The present disclosure relates to a co-located base load power source and gas turbine cycle with a heat recovery steam generator and particularly but not exclusively relates to a method of and apparatus for starting a wet gas turbine cycle.
Power plants for the generation of power (e.g. motive or electrical) may for example include nuclear, coal or gas powered plants. Nuclear power plants typically comprise a nuclear generator, which may heat a steam cycle, for example, via a intermediary working fluid. The steam cycle may in turn power a steam turbine. A nuclear power plant typically has very little load following capability, and may therefore operate at a base load. Base load electricity from nuclear plants typically command the lowest selling price. By contrast, gas fired power plants, which typically use gas turbines, may have a better load following capability.
There are many types of gas turbine, for example, simple cycle and advanced cycle gas turbines. A simple cycle gas turbine is able to respond rapidly to load changes, including rapid start up. The rapid response is particularly true for aero-derivatives and 10 minutes is an industry standard rapid start time for engines in the 40-100 MW class. However, simple cycle gas turbine plants have relatively low thermal efficiencies, typically up to around 42-44%.
In this respect, a combined cycle gas turbine power plant, with a separate steam turbine powered by steam generated in a gas turbine exhaust heat exchanger, may provide a higher thermal efficiency, e.g. up to 60%. Other advanced gas turbine cycles involving water, e.g. with steam injection into the gas turbine engine rather than a steam turbine, may also provide higher thermal efficiencies. Examples of such advanced gas turbine cycles are shown in
The water may be injected at points other than those shown in
Such advanced gas turbine cycles do not typically have a rapid start up time. For example, boilers, heat exchangers and steam turbines (in the case of a combined cycle), may suffer high transient thermal stresses. Heat Recovery Steam Generators (HRSG) require typically 15 to 45 minutes to reach full output with steam output ramping up as the HRSG attains full temperature. There is currently no way to achieve a 10 minute start for gas turbine cycles involving steam. Boiler, e.g. HRSG, start times are too long, and other ways of producing steam are very limited. In addition, the gas turbine design capacity must be increased to accept large steam flows, which means its performance is compromised during start when steam is not yet available. It is therefore difficult to combine the rapid start of a simple cycle gas turbine with the higher efficiencies of the advanced gas cycles.
The present invention seeks to address these issues.
According to a first aspect of the present disclosure there is provided a method of starting a gas turbine cycle comprising a gas turbine and a heat recovery steam generator or exhaust gas heat exchanger, the method comprising: heating water in a steam cycle with a base load heat source; powering one or more steam turbines with steam from said steam cycle; and diverting a portion of the steam from the steam cycle to the gas turbine cycle, so that the gas turbine reaches a rated power output more rapidly than without the diversion of the portion of the steam from the steam cycle.
According to a second aspect of the present disclosure there is provided a power generation assembly connectable to a base load heat source arranged to heat water in a steam cycle and power one or more steam turbines, the power generation assembly comprising: a gas turbine cycle comprising a gas turbine and a heat recovery steam generator or exhaust gas heat exchanger; and diverting apparatus configured to selectively divert a portion of steam from the steam cycle to the gas turbine cycle on start up of the gas turbine, so that the gas turbine reaches a rated power output more rapidly than without the diversion of the portion of the steam from the steam cycle.
Steam may be diverted to upstream and/or downstream of a heat recovery steam generator steam flow path. Diversion of the portion of the steam from the steam cycle may be stopped, for example once the gas turbine has reached the rated power output. The portion of the steam from the steam cycle may be diverted at the lowest pressure compatible with the gas turbine. Components of the gas turbine cycle may be preheated with the portion of the steam diverted from the steam cycle.
A first reservoir may be provided in the steam cycle. The first reservoir may be arranged to smooth out variations in the flow in the steam cycle. The first reservoir may be arranged in series in the steam cycle, for example between first and second pumps provided in the steam cycle. Water may be returned from the gas turbine to the first reservoir. Liquid water may be stored in the first reservoir.
A second reservoir may also be provided. The second reservoir may be arranged to store the portion of the steam from the steam cycle for diversion to the gas turbine. The second reservoir may be arranged upstream of one or more of the steam turbines. The second reservoir may be arranged in series with the steam cycle. The second reservoir may be between the base load heat source and one or more of the steam turbines. Alternatively, the second reservoir may be arranged in a branch of the steam cycle parallel with the steam turbine.
The base load heat source may comprise one or more of a nuclear power plant, a coal fired power plant, an oil fired power plant, a hydrogen fired power plant or any other base load heat source. The base load heat source may be operated at substantially full power output during diversion of the portion of the steam from the steam cycle. The gas turbine cycle may comprise a HAT, STIG, TOPHAT, combined cycle or any other water injected cycle. An electrical grid connection may be shared between a first generator connected to the steam turbines and a second generator connected to the gas turbine. Hydrogen may be burned in a combustion chamber of the gas turbine.
For a better understanding of the present invention, and to show more clearly how it may be carried into effect, reference will now be made, by way of example, to the accompanying drawings, in which:
With reference to
The power generation assembly may comprise a gas turbine cycle comprising a gas turbine 9 and a heat recovery steam generator 10. The gas turbine 9 may comprise one or more compressors 2, one or more turbines 4, one or more shafts 6 therebetween and a combustion chamber 8. The gas turbine 9 may further comprise a conventional low cost start system (not shown), e.g. an electric starter motor. The heat recovery steam generator 10 may generate steam from the heat of the gas turbine exhaust and the steam generated may be used to power a steam turbine (e.g. a combined cycle) or be injected into the gas turbine compressors 2, combustion chamber 8, turbines 4 and/or at any point therebetween. For example, steam raised in the heat recovery steam generator 10 may be injected into the combustion chamber 8 and/or high pressure cooling system upstream of the turbines 4. The gas turbine cycle may for example comprise a HAT, STIG, TOPHAT, combined cycle or any other cycle with liquid, e.g. water, and gaseous, e.g. air, components. In particular, the present disclosure may relate to the co-location of a steam injected gas turbine, e.g. STIG, with a nuclear plant.
The steam cycle 22 may comprise one or more steam turbines 24a, 24b, a condenser 26 and one or more pumps 28a, 28b. The steam turbines 24a, 24b, condenser 26 and pumps 28a, 28bmay be arranged in a conventional manner and with piping between the components. The steam cycle may further comprise a first reservoir 32, e.g. an oversized hot well. The first reservoir 32 may be arranged to smooth out variations in the flow in the steam cycle, for example by acting as a buffer. The first reservoir 32 may be arranged in series in the steam cycle 22, for example between pumps 28a, 28b provided in the steam cycle 22. Water may be returned from the gas turbine 9 to the first reservoir 32. Liquid water may be stored in the first reservoir 32.
The power generation assembly may further comprise diverting apparatus 30. The diverting apparatus 30 may comprise one or more valves. In particular, the diverting apparatus may comprise large nuclear quality stop and/or non-return valves to isolate the gas turbine 9 from the steam cycle 22 when the gas turbine is not in use. The diverting apparatus 30 may be configured to selectively divert a portion of steam from the steam cycle 22 to the gas turbine 9 on start up of the gas turbine, so that the gas turbine reaches a rated power output more rapidly than without the diversion of the portion of the steam from the steam cycle.
The portion of the steam diverted from the steam cycle 22 may be diverted to the heat recovery steam generator 10 in order to warm up the heat recovery steam generator. Alternatively, or additionally, the steam diverted from the steam cycle 22 may be injected into the gas turbine compressors 2, combustion chamber 8, turbines 4 and/or at any point therebetween. For example, the diverted steam may be injected into the steam side of the gas turbine cycle upstream and/or downstream of the heat recovery steam generator 10. Water from the gas turbine exhaust may be condensed out and returned to the steam cycle 22. Water collected in this way may be returned to the first reservoir 32. The diverted steam may also be used to preheat other components of the gas turbine 9, for example the compressor, combustor or turbine casings. Such preheating may also reduce overall start time and/or increase equipment life.
Accordingly, the gas turbine cycle comprising a gas turbine 9 and a heat recovery steam generator 10, may be started by: heating water in the steam cycle 22 with the base load heat source 20; powering one or more steam turbines 26 with steam from said steam cycle 22; and diverting a portion of the steam from the steam cycle 22 to the gas turbine 9, so that the gas turbine reaches a rated power output more rapidly than without the diversion of the portion of the steam from the steam cycle 22.
The gas turbine 9 may be started while the base load plant 20 is at full output. Initially steam may be taken from a bleed in the steam turbine 24a, 24b. The steam turbine's power output may therefore be reduced, but this reduction may be offset at least as much by the additional power generated by the gas turbine 9. By taking stored water from the first reservoir 32 the steam cycle 22 and hence base load heat source 20 may see little change in its steam inlet or outlet conditions during the time taken for the gas turbine heat recovery steam generator 10 to reach full output. The gas turbine power output can thus be added to the base load plant power output very quickly without compromising the base load plant steam operation.
The portion of the steam from the steam cycle 22 may be diverted at the lowest pressure from the steam cycle 22 compatible with the gas turbine 9. The pressure of the portion of steam diverted to the gas turbine may be higher than the gas turbine compressor 2 delivery pressure. The diverted steam may be at a pressure of 50 bar (50×105 Pa) or more and at a temperature of approximately 450° C. The diverted flow of steam may be at a flow rate of approximately 20 kg/s. Such a flow rate may be required within minutes of starting the gas turbine 9. Flow of the diverted steam may be reduced after approximately 10 minutes and may be stopped within approximately 45 minutes.
With reference to
With reference to
Power generation plant types are typically located separately and have their own electrical grid connections and other infrastructure. However, the grid connections and other infrastructure all require considerable investment. This is particularly true for nuclear power plants because for safety reasons many important features, including electricity supply, have to be duplicated to provide redundant backup. In the arrangement shown in
Advantageously, the present disclosure allows a rapid gas turbine start up using steam from the base load power plant, e.g. nuclear plant, to feed the gas turbine engine and/or to safely warm the boiler. The present disclosure permits the use of a high efficiency advanced gas turbine cycle in a load following configuration. A cost saving by sharing of features such as the redundant grid connection may also be achieved.
Furthermore, a power plant with a more flexible power output may result. A higher price for any electricity sold, compared to a base load power plant, may thus be achieved. The gas turbine may also provide site backup power, avoiding the cost of additional generating capacity (backup diesels or gas turbines).
The present disclosure may provide a power generation arrangement with high power density (and hence cost effectiveness) and high fuel efficiency, which also may be dispatched within 10 minutes. Such an arrangement may be useful for both emergency grid and base load generation.
The plant could be used to produce energy from stored Hydrogen. This has significantly different combustion characteristics than natural gas, and a further synergy would be the very beneficial use of steam in the gas turbine combustion process, for example by reducing the high combustion temperature of Hydrogen. The Hydrogen could be derived from nuclear power, or exported from another plant, for example electrolysis cells for the creation of sodium hydroxide.