The present invention relates to a power system state estimation device which in order to properly perform monitoring of the state of the entire power system, estimates a power state of any point of the power system with high accuracy, using measurement information of each sensor, and a power system using the same.
Regarding a power system, there has recently been an increasing demand for maintenance of the frequency and voltage at the introduction of a distributed power supply and efficient use of equipment in a power company. Therefore, the need to manage the power state of the voltage, current or the like representing the actual conditions of the power system is further increasing.
In the power state management, the power state of any point of the power system has been estimated by a power flow calculation or a power state calculation method called state estimation, using measurement information of each sensor for measuring a power state, which is provided at a limited point in the power system.
As the background art in the present technical field, there has been described in a Patent Literature 1 that “in the voltage management of each distribution line and operation control, the locations to install measuring instruments necessary to grasp the voltage distribution of the distribution line and the power flow state can be determined such that the best effect (such as the accuracy of a distribution line state calculation) is obtained in a minimum number”.
Further, there has been described in a Patent Literature 2 that “the power flow state of a power distribution system and the error of each measuring device are estimated together from voltage/current measurement values of the power distribution system”.
Furthermore, there has been described in a Patent Literature 3 that “there is provided a state estimation method of a power system, which formulates the weights given to each observation value and reliably converges even in a system having a large variation in impedance”.
PTL 1: Japanese Patent Application Laid-Open No. 2008-72791
PTL 2: Japanese Patent Application Laid-Open No. 2008-154418
PTL 3: Japanese Patent Application Laid-Open No. 63-73831
Considering these known background arts, any of the Patent Literatures 1 through 3 has means for calculating the power state on the basis of the measurement information of the sensors. Therefore, the state estimation accuracy of the power system depends on the sensors. Preferably, a lot of sensors of high accuracy are arranged in the power system. Further, there is desired one higher in accuracy as the estimation method.
For the sensors, in the Patent Literature 1 of them, the optimal installation location is determined in consideration of the estimation accuracy of each power state and cost when adding the sensor in the power system. Further, in the Patent Literature 2, in order to make a high-accuracy operation, the amount of correction of the estimated value is calculated in advance using the deviation between the measurement information of the sensor and the estimated value by the power state calculation, and the estimated value is modified using the correction amount.
However, even in both of the Patent Literatures 1 and 2, the measurement information on all sensors installed in the power system has been uniformly used. Therefore, the estimation accuracy may vary, but this problem is not taken into consideration.
Variation examples are introduced. For example, the estimation accuracy of the voltage is in no small degree related to the power factor that is one of the measurement information of the sensor. Therefore, in an operating time zone of a plant large in load, the power factor near the plant may exhibit characteristics (load characteristics) such as singular values greatly different from other places on the system. Further, when a phase advance capacitor for power factor adjustment is introduced in the factory, singular values rather than specific in the operating time zone may exhibit in a non-operating time zone in reverse.
However, in the power state calculation when only fewer sensors are installed in the system, there is a case where the calculation is performed using information of the singular value as a representative value of a section sandwiched by the sensors. When interpolating the value of the section sandwiched by the sensors, it is considered that if any of the sensors before and after the same exhibits the characteristics such as the singular value, variations occur in the power state estimation value accuracy of the entire power system.
In the Patent Literature 3, a convergent solution is obtained without uniformly using measurement information for all sensors installed in the power system by allowing the measurement information of each sensor to have a weight.
However, the Patent Literature 3 is intended to change the weight depending on the impedance (magnitude fixed according to the power system) of a line branch. The relative weight between the sensors is, so to speak, fixed. Further, the Patent Literature 3 is similar to the Patent Literatures 1 and 2 in that the weight is not brought to zero since the impedance is not zero in the actual power system, and the measurement information for all sensors are used.
As described above, when the load characteristics change dynamically, it is considered that it is difficult to dynamically cope therewith inclusive of the non-use of the measurement information for some sensors.
Thus, an object of the present invention is intended to solve the above problems and is to provide a power system state estimation device which in order to properly perform monitoring of the state of the entire power system, estimates a power state of any point of the power system with high accuracy, using measurement information of some of sensors, and a power system using the same.
The power system state estimation device according to the present invention made to solve the above problems and the power system using the same are characterized in that in a power system having a plurality of sensors for measuring a power state, a sensor exhibiting a peculiar tendency is identified and the power state of any point of the power system is estimated using a sensor excluding the corresponding sensor. A method for identifying a sensor exhibiting a peculiar tendency is proposed.
Specifically, a power system state estimation device is configured as follows:
There is provided a power system state estimation device having a plurality of sensors disposed in respective points of a power system and estimating a state of the power system using the output of the sensors, which includes a power system data database which holds node information indicative of positions in the power system and facility information including the sensors in association with each other, a sensor data database which holds the output of the sensors therein, an estimation environment setting unit which determines a sensor to be used when a power state (in particular, reactive power) at a particular node is estimated, using the information of the power system data database, and a state estimation unit which in correspondence to the sensor used at the particular node determined by the estimation environment setting unit, obtains the output of the sensor from the sensor data database and performs state estimation for the entire power system. The estimation environment setting unit includes a sensor identifying unit for identifying that the sensor installed in the power system is a sensor exhibiting a peculiar tendency, and a sensor changing unit for changing a sensor used to estimate a power state (in particular, reactive power) at a node corresponding to the identified sensor.
Further, a power system is configured as follows:
There is provided a power system including a plurality of sensors disposed in respective points of a power system, a power state control device disposed in each point of the power system and capable of controlling a power state of the power system, a power system state estimation device which estimates a power system state using the output of the sensors, and a power system control central device which provides an operation signal to the power state control device in response to the power system state from the power system state estimation device, characterized in that the power system state estimation device includes a power system data database which holds node information indicative of positions in the power system and facility information including the sensors in association with each other, a sensor data database which holds the output of the sensors therein, an estimation environment setting unit which determines a sensor to be used when a power state at a particular node is estimated, using the information of the power system data database, and a state estimation unit which in correspondence to the sensor used at the particular node determined by the estimation environment setting unit, obtains the output of the sensor from the sensor data database and performs state estimation for the entire power system, and the estimation environment setting unit includes a sensor identifying unit for identifying that the sensor installed in the power system is a sensor exhibiting a peculiar tendency, and a sensor changing unit for changing a sensor used at a node corresponding to the identified sensor.
According to the present invention, in order to properly perform monitoring of the state of the entire power system, the power state of any point of the power system is estimated using the measurement information of the remaining sensors excluding the sensor exhibiting the peculiar tendency, thereby enabling estimation thereof with high accuracy.
According to an exemplary embodiment, since the accuracy of the state estimation is improved, it becomes possible to support a suitable introduction plan of system facilities such as pole transformers, SVR, etc. It is thus possible to improve the utilization efficiency of the facilities.
Further, according to an exemplary embodiment, the optimum control amount of each control device is determined using the estimated power state. As a result, it is possible to reduce the amount of power loss in the power system and the amount of deviation from the specified range of the voltage. The quality of power can hence be maintained.
Exemplary embodiments of the present invention will hereinafter be described using the drawings. In an example 1, a description will be made of an example of a power system state estimation device 3 which estimates a power state of any point of a power system using measurement information of a sensor. In an example 2, a description will be made of an example of a power system using the power system state estimation device 3.
In the present example, a description will be made of an example of a power system state estimation device 3 that estimates a power state of any point of a power system using measurement information of a sensor. However, before its description, a description will be made of a typical power system in which the power system state estimation device 3 is installed.
An example of the typical power system in which the power system state estimation device 3 of the present invention is installed is shown in
In this figure, 20 is a node that represents a point. For example, a node indicating the installation location of a transformer of a substation is 20a, and nodes each indicating the installation location of a utility pole are from 20b to 20h. Incidentally, the utility pole is appropriately provided with devices such as a sensor 22, a pole transformer 23, a voltage adjusting device 25, etc. Further, a sensor 22e is installed in the transformer of the substation. Therefore, for example, the node 20c of the utility pole equipped with the sensor 22a can also be represented as the node of the installation point of the sensor 22a. Likewise, the node 20d of the utility pole equipped with the pole transformer 23a can be expressed as the node of the pole transformer 23a, and the node 20e of the utility pole equipped with the voltage adjusting device 25a can be expressed as the node of the voltage adjusting device 25a.
Further, in this figure, 21 represents a branch that connects between the nodes. Thus, the branch in the power system represents a transmission/distribution line.
Moreover, in
Comparing
In
The flow of rough processing in the power system state estimation device 3 will next be described. First, the estimation environment setting unit 30 reads the power system data related to the facility (facility such as the substation transformer 20, pole transformer 23, voltage adjusting device 25, customers 24, or the like inclusive of the sensor 22) that makes up the power system targeted for state monitoring from the power system data database DB1. In addition, the sensor to be used when performing the power state estimation is set. The state estimation unit 32 reads the measurement information of the sensor set in the estimation environment setting unit 30 from the sensor data database DB2. Further, using this data, the power state (current, voltage, phase or the like) of any point of the power system is calculated by the state estimation calculation.
The present invention is characterized by the processing of the estimation environment setting unit 30. The following description will be made centering on the estimation environment setting unit 30. A process in the state estimation unit 32 can be achieved using the existing known technique through the use of the information from the sensor set by the estimation environment setting unit 30.
An example of power system data used in the estimation environment setting unit 30 is shown in
The power system data is data set in advance according to the configuration of the power system and stored in the power system data database DB1. Incidentally, the data in the typical power system shown in
The data of
Further, a node 20e defined as a node No. 5 is distant 2000 meters from the substation and stored in association with the sensor 22b and the voltage adjusting device 25a as a facility. A node 24a defined as a node No. 9 is distant 1700 meters from the substation and stored in association with the customer 24a as a facility.
Incidentally, since the meaning of the description about other nodes in
The data in
Regarding how to read the data in
Since other branches of
An example of the sensor data stored in the sensor data database DB2 of
The sensor data used in
These sensors are connected to the power system information collecting device 26 through the communication network 27. The sensor data measured by the sensors are collected and stored in the sensor data database DB2 in the power system information collecting device 26. Incidentally, the power system state estimation device 3 manages various data related to the power system inclusive of the sensor data and the power system data.
In
The estimation environment setting unit 30 of
An example of the estimated environmental data is shown in
These estimated environmental data are constructed of the node number and the sensor ID in pairs. This is intended to show that supposing, for example, the load is calculated as the power state of the customer connected to each node, the measurement information of the sensor ID used upon this calculation is used.
In the first estimated environmental data shown in
In the second estimated environmental data shown in
In another example illustrative of the change in the combination in
Incidentally, here, the “sensor exhibiting the peculiar tendency” is a sensor which does not show the correct value due to the environment in which the sensor is put, or shows a peculiar tendency when compared with the average sensor and which has a circumstance such as nonuniformity of the measurement environment. It is not a malfunction of the sensor. For example, the power factor for large customers vicinity may indicate aspects different from the surroundings under the influence of operating states or introduced facilities (phase advance capacitors or the like) for large customers such as plants. Therefore, with the exception of this sensor, the power state estimation of each portion is performed by the combination of
For the identification of the sensor exhibiting the peculiar tendency, it will be described later more specifically inclusive of a determination method. Incidentally, the availability of the load (active power P, reactive power Q) of the customers connected to each node will be described later as the description of the function of the state estimation unit 32.
Thus,
In
In the third estimated environmental data of
For example, the node No. 2 means that both of the immediately upstream sensor 22e and the immediately downstream sensor 22a are used, and a value obtained by multiplying their outputs by 0.5 as weights (uniform loads) respectively and adding the same is used as a measurement signal at this node. Further, for example, the node No. 4 means that both of the immediately upstream sensor 22a and the immediately downstream sensor 22b are used, and a value obtained by multiplying their outputs by 0.8 and 0.2 as different weights (non-uniform loads) respectively and adding the same is used as a measurement signal at this node. What the weight distribution should be done is suitably determined in consideration of the environment of the system.
Incidentally, it is needless to say that when obtaining the third estimated environmental data, some of the sensors descried in
A description will next be made of a method of creating the above estimated environmental data in
<First Estimated Environmental Data Creating Method: Creating Method of First Estimated Environmental Data in FIG. 7>
In this case, the estimated environmental data may be determined in advance by a user such as an administrator of the power system or the like and stored in a predetermined file format. The estimation environment setting unit 30 has the function of supporting the file creation of estimated environmental data such as text editors. In this case, the content of the file format prepared in advance is taken as the first estimated environmental data as it is.
<Second Estimated Environmental Data Creating Method: Creating Method of Second Estimated Environmental Data in FIG. 8>
As a premise of this description, a consumer ID (although not described in
The estimation environment setting unit 30 determines the percentage of the entire power system for each customer type and also determines a representative customer type for each sensor in consideration of the type of customers therearound. Specifically, for example, 70% of all customers are taken to be residential areas in the power system of
Here, the periphery of the sensor means that the straight line distance from the sensor or the extension distance of each wire up to the customer from the sensor is within a predetermined distance. At this time, the representative customer type of the power system is taken as the housing highest in proportion. The sensors (22e, 22b and 22d) in which the representative customer type is housing are selected, and the sensors (22a and 22c) for the other types are not selected. Here, the meaning of “not selected” is to avoid the use of the sensors (22a and 22c) in the table of the first estimated environmental data of
Based on the list of the sensors selected in the above-described manner, the sensor for calculating the reactive power of each of the customers connected to each node is determined. According to the method of determining the sensors for each node, for example, the closest sensor lying on the upstream side (on the substation side) of the target node is determined (excluding the sensors that are not selected above). For example, the sensor 22e is selected for the nodes 1 and 2 as it is. Since the sensor 22a is not selected for the nodes 3 and 4, the sensor 22e nearest on the upstream side is selected. As other nodes are determined in the same manner, the estimated environmental data of
Thus, in the second estimated environmental data creating method for creating the second environmental data in
<Third Estimated Environmental Data Creating Method: Creating Method of Second Estimated Environmental Data in FIG. 8>
Although the second estimated environmental data of
In this case, the estimation environment setting unit 30 refers to the sensor data in addition to the power system data. Here, as illustrated in
A power factor Pf is measured every phase like a A-phase, a B-phase and a C-phase, but an example of handling the average value of three phases is shown as an example. That is, a three-phase average power factor is obtained for each time t•sensor. Incidentally, instead of the three-phase average value, the respective phases may be treated individually. Next, the three-phase average power factor is further averaged in the sensor unit, based on the so-obtained three-phase power factor (Pf ((t)) for each time t•sensor to obtain an average power factor Pfm ((equation 1)) for each sensor and a standard deviation σpf ((equation 2)). Incidentally, n is the number of sensors.
Clustering (cluster analysis) is performed based on the so-obtained average power factor Pfm and standard deviation σpf for each sensor. The sensors are divided into several groups according to the characteristic distribution of the power factor.
As this sensor clustering method, for example, the K-means method may be used. An example of group classification of sensors by the clustering method is shown in
The sensors are classified into groups of 80 and 81 when divided into two groups by the clustering method, based on this. The group 80 includes 22e, 22b and 22d, and the group 81 includes 22a and 22c. Further, it can be seen that 22e, 22b and 22d of the group 80 are located close to each other and high in the degree of showing the same output tendency, whereas 22a and 22c of the group 81 are relatively discrete and high in the degree of showing output tendencies different even as belonging to the group.
As a result, the group 80 becomes a majority that includes three sensors therein. The sensors 22e, 22d and 22d that belong to the group 80 are selected. It turns out that these selected sensors 22e, 22b and 22d are all sensors disposed around the residential area and different in output tendency from the non-selected sensors 22a and 22c lying in the industrial and commercial zones. Thus, the sensors placed under the characteristic distribution of similar power factors are used, thereby resulting in obtaining the estimated solution of the power state stably and with satisfactory accuracy. Based on the list of the sensors selected in this manner, the sensor for calculating the reactive power of each of the customers connected to each node is determined as with the second estimated environmental data creating example.
In the third estimated environmental data creating method, the second estimated environmental data of
<Fourth Estimated Environmental Data Creating Method: Creating Method of Second Estimated Environmental Data in FIG. 8>
Also in the present case, the second estimated environmental data of
The estimation environment setting unit 30 refers to the sensor data in addition to the power system data in a manner similar to the third estimated environmental data creating example. Even here, as with the third estimated environmental data creating example, attention is paid to the average value of the three-phase power factor of each measurement information, and the average power factor Pfm for each sensor is obtained by the equation (1). Next, averaging is further performed for all sensors from the average power factor Pfm thereby to obtain an average power factor PfM for all the sensors. The average power factor PfM for all the sensors is regarded as the representative power factor of the corresponding power system.
Next, among all the sensors, a combination of sensors used for the calculation of node reactive power is determined. In the present example, since there are five sensors (22a, 22b, 22c, 22d and 22e), the number of combinations of sensors is 25−1 (=31) ways (one or more sensors are used).
Then, the average power factor Pfm (i) of each combination is calculated. Here, i is the number of the combination (1 to 31). Of the average power factor Pfm (i) of each combination determined in this way, the combination of the sensors (less than or equal to a predetermined value in terms of a deviation) closer to the average power factor PfM for all the sensors is extracted one or more. Incidentally, the combinations using all the sensors are always extracted because of being close to the average power factor PfM for all the sensors (the deviation is zero).
For the respective combinations of the sensors extracted in this manner, the standard deviation σpf of the average power factor (Pf (t)) of each sensor is obtained by the equation (2) (however, the standard deviation is taken to be zero in the case of one sensor).
Then, the standard deviations of the extracted combinations of sensors are respectively compared, and the combination minimized in standard deviation is selected. When the combination minimized in the standard deviation exists in plural form, there is selected one in which the average power factor Pfm (i) is closest to the average power factor PfM of all sensors. Thus, the sensors having the characteristics (comparable in average and variation) of the similar power factors are used, thus resulting in obtaining an estimated solution of a power state stably and with satisfactory accuracy.
Based on the list of the sensors included in the combination selected in this manner, the sensor for calculating the reactive power of each of the customers connected to each node is determined as with the second and third estimated environmental data creating examples. The estimated environmental data in
<Fifth Estimated Environmental Data Creating Method: Creating Method of Second Estimated Environmental Data in FIG. 8>
Also in the present case, the second estimated environmental data of
The estimation environment setting unit 30 refers to the sensor data in addition to the power system data in a manner similar to the fourth estimated environmental data creating example. Here, using respective three-phase average values of measurement information (three-phase current, voltage and power factor) for each sensor, an average value Sj (t) thereof (average current Ij (t), average voltage Vj (t), average power factor Pij (t)) is calculated in a manner similar to the equation (1).
Here, j indicates the sensor. Next, of all the sensors, the combination of the sensors used in the calculation of node reactive power is determined. In the present example, since there are five sensors (22a, 22b, 22c, 22d and 22e), the number of combinations of sensors is 25−1 (=31) ways (one or more sensors are used).
Then, the estimated environmental data in each combination are respectively created. The creating method of the estimated environmental data is similar to the second estimated environmental data creating method. In determining the sensor for each node, the sensor may be taken to be the closest sensor that is on the upstream side (substation side) of a target node, for example.
Next, for each combination, the power state estimation calculation to be executed in the state estimation unit 32 to be described later is carried out using the created estimated environmental data and sensor data. Thus, for each combination, the estimated value of the power state (current, voltage, power factor, active power, reactive power or the like) of any point of the power system is calculated.
Then, for an evaluation point j (one or more sensor installation points) on the power system defined in advance for a predetermined period, sensor data Sj (t) at a time t is taken to be true, and the sum of deviations between the sensor data and a calculated power state estimation value Eij (t) is calculated as an evaluation value Yi of a combination i by an equation (3), for example.
Here, wj is a weight set for each sensor data. The sensor data Sj and the power state estimation value Eij are a power state of the same type, but may be plural with no need to be necessarily single.
For example, when two types of current and voltage are used, the evaluation value Yi becomes a square sum of respective deviations between the current and voltage. Comparing the evaluation values for each combination calculated in this way, a combination minimal in evaluation value is extracted.
This results in the use of such a sensor that a power state estimation value minimal in deviation from the sensor data is obtained. As a result, it is possible to obtain an estimated solution of a power state stably and with good accuracy. Based on the list of the sensors included in the combination selected in this manner, the sensor for calculating the reactive power of each of the customers connected to each node is determined in a manner similar to the second through fourth estimated environmental data creating examples. The estimated environmental data such as shown in
The foregoing has described the several techniques for obtaining the estimated environmental data in
For example, the estimated environmental data created in the second through fifth estimated environmental data creating methods and stored in the estimated environment data database DB3 should not necessarily be the same for a whole 365 days. It may be possible to create estimated environmental data every day of the week or for each time zone in consideration of an operating period of a plant, commerce or the like, etc.
Alternatively, the estimated environmental data may dynamically be created according to the magnitude of load power (e.g., active power transmitted from the substation) flowing through the power system. The estimated environmental data are created divided into, for example, two cases where the active power of the substation exceeds a predetermined threshold value (heavy load) and is a threshold value or less (light load). Incidentally, the number of estimated environmental data may be increased by increasing the number of threshold values.
By doing as mentioned above, it is possible to perform the state estimation calculation with higher accuracy since the estimated environmental data matched with the load state of the power system is created.
Next, returning to
Although there are several in the way of the state estimation calculation, there is known as the simplest method, one for calculating a power state 120 of any position by linear interpolation such as interpolation, extrapolation or the like, using the position (distance from the substation) of such a sensor as shown in
Incidentally, in the same drawing, the horizontal axis indicates the distance from the substation, and the power state of the vertical axis is for example, a voltage. When the voltages at two points (22e and 22b) are being measured, a straight line 120 connecting these voltages is assumed, and the voltage Vx of any point Px is estimated by linear interpolation such as interpolation or extrapolation.
As another state estimation calculating method, a method using a power equation will be explained using a model system shown in
In the power equation, the formulation of the node (injected power) is first performed. Assuming that a phase difference obtained when the phase angles of the nodes i and j are respectively taken to be θi and θj, is δ (=θi−θj), the active power Pi and reactive power Qi of the node i are represented by equations (4) and (5) respectively.
Next, the formulation of the branch (line power) ij is performed. The active power Pij and reactive power Qij of the branch ij that connects the node i and j are respectively represented by equations (6) and (7).
[Equation 6]
P
ij
=G
ij
|V
i|2−|Vi∥Vj(Gij cos δ+Bij sin δ) (6)
[Equation 7]
Q
ij
=−B
ij
|V
i|2−|Vi∥Vj|(Gij sin δ−Bij cos δ) (7)
Next, the formulation of a state estimation calculation will be described. The state estimation calculation is the problem of determining a state variable x that satisfies the equation (8).
[Equation 8]
z=h(x)+v (8)
where
z: observation value (magnitude of voltage measured by sensor or AMI, node injection power, and power state of branch),
h: non-linear function (Pij, Pij and Qi and voltage Vi formulated in the above),
x: state variable (Vi, δij), and
v: noise included in observation value.
Here, the noise v included in the observation value is regarded as white noise.
In addition, the observed value of the load (active power Pi, reactive power Qi) of the customers connected to each node will be described. Since the active power is measured by AMI (Advanced Metering Infrastructure) by which it is measured separately, its measured value may be used. Since the reactive power is not measured by AMI (AMI measures only active power because it is mainly used for the purpose of automatic metering), the reactive power is determined by an equation (9) from the active power Pi measured by AMI and the power factor Pf measured by the sensor 22 (however, the sign of the reactive power is taken to be positive in the case of a lagging power factor and negative in the case of a leading power factor).
Thus, in order to calculate the equivalent of a measured value of the load (reactive power) of the node, the power factor information of the sensor specified by the estimated environmental data is used.
Upon determining a solution to the state estimation calculation, the initial values of state variables Vi and δij are taken to be 1.0 [pu] and 0.0 [deg] respectively, and their h (x) are obtained by the equations (4) through (7). Here, in the state estimation calculation using the least squares method, an objective function J (x) in an equation (10) is minimized.
Thus, such state variables x (voltage Vi and phase difference δij) as to minimize the sum of squares of weighted deviations of all observation values are determined. Power for the node and branch are determined by the equations (4) through (7) using the state variables. Further, current Iij is also determined by an equation (11).
As described above, the various power states (active power, reactive power, voltage and phase of each node, and active power, reactive power and current of each branch, etc.) are determined in such a manner that the sum of the errors of the sensor data becomes minimal. Therefore, the power state does not necessarily match with the sensor data.
This is because on the assumption that the measurement errors and the errors due to the deviation of the measurement timing, etc. are included in the sensor data, the whole power state is estimated in such a manner that the power states of the entire power system are made coherent well.
As described above, the state estimation unit 32 can calculate the estimated value of the power state of any point in the power system to minimize the deviation between the estimated environmental data created by the estimation environment setting unit 30 and the sensor data, using the estimated environmental data and the sensor data.
As described above, if the power system state estimation device of the present invention is used, the state of any point of the power system can be estimated with high accuracy using the measurement information of some of the sensors in order to take into consideration the dynamic load characteristics of the power system and appropriately perform the monitoring of the status of the entire power system. Further, since the accuracy of the state estimation is improved, it becomes possible to support a suitable introduction plan of system facilities such as pole transformers, SVR, etc. It is thus possible to improve the utilization efficiency of the facilities. Incidentally, there is no choice but to introduce overspec facilities each given a margin of an error when the accuracy is poor.
In the present example, a description will be made of an example of a power system using a power system state estimation device 3.
As shown in the drawing, the power system using the power system state estimation device 3 is comprised of a power system data database DB1, a sensor data database DB2, the power system state estimation device 3, a power state estimation data database DB4, a power system control central device 5, a power system comprised of substations 20 and sensors 22, voltage adjusting devices 25, customers 24, pole transformers 23, etc., a power system information collecting device 26, and a communication network 27.
The devices constituting the power system, the power system state estimation device 3, the power system information collecting device 26 and the power system control central device 5 are connected to the communication network 27. The configuration of
Next, the flow of rough processing in the power system using the power system state estimation device 3 will be described. The power system state estimation device 3 performs a state estimation calculation using real-time sensor data or the like obtained via the communication network 27 and outputs power state estimation data of any point of the power system to the power state estimation data database DB4.
The power system control central device 5 calculates the control amount of each device constituting the power system, using the power state estimation data stored in the power state estimation data database DB4 and gives a control command to each device via the communication network 27, based on the control amount. Each device constituting the power system performs a control operation according to the control command given from the power system control central device 5.
Subsequently, the content or function of each of the remaining parts constituting the power system using the power system state estimation device 3 will be described.
The power state estimation data database DB4 is power state estimation data of any point of the power system outputted from the power system state estimation device 3. The power state estimation data database DB4 includes, for example, the active power, reactive power, voltage and phase of each node, and the active power, reactive power and current of each branch, etc.
The power system control central device 5 calculates the control amount of each device constituting the power system using the power state estimation data stored in the power state estimation data database DB4 and gives a control command to each device via the communication network 27, based on the control amount.
Here, an example of a method for calculating the control amount of each device constituting the power system will be explained using a flowchart of
First, a controllable device connected to the power system is extracted. In the example of
For example, under the premise that controllable devices are those described above, in first Step S110, all combinations of control amount candidates for these devices are set.
Next, in Step S111, in a certain combination, the power state estimation value of the power system when the control amount is commanded is calculated. Upon its calculation, the function of the state estimation unit 32 is used.
Next, in Step S112, an evaluation index is calculated. The evaluation index is calculated using the results obtained by the state estimation calculation, but as the evaluation index, for example, the sum of the amount of power loss and the amount of deviation from the specified range of the voltage in the power system, etc. are exemplified. It is desirable to minimize such an evaluation index in terms of the efficiency of power transmission and distribution and power quality.
Next, in Step S113, the evaluation index is compared to the current evaluation index minimum value. In this case, the evaluation index minimum value (initial value) in the first combination may be taken as an extremely large value on the assumption that it is updated.
As a result of the comparison, when the calculated evaluation index is smaller than the current evaluation index minimum value (Yes in Step S113), the corresponding control amount combination is stored in Step S114, and the evaluation index minimum value is updated to this evaluation index.
When the calculated evaluation index is not smaller than the current evaluation index minimum value (No in Step S113), the flowchart proceeds to Step S115.
Next, in Step S115, a check is made as to whether all combinations have been finished. If all the combinations are not finished (No in Step S115), the flowchart returns to Step S110 to continue the processing.
If all the combinations are finished (Yes in Step S115), the flowchart proceeds to Step S116 where the power system control central device refers to the control amount combination that is the currently-stored evaluation index minimum value and issues a control amount command to each control device.
If done as mentioned above, it is possible for the power system control central device 5 to determine the optimum control amount of each control device using the output of the power system state estimation device 3. As a result, it is possible to reduce the amount of power loss in the power system and the amount of deviation from the specified range of the voltage and maintain the quality of power.
Number | Date | Country | Kind |
---|---|---|---|
2011-209757 | Sep 2011 | JP | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/JP2012/070063 | 8/7/2012 | WO | 00 | 2/20/2014 |