating guns from the opposing ends of the tandem sub until the slots are lined up with the alignment screw in the respective side ports.
Also, the method includes rotationally aligning charges of each of the first and second perforating guns. This is done by further rotating each gun barrel housing relative to the tandem sub until the charges associated with each perforating gun are in linear alignment. Note that this rotational movement may be done without moving the slots out of alignment with the side ports.
Then, each alignment screw is backed out of its respective side port until a head of each alignment screw locks into an inner groove of the slot in the corresponding perforating gun. This serves to rotationally lock the tubular housing (or gun barrel housing) relative to the tandem sub. This step also serves to rotationally align charges of each of the first and second perforating guns.
Optionally, the method further comprises pumping the second perforating gun, the tandem sub and the first perforating gun into a wellbore at the end of an electric line. Optionally, charges are placed on only one side of each of the tubular housings so that perforations may be formed along the production casing in a direction opposite the direction of an adjacent parent wellbore.
So that the manner in which the present inventions can be better understood, certain illustrations, charts and/or flow charts are appended hereto. It is to be noted, however, that the drawings illustrate only selected embodiments of the inventions and are therefore not to be considered limiting of scope, for the inventions may admit to other equally effective embodiments and applications.
For purposes of the present application, it will be understood that the term “hydrocarbon” refers to an organic compound that includes primarily, if not exclusively, the elements hydrogen and carbon. Hydrocarbons may also include other elements, such as, but not limited to, halogens, metallic elements, nitrogen, carbon dioxide, and/or sulfuric components such as hydrogen sulfide.
As used herein, the terms “produced fluids,” “reservoir fluids” and “production fluids” refer to liquids and/or gases removed from a subsurface formation, including, for example, an organic-rich rock formation. Produced fluids may include both hydrocarbon fluids and non-hydrocarbon fluids. Production fluids may include, but are not limited to, oil, natural gas, pyrolyzed shale oil, synthesis gas, a pyrolysis product of coal, nitrogen, carbon dioxide, hydrogen sulfide and water.
As used herein, the term “fluid” refers to gases, liquids, and combinations of gases and liquids, as well as to combinations of gases and solids, combinations of liquids and solids, and combinations of gases, liquids, and solids as a slurry.
As used herein, the term “subsurface” refers to geologic strata occurring below the earth's surface.
As used herein, the term “formation” refers to any definable subsurface region regardless of size. The formation may contain one or more hydrocarbon-containing layers, one or more non-hydrocarbon containing layers, an overburden, and/or an underburden of any geologic formation. A formation can refer to a single set of related geologic strata of a specific rock type, or to a set of geologic strata of different rock types that contribute to or are encountered in, for example, without limitation, (i) the creation, generation and/or entrapment of hydrocarbons or minerals, and (ii) the execution of processes used to extract hydrocarbons or minerals from the subsurface region.
As used herein, the term “wellbore” refers to a hole in the subsurface made by drilling or insertion of a conduit into the subsurface. A wellbore may have a substantially circular cross section, or other cross-sectional shapes. The term “well,” when referring to an opening in the formation, may be used interchangeably with the term “wellbore.”
As used herein, the term “sub” generally refers to a cylindrical body. The sub may have opposing threaded ends and is used to connect tubular bodies in series.
Reference herein to “one embodiment” or “an embodiment” means that a particular feature, structure or characteristic described in connection with an embodiment is included in at least one embodiment of the subject matter disclosed. Thus, the appearance of the phrases “in one embodiment” or “in an embodiment” in various places throughout the specification is not necessarily referring to the same embodiment.
The following description of the embodiments refers to the accompanying drawings. The same reference numbers in different drawings identify the same or similar elements.
The following detailed description does not limit the invention. Instead, the scope of the invention is defined by the appended claims. The following embodiments are discussed, for simplicity, with regard to attaching two perforating guns to each other through a tandem sub.
In the following, the terms “upstream” and “downstream” are being used to indicate that one gun barrel may be situated above and below, respectively, in relation to a given element in the well. Alternatively, “upstream” and “downstream” may refer to first and second gun barrels along a horizontal wellbore. One skilled in the art would understand that the invention is not limited only to the upstream gun or only to the downstream gun, but in fact can be applied to either gun. In other words, the terms “upstream” and “downstream” or “first” and “second” are not used in a restrictive manner, but only to indicate, in a specific embodiment, the relative positions of gun barrel housings.
Each perforating gun 310, 320 comprises a respective gun barrel 315, 325. Each of the gun barrels 315, 325 defines a tubular housing fabricated from steel (or other metal). The gun barrels 315, 325 are dimensioned to house components of any known perforating gun. Such components include a detonator and a detonator cord. The detonator receives an electrical signal from a firing head.
The detonator cord is a plastic straw packed that runs along an internal bore of the housing, and is packed with an explosive such as RDX. When current is run through the detonator, a small explosion is set off by the electrically heated resistor. This small explosion sets of the detonator cord along the selected perforating gun.
In addition, each gun barrel 315, 325 will house a carrier tube and associated charges. An illustrative carrier tube is shown in
The first perforating gun 310 has a first end 312 and a second end 314. Similarly, the second perforating gun 320 has a first end 322 and a second end 324. When placed in a wellbore, each of the first ends 312, 322 represents an upstream end while each of the second ends 314, 324 represents a downstream end. It is understood that in “oil patch” convention, the left end of a tool indicates the upstream end while the right end of a tool represents the downstream end. In practice, each perforating gun 310, 320 may be between 18 inches and five feet in length.
As shown in
The tandem sub 330 represents a tubular body also fabricated from steel (or other metal). The tandem sub 330 is shown in cross-section, revealing an inner bore 335. The inner bore 335 includes a bulkhead receptacle 337, meaning that a portion of the inner bore 335 is configured to closely receive a bulkhead assembly.
It is also seen that each perforating gun 310, 320 comprises a series of openings 317. The openings 317 are shown in alignment with each other. The openings 317 receive charges from respective carrier tubes. An illustrative carrier tube and charges are again shown in
A pair of circular grooves 412 is formed along the body. The grooves 412 are dimensioned and configured to receive respective o-rings (not shown). The o-rings preferably define elastomeric seals that closely fit between an outer diameter of the bulkhead 410 and a surrounding bulkhead receptacle (not shown) within the inner bore 335. The o-rings provide a pressure seal for the bulkhead 410.
The bulkhead assembly 400 also includes a contact pin 420. The contact pin 420 defines an elongated body that is fabricated from brass, or a metal alloying comprised substantially of brass. Thus, the contact pin 420 is electrically conductive.
Opposing ends of the contact pin 420 are seen extending out of the bulkhead 410. The tip 425, 427 of each end serves as a contact head. The contact head 425 extends into an electrical switch assembly (not shown), and delivers an initiation signal from the surface. The contact pin 420 is designed to be in electrical communication with an electrical wire that extends down through the first perforating gun 310. The wire is in electrical communication with an electric line (such as the wire 240 shown in
In operation, the operator will send a signal from the surface 105, down the wireline 240, through the body of the pin 420, to the contact head 425 (sometimes referred to as a firing head) and to the detonator inside of a gun barrel (such as upstream gun barrel 315). The detonator ignites the explosive material within the detonator cord. From there, charges are delivered into the surrounding casing as discussed above. Where a series of gun barrels is used in a gun assembly, the signal from the wireline 240 will be transmitted through a series of bulkheads and pins to the charges to be activated, typically from the downstream end, up.
Returning to
In
Of interest, the alignment screws 340 in
After the gun barrel housings 315, 325 have been threaded onto the opposing ends 332, 334 of the tandem sub 330, the gun barrel housings 315, 325 are slowly unthreaded (or backed away) from the shoulders 336 until the slots 316 are aligned with the alignment screw heads 347. Ideally, this will not take more than 720° (or two full turns) of rotation. Once the tapered head 347 of each alignment screw 340 is aligned with a slot 316, the alignment screw 340 is backed out into the tapered slot, that is, a stepped surface 319, in each gun barrel housing 315, 325. This serves to rotationally lock each gun barrel housing 315, 325 relative to the tandem sub 330.
As arranged in
The screw 340 is captured by the gun barrel housing 315 or 325 in case it becomes loose during operation, preventing the screw 340 from falling out in the wellbore. In one aspect, the screw 340 is made with a flange that captures it to simplify the orienting slot design in the gun barrel housing 315 or 325.
As part of the use of the perforating gun orienting system, the operator will align charges associated with the perforating guns 310, 320. Stated another way, the gun charges are linearly aligned between the first perforating gun 310 and the second perforating gun 320. Preferably, the slots 316 and cap screws 340 accommodate a full 360° rotation of the gun barrel housing 315. However, it is anticipated that alignment of the gun barrel slots 316 with respect side portals 345 will automatically align the charge openings 317.
Illustrative insulators 530, 540 are shown extending from the upstream 522 and downstream 524 ends of the body 510, respectively. Power and signal wires 545 may pass through these insulators 530, 540 en route to adjacent perforating guns.
The tubular body 510 also includes a series of charges 520. In the typical carrier tube arrangement, charges 520 are spaced apart radially and longitudinally along the tubular body 510, allowing shots to be fired in all radial directions through the casing 150. However, in the arrangement of
Based on the tandem sub 330, the unique carrier tube 500, the alignment screws 340 and the perforating gun orienting system discussed above, a method of aligning shots in a perforating gun assembly is also provided herein. In one embodiment, the method first comprises providing a first perforating gun. The first perforating gun has a tubular housing having a first end and an opposing second end. The tubular housing serves as a gun barrel housing.
The method also includes providing a second perforating gun. As with the first perforating gun, the second perforating gun also includes a tubular housing having a first end and an opposing second end, and serves as a gun barrel housing.
The second end of the first perforating gun comprises a slot. Similarly, the first end of the second perforating gun also comprises a slot. Each slot may include a stepped surface along an inner diameter of the respective tubular housing. (The stepped surface is shown at 319 in
The method further includes providing a tandem sub. The tandem sub has first and second opposing ends, with each end defining a male threaded connector. In other words, a male-by-male tubular body is provided. Each end of the tandem sub includes a side port. The side ports are configured to receive a threaded alignment screw. (An enlarged view of the alignment screws having socket heads is shown in
In a preferred embodiment, the tandem sub also includes a circular shoulder. (The circular shoulder is shown at 306 in
The method additionally comprises running an alignment screw into each side port of the tandem sub such that a top of each alignment screw resides below an inner diameter of the tubular housing of the connected perforating guns. In one aspect, the operator simply runs the alignment screws all the way into the respective side ports. (Side ports are shown at 345 in
As a next step, the method includes threadedly connecting the second end of the first perforating gun with the first end of the second perforating gun. This is done using the tandem sub as a threaded connector. Preferably, each of the first and second ends of each of the first and second perforating guns comprises female threads, forming a female-by-female tubular body. This allows the perforating guns to quickly and rotationally connect to the tandem sub. In one aspect, threadedly connecting the second end of the first perforating gun with the first end of the second perforating gun comprises threading each of the first and second perforating guns onto the tandem sub until a gun barrel shoulder is against a corresponding side of the tandem sub shoulder. Thus, the gun barrel housings “shoulder out” against the tandem sub.
The method further comprises rotationally unthreading each of the first and second perforating guns from the opposing ends of the tandem sub until the slots are lined up with an alignment screw in the respective side ports. (
Also, the method includes rotationally aligning charges of each of the first and second perforating guns. This is done by further rotating each gun barrel housing relative to the tandem sub until the charges associated with each perforating gun are in linear alignment. Note that this rotational movement may be done without moving the slots out of alignment with the side ports, up to 360° and preferably up to 720° of rotation. (Charges are shown at 520 in
To accommodate this step, it is preferred that the head of each alignment screw comprises a tapered head that mates with the stepped surface. In addition, each slot in the perforating guns will have preferably have an open end. (The open end is shown at 313 in
In addition to providing alignment of the charges as between adjoining perforating guns, the charges are preferably oriented in a desired direction within the horizontal portion of a wellbore. In one preferred embodiment, the charges are placed so that they may deliver shots horizontally into the wellbore, either on one side of the casing or on both sides of the casing. To effectuate this, an eccentric weighting sub may be placed along a tool string comprising the perforating guns and the orienting tandem sub. Preferably, a pair of weighting subs are used, with one being placed at each end of the tool string.
Preferably, the charges are offset at 180° from each other, residing on opposing sides of a carrier tube. In one aspect, 3 to 5 charges reside on one side of a carrier tube while 3 to 5 charges reside on an opposing side of the carrier tube, offset by 180°. (Refer again to
The perforating guns 310, 320 are threadedly connected by means of a tandem sub 330. The tandem sub 330 is in accordance with the orienting tandem sub 330 described above in connection with
At opposing ends of the perforating guns 310, 320 is a pair of tubular subs 350. Each sub 350 is weighted on one side, using weights 357. Each weighted sub 350 is connected to a perforating gun 310 or 320 by means of a threaded connection 355, which may be an end plate such as end plates 322 or 324 shown in
In the arrangement of
In one aspect, charges 520 are positioned on only one side of the perforating guns 310, 320. This enables the operator to shoot charges into only one side of a string of production casing 150. Then, when a hydraulic fracturing operation is conducted, fracturing fluid is injected in only one direction, such as in a direction away from a pressure sink caused by an existing parent wellbore. This may be beneficial if the operator wishes to avoid a frac hit.
Optionally, the method further comprises pumping the second perforating gun, the tandem sub and the first perforating gun into a wellbore at the end of an electric line. This is done prior to the actual shooting of charges at selected depths along the wellbore. The second perforating gun, the tandem sub, the first perforating gun, the charges and the opposing weighted subs form a perforating gun assembly.
Where one or more weighted, eccentric subs are used, the method may further comprise allowing the eccentric subs to rotate along respective bearings, thereby placing the charges associated with the perforating guns into a horizontal (or other desired) orientation.
There are alternate embodiments to the perforating gun orienting system as shown in
As can be seen, a method of aligning charge shots in a perforating gun assembly is provided herein. The method employs the perforating gun orienting system as described above, in its various embodiments. In the system, first and second perforating guns are provided, wherein each perforating gun has a gun barrel housing having a slot. Each gun barrel housing provides female threads, which connect to a male-by-male threaded tandem sub. Beneficially, the tandem sub includes side ports at opposing ends.
In operation, a pair of alignment screws is provided. Each alignment screw is run into a side port in the tandem sub. The gun barrel housings are then threaded onto the tandem sub at opposing ends, and the charges of the two perforating guns are placed in alignment. Each gun barrel includes a slot that is rotationally aligned with a respective alignment screw (as residing within a side port). The alignment screw is then unthreaded, or backed out, of the side ports and locked into a respective gun barrel slot. This, in turn, places the charges in the respective perforating guns in fixed alignment.
In some cases, the operator may desire that shots be fired not only horizontally, but also in one direction only. This helps the service company generate and propagate fractures in a particular part of a formation, which may be of benefit in avoiding frac hits. Those of ordinary skill in the art will appreciate that frac hits are generally a by-product of in-fill drilling, meaning that a new wellbore (sometimes referred to as a “child well”) is being completed in proximity to existing wellbores (referred to as “offset” or “parent wells”) within a hydrocarbon-producing field. Frac hits are also, of course, a by-product of tight well spacing. Ultimately, however, frac hits are the result of the operator being unable to control or “direct” the propagation of fractures within the pay zone.
Based on the disclosure provided above, a method of avoiding a frac hit in a hydrocarbon producing field is also provided. In one embodiment, the method first comprises locating a parent wellbore in a hydrocarbon producing field. Similarly, the method also includes locating a child wellbore in the hydrocarbon producing field. The child well is sometimes referred to as an “offset well.”
The method additionally includes running a perforating gun assembly into the child wellbore. The perforating gun assembly is constructed in accordance with the perforating gun assembly described above, in its various embodiment.
The method then includes:
In connection with avoiding a frac hit, the method may further comprise:
In order to provide this orientation, current practice is to employ a weight bar. The weight bar is placed along an eccentric sub having bearings at each end. Once the perforating gun assembly is in place, the weight bar will rotate into position at the bottom (relative to vertical) of the wellbore, thereby orienting the perforating guns and placing the charges at a horizontal position.
The method may further include sending an actuation signal down the electric line to initiate charges and to create perforations in a direction that is generally opposite from a direction of the parent wellbore.
Further, variations of the tool and of methods for using the tool within a wellbore may fall within the spirit of the claims, below. It will be appreciated that the inventions are susceptible to other modifications, variations and changes without departing from the spirit thereof.
The present application is filed as a Divisional of U.S. Ser. No. 16/833,114. That application was filed on Mar. 27, 2020 and is entitled “Perforating Gun Orienting System, and Method of Aligning Shots in a Perforating Gun.” The parent application claimed the benefit of U.S. Ser. No. 62/827,497 filed Apr. 1, 2019. That application was also entitled “Perforating Gun Orienting System, and Method of Aligning Shots in a Perforating Gun.” Each of these applications is incorporated herein in its entirety by reference.
Number | Date | Country | |
---|---|---|---|
62827497 | Apr 2019 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16833114 | Mar 2020 | US |
Child | 17411933 | US |