1. Field of the Invention
The present invention relates to precast composite floor systems.
2. Related Technology
Precast concrete construction is often used for commercial and industrial buildings, as well as some larger residential buildings such as apartment complexes. Precast construction has several advantages, such as more rapid erection of a building, good quality control, and allowing a majority of the building structural members to be precast. Conventional precast structures, however, suffer from several disadvantages, such as being heavy and requiring complex connections between precast members and to the rest of the building structure.
Currently, precast single tee and double tee panels are used for constructing floors. The precast single and double tees are typically eight feet wide and often between 25 and 40 feet long or longer. The single tee sections typically have a deck surface about 1.5 to 2 inches thick and a beam portion extending down from the deck surface along the longitudinal center of the deck. The beam is usually about 8 inches thick and about 24 inches tall.
Double tee panels usually have a deck surface which is about 2 inches thick and have two beams extending down from the deck. The beams are placed about four feet apart running down the length of the panel, and are about 6 inches thick and 24 inches tall. Often, after the single and double tee panels are installed, about 2 or 3 inches of concrete is placed on top of the panels.
Single and double tee panels can be heavy. Heavy floor panels can require heavier columns and beams (i.e., columns and beams with increased strength and structural integral) to support the floor panels and so on, increasing the weight of nearly every structural part of the building structure. Heavier structural elements often use more materials and are thus more expensive, require increased lateral and vertical support, and may limit the height of the building for a particular soil load bearing capacity.
In at least one example, a composite floor panel includes a frame assembly having a base plate, a plurality of first lateral supports secured to the base plate, and a plurality of second lateral supports secured to the base plate. The first lateral supports lie in a first plane and the second lateral supports lie in a second plane. The first plane and the second plane each intersect the base plate and the first plane is disposed at an angle relative to the second plane. The composite floor panel also includes a concrete portion coupled to and supported by the first lateral supports and the second lateral supports.
In at least one example, a composite floor panel includes a frame assembly including a base, a plurality of first supports each having an upper end and a lower end. The lower end of the first supports is coupled to the base. The composite floor panel also includes a plurality of second supports each having an upper end and a lower end. The lower ends of the second supports are coupled to the base. A concrete portion includes a slab portion having a top surface, a first beam portion extending away from the top surface of the slab portion, and a second beam portion extending away from the top surface of the slab portion and being spaced apart from the first beam portion. The upper ends of the first supports are coupled to the first beam portion and the upper ends of the second are coupled to the second beam portion.
A method of forming a composite panel can include securing a plurality of supports to a base plate, positioning a form with respect to the supports, and pouring concrete into the form to form a concrete portion. The concrete portion includes a slab portion with a length and a width, a first beam portion, and a second beam portion spaced apart from each other relative to the width of the slab portion, wherein each of the first beam portion and the second beam portion extend along at least a portion of the length of the slab portion and away from a top surface of the slab portion.
In at least one example, a precast structural floor system includes a plurality of girders and a plurality of composite floor panels. Each composite floor panel includes a concrete portion and a frame assembly. The concrete portion includes a concrete slab having a length and a width, a first beam portion and a second beam portion extending from a top surface of the concrete slab. The first beam portion and the second beam portion can be spaced apart from each other relative to the width of the concrete slab. Each of the first and second beam portion can extend along at least a portion of the length of the concrete slab. The frame assembly includes a base plate and at least one support assembly including first supports extending between the first beam portion and the base plate and second supports extending between the second beam portion and the base plate.
This Summary is provided to introduce a selection of concepts in a simplified form that are further described below in the Detailed Description. This Summary is not intended to identify key features or essential characteristics of the claimed subject matter, nor is it intended to be used as an aid in determining the scope of the claimed subject matter.
Various embodiments of the present invention are shown and described in reference to the numbered drawings wherein:
It will be appreciated that the drawings are illustrative and not limiting of the scope of the invention which is defined by the appended claims. The embodiments shown accomplish various aspects and objects of the invention. It is appreciated that it is not possible to clearly show each element and aspect of the invention in a single figure, and as such, multiple figures are presented to separately illustrate the various details of the invention in greater clarity. Similarly, not every embodiment need accomplish all advantages of the present invention.
The invention and accompanying drawings will now be discussed in reference to the numerals provided therein so as to enable one skilled in the art to practice the present invention. The drawings and descriptions are exemplary of various aspects of the invention and are not intended to narrow the scope of the appended claims.
The present system has several advantages over conventional concrete double tee systems. The biggest advantage is the reduced weight. A conventional concrete double tee system with similar spans and loading conditions would weigh approximately 100% more per square foot than the present invention. Other structural members such as concrete girders and concrete columns that are used with double tee systems are also much heavier than columns used with the present invention. Increased weight of the double tee floor system necessitates larger footings and foundation walls. This is restrictive for taller structures and for construction in areas with poor soil bearing capacity.
The vertical legs or walls of a double tee floor panel are solid and will not allow for passage of mechanical, plumbing or electrical through the Tee, thereby increasing the floor to floor dimension because all of the utilities need to be run below the floor structure. Openings in the stem wall of the present system allow the mechanical, electrical and plumbing to pass through the structure, thereby eliminating the need to run these elements below the floor structure.
The present system also allows for greater flexibility in locating slab penetrations (openings through the floor slab) because the beams are spaced farther apart, typically 8 feet on center versus 4 or 5 feet for the legs of a double tee system.
Double tee systems are assembled by weld plates embedded in each component and must bear on concrete or masonry structures. The current system is bolted into a lighter steel structure which makes it possible to use in mid to high-rise construction.
Conventional steel and concrete composite construction also has several problems which are alleviated by the present invention. Conventional composite floor framing is very labor intensive on site. After installation of the columns for a conventionally framed floor, the rest of the materials for the conventional system are installed individually, and include the girders, joists, metal deck, nelson studs, reinforcing, edge enclosures, and poured concrete. This assembly takes much longer than the present invention due to the precast nature of the present system. With the present invention, tradesmen are able to occupy the floor to complete construction in a much shorter time frame which means shortened overall construction time.
Because of the way the calculations are performed for a conventional composite floor, the concrete that is below the top of the flute in the decking is not used in the composite section, but still contributes to the weight of the concrete in the building and the cost for that material. By precasting the floor panels, the present system has eliminated the need for the metal deck. This eliminates the material and the labor required to weld the steel deck in place.
In normal steel construction, the controlling factor over the size of the steel members is the necessity of the steel framing members to carry the full weight of the wet concrete without any of the concrete strength. In the present invention, the steel beams will be completely shored by the forms while the concrete is wet. This by itself reduces the size of the steel beam and eliminates the need for precambering the beam since the beams aren't required to support the weight of the wet concrete.
Additionally, in normal steel construction the beams are aligned so that the tops of the girders and joists are flush. This is done because the metal deck is placed on the joists and girders and the deck is used as a form for the concrete slab. When calculating the section properties for this system, the distance from the top of steel beam to the middle of the concrete is one of the biggest factors. The present invention places a composite stem wall between the steel beam and the concrete deck, thereby increasing the distance from top of the steel beam to the centerline of the concrete slab. As such, the load-bearing strength and span capabilities of the precast panel system are greatly increased. The present flooring system eliminates a significant amount of steel and concrete material as compared to a conventional poured-in-place system.
In describing the composite flooring system of the present invention, multiple views of the floor panel and girder are shown, including views of the parts thereof and cross-sectional views showing the internal construction thereof. Not every structure of the panel or girder is labeled or discussed with respect to every figure for clarity, but are understood to be part of the panel or girder.
As shown in
The concrete slab 2 is typically 3 inches thick and is supported by and connected to the concrete stem wall 4. The stem wall 4 is connected to the steel beam, which is the lower portion of the tee, by welded studs and/or rebar. The concrete and steel together form a composite floor panel.
When a beam supported at both ends is loaded the top half of the beam is under compression while the bottom half of the beam is under tension. Concrete has high compressive strength but low tensile strength, while steel has high tensile and compressive strength. In the present invention, the concrete slab at the top of the tee is under compression and the steel beam at the lower portion of the tee is under tension. The configuration of materials of the floor panel 15 utilizes the best structural properties of each material, making the panel more efficient.
The stem wall 4, for the majority of the span of the floor, can have large openings 4a, or blockouts. Preferably, 50 percent of the thickness of the floor deck 2 is retained at the top of the stem wall 4, leaving a small ridge as is visible in
Diagonal braces 3 which are welded to the panel beam 1 and embedded weld plates in the slab 2 provide additional support for the slab. In a typical configuration, the floor slab 2 is about 8 feet wide and between 5 and 40 feet long. The concrete floor deck 2 is typically about 3 inches thick. The stem wall 4 is typically between 12 and 36 inches tall. The openings 4a in the stem wall 4 are typically located adjacent the stem wall, and may occupy the entire height of the stem wall if necessary. Thus, for an exemplary 24 inch stem wall 4, the openings 4a may be about 24 inches wide and 24 inches tall and have approximately 12 inch pillars of concrete between the openings. The steel beam 1 is typically about 12 inches tall and between 4 and flinches wide.
As shown in
The girder 16 is typically long enough to support several floor sections as shown in
Panel Construction
The composite panel 15 is cast in steel forms 30, as shown in
The structure of the floor panel 15 is illustrated in
Lifting loops 10 made from reinforcing bar which have been bent into u-shapes are welded to the top flange 1b of the beam at a point between the vertical reinforcing bars 6 where the concrete of the stem wall 4 will be poured to surround the lifting loops 10 and vertical reinforcing bars 6, leaving the tops of the lifting loops uncovered by concrete for lifting the panel with a crane. The length of the lifting loops 10 is approximately 0.25″ less than the distance from the top side of the top flange 1b of the beam 1 to the top surface of the finished concrete slab 2. Lifting loops 10 are spaced at intervals determined by the overall length of the composite panel 15. Typically three lifting loops 10 are used per panel 15, with a minimum of two lifting loops on any single panel.
The beam assembly, consisting of the wide flange beam 1, lifting loops 10 and vertical L-shaped reinforcing bar 6, is then moved to a floor-mounted jig to hold it steady while the horizontal slab reinforcing rebar 8, 9 is tied to the horizontal leg 6a of the L-shaped vertical reinforcing bars 6. Reinforcing bars 9 running parallel to the longitudinal axis of the beam 1 are tied into place using standard tie wire to the underside of the horizontal leg 6a of the L-shaped reinforcing bar 6 which was welded to the beam 1. Horizontal reinforcing bars 8 running perpendicular to the longitudinal axis of the beam 1 are tied to the previously installed horizontal reinforcing bars 9 which are running parallel to the longitudinal axis of the beam 1. Reinforcing bars 8, 9 are cut to a length about two inches shorter than the overall length or width of the slab 2 in which they are to be cast. Horizontal reinforcing bars 8, 9 are typically tied with 16 gauge tie wire at all intersections.
Openings 4a in the concrete stem wall 4 are created by attaching a formed shape to the beam 1 between the vertical reinforcing bars 6. These openings 4a are typically referred to as blockouts. Blockout forms are made using a variety of materials, including but not limited to, styrene foam, rubber, wood and steel. The most common method of blockout form construction is styrene foam blocks which are secured to the beam 1 by use of tape or glue. The blockout forms are coated in form release oil or silicone to prevent it from bonding to the stem wall concrete 4 that is poured around it.
Weld plates 5, 11 are placed into the form bed and secured by tie wire or small bolts to hold the weld plates into position until the concrete has cured sufficiently. These weld plates are also referred to as embedded weld plates or simply as embeds. There are several configurations of weld plates 5, 11 used at different locations in the panel slab 2. The slab edge embed 5 consists of a short length of angle iron 5a, usually eight to twelve inches in length, with two straight reinforcing bars 5b welded to the inside of the angle 5a in a manner so that they extend out in the horizontal plane of the concrete slab 2 once they are placed in the forms. The weld plates 5, 11 are spaced at equal intervals along both sides of the concrete slab 2 and are used to connect adjacent panels 15 to each other at the slab 2 level.
Slab end weld plates 11 consist of short lengths of flat steel bar 11a, usually eight to twelve inches in length, with two L-shaped reinforcing bars 11b welded to one side of the flat bar and positioned so that the long leg of the L-shape will extend outward into the horizontal plane of the concrete slab 2 once they are placed in the forms. Slab end weld plates 11 are used to secure the panel slab 2 to the girder 16 below.
The beam assembly, consisting of the steel wide flange beam 1 with attached vertical reinforcing 6, the horizontal slab reinforcing 8, 9 and the stem wall blockout forms, is lifted and set into the forms which have been sprayed with form release oil. The weld plates 5, 11 have been tied or bolted to the forms and are then in contact with the horizontal reinforcing rebar 8, 9 and all bars of the weld plates 5, 11 are then tied with 16 gauge tie wire to intersecting reinforcing bars at each intersection.
Rebar chairs may be placed under the horizontal reinforcing 9 to maintain the minimum distance between the bottom surface 2a of the concrete slab 2 and the underside of the horizontal reinforcing 9. Rebar chairs are spaced as needed, as determined by visual inspection once the beam assembly has been set in place and all weld plates 5, 11 have been tied securely to the horizontal reinforcing 8, 9.
Concrete is placed in the forms in a manner to ensure that all reinforcing bar 8, 9 is sufficiently covered. The upper surface of the concrete slab 2b is finished to industry standards for concrete floors. Typically the panels 15 are covered by plastic or concrete blankets and heated air is introduced under the forms to accelerate curing of the concrete. Once the concrete has cured sufficiently the panel 15 is lifted out of the forms by the lifting loops 10 attached to the beam 1. The panel 15 is set on a flat, level surface and is held level by blocking, stands or other means acceptable to hold it level without putting excessive stresses on anyone point in the panel 15.
Braces 3 are then welded to the underside of the slab at the slab edge weld plates 5 and run diagonally down to intersect with the vertical web 1d of the wide flange panel beam 1. The brace 3 is welded to the beam 1 and the embed 5 so that in plan view the brace is perpendicular to the longitudinal axis of the panel beam 1. One brace 3 is attached at each slab edge embed 5.
The blockout forms are removed from the beam assembly leaving voids in the concrete stem wall 4. All bolts or tie wire which were used to secure the weld plates 5,11 in place before the concrete was formed and which are projecting from the concrete slab 2 are cut off flush with the bottom surface of the concrete slab 2a.
Girder Construction
As shown in
Lifting loops 10, made from reinforcing bar which has been bent into a u-shape, are welded to the top flange 17b of the beam. The length of the lifting loops 10 is approximately 0.25″ less than the distance from the top side of the top flange 17b of the beam to the top surface of the girder stem wall. Lifting loops 10 are spaced at intervals determined by the overall length of the composite girder 16. A minimum of two lifting loops 10 are used on any single girder 16.
The beam assembly, consisting of the wide flange beam 17, lifting loops 10 and vertical L-shaped reinforcing bar 18, is then moved to a floor-mounted jig to hold it steady while the horizontal reinforcing 19 is tied to the horizontal leg of the I-shaped vertical reinforcing bars 18 which have been welded to the beam 17. Reinforcing bars 19 running parallel to the longitudinal axis of the beam 17 are tied into place using 16 gauge tie wire to the top side of the horizontal leg 18a of the L-shaped reinforcing bar 18 which was welded to the beam 17.
Blockouts or openings 12a in the concrete of the girder 16 are created by attaching a formed shape to the beam 17 between the vertical reinforcing bars 18 which were welded to the beam 17. The blockouts 12a in a girder 16 are formed in the same manner as the blockouts in a panel stem wall 4.
The girder beam assembly is placed into the forms 31 on its side (although they could also be poured vertically. Rebar chairs 14 are used as necessary to keep the rebar 19 away from the form bed. Weld plates 25 (as shown in
Floor Assembly
Once the girders 16 are in position, the panels 15 can be installed. A panel 15 is lifted by a crane secured to the lifting loops 10 which were welded to the panel beam 1 and embedded into the concrete of the stem wall 4. The panel 15 is set into place so that the vertical web 1c of the panel beam 1 is in line with the appropriate shear tab 21. The shear tabs are welded inside the girder beam 17, connecting to the top flange, bottom flange, and web as shown. A separate bolt plate 20 is attached to both the girder shear tab 21 and the panel beam 1 with bolts. The bolted connection transfers all of the gravity forces acting on the panel 15 into the girder beam 17.
Floor panels 15 are connected to each other through the embedded weld plates 5a at the slab edges. Lateral forces are transferred through these connections at the slab edge. As shown in
The underside of the panel slab 2 is attached to the top of the girder 16 by welding the embedded weld plate 11 in the bottom of the slab 2 to the embed weld plate 25 in the top of the girder 16. Once all of the floor panels 15 are in place and all joints have been filled with grout 24 a lightweight topping of concrete 26 is often poured over the floor slabs 2 to provide the final wear surface and level out any variations in the slab elevations.
As illustrated in
In at least one example, the supports 230A-230H are oriented such that the supports 230A-230H are positioned in a common plane as shown more clearly in
As also shown in
The supports 235A-235H can be secured to the base plate 225 in any suitable manner at any number of desired locations. In at least one example, the supports 235A-235H are secured to the base plate 225 in such a manner that junctions of the supports 235A-235H and the base plate 225 lie in a line on the base plate 225. In at least one example, the junctions between the base plate 225 and the supports 235A-235H and the junctions between the base plate 225 and the supports 230A-230H all lie in a common plane on the base plate 225. It will be appreciated that other configurations are also possible.
In addition, one or more of the supports 230A-230H of the first set of lateral support members 215 can be joined at substantially the same location on the base plate 225 as one or more of the supports 235A-235H of the second set of lateral support members 215. In particular, as shown in
As shown in
According to one embodiment of the invention, the first and second sets of lateral support members 215, 220 can be secured to the concrete portion 210 so as to have substantially similar distances between first ends of adjacent supports. For example, in one embodiment, the distance between the first end of support 230A and the first end of support 235A is substantially equal to the distance between the first end of support 230A and the first end of support 230B, which can be substantially equal to the distance between the first end of support 235A and the first end of support 235B, which can be substantially the same distance between the first end of support 230B and the first end of support 230C, and so forth. In another embodiment, the distance between the first end of support 230B and the first end of support 230C is substantially equal to the distance between the first end of support 235B and the first end of support 235C.
As also shown in
In at least one example, the supports 230A-230H, 235A-235H, can be formed of a high-strength material, such as steel. For example, the supports 230A-230H, 235A-235H, can be formed from rolled steel angle members and/or heavy gauge bent shapes. The girder connection plates 247-249 can also be formed of a high-strength material, such as steel, including rolled steel angle members and/or heavy gauge bent shapes.
In at least one example, the base plate 225 can be a steel plate with a thickness of between about ⅜ inch and about ⅝ or more. Further, as shown in
As shown in the illustrated embodiment, a girder connection plate 251 is provided which can be secured to end support 250A, and another girder connection plate 252 is provided which can be secured to a similar end support 250B positioned on the opposing end of the composite panel 200. In the illustrated example, the girder connection plate 251 is positioned beneath the end edge 240 of the concrete portion while girder connection 252 is positioned beneath the opposing end edge 245 of the concrete portion 210. Such configuration can allow the girder connection plates 251, 252 to thereby support opposing ends of the concrete portion 210. Referring again briefly to
Support member 215 can be positioned in a corresponding manner with the position of support members 220, such that adjacent supports can share a common plane. For example,
In the illustrated example, the first lateral portion 270A defines a channel 275 that is adapted to facilitate connection a first composite panel to a second composite panel. The channel 275 is formed by a ledge 277 that is recessed below a plane defined by the top surface 267. A shoulder 280 forms a transition between the ledge 277 and the top surface 267. In the example illustrated in
In the illustrated example, the second lateral portion 270B has a shape that is complimentary to the channel 275 in the first lateral portion 270A to facilitate joining of composite panels together. Accordingly, the second lateral portion 270B can form a tab 285 that includes a shoulder 287 of a shape that is complimentary to the shoulder 280 of the first lateral portion 270A. In at least one example, holes 290 (best seen in
As shown in
Referring again to
As shown particularly in
In at least one example, the foam insulation form 295 can have a shape that is the negative or inverse of the concrete portion 210, including any desired part of the slab portion 260 and/or the first and second beam portions 265A, 265B. Such a configuration can also provide a layer of floor insulation for both sound and temperature. Further, the foam insulation form 295 can also be used to house and otherwise preinstall a radiant floor heating and cooling system as desired. The foam insulation form 295 can be provided separately or can be used during the formation of the slab portion 260 and the first and second beam portions 265A, 265B. One exemplary method of forming the composite panel 200 will now be discussed in more detail. Though various steps will be described in an exemplary order, it will be appreciated that the steps described below can be performed in a different order and some steps can be omitted entirely as appropriate or desired. Further, steps can be combined and/or split as desired.
Referring collectively to
After supports 215,220 and end supports 250A,250B are secured to base plate 225, the foam insulation form 295 is then positioned relative to the supports 230A-230H, 235A-235H, 250A,250B. The foam insulation form 295 can be supported in any suitable manner to maintain the foam insulation form 295 at a desired position and orientation relative to the base plate 225 and the supports 230A-230H, 235A-235H, 250A-250B.
Thereafter, reinforcements such as nelson studs 6, reinforcing rebar 8, 9 (all described above with reference to
In one embodiment, securing the first ends of the supports 215,220,250A,250B to the concrete portion 210 can include forming a beam around at least a portion of the first end of a support. In an alternative embodiment, securing the first end of a support to the concrete portion can include securing at least a portion of the first end of the support to a reinforcement member, such as rebar or a metal plate or some other type of fixture designed to be enclosed within the beam. In this manner, the support is coupled or otherwise connected to the beam and ultimately to the concrete portion. The bolts 282 can also be positioned and/or secured to the reinforcements as desired, or can be simply anchored in the concrete.
Thereafter, the first and second beam portions 265A, 265B and at least a portion of the slab portion 260 can be formed by pouring concrete into the foam insulation form 295. Thereafter, the concrete can be cured and the composite panel 200 can be ready for assembly with other composite panels 200 to form a precast structural floor system 300 (
Accordingly, a composite panel 200 can be formed that includes first and second beam portions 265A, 265B that are thicker than other parts of the concrete portion 210. The first and second beam portions 265A, 265B support the slab portion 260 in two areas and can allow for better support both between the beam portions 265A, 265B and on the cantilever. Further, such a configuration can lead to a stiffer floor while reducing the amount of concrete utilized in other designs, such as some described herein previously. Accordingly, composite panels 200 can be formed that include a frame assembly 205 and a concrete portion 210. The composite panels 200 can then be used to form a pre-cast structural floor system, as will now be discussed in more detail.
Accordingly, as shown in
As shown in
As illustrated in
As the composite panels 200 thus tip, the tab 285 on the second lateral portion 270B of one composite panel 200 is brought into contact with the first lateral portion 270A of an adjacent composite panel 200. As shown in
With the heavy end of one composite panel 200 set onto an adjacent composite panel 200, it can be easier for all of the composite panels 200 to be level, because the composite panels 200 will naturally want to tip onto the connection and once connected will help balance each other out.
Accordingly, the composite panel 200′ can be similar to the composite panel 200 described above except that an arch 400 is formed in the slab portion 260′ between first and second beam portions 265A′, 265B′. Such a configuration can provide a smooth transition between the first and second beam portions 265A′, 265B′, which can reduce stress risers within the slab portion 260′ by reducing sharp corners.
According to an embodiment, a composite floor panel is disclosed comprising a concrete slab, and a frame assembly adapted to support the concrete slab, the frame assembly having a first and second set of support members, wherein each support member has a first end and an opposing second end, wherein each first end of the support members is coupled together and each second end of the support members is coupled to the concrete slab, wherein a first support member of the first set of support members shares a common plane with a first support member of the second set of support members and wherein the first support member of the first set of support members shares a common plane with a second support member of the first set of support members.
According to an embodiment, a composite floor panel is disclosed comprising: (i) a concrete slab, and (ii) a frame coupled to and adapted to support the slab, wherein the frame comprises: (a) a base plate, and (b) a plurality of support members each having a first end and a second end, wherein each of the first ends of the plurality of support members is coupled to the base plate at a common location on the base plate and each of the second ends of the plurality of support members is coupled to the concrete slab at distinct locations on the concrete slab thus causing the plurality of support members to be angled with respect to at least one of the concrete slab or each other.
According to an embodiment, a composite floor panel is disclosed comprising a concrete slab, and a frame assembly adapted to support the concrete slab, wherein the frame assembly comprises a plurality of support members coupled to the concrete slab, wherein the plurality of support members are angled with respect to at least one of the concrete slab and each other, wherein a first support member of the plurality of support members shares a first common plane with a second support member of the plurality of support members and wherein the first support member shares a second common plane with a third support member of the plurality of support members, wherein the first common plane is different than the second common plane.
The present invention may be embodied in other specific forms without departing from its spirit or essential characteristics. The described embodiments are to be considered in all respects only as illustrative and not restrictive. The scope of the invention is, therefore, indicated by the appended claims rather than by the foregoing description. All changes which come within the meaning and range of equivalency of the claims are to be embraced within their scope.
This application is a continuation of U.S. patent application Ser. No. 12/618,380, filed Nov. 13, 2009, now U.S. Pat. No. 8,297,017, which is hereby incorporated herein in its entirety, and which is a continuation-in-part of prior U.S. patent application Ser. No. 12/465,597 entitled PRECAST COMPOSITE STRUCTURAL FLOOR SYSTEM filed May 13, 2009, now U.S. Pat. No. 8,161,691, which claims the benefit of U.S. Provisional Application Ser. No. 61/053,147, filed May 14, 2008 the content of each of which are hereby incorporated by reference in their entirety.
Number | Name | Date | Kind |
---|---|---|---|
644940 | Orr | Mar 1900 | A |
1321213 | Johnson | Nov 1919 | A |
1863258 | Tashijan | Jun 1932 | A |
1891763 | Henderson | Dec 1932 | A |
1979643 | Sahlberg | Nov 1934 | A |
2016616 | Schaub | Oct 1935 | A |
2040578 | Venzie | May 1936 | A |
2171338 | Henderson | Aug 1939 | A |
2184464 | Myers | Dec 1939 | A |
2294554 | Henderson | Sep 1942 | A |
2297952 | Friberg | Oct 1942 | A |
2423695 | Falco | Jul 1947 | A |
2558946 | Bertram | Jul 1951 | A |
2592634 | Hart | Apr 1952 | A |
2675695 | Coff | Apr 1954 | A |
2987855 | Singleton | Jun 1961 | A |
3091313 | Colbath | May 1963 | A |
3103025 | Gassner et al. | Sep 1963 | A |
3110049 | Nagin | Nov 1963 | A |
3210900 | Konrad | Oct 1965 | A |
3257764 | Cripe | Jun 1966 | A |
3282017 | Rothermel | Nov 1966 | A |
3385015 | Hadley | May 1968 | A |
3550332 | Wiesman | Dec 1970 | A |
3555763 | Bloxom | Jan 1971 | A |
3567816 | Embree | Mar 1971 | A |
3683580 | McManus | Aug 1972 | A |
3728835 | McManus | Apr 1973 | A |
3800490 | Conte | Apr 1974 | A |
3841597 | Butts et al. | Oct 1974 | A |
3842558 | Scholz et al. | Oct 1974 | A |
3848381 | Bloxom | Nov 1974 | A |
3885369 | Ott | May 1975 | A |
3893276 | Brown | Jul 1975 | A |
RE29249 | Rice | Jun 1977 | E |
4090336 | Carroll | May 1978 | A |
4115971 | Varga | Sep 1978 | A |
4120131 | Carroll | Oct 1978 | A |
4282619 | Rooney | Aug 1981 | A |
4300320 | Rooney | Nov 1981 | A |
4416099 | Fiergolla et al. | Nov 1983 | A |
4441292 | Ericsson | Apr 1984 | A |
4442648 | Reece | Apr 1984 | A |
4495688 | Longpre et al. | Jan 1985 | A |
4507901 | Carroll | Apr 1985 | A |
4529051 | Stolz et al. | Jul 1985 | A |
4646493 | Grossman | Mar 1987 | A |
4653237 | Taft | Mar 1987 | A |
4700519 | Person et al. | Oct 1987 | A |
4715155 | Holtz | Dec 1987 | A |
4729201 | Laurus | Mar 1988 | A |
4741063 | Diana | May 1988 | A |
4741138 | Rongoe | May 1988 | A |
4781006 | Haynes | Nov 1988 | A |
4885884 | Schilger | Dec 1989 | A |
4912794 | Thivans | Apr 1990 | A |
4942707 | Huettemann | Jul 1990 | A |
4972537 | Slaw | Nov 1990 | A |
4991248 | Allen | Feb 1991 | A |
4993094 | Muller | Feb 1991 | A |
5025522 | Eskew et al. | Jun 1991 | A |
5027713 | Kindmann et al. | Jul 1991 | A |
5029426 | Larson et al. | Jul 1991 | A |
5052309 | Haselwander et al. | Oct 1991 | A |
5131201 | Larson et al. | Jul 1992 | A |
5279093 | Mead | Jan 1994 | A |
5317854 | Yoshida et al. | Jun 1994 | A |
5373675 | Ellison | Dec 1994 | A |
5381635 | Sanger | Jan 1995 | A |
5448866 | Saito et al. | Sep 1995 | A |
5596856 | Lebon | Jan 1997 | A |
5671573 | Tadros et al. | Sep 1997 | A |
5678373 | Franklin et al. | Oct 1997 | A |
5884442 | Breault | Mar 1999 | A |
5924254 | Franklin et al. | Jul 1999 | A |
5930965 | Carver | Aug 1999 | A |
5978997 | Grossman | Nov 1999 | A |
6094878 | Schluter | Aug 2000 | A |
6101779 | Davenport | Aug 2000 | A |
6390438 | McManus | May 2002 | B1 |
6474029 | Cook et al. | Nov 2002 | B1 |
6494008 | Bloem et al. | Dec 2002 | B1 |
6622442 | Kwon | Sep 2003 | B2 |
6668412 | Tadros et al. | Dec 2003 | B1 |
6668507 | Blanchet | Dec 2003 | B2 |
6708362 | Allen | Mar 2004 | B1 |
6709192 | Smith | Mar 2004 | B2 |
6729094 | Spencer et al. | May 2004 | B1 |
6898908 | Messenger et al. | May 2005 | B2 |
6915615 | Won | Jul 2005 | B2 |
7010890 | DeSutter | Mar 2006 | B2 |
7275348 | Desutter | Oct 2007 | B2 |
7448170 | Skendzic et al. | Nov 2008 | B2 |
7779590 | Hsu et al. | Aug 2010 | B2 |
8015771 | LeBlang | Sep 2011 | B2 |
8161691 | Platt et al. | Apr 2012 | B2 |
8201363 | Studebaker et al. | Jun 2012 | B2 |
8429876 | Aburto | Apr 2013 | B2 |
20030093961 | Grossman | May 2003 | A1 |
20030182883 | Won | Oct 2003 | A1 |
20050262786 | Messenger et al. | Dec 2005 | A1 |
20060059835 | Werner | Mar 2006 | A1 |
20060272267 | Mentado-Duran | Dec 2006 | A1 |
20090100794 | Holmes et al. | Apr 2009 | A1 |
20090288355 | Platt et al. | Nov 2009 | A1 |
20100132283 | Platt et al. | Jun 2010 | A1 |
20110196561 | Jorgensen | Aug 2011 | A1 |
20110271617 | Platt et al. | Nov 2011 | A1 |
20110271618 | Platt et al. | Nov 2011 | A1 |
Number | Date | Country |
---|---|---|
3837774 | May 1990 | DE |
0011555 | May 1980 | EP |
922480 | Jun 1947 | FR |
1322754 | Jul 1973 | GB |
8-060776 | Mar 1996 | JP |
11-236743 | Aug 1999 | JP |
2002-356913 | Dec 2002 | JP |
2010-265689 | Nov 2010 | JP |
WO 02090660 | Nov 2002 | WO |
Entry |
---|
ISR and Written Opinion from PCT/US2009/064451, May 13, 2012. |
ISR from PCT/US2011/026744, Dec. 13, 2011. |
ISR from PCT/US2011/026751, Dec. 5, 2011. |
Number | Date | Country | |
---|---|---|---|
20130091794 A1 | Apr 2013 | US |
Number | Date | Country | |
---|---|---|---|
61053147 | May 2008 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 12618380 | Nov 2009 | US |
Child | 13663368 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 12465597 | May 2009 | US |
Child | 12618380 | US |