This description relates generally to floor construction using post-tensioned concrete slabs.
Generally, a process for new floor construction using post-tensioned concrete slabs requires a gap (also known as a leave out, a pour strip out, etc.) that separates adjacent concrete slabs (also known as pours or castings). Generally, the gap is four feet and more in length. That is, several feet in distance separates the two ends of the post-tensioned concrete slabs. Sometimes the gap distance (the distance which separates the two ends of the post-tensioned concrete slabs) may be called a “width,” but for clarity and consistency, the term “width” is used herein to describe the distance along the direction labeled “W,” and the term “length” is used herein to describe the distance along the direction labeled “L” (e.g., see
Prestressed concrete is a type of reinforced concrete which has been subjected to external compressive forces prior to the application of load. Prestressed concrete is categorized as either pre-tensioned or post-tensioned.
Pre-tensioned concrete is formed by a process including initial stressing of a wire strand system and then casting concrete around the stressed wire strand system. The stress from the wire strand system transfers to the concrete after the concrete has reached a specified strength (e.g., cured to a set specification).
Post-tensioned concrete is formed by a process of casting wet concrete around an unstressed wire strand system and then stressing the wire strand system after the concrete has reached specified strength (e.g., cured to a set specification). For example, post-tensioned concrete can have a wire strand system which has a wire enclosed in a duct (e.g., pipe, conduit, etc.). Concrete is formed around the duct and the concrete sets and cures. Then, the wire is stressed and grout material (e.g., a mixture of cement, sand, aggregate, and water) is pumped into the cavity surrounding the wire. The grout material bonds the wire to the duct, and the duct is bonded to the cured concrete. Thus, the stress applied to the wire can be transferred to the concrete. The applied stress (e.g., forces applied to the wire strand system) in the post-tensioning process causes a volume change (and/or a length change) to the concrete material. The volume change of the concrete material causes a change in the length of the concrete slab. The length change is a shortening in the direction parallel to applied stress (e.g., the post-tensioning force).
Each of the slabs 12, 14 changes volume due to their tensioning processes. The typical tensioning process for a typical floor construction uses the gap 16, which is typically four to eight feet in length, for accommodating appropriate tooling and equipment (and also for access by workers) to tension the slabs 12, 14. Further, the gap 16 (i.e., the separation between the two slabs 12, 14) becomes longer (e.g., along direction L shown in
For example, in a typical hotel floor construction, the gap 16 can be about sixty to seventy feet in width and four to eight feet in length. Generally, the gap 16 is left open for twenty to thirty days to allow most of the volume changes (i.e., slab shortening) to occur to the post-tensioned concrete slabs 12, 14. After the twenty to thirty days, the gap 16 is filled in (i.e., lap spliced) with a pour strip 18 to provide a structural continuity of the floor construction 10 required by the final design to resist all required loads.
Referring back to
Devices, systems, and methods for connecting post-tensioned concrete slabs in new floor construction reduce the distance (e.g., length) of the gap between the post-tensioned concrete slabs as compared to conventional construction. Accordingly, the devices, systems, and methods disclosed herein advantageously reduce project construction time by reducing the time delay in accessing the floor underneath the slabs due to, for example, safety and/or weather conditions.
An embodiment of concrete construction (e.g., a new floor construction) includes a first post-tensioned concrete slab and a second post-tensioned concrete slab, said first post-tensioned concrete slab and said second post-tensioned concrete slab having respective upper surfaces that are generally aligned, said first post-tensioned concrete slab including a first rebar installed therein, said second post-tensioned concrete slab including a second rebar installed therein, said first post-tensioned concrete slab and second post-tensioned concrete slab being separated by a gap so that the concrete material of said first post-tensioned concrete slab is not in contact with the concrete material of said second post-tensioned concrete slab, said construction comprises a splice device positioned in the gap splicing together a portion of the first rebar and a portion of the second rebar.
In an embodiment of the concrete construction, said splice device includes a cavity that contains said end portion of the second rebar. In an embodiment of the concrete construction, said cavity also contains said end portion of the first rebar. In an embodiment of the concrete construction, said cavity does not contain said end portion of the first rebar. In an embodiment of the concrete construction, said splice device is connected to said end portion of the first rebar. In an embodiment of the concrete construction, said splice device is connected to said end portion of the first rebar at an end of said splice device, wherein said end has a threaded surface which mates with a threaded surface of said end portion of the first rebar. In an embodiment of the concrete construction, said splice device is connected to said first rebar by a weld. In an embodiment of the concrete construction, said splice device is connected to said second rebar by a weld. In an embodiment of the concrete construction, the concrete material of said first post-tensioned concrete slab is not in contact with the concrete material of said second post-tensioned concrete slab.
In another embodiment of the concrete construction, the gap has a longer dimension for one side-to-side and a shorter dimension for another side-to-side, the shorter dimension (e.g., along the “L” direction of the floor construction shown in
In an embodiment of the concrete construction, said splice device splices together the first rebar and the second rebar so that said first rebar and the second rebar are parallel with each other. In an embodiment of the concrete construction, said splice device splices together the first rebar and the second rebar so that said first rebar and the second rebar are inline.
In an embodiment of the concrete construction, a strip of non-shrink material is placed in the gap, wherein said strip has a compressive strength that is greater than or equal to the compressive strength of the concrete material of said first post-tensioned concrete slab and/or the concrete material of said first post-tensioned concrete slab.
In an embodiment of the concrete construction, the strip of non-shrink material completely surrounds the splice device. In an embodiment of the concrete construction, the strip has a longer dimension for one side-to-side and a shorter dimension for another side-to-side, the shorter dimension (e.g., along the “L” direction of the floor construction shown in
In an embodiment of a method for making a concrete construction including a first post-tensioned concrete slab and a second post-tensioned concrete slab separated by a gap, the method comprises forming said first post-tensioned concrete slab, wherein said first post-tensioned concrete slab includes a first rebar installed therein; prior to pouring a second concrete slab, positioning a second rebar for said second concrete slab so that a portion of said second concrete slab is generally in line with a portion of said first rebar; pouring said second concrete slab; forming a second post-tensioned concrete slab by tensioning said second concrete slab, thus forming said gap between said first post-tensioned concrete slab and said second post-tensioned concrete slab, wherein said gap has a longer dimension for one side-to-side and a shorter dimension for another side-to-side; positioning a splice device to contact both a portion of said first rebar and a portion of said second rebar; and securely connecting said splice device to said end portion of said second rebar.
In an embodiment of the method for making a concrete construction including a first post-tensioned concrete slab and a second post-tensioned concrete slab, the method comprises forming said first post-tensioned concrete slab, wherein said first post-tensioned concrete slab includes a first rebar installed therein; before a second post-tensioned concrete slab has been formed, positioning a splice device at an end portion of the first rebar, but not securely connecting said splice device to an end portion of the first rebar; before the second post-tensioned concrete slab has been formed, positioning an end portion of a second rebar inside a chamber of said splice device, but not securely connecting said splice device to an end portion of the second rebar; forming said second post-tensioned concrete slab so that said second rebar is installed therein, wherein said first post-tensioned concrete slab and second post-tensioned concrete slab are separated by a gap so that the concrete material of said first post-tensioned concrete slab is not in contact with the concrete material of said second post-tensioned concrete slab, and said end portion of said second rebar is allowed to move with respect to the splice device during the creating of said second post-tensioned concrete slab; and securely connecting said splice device to said end portion of said first rebar and said end portion of said second rebar.
In another embodiment of the method, said gap is formed so that the gap has a longer dimension for one side-to-side and a shorter dimension for another side-to-side, the shorter dimension (e.g., along the “L.” direction of the floor construction shown in
In an embodiment of the method, the process further includes forming a strip of material in said gap with a non-shrink material, wherein said strip has a compressive strength that is greater than or equal to the compressive strength of the concrete material of said first post-tensioned concrete slab and/or the concrete material of said first post-tensioned concrete slab.
The present disclosure may be further understood with reference to the following description and the appended drawings, wherein like elements are referred to with the same reference numerals. Systems, methods, and devices disclosed herein are directed towards reducing the gap between post-tensioned concrete slabs in a floor construction, so that time delay caused by the existence of conventional gaps in the floor construction can be reduced and/or eliminated.
Accordingly, the floor construction 100 can advantageously reduce the overall construction time of the construction project associated with the floor construction 100, because the time delay in accessing the floor underneath the floor construction 100 due to, for example, safety and/or weather conditions, is substantially reduced or eliminated. Further, in a multi-level building construction having one or more floors, the floor construction 100 can be placed above another floor. These floors are connected to and accessible via a construction elevator 108. Accordingly, during the construction of the floor construction 100, the slab 104 area can be accessed via the elevator 108 because the gap 106 has a distance that is small (or short) enough that the gap 106 can be crossed over, and/or the gap 106 can be covered with small piece of material such as, for example, a sheet of metal or a plank of wood, to serve as a short bridge between the slabs 102, 104. Accordingly, the construction equipment can be easily moved between slab 104 and slab 102. Thus, the generally required twenty to thirty day waiting period for accessing areas of the floor that cannot be reached due to the conventional gap (16 shown in
Further, the gap 106 can substantially reduce or prevent weather conditions to intrude into the floor beneath the floor construction 100. Thus, weather conditions no longer prevent work from being performed in the floor underneath the floor construction 100. Therefore, waiting and time delay associated with weather conditions can be reduced or eliminated from the construction process.
The process further includes a step 406 of positioning the rebars for the second concrete slab so that their ends are positioned within respective inner chambers of the splice devices prior to pouring the concrete for the second concrete slab. These rebars are positioned so that they can move with respect to the splice devices. That is, the rebars for the second concrete slab are not secured to the splice devices at this stage of the process. It is preferable that the positioning of the rebars for the second concrete slab with respect to the splice devices are done after the first concrete slab has been tensioned (e.g., using the wire strand system that is included in the first concrete slab) and has gone through the volume change, becoming the first post-tensioned concrete slab. Thus, the positioning of the splice devices and then the positioning of the rebars for the second concrete slab can be done with a desired gap space in mind. That is, after the first post-tensioned concrete slab has formed, the length change along the length direction of the rebars would have been completed. Thus, when the splice devices are attached to the rebars of the first post-tensioned concrete slab, the length of the gap can be estimated and/or substantially determined. It is preferable that this estimated and/or substantially determined gap distance is less than a foot. Further, at this stage in the process 400, the splice devices are positioned where the gap between the first and second concrete slabs will exist when the second concrete slab is formed.
The process includes a step 408 of pouring and forming the second concrete slab. The second concrete slab includes one or more rebars that have been positioned with the splice devices. Then, the second concrete slab is allowed to shorten along the length direction of the rebar by and due to tensioning of a wire strand system in the second concrete slab. Because the rebars for the second concrete slab are not secured to the splice devices during step 410, the rebars can and do move with respect to the splice devices during the tensioning of the second concrete slab.
After the volume changes due to tensioning of the second concrete slab has been completed, the second concrete slab is the second post-tensioned concrete slab. The process 400 includes a step 412 of connecting and/or securing the rebars of the second post-tensioned concrete slab to the splice devices. In addition, if in the step 404 of connecting the splice device to the rebar of the first concrete slab, the splice device was not secured to the rebar of the first concrete slab, then, in step 412, the splice device can be secured to the first rebar of the first post-tensioned concrete slab. Accordingly, in the step 412, both of the first and second rebars of the first and second post-tensioned concrete slabs can be secured (e.g., connected) to the splice device. This particular step can depend on the particular features of the splice device used.
At this stage in the process, the gap between the first post-tensioned concrete slab and the second post-tensioned concrete slab is generally fixed. Accordingly, the gap distance is generally known. The gap distance of three feet or less is possible. Preferably, the gap distance at this stage is one foot or less.
The process 400 includes a step 414 of filling in the gap between the first and second post-tensioned concrete slabs with material to form a pour strip. When the pour strip is formed in the gap, the splice devices connected to the rebars of the first and second post-tensioned concrete slabs are covered by the pour strip. It is preferable that the splice devices positioned in the gap are completely covered by the pour strip.
After the volume change due to tensioning has been completed and the second post-tensioned concrete slab 522 has formed, the gap 524 between the first post-tensioned concrete slab 504 and the second post-tensioned concrete slab 522 is substantially defined. The gap 524 is preferably less than a foot in distance between the ends of the first post-tensioned concrete slab 504 and the second post-tensioned concrete slab 522. However, it is required that the minimum distance of the gap 524 is the length of the splice device (e.g., 512, 514 shown in
The floor construction 500e is positioned substantially horizontal with respect to the earth, and the floor construction 500e includes the first post-tensioned concrete slab 504 and the second post-tensioned concrete slab 522 separated by the gap 524. In the gap 524 space, the splice device 512 is connected and/or secured to both rebars 506, 516. Also in the gap 524 space, the splice device 514 is connected and/or secured to both rebars 508, 518. The splice devices 512, 514 are secured to the respective rebars 506, 508, 516, 518 with sufficient strength for structural applicability for connecting the two post-tensioned concrete slabs 504, 522 for structural purposes.
The process 600 includes a step 606 of pouring and forming the second concrete slab. The rebars for the second concrete slab are positioned so that their ends are positioned near respective ends of the respective rebars of the first post-tensioned concrete slab. For example, the ends of the rebars of the second concrete slab are positioned so that the rebars of the second concrete slab are generally in line with the respective rebars of the first post-tensioned concrete slab. It is preferable that the positioning of the rebars for the second concrete slab with respect to the splice devices are done after the first concrete slab has been tensioned (e.g., using the wire strand system that is included in the first concrete slab) and has gone through the volume change, becoming the first post-tensioned concrete slab. Thus, the positioning of the rebars for the second concrete slab can be done with a desired gap space distance in mind. That is, after the first post-tensioned concrete slab has formed, the length change along the length direction of the rebars would have been completed. It is preferable that the gap distance is less than a foot. Further, at this stage in the process 600, the splice devices are not yet positioned where the gap between the first and second concrete slabs will exist when the second concrete slab is formed.
Then, in step 608, the second concrete slab is allowed to shorten along the length direction of the rebar by and due to tensioning of a wire strand system in the second concrete slab. Because the rebars for the second concrete slab can and do move with respect to the respective ends of the rebars of the first post-tensioned concrete slab during the tensioning of the second concrete slab.
After the volume changes due to tensioning of the second concrete slab has been completed, the second concrete slab is the second post-tensioned concrete slab. The process 600 includes a step 610 of positioning a splice device at one end portion of the rebar of the first post-tensioned concrete slab and at one end portion of the rebar of the second post-tensioned concrete slab. Then, in step 612, the splice device is connected to the end portions of the rebars. Preferably, the two rebus that are connected to the splice device are generally in line with each other. Carrying out the connection step 612 can depend on the particular features of the splice device used, as shown in examples in
At this stage in the process, the gap between the first post-tensioned concrete slab and the second post-tensioned concrete slab is generally fixed. Accordingly, the gap distance is generally known. The gap distance of three feet or less is possible. Preferably, the gap distance is one foot or less.
The process 600 includes a step 614 of filling in the gap between the first and second post-tensioned concrete slabs with material to form a pour strip. When the pour strip is formed in the gap, the splice devices connected to the rebars of the first and second post-tensioned concrete slabs are covered by the pour strip. It is preferable that the splice devices positioned in the gap are completely covered by the pour strip.
During the change in volume and length of the second concrete slab, the rebars 711, 712 are allowed to move with respect to the rebars 704, 706 (see step 608 in the process 600 of
After the volume change due to tensioning has been completed and the second post-tensioned concrete slab 716 has formed, the gap 718 between the first post-tensioned concrete slab 710 and the second post-tensioned concrete slab 716 is substantially defined. The gap 718 is preferably less than a foot in distance. However, the minimum distance of the gap 718 must be the length of the splice device (e.g., 720, 722 shown in
The splice devices 720, 722 are then securely connected to the rebars 704, 706, 711, 712 (see step 612 of the process 600 in
The floor construction 700e is positioned substantially horizontal with respect to the earth. In the gap 718, the splice devices 720, 722 are secured to the respective rebars 704, 706, 711, 712 with sufficient strength for structural applicability for connecting the two post-tensioned concrete slabs 710, 716 for structural purposes.
Applications of the embodiments disclosed herein include all aspects of construction, including, but not limited to, buildings, towers, floating terminals, ocean structures and ships, storage tanks, nuclear containing vessels, bridge piers, bridge ducts, foundation soil anchorages, and virtually all other types of installations where normally reinforced concrete may be acceptable.
Preferred embodiments have been described. Those skilled in the art will appreciate that various modifications and substitutions are possible, without departing from the scope of the invention as claimed and disclosed, including the full scope of equivalents thereof.
Number | Date | Country | |
---|---|---|---|
61920580 | Dec 2013 | US |