The present disclosure relates to concrete tanks for storing liquefied gases and, more particularly, to methods for manufacturing precast, prestressed concrete tanks for storing liquefied gases.
Many gases, such as methane, nitrogen, and natural gas, are stored at temperatures far below the usual ambient temperatures so that they may be kept in a liquid form. This permits large quantities of the gas to be stored in an otherwise limited volume of space. Such low temperature liquefied gases are usually not maintained at high pressure, but rather are maintained at about atmospheric pressure or under a relatively low pressure. Thus, the storage tank or facility need not be designed for great internal pressure.
Precast, prestressed concrete tanks are well-known for storage of liquefied gases, for example, as described in U.S. Pat. Nos. 3,092,933, 3,633,328, and 3,488,972, all to Closner et al. and assigned to Preload Corp. Typically, precast, prestressed concrete tanks have an inner wall defining a primary tank, and an outer wall defining a secondary tank. The outer wall is prestressed by an application of wire windings under tension around the outer wall. The inner wall is typically constructed of 9% nickel steel or some other type of steel suitable for use at cryogenic temperatures. In some cases, the inner tank may also be precast, prestressed concrete.
During construction of precast, prestressed concrete tanks, when the outer wall is built first, the inner wall must either be inserted through an opening in the top of the tank, or by tunneling underneath the foundation to insert the inner wall from beneath the tank. However, these conventional construction practices for precast, prestressed concrete tanks are complicated and undesirable.
There is a continuing need for a precast, prestressed concrete tank and method that facilitates construction of a primary tank within a secondary tank. Desirably, the precast, prestressed concrete tank and method permits for the construction of the inner wall after the outer wall has been erected, but without requiring insertion through a top of the outer wall, or by tunneling underneath the outer wall.
In concordance with the instant disclosure, a precast, prestressed concrete tank and method that facilitates construction of a primary inner tank within a secondary outer tank, and which permits for the construction of the inner wall after the outer wall has been erected, but without requiring insertion through a top of the outer wall, or by tunneling underneath the outer wall, is surprisingly discovered.
In one embodiment, a precast, prestressed concrete tank includes a primary tank with an inner wall and a secondary tank with an outer wall (precast, prestressed concrete) and wire windings. The primary tank is disposed inside of the secondary tank. The secondary tank has a plurality of first precast outer wall panels, and a temporary construction opening frame. During assembly of the precast, prestressed concrete tank, the temporary construction opening frame defines an access doorway. The temporary construction opening frame is disposed on a foundation base slab and sealed.
In another embodiment, a precast, prestressed concrete tank includes a primary tank having an inner wall, and a secondary tank having an outer wall with wire windings. The primary tank is disposed inside of the secondary tank. The secondary tank includes a plurality of first precast outer wall panels, at least one second precast outer wall panel, and a temporary construction opening frame disposed on a foundation base slab. The temporary construction opening frame has a base section, a pair of column sections, and a header beam section. The temporary construction opening frame is disposed between a pair of the first precast outer wall panels and has two second precast outer wall panels disposed on top of the header beam section. Each of the second precast outer wall panels has a height shorter than a height of the first precast outer wall panels. The temporary construction opening frame has a plurality of clamps. The clamps affix the first wire windings to the temporary construction opening frame. The temporary construction opening frame is sealed with an inner plate, a first layer of shotcrete, an outer plate, and a second layer of shotcrete and further wrapped in an additional phase of wire windings.
In a further embodiment, a method for manufacturing a precast, prestressed concrete tank includes a provision of a plurality of first precast outer wall panels and at least one second precast outer wall panel. The at least one second precast outer wall panel is shorter than each of the first precast outer wall panels. A temporary construction opening frame is also provided. The temporary construction opening frame defines an access doorway and includes a plurality of clamps. The first precast outer wall panels, the at least one second precast outer wall panel, and the temporary construction opening frame are then assembled to provide a secondary tank assembly. The access doorway of the temporary construction opening frame provides access to an interior of the secondary tank assembly. A single phase of wire windings is then wound around at least a portion of the second tank assembly. The wire windings are clamped over the temporary construction opening frame with the clamps. The wire windings over the access doorway of the temporary construction opening frame are then cut, leaving the remainder of the wire windings held in place under tension by the clamps. A primary tank assembly is then assembled within the secondary tank assembly by delivery of components through the access doorway. The access doorway of the temporary construction opening frame is then sealed.
Further areas of applicability will become apparent from the description provided herein. It should be understood that the description and specific examples are intended for purposes of illustration only and are not intended to limit the scope of the present disclosure.
The drawings described herein are for illustration purposes only and are not intended to limit the scope of the present disclosure in any way. The above, as well as other advantages of the present disclosure, will become readily apparent to those skilled in the art from the following detailed description, particularly when considered in the light of the drawings described hereafter.
The following detailed description and appended drawings describe and illustrate various exemplary embodiments of the disclosure. The description and drawings serve to enable one skilled in the art to make and use the disclosure and are not intended to limit the scope of the disclosure in any manner.
In
As shown in
In the embodiments shown in
As shown in
The first precast outer wall panels 8 and the at least one second precast outer wall panel 12 may be fabricated from steel rebar reinforced concrete, as a non-limiting example. Other suitable materials and means for manufacturing the precast wall panels 8, 12 may also be selected, as desired.
With reference to
In certain embodiments, each of the first precast outer wall panels 8 and the at least one second precast outer wall panel 12 may have a substantially rectangular side profile with a slightly arcuate cross section across a width of the panel 8, 12. Advantageously, the curvature of the first precast outer wall panels 8 and the at least one second precast outer wall panel 12 allows for multiple first precast outer wall panels 8 to form the cylindrical structure of the outer wall 32 of the secondary tank 6, as depicted in
With renewed reference to
In particular embodiments, each of has the base section 14, the pair of column sections 16, and the header beam section 18 of the temporary construction opening frame 10 may have hollow channels (not shown) that may be filled with high-strength grout during the construction thereof. The high strength grout is configured to both strengthen the temporary construction opening frame 10 and help integrate the temporary construction opening frame 10 with the panels 8, 12. In particular, the high-strength grout may be a non-shrink, non-bleed grout. The high-strength grout may be selected to have a compression strength at least equal to a compression strength of the concrete used to fabricate the panels 8, 12 of the secondary tank 6.
As shown in
With continued reference to
In particular, the sketch plate 26 may be fabricated from 9% Ni steel, although other suitable materials may also be used. The sketch plate 26 may be welded together around the entire perimeter beneath the eventual outer wall, with a “mirror-8” finished stainless steel plate epoxied to the underside of the sketch plate 26 and resting over the slide bearings.
Likewise, the skirt plate 28 may be fabricated from 9% Ni steel or any other suitable material and welded together around the entire perimeter just outbound of the outer wall 32 and just inbound from the seismic base cables of the foundation base slab 30. As disclosed, the base section 14 of the temporary construction opening frame 10 is integrally fabricated with the skirt plate 28. The skirt plate 28 is welded to the sketch plate 26 to form a bottom corner of the outer wall 32 of the secondary tank 6. The first precast outer wall panels 8 rest inside and abut the bottom corner defined by the sketch plate 26 and the skirt plate 28.
As shown in
During assembly, as also shown in
With reference to
In one non-limiting example, the clamps 34 may each have a pair of clamp bodies 40, for example, as shown in
During assembly, and as shown in
As shown in
For example, the inner plate 46 may be fabricated from 9% Ni steel and is configured to seal the temporary construction opening 20. The inner plate 46 may be welded to the temporary construction opening frame 10. The inner plate 46 may also have a plurality of vertical supports and at least one horizontal support. The various supports leave hollow channels across the surface of the inner plate 46. The first application of shotcrete 48 of the plate assembly 44 may then be disposed on the hollow channels of the inner plate 46.
The outer plate 50 may be fabricated from 9% Ni steel and may likewise be configured to seal the temporary construction opening 20. The outer plater 50 is disposed on the first application of shotcrete 48 and on the temporary construction opening frame 10 where the outer plate 50 is welded to the temporary construction opening frame 10. The outer plate 50 may include two separate plates that are placed approximately parallel to one another. The plates may be welded to both the temporary construction opening frame 10 and the horizontal support of the inner plate 46. The second application of shotcrete 52 is disposed on the outer plate 50.
Where the plate assembly 44 has been installed to seal the temporary construction opening 20, the plate assembly is further spaced apart from the inner wall 22 of the primary tank 4, as also depicted in
Following the application of the second or additional phase of wire windings 54, the additional phase of wire windings may be further covered by shotcrete to thereby complete the constructions of the tank 2, as shown in
The present disclosure further includes the method 100 for manufacturing the precast, prestressed concrete tank 2, as shown in
The method 100 includes a first step 102 of providing the plurality of first precast outer wall panels 8 and the at least one second precast outer wall panel 12. As described, the at least one second precast outer wall panel 12 has the height (H2) that is shorter than the height (H1) of each of the first precast outer wall panels 8. The temporary construction opening frame 10 may also have a height (H3), with a sum of the height (H2) and the height (H3) being roughly equal to the height (H1) in certain embodiments, as shown in
The second step 104 of the method 100 includes providing the temporary construction opening frame 10, as shown in
The method 100 then includes a third step 106 of assembling the first precast outer wall panels 8, the at least one second precast outer wall panel 12, and the temporary construction opening frame 10 to provide the outer wall 32 of the secondary tank 6, as shown in
This assembly under the third step 106 may include a lifting of the first precast outer wall panels 8 with a crane, and a setting the first precast outer wall panels 8 in place around the bottom corner of the base 24. One of the first precast outer wall panels 8 is disposed on the first side of the temporary construction opening frame 10, and another of the precast outer wall panels 8 is disposed on the second side of the temporary construction opening frame 10. The at least one second precast outer wall panel 12 is then disposed on the header beam section 18 of the temporary construction opening frame 10.
The individual first precast outer wall panels 8, the second precast outer wall panels 12, and the temporary construction opening frame 10 are subsequently welded together along their respective welding plates within the panels 8, 12. Shotcrete is then applied between the first precast outer wall panels 8, the second precast outer wall panels 12, and the temporary construction opening frame 10. The shotcrete is also then applied to the entire outer wall 32 defined by the assembled panels 8, 12.
A fourth step 108 in the method 100 includes filling the temporary construction opening with a temporary backing 38. Advantageously, the temporary backing 38 fills the temporary construction opening 20 during subsequent steps of the method 100, which allows the secondary tank 6 to be prestressed with the first stage of wire windings 36.
In particular, as depicted in
The sixth step 112 of the method 100 includes clamping the first phase of wire windings 36 over the temporary construction opening frame 10 and the temporary backing 38. More specifically, the threaded fastener 42 of each of the clamps 34 may be tightened over associated ones of the wire windings 36. The threaded fastener 42 pulls the clamp bodies 40 toward each other to cause the clamping action on the wire winding 36 when disposed in the recess 41 between the clamp bodies 40. The wire windings 36 furthermore may be welded to the clamps 34 to further secure the wire windings 36 to the clamps 34.
The method 100 has a seventh step 114 that includes cutting the first phase of wire windings 34 over the temporary construction opening 20 as defined by the temporary construction opening frame 10. The remainder of the wire windings are held in place under the tension by the clamps 34. As shown in
The eighth step 116 of the method 100 includes a removing of the temporary backing 36 from the temporary construction opening frame 10. Advantageously, after the first phase of wire windings 36 have been cut, the temporary backing 38 may be removed to allow the assembly of the primary tank 4 though the temporary construction opening 20. In particular, preformed wall portions of the primary tank 4 may be inserted through the opening or access doorway 20. The dome 15 is fabricated concurrently with the installation of the secondary tank 6. The dome may also be installed on top of the secondary tank 6 before the primary tank 4 is built within the secondary tank 6, for example, as shown in
The method 100 further includes a ninth step 118 of assembling the primary tank 4 within the secondary tank 6 by delivery and installation of components through the temporary construction opening 20. For this purpose, a ramp 56 may be built adjacent to the temporary construction opening 20 to facilitate the movement of equipment and components for the primary tank 4 inside the secondary tank 6. The primary tank 4 is then assembled within the secondary tank 6 by delivery of the necessary components through the access doorway 20.
Once the primary tank 4 is completed within the secondary tank 6, a tenth step 120 of the method 100 includes a sealing of the access doorway 20 of the temporary construction opening frame 10. The tenth step 120 of sealing the temporary construction opening 20 may specifically include a welding of the inner plate 46 to the temporary construction opening frame 10. The temporary construction opening is then further sealed by the first application of shotcrete 48. The outer plate 50 is then welded to the temporary construction opening frame 10 and the inner plate 46. The second application of shotcrete 52 is then applied over the outer plate 50. An exemplary construction of the plate assembly 44 is also described further hereinabove and shown in
The method 100 then includes an eleventh step 122 of winding additional phases of wire windings 54 around the secondary tank 6, for example, as shown in
A twelfth step 124 of the method 100 may include applying a final layer of shotcrete to the secondary tank 6. Following this final application of shotcrete, the tank 2, as shown in
Various materials and dimensions are described and shown in the drawings, for purposes of illustrating the illustrative embodiment. However, it should be appreciated that one of ordinary skill in the art may select other suitable materials and dimensions for the prestressed reinforced concrete tank 2 without departing from the scope of the present disclosure.
Advantageously, the temporary construction opening frame 10 of the precast, prestressed concrete tank 2 and related manufacturing method facilitates the manufacturing of the precast, prestressed concrete tank 2 without having to resort to tunneling through the bottom of, or lifting of the components through the top of, the secondary tank 6 when manufacturing the primary tank 4.
More specifically, it should be understood that the components forming the primary tank 4 may be inserted through the temporary construction opening 20, which is subsequently sealed so that the secondary tank 6 may be completed following the assembly of the primary tank 4.
From the foregoing description, one ordinarily skilled in the art can easily ascertain the essential characteristics of this invention and, without departing from the spirit and scope thereof, can make various changes and modifications to the invention to adapt it to various usages and conditions.
This application is a continuation application of U.S. patent application Ser. No. 16/695,431, filed on Nov. 26, 2019, which in turn is a divisional application of U.S. patent application Ser. No. 16/211,373, filed on Dec. 6, 2018, now U.S. Pat. No. 10,597,888, issued on Mar. 24, 2020, which in turn claims the benefit of U.S. Provisional Application Ser. No. 62/607,356, filed on Dec. 19, 2017. The entire disclosures of the above applications are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
1467121 | Smith et al. | Sep 1923 | A |
1738521 | Bomhoff | Dec 1929 | A |
3092933 | Closner et al. | Jun 1963 | A |
3146549 | James | Sep 1964 | A |
3280525 | Crowley | Oct 1966 | A |
3407606 | Khan et al. | Oct 1968 | A |
3408784 | Crowley | Nov 1968 | A |
3436052 | Ocampo | Apr 1969 | A |
3488972 | Closner | Jan 1970 | A |
3633328 | Closner et al. | Jan 1972 | A |
3822520 | Cram, Jr. | Jul 1974 | A |
3824751 | Shelander | Jul 1974 | A |
4015383 | Crowley | Apr 1977 | A |
4043089 | Bush et al. | Aug 1977 | A |
4069642 | Hendriks | Jan 1978 | A |
4126976 | Crowley | Nov 1978 | A |
4155967 | South et al. | May 1979 | A |
4270323 | Crowley | Jun 1981 | A |
4365455 | Braine | Dec 1982 | A |
5460462 | Regan | Oct 1995 | A |
5590497 | Moore | Jan 1997 | A |
8336263 | Schultz et al. | Dec 2012 | B2 |
9284114 | Hoyle et al. | Mar 2016 | B2 |
9650800 | Close | May 2017 | B2 |
10975589 | Mehta | Apr 2021 | B2 |
20120023845 | Shockley et al. | Feb 2012 | A1 |
20160046437 | Hoyle et al. | Feb 2016 | A1 |
Number | Date | Country | |
---|---|---|---|
20210079680 A1 | Mar 2021 | US |
Number | Date | Country | |
---|---|---|---|
62607356 | Dec 2017 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16211373 | Dec 2018 | US |
Child | 16695431 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16695431 | Nov 2019 | US |
Child | 17104498 | US |