A specific embodiment of the present invention will now be described by way of example only, and with reference to the accompanying drawings, in which:—
a is an enlarged view of a portion of the shank of the rock dowel shown in
b in an elevation of one face “A” of the rock dowel of
c in an elevation of the opposite face “B” of the rock dowel of
Referring to the drawings,
The vanes 20, 22 of the first group 16 of projecting mixing vanes adjacent the threaded portion 14, project approximately 0.5 mm-1 mm out from the dowel shank 12, most preferably about 1 mm. Vanes 20, 22 extend out from opposed sides of the dowel shank separated by diametrically opposed flattened portions 24 of the shank, of which only one is shown. The vanes 20 extending from one side of the shank are offset from those 22 extending from the opposite side of the shank.
With reference to
There are approximately ten vanes extending from either side of the shaft in the first group 16, however the specific number of vanes is not critical and may be varied.
There is a gap 12a on the shank where there are no vanes followed by the second group of vanes 18. The configuration of the second group is largely the same as that of the first group, with vanes 26 and 28 being offset relative to one another and separated by opposed flattened portions 24. The length of the gap 12a is not critical. The size of the vanes 26, 28 is greater than those of the first group, projecting from about 1.5 to 2 mm from the shank. While there are approximately ten vanes extending from either side of the shaft in the second group, the specific number of vanes is not critical and may be varied.
There is a gap 12b on the shank where there are no vanes followed by the third and final group of vanes 20 located at the distal or tip end of the shank. The configuration of the third group is largely the same as that of the first and second groups, with vanes 30 and 32 being offset relative to one another and separated by a flattened portions 24. The length of the gap 12b is again, not critical. The size of the vanes 30, 32 is greater than those of the second group, projecting from about 2.5 to 3 mm from the shank. The number of vanes in the third group should preferably be limited to between two and eight vanes on each side of the shank.
In all the groups 16, 18 and 20, the spacing between the vanes in each section can vary between 10 mm-30 mm, but is preferably about 20 mm.
In use, with reference to
During the dowel 2 spinning operation, both capsule compartments 111 and 112 must be broken open and fully mixed together.
The cross-sectional area of the resin compartment 111 is approximately 445 mm2. The cross-sectional area of the smaller catalyst compartment 112 is only approximately 65 mm2. With previous rock-dowels of the prior art, often a dowel will pierce the larger compartment 111 and miss the smaller catalyst compartment 112 partly or wholly, allowing the compartment 112 or casings 109 and 110 to wrap around the spinning dowel 2, failing to mix the resins 111 and 112 and causing “gloving.
In use the dowel 12 is inserted into the hole to pierce the capsules and is spun to mix the resin and catalyst.
With the rock-dowel 10 embodying the present invention, the vanes project out from the shank creating a larger effective spin diameter. In particular, the mixing vanes 30, 32 project out from the dowel shank by approximately 2.5 mm-3 mm creating a spin diameter of up to 6 mm larger than the diameter of the dowel shank 12. As the normal shank 12 diameter is 20 mm-22 mm the spin diameter is up to 26 mm-28 mm in a predrilled hole 4 of approximately 28 mm-32 mm depending on the drill diameter and strata condition of the coal strata. This improves the mixing and increases the chances of properly piercing and mixing both compartments.
While less critical than the end vanes 30 and 32, the vanes in the groups 18 and 20 also project from the dowel shank 12 and create a vigorous agitating and mixing environment.
As discussed above because the part-helical mixing vanes on opposite sides of the shank are opposite in sense, being left and right handed the vanes agitate the two part resin driving it back and forth in turn, without forcing the resin or the casings either into or out of the hole.
The annulus gap 4a, that is, the difference between the effective diameter of the spinning dowel 10 and the pre-drilled hole 4 diameter is dramatically reduced whilst still allowing room for the mixed but as yet unhardened resin 4a to travel up the dowel shank 12 towards the dowel head as the dowel is thrust deeper into the predrilled hole 4 displacing the mixed resin 4a, and without significantly increasing the volume of the shank 12. Increasing the volume of the shank would not only leave less room for the resin mixture to move but also increase the materials used to make the shank and consequently its cost.
To show how the spin diameter affects the performance of the encapsulation process, by mixing the resin 4a and preventing the ruptured resin capsule casings 109 and 110 from wrapping around the spinning dowel 2, the effect of larger spin diameters can be expressed in area values.
For example, a 28 mm diameter drilled hole 4 has a diameter area of 616 mm2, a 20 mm diameter dowel has a diameter area of 314 mm or approximately 51% compared to the hole, this means that the “free area” not affected by the spinning dowel is 302 mm2.
The same 20 mm diameter dowel with a 3 mm projection on both sides has a spin diameter of 26 mm and a spin diameter area of 513 mm with a “free area” not affected by the spinning dowel 10 of only 85 mm2, a reduction of over 70% without enlarging the dowel shank diameter or increasing the effective dowel cost. The unaffected “free area” is reduced to approximately 14% of the diameter area of the drilled hole 4
The spin diameter area of the dowel 2 is the most critical element to achieve satisfactory encapsulation and should range between 60%-85% of the drilled hole diameter area. These percentages are not achievable without the mixing vanes 30, 32, as the diameter of the spinning dowel 2 becomes too large to allow the mixed resin 4a to transfer backwards towards the hole opening and encapsulate the dowel.
The spin diameter of the vanes increases the effective spin diameter of the dowel shank by between 15 and 50%.
By narrowing the annular gap 4a both resin casings 109 and 110 are broken and then thrust down into the back of the hole 4 by the spinning dowel 10 so that the casings 109 and 110 cannot wrap around the spinning dowel shank 12.
The dowel 10 shown in
In a variant, a smaller shank diameter could be used but with larger vanes. For example with a shank diameter of 18 mm, the vanes 16 could project out from the dowel shank by 1.5 mm-2 mm, the vanes 18 could project by 2.5 mm-3 mm and the vanes 20 by 3.5 mm-4 mm.
During the spinning operation to assist in the migration of the mixed but as yet unhardened resin 4a up towards the dowel head the dowel shank 2a should be constrained in diameter and could even be tapered or stepped approximately 2 mm so that it has a smaller diameter at the dowel shank tip. This reduces back pressure in the hole 4 and on the unmixed resin 4a which, if allowed, can migrate into the fissures of the fractured coal material and cause a loss in bonding to the coal strata.
The position of the breakout cap 126 as shown in
The lesser projection of the threaded portion 14 is particularly significant when the installation operator has used what is termed a “thrust” installation. In such an operation, immediately on completion of the dowel spinning stage, the dowel 10 is thrust hard against the washer plate 3 and strata surface 5 and held whilst the resin in the gap 4a is hardening. The nut 13 when finally tightened will only advance several threads and not project any further than approximately 25 mm out from the end of the barrel section 120 or project no more than the original position of the hexagon section 122 before it separates from the barrel 120.
The position of the cap 126 in the nut 13 may also be critical for other reasons. The size and configuration of the hexagonal section 122 is dictated in coal tunnels by the size of the steel nut used in the other non cuttable areas as the operators refuse to constantly keep changing the drill chuck socket to suit plastic nuts. Traditionally with both steel and plastic nuts the position of the cap has been at the very end of the hexagonal section 112 or at the top of the nut 13. The hexagonal size restriction has created a problem for plastic nuts in that to obtain a high cap breakout value the whole or part of the top of the hexagon breaks away with the cap yielding enormous variations and unreliable cap breakout values. By placing the cap in between the hexagon 122 and barrel section 120 as shown in
The size of the apertures 128 will vary with the required torque value required which will vary with the diameter of the rock-dowel 10 and the ultimate strength of the dowel shank 12.
A significant feature and advantage of this reinforcing system is that if the encapsulation is faulty or insufficient the hexagon and barrel section will not separate. Instead the whole head of the dowel will shear off as the torque value of the dowel will be exceeded before the torque value of the separating barrel 120 and hexagon 122 sections is reached. The operators are thus instantly alerted to the dowel head and shank failure and must install another replacement dowel with a longer resin capsule to complete the reinforcement.
In this way the reinforcing system is fail safe in that operators no longer have to be too careful and tentative when tightening the nut and are confident that the dowel 10 is undamaged and a minimum force of approximately 2 tonnes-4 tonnes load is applied to the strata 5 surface. This system speeds up the installation operation and removes the remedial repair work required when the reinforcement system is not installed correctly and the strata 5 begins to collapses
In
The nut 1 in
The second stage of installation is the further tightening of the nut 1 down onto the plate 3 and strata surface 5. The section with holes or apertures 1a allows the hexagon shaped back of the nut 1b to shear off at a prescribed torque value. Sometimes there can be a steel or plastic mesh between the strata surface and the washer, this is to hold back coal from falling out from areas between the spacings of the dowel installation.
It will be appreciated by persons skilled in the art that numerous variations and/or modifications may be made to the invention as shown in the specific embodiments without departing from the spirit or scope of the invention as broadly described. The present embodiments are, therefore, to be considered in all aspects as illustrative and not restrictive
| Number | Date | Country | Kind |
|---|---|---|---|
| 2006202175 | May 2006 | AU | national |