BACKGROUND OF THE INVENTION
The present invention relates to static building structures, and more particularly, to precast wall panels that may be interconnected to form a core or perimeter wall system for erecting or constructing a high-rise building or other walled structure.
High-rise buildings typically are constructed to have six or more floors or stories above ground level. The design of a high-rise building is usually governed by wind effects. One of the most efficient structural systems to resist wind loads for a high-rise building is an interior or core wall system. Conventional core wall systems for high-rise buildings are typically constructed from concrete (cast-in-place over rebar cages for reinforcement) for each story of the high-rise building. In certain markets, conventional core wall systems incorporate structural steel columns and floor beams erected prior to the construction of the cast-in-place core walls. In these conventional core wall systems, concrete is cast in place over the structural steel columns and floor beams. A concrete core wall system provides a number of benefits compared to a structural steel system. Concrete core walls have higher structural damping than structural steel systems, therefore reducing the amount of sway and drift due to wind loads. Concrete core walls provide increased safety and security for fire stairs, standpipes, and communications systems. Because of these reasons, following the events of Sep. 11, 2001, there has been even more emphasis on the use of concrete core walls systems for erecting or constructing high-rise buildings.
As previously noted, conventional concrete core systems used to erect a high-rise building have been constructed using cast-in-place reinforced concrete, including concrete cast-in-place over a previously erected steel structure. The disadvantages of cast-in-place concrete cores versus structural steel core frames is the labor intensity, extended construction schedule, miss-located embedded plates, and shrinkage and creep effects. Moreover, construction workers often cannot work on a floor or story of a high-rise building while concrete contractors are working on a story above the construction workers due to the risk of falling concrete. Thus, using cast-in-place concrete core wall systems to construct or erect a high-rise building often increases the time required to erect the building and adds costs if other construction workers are idled while the concrete contractors work to form the cast-in-place concrete core wall systems.
Conventional precast modular components (such as those described in U.S. Pat. Nos. 3,952,471; 4,142,340; 6,076,319; 6,301,851; 6,457,281 and 6,493,996) have been used to construct volumetric enclosures such as low rise building structures, rooms, basements, cisterns, factories, retaining walls, and flood control dykes. However, these conventional precast components are not suitable for constructing or erecting a high-rise building. In particular, these conventional precast components, and structures built from such components, lack sufficient strength to resist and transfer wind and gravity loads as present in core wall systems of a high-rise building.
There is therefore a need for precast wall panels and a method of constructing a precast wall system that overcomes the problems noted above and enables the erection of core walls for a high-rise building.
SUMMARY OF THE INVENTION
Systems and methods consistent with the present invention provide precast wall panels that may be interconnected to form a core or perimeter wall system for erecting or constructing a high-rise building or other walled structure. Precast core or perimeter wall systems (hereinafter a “precast wall system”) consistent with the present invention offer an attractive alternative to cast-in-place concrete core systems. Precast wall panels as described herein may be prepared (using concrete or other cementitious material) in advance under controlled conditions providing improved quality control and an opportunity for pre-inspection, verification and correction, if necessary, before being shipped to the construction site, therefore resulting in superior quality products. The precast wall panels also allow construction of a high-rise building even under difficult weather conditions. Furthermore, the construction speed possible with precast wall systems consistent with the present invention reduces construction schedule, minimizes on-site labor costs, and provides significant economy to the high-rise building project.
In accordance with systems consistent with the present invention, a precast wall system is provided. The precast wall system comprises a plurality of interconnected precast panels. Each precast panel has a top end plate, a bottom end plate, a plurality of vertical bars disposed between and attached to the end plates (to effectively function as one means to transfer vertical loads), and a cementitious material (such as concrete) encasing the vertical bars and defining a plurality of sides of the respective panel. In one implementation, a second plurality of the interconnected precast panels are arranged on and vertically adjacent to a first plurality of the interconnected precast panels and the top end plate of each panel corresponding the first plurality is connected to the bottom end plate of a respective one of the panels corresponding to the second plurality. Each of the interconnected precast panels may have a length corresponding to one or more stories of a building.
In addition, in one implementation for vertically connecting the precast panels, the precast wall system may further comprise a panel-to-panel vertical reinforcing member, such as a vertical reinforcing bar or tensioning cable. In this implementation, a first of the first plurality of precast panels has a duct extending from the top end plate of the first panel towards the bottom plate of the first panel. The top end plate of the first panel has a opening extending through the top end plate and in axial alignment with the duct of the first panel. A second of the second plurality of precast panels also has a duct extending from the top end plate of the second panel to the bottom plate of the second panel. The two end plates of the second panel each has a opening extending through the respective plate and in axial alignment with the duct of the second panel. The vertical reinforcing member is disposed in and extends through the duct of the second panel, the opening of the bottom end plate of the second panel, the opening of the top end plate of the first panel and the duct of the first panel.
In one implementation for horizontally connecting the precast panels, a first of the precast panels has a first side plate affixed to a side of the first precast panel and a second of the precast panels has a second side plate affixed to a side of the second precast panel that is adjacent to the first precast panel. The first side plate of the first precast panel is affixed to the second side plate of the second precast panel.
In another implementation for horizontally connecting the precast panels, the precast wall system may include a panel-to-panel horizontal reinforcing member, such as a vertical reinforcing bar or tensioning cable. A first of the first plurality of precast panels has a first duct extending through a first width of the first panel. A second of the second plurality of precast panels has a second duct extending through a second width of the second panel in axial alignment with the first duct of the first panel. The horizontal reinforcing member is disposed in and extends through the first duct of the panel and the second duct of the second panel.
In accordance with systems consistent with the present invention, another embodiment of a precast wall system is provided. The precast wall system comprises a plurality of precast panels. Each precast panel includes a cementitious material (such as reinforced concrete) and has a right side, a left side, a front side and a back side defining a plurality of corner edges extending a height of the respective precast panel. Each precast panel further includes a plurality of structural angles. Each angle is disposed along a respective one of the corner edges of the precast panel. Each angle has a first leg that extends along and is embedded in one of the right side or the left side of the panel and a second leg that extends along and is embedded in one of the front side or the back side of the respective panel. To implement a vertical panel-to-panel connection (in addition to or in lieu of affixing facing end plates of the first and second panels), a first of the precast panels may be arranged vertically on a second of the precast panels and each structural angle of the first precast panel may then be affixed to a corresponding one of the structural angles of the second precast panel. To implement a horizontal panel-to-panel connection, each structural angle of the first precast panel may have a leg embedded on the right side of the first precast panel that is horizontally aligned with and affixed to a corresponding structural angle of another of the precast panels having a leg embedded on the left side of the other precast panel.
Another embodiment of a precast panel is provided, in which the precast panel comprises a cementitious material and has a top end, a bottom end, a front side and a back side. The precast panel further includes a first plurality of lifting lugs. Each lifting lug includes a body and a first end extending and curving away from the body. The body of each lifting lug is configured to be removably attached to one of the front side or back side of the precast panel. The first end of each lifting lug has an attachment point (such as an orifice) for a hoisting rig. The first plurality of lifting lugs are attached in proximity to and spaced about the top end of the precast panel so that the first end of each lifting lug extends beyond and curves away from the top end. In one implementation, the first end of each lifting lug curves away from the top end of the precast panel such that the first end of each lifting lug is effective to capture and guide another vertically adjacent precast panel towards the top end of the precast panel having the first plurality of lifting lugs. In addition, the precast panel having the first plurality of lifting lugs may also have a second plurality of lifting lugs attached in proximity to and spaced about the bottom end of the precast panel. The first end of each of the second plurality of lifting lugs extends beyond and curves away from the bottom end of the precast panel such that the first end of each of the second plurality of lifting lugs effectively captures a top end of another precast panel disposed below the precast panel having the second plurality of lifting lugs.
Other systems, methods, features, and advantages of the present invention will be or will become apparent to one with skill in the art upon examination of the following figures and detailed description. It is intended that all such additional systems, methods, features, and advantages be included within this description, be within the scope of the invention, and be protected by the accompanying claims.
BRIEF DESCRIPTION OF THE DRAWINGS
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate an implementation of the present invention and, together with the description, serve to explain the advantages and principles of the invention. In the drawings:
FIG. 1 is a perspective view of an exemplary precast wall system consistent with the present invention;
FIG. 2 is a perspective view of one story of the precast wall system of FIG. 1 disposed on a foundation;
FIG. 3A is a cross-section view of a precast panel of the precast wall system as shown in FIG. 2, illustrating one embodiment for connecting the precast panel to the foundation;
FIG. 3B is a cross-section view of a precast panel of the precast wall system as shown in FIG. 2, illustrating one embodiment for connecting the precast panel to the foundation;
FIG. 4 is a perspective view the precast wall system of FIG. 1 disposed on cast-in-place wall system;
FIG. 5 is a top view of an exemplary story or floor of the precast wall system of FIG. 1;
FIG. 6 is a side view of the precast wall system of FIG. 1;
FIG. 7 is a vertical cross-sectional view of an exemplary interior panel that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the interior panel has side plates for connecting the interior panel to another horizontally adjacent precast panel and one or more vertical ducts adapted to receive a respective reinforcing bar for vertically connecting the interior panel to another vertically adjacent precast panel;
FIG. 8 is a vertical cross-sectional view of an exemplary opening precast panel that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the opening panel has one or more link beams that define a passage for persons, plumbing, ducts or other mechanical systems;
FIG. 9 is a vertical cross-sectional view of two or more exemplary precast panels that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panels have one or more horizontal ducts adapted to receive a respective reinforcing bar for horizontally connecting the precast panels to each other;
FIG. 10 is a vertical cross-sectional view of another two or more exemplary precast panels that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panels each has a side and a shear key disposed or formed on the side of the respective panel for horizontally mating or aligning the panel to another precast panel;
FIG. 11 is a horizontal cross-sectional view of an exemplary precast panel (e.g., an opening precast panel) that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panel has a plurality of horizontal bars and a plurality of vertical bars encased in concrete within the precast panel;
FIG. 12 is a horizontal cross-sectional view of another exemplary precast panel (e.g., an interior precast panel) that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panel has one or more support members encased in concrete within the precast panel to provide additional strength to the precast panel;
FIG. 13A is a perspective view of two exemplary precast panels of the precast wall system of FIG. 1, where the two precast panels each have end plates that are vertically connected in accordance with one embodiment of the present invention;
FIG. 13B is a side view of the two vertically connected precast panels in FIG. 13A;
FIG. 14A is a vertical cross-sectional view of two exemplary precast panels of the precast wall system of FIG. 1, where the two precast panels each have end plates that are vertically connected in accordance with another embodiment of the present invention;
FIG. 14B is a vertical cross-sectional view of the two vertically connected precast panels in FIG. 14A;
FIG. 14C is a magnified view of the two vertically connected precast panels in FIG. 14B, where one of the end plates is longer than the other to define a weld joint between the two end plates;
FIG. 14D is a magnified view of the two vertically connected precast panels in FIG. 14B, where a lap plate is employed to affix together the end plates of the panels;
FIG. 14E is a magnified view of the two vertically connected precast panels in FIG. 14B, where one of the end plates is beveled to enable a weld joint penetration between the two the end plates of the panels;
FIG. 15 is a magnified view of a vertical bar encased in an exemplary precast panel consistent with the present invention, where the vertical bar is attached to an internal surface of an end plate of the precast panel via a coupler, such as a rebar coupler.
FIG. 16A is a vertical cross-sectional view of two precast panels vertically connected in accordance with the present invention, where the top one of the two precast panels is thinner than the bottom precast panel;
FIG. 16B is a vertical cross-sectional view of another two precast panels vertically connected in accordance with the present invention, where the top one of the two precast panels is thinner than the bottom precast panel and each panel has one or more vertical ducts adapted to receive a respective reinforcing bar for vertically connecting the two panels to each another;
FIG. 17 depicts two precast panels horizontally connected in accordance with the present invention, where an internal surface of at least one of the precast panels includes an embedded beam segment for connecting to a floor beam and an embedded gusset plate for connecting a brace member at an angle diagonal to the internal surface of the precast panel;
FIG. 18A is a vertical cross-sectional view of a portion of one of the precast panels in FIG. 17, illustrating one implementation for connecting a floor beam to the embedded plate in the precast panel and a floor slab to the precast panel;
FIG. 18B is a perspective view of one embodiment of the precast panel in FIG. 18A, illustrating one implementation for connecting a floor slab (disposed over the floor beam) to the precast panel;
FIG. 18C is a perspective view of another embodiment of the precast panel in FIG. 18A, illustrating another implementation for connecting a floor slab (disposed over the floor beam) to the precast panel;
FIG. 19A is a vertical cross-sectional view of the portion of an exemplary precast panel, illustrating one implementation for connecting a floor slab that is not disposed over a floor beam to the precast panel;
FIG. 19B is a perspective view of the precast panel in FIG. 19A, illustrating the connection of the floor slab to the precast panel;
FIG. 20A depicts an exemplary support frame that may be employed between and connecting opposing precast panels in the precast wall system of FIG. 1 in accordance with the present invention;
FIG. 20B depicts one embodiment of the support frame of FIG. 20A in which temporary posts are employed to support the support frame when attached to a foundation, foundation wall, or previously erected precast tier before a first or next level of the precast panels is erected to form the precast wall system;
FIG. 20C depicts one embodiment of one of the temporary posts employed in support the support frame in FIG. 20B;
FIG. 20D depicts another exemplary support frame that may be employed between and connecting opposing precast panels in the precast wall system of FIG. 1 in accordance with the present invention, where another embodiment of temporary posts are used to support the support frame when attached to a foundation, foundation wall, or previously erected precast tier before a first or next level of the precast panels is erected to form the precast wall system;
FIG. 21 depicts one implementation for connecting a diagonal brace of the support frame to an embedded gusset plate of one of the opposing precast panels in the precast wall system of FIG. 1;
FIG. 22A is a horizontal cross-sectional view of another two exemplary precast panels that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panels each has a side and shear keys disposed or formed on the side of the respective panel for horizontally mating or aligning the panel to another precast panel, and in combination with a horizontal reinforcing bar resists large horizontal shear forces perpendicular to the plane of the wall defined by the two precast panels;
FIG. 22B is a horizontal cross-sectional view of another two exemplary precast panels that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where one of the panels has a vertical indentation on the side of the panel that is to be connected with the right panel to form a joint, which when filled with grout fills the indentation to effectively inhibit the passage of flame or hot gases between the joint.
FIG. 23A depicts a vertical cross-sectional front view of another exemplary precast panel that may be employed to construct the precast wall system of FIG. 1 in accordance with the present invention, where the precast panel has a plurality of metal angles, each disposed in proximity to a respective corner of the precast panel such that each metal angle is adapted to connect the precast panel to another horizontally adjacent precast panel;
FIG. 23B depicts a left side view of the precast panel of FIG. 23A and the metal angles affixed thereto;
FIG. 23C depicts a horizontal cross-sectional view of the precast panel of FIG. 23A and the metal angles affixed in proximity to top end corners of the precast panel;
FIG. 24 depicts a precast panel erection aid platform that may be employed to construct a precast wall system in accordance with the present invention;
FIG. 25 depicts angle brackets that may be temporarily attached to ends of precast panels to vertically align the precast panels during the construction process of the precast wall system;
FIG. 26A depicts a front view a precast panel and a plurality of lifting lugs temporarily attached to ends of the precast panel to aid in lifting the precast panel and for guiding the precast panel into alignment with another vertically adjacent precast panel that was previously erected during the construction process of the precast wall system;
FIG. 26B depicts a side view of the precast panel and the lifting lugs shown in FIG. 26A;
FIG. 26C depicts a magnified front view of one lifting lug shown in FIG. 26A as temporarily attached to the precast panel and another lifting lug temporarily attached to another vertically adjacent precast panel, where the two lifting lugs are functioning as guides to aid in the alignment of the two precast panels;
FIG. 26D depicts a magnified side view of two lifting lugs temporarily attached to a front side and a back side of the precast panel shown in FIG. 26A, where the two lifting lugs are functioning as guides to aid in the alignment of the precast panel with another vertically adjacent precast panel;
FIGS. 27A-27C depict a flow chart illustrating an exemplary process for constructing a precast wall system in accordance with the present invention; and
FIG. 28 depicts a sequence of erecting precast panels in a first tier of the precast wall system constructed in accordance with the process illustrated in FIGS. 27A-27C.
DETAILED DESCRIPTION OF THE INVENTION
Reference will now be made in detail to an implementation in accordance with methods, systems, and products consistent with the present invention as illustrated in the accompanying drawings.
The effects of creep and shrinkage can be considerable in tall or high-rise buildings. In a precast wall system consistent with the present invention, these effects are reduced as compared to cast-in-place constructed walls. As disclosed in further detail herein, precast panels consistent with the present invention are pre-formed using a cementitious material such as concrete such that a large portion of the shrinkage of the concrete occurs during the early stages of curing (i.e., before the precast panel is placed or set in the building or structure). During this period, precast panels as disclosed herein have very little restraint at their edges and therefore develop less shrinkage stresses than comparable cast-in-place walls. Because a large portion of the shrinkage occurs before the precast panels are erected to construct or placed in the building, the dimensional changes to the building are reduced particularly the differential movements between the core and perimeter columns. In addition, because the precast panels are initially loaded (e.g., with an additional story structure for the building) after a later curing age than in cast-in-place construction, the effect of creep is also reduced by precast panels consistent with the present invention. Other advantages of the present invention are disclosed or will become apparent in the description to follow.
FIG. 1 is a perspective view of an exemplary precast wall panel system 100 consistent with the present invention. The precast wall system 100 may be erected or constructed on a cast-in-place foundation 50 as shown in FIGS. 2 and 3, or on a standard cast-in-place wall system 60 as shown in FIG. 4. The precast wall system 100 comprises multiple precast panels 102, 104, 106, 108 and 110 that may be interconnected horizontally and vertically to construct multiple core or perimeter walls of multiple stories of a high-rise building. In particular, pluralities or groups (112a, 112b and 112c) of the precast panels 102, 104, 106, 108 and 110 are interconnected horizontally or side-by-side to respectively define one or more stories of a building or core walls for the building. After a first group 112a of the precast panels are erected on a foundation 50 or a lower wall system 60, additional groups 112b and 112c of the precast panels 102, 104, 106, 108 and 110 may be arranged on and vertically interconnected to the lower group (e.g., 112a or 112c in FIG. 1) of precast panels 102, 104, 106, 108 and 110.
In the implementation shown in FIG. 1, each precast panel 102, 104, 106, 108 and 110 in each group 112a, 112b and 112c of precast panels has a length corresponding to two stories of a building such that the precast wall system 100 reflects a six story section. However, the length of each precast panel may vary between groups such that a first group 112a of panels may correspond to one story or more stories, and each succeeding group 112b and 112c may each correspond to the same number or a different number of stories of the building.
Note, for clarity in the discussion to follow, the reference number of the precast panels 102, 104, 106, 108 and 110 is augmented with an “a” designator to indicate that the respective panel 102a, 104a, 106a, 108a or 110a is included in the first group or plurality 112a of precast panels, a “b” designator to indicate the respective panel 102b, 104b, 106b, 108b or 110b is included in the second group or plurality 112b of precast panels, or a “c” designator to indicate the respective panel 102c, 104c, 106c, 108c or 110c is included in the third group or plurality 112c of precast panels.
The precast panels 102, 104, 106, 108 and 110 may correspond to one of three types of panels: an interior panel 102, a corner panel 104, and an opening panel 106, 108 and 110. Each interior panel 102 is disposed between two adjacent panels that may be two other interior panels 102, two corner panels 104, two opening panels 106, 108 or 110, or some combination thereof. Each interior panel 102 preferably has a horizontal rectangular cross-section. However, the interior panel 102 may have another cross-section shape, such as a bowed front side and/or back side. Corner panels 104 are also disposed between two adjacent panels (e.g., two interior panels 102 or two opening panels 106, 108 and 110). In one implementation, each corner panel 104 has a horizontal L-shaped cross-section, enabling walls of the precast wall system 100 to be erected with different orientations (like for example perpendicular walls as shown in FIG. 1). However, corner panels 104 may have a non-right angle shape with sides that define an interior angle that is more or less than 90° (more or less than a right angle) to interconnect core non-orthogonal walls of the precast wall system 100 with a shape that is not rectangular. As described in further detail below, opening panels 106, 108 and 110 have one or more link beams (or beam segments) 114 or 116 that define an opening or gap between the respective opening panel and an adjacent opening panel, where the opening or gap is sufficient to enable a person to pass, or for passage of mechanical, electrical, or plumbing systems. The different precast panels 102, 104, 106, 108 and 110 may be interconnected to each other via one or more of the panel-to-panel vertical connections, horizontal panel-to-panel connections, and/or link beam connections discussed in detail herein.
Each precast panel 102, 104, 106, 108 and 110 has a top end plate (e.g., 702 in FIGS. 7-10, 1306 in FIGS. 13A & 13B, 1406 in FIGS. 14A-14E, and 702 in FIGS. 16A & 16B) and a bottom end plate (e.g., 302 in FIG. 3A, 704 in FIGS. 3B & 7-10, 1308 in FIGS. 13A & 13B, 1408 in FIGS. 14A-14E and 704 in FIGS. 16A & 16B), where the two end plates define a top side 710 and a bottom side 712 of the respective precast panel. The end plates of each precast panel 102, 104, 106, 108 and 110 enable the respective precast panel to be interconnected to a vertically adjacent precast panel. For example, the first group 112a of the interconnected precast panels 102, 104, 106, 108 and 110 shown in FIG. 1 are arranged vertically with the second group 112b of the interconnected precast panels 102, 104, 106, 108 and 110 so that the top end plate 702, 1306 or 1406 of each panel 102a, 104a, 106a, 108a, and 110a corresponding to the first group 112a is connected to the bottom end plate 704, 1308 or 1408 of a respective one of the panels 102b, 104b, 106b, 108b or 110b corresponding to the second group 112b. Implementations of such vertical panel-to-panel connections (between end plates of vertically adjacent precast panels) are discussed in further detail herein. Each end plate of a precast panel 102, 104, 106, 108 or 110 preferably has an acceptable flatness tolerance or an exterior milled surface, enabling transferring of large compression stresses (2000 psi to 6,000 psi) by direct bearing between the end plates of vertically adjacent precast panels 102, 104, 106, 108 or 110. The vertical dimension of the end plates of each precast panel 700, 102, 104, 106, 108 or 110 is determined based on the required forces to be transferred.
Each precast panel 102, 104, 106, 108 and 110 further includes a plurality of vertical bars (e.g., 706 in FIG. 7) disposed between and attached to the end plates and a cementitious material (e.g., 708 in FIG. 7) encasing the vertical bars 706 and defining a plurality of sides (e.g., right side 714, left side 716, front side 718 and back side 720 in FIGS. 1 and 7) of the respective panel. The end plates may be made of steel or other high strength metal or metal alloy. Each vertical bar 706 may be a rebar, a steel rod, or another bar type made from a high strength material that may be used to reinforce cement or concrete.
The cementitious material 708 may be a standard construction cement (such as Portland cement), epoxy-resins without course aggregate, concrete or combination thereof. The cementitious material 708 is reinforced with vertical bars 706 between the respective end plates 302, 702, 704, 1306, 1308, 1406 or 1408. As discussed herein, one or more of the precast panels 102, 104, 106, 108 and 110 may include a plurality of horizontal bars or transverse ties (e.g., 709 in FIG. 7), each of which is connected to (or wrapped around) at least two vertical bars 706 disposed adjacent to opposing sides of the respective panel in order to further reinforce the cementitious material 708 of the panel.
In one implementation, the cementitious material 708 may comprise fiber and particle reinforced concrete. The fibers may be carbon fibers, metal fibers, or other type of fibers arranged within the respective precast panel 102, 104, 106, 108 or 110 according to a predefined orientation (e.g., for long continuous fibers that may be longer than one inch) or a random orientation (for small fibers that less than one inch).
The strength of the cementitious material 708 (e.g., concrete) that is used to form the precast panels 102, 104, 106, 108 or 110 may be determined based on the required force capacity of the respective panel (i.e., to resist the forces resulting from the combination of the loads acting on the building) and to satisfy serviceability requirements (e.g., to limit building wind deflections and accelerations to acceptable values). For example, the cementitious material 708 may be comprised of concrete having compressive strengths in a range of approximately 5,000 psi to approximately 16,000 psi. However, the cementitious material may comprise concrete having higher strengths that may be achieved, for example, with the addition of pozzolan, aggregate or fibers.
The dimensions of the individual precast panels 102, 104, 106, 108 or 110 are typically determined based on the capacity of the lifting and transportation equipment, which generally enable precast structural panels 102, 104, 106, 108 or 110 to be formed to a length or height of two stories (e.g., approximately 20-30 feet). However, with larger capacity lifting and transportation equipment, the precast panels 102, 104, 106108 or 110 may be formed to be higher than three or more stories of a building. In one implementation, the width of the interior precast panels 102 is in a range of approximately 5 to 10 feet. Corner precast panels 104 may have a smaller width in each direction, with an outer dimension of about 4 to 6 feet in each direction. Opening precast panels 106, 108 and 110 have larger widths to accommodate the width of the link beams 114 and 116. The thickness of the precast panels 102, 104, 106, 108 or 110 is based on strength and serviceability requirements for the building to be erected and may vary by story (or by two stories or other story multiple) through the height of the building, with thickness values ranging from about 1 to 4 feet.
As discussed in further detail herein, in one implementation as shown in FIG. 1, the precast wall system 100 may include a bracing system 118 that has one or more support frames 120, 122 or 124 that are each disposed between and attached to a respective first pair of vertically interconnected precast panels (e.g., employed in groups 112a & 112b or groups 112b & 112c of the precast panels) and a respective second pair of vertically interconnected precast panels (e.g., also employed in groups 112a & 112b or groups 112b & 112c of the precast panels) that are disposed opposite to the first pair. The bracing system 118 may be erected in advance of or in conjunction with the first group 112a of the precast panels in order to aid in erecting and bracing subsequent groups 112b and 112c of precast panels. In this implementation of the precast wall system 100, the support frames 120, 122 and 124 employed in the bracing system 118 become an integral part of the lateral force resisting system of the building when connected to the vertically interconnected pairs of precast panels as further described below.
Returning, FIG. 3A is a general cross-section view of a precast panel 200 consistent with the present invention that is representative of one implementation for connecting an interior panel 102, a corner panel 104 or an opening panel 106, 108 or 110 to a foundation 50 or cast-in-place wall 60. As shown in FIG. 3A, the bottom end plate (e.g., 302) of each precast panel 102a, 104a, 106a, 108a and 110a included in the first group 112a of panels (e.g., corresponding to the first two stories of the building) may be anchored to the foundation 50 or a cast-in-place wall 60 using one or more anchor bolts 304 that are disposed in and extend through a respective opening 306 in the bottom end plate 302 and embedded in the foundation or cast-in-place wall 60. The dimensions of the anchor bolts 304 are generally in the range of 1 inch to 4 inches with a yield stress of 36 ksi to 105 ksi for the precast panels. However, anchor bolts 304 having a larger diameter may be used to achieve a greater strength. Moreover, the dimensions of the anchor bolts 304 may vary based on the height, weight or other dimensions of the precast panel 200 in the first group 112a of panels to be anchored to the foundation as well as the panels 102, 104, 106, 108 and 110 to be vertically interconnected to the respective panel 200 in the first group 112a. Shims 308 may also be employed to align or orient the precast panel 200 relative to the foundation or cast-in-place wall 60.
FIG. 3B is a cross-section view of another exemplary precast panel 310 consistent with the present invention that is representative of an alternate implementation for connecting an interior panel 102, a corner panel 104 or an opening panel 106, 108 or 110 to a foundation 50 or cast-in-place wall 60. The precast panel 310 is precast similar to the precast panel 700 described in further detail below. In particular, in the implementation shown in FIG. 3B, the precast panel 310 has a top end plate 702 (not shown in FIG. 3B), a bottom end plate 704 and a plurality of vertical bars 706 disposed between and attached to the end plates 702 and 704 and a cementitious material 708 encasing the vertical bars 706 and defining the right side 714, left side 716, front side 718 and back side 720 of the panel 310 between the top end plate 702 and the bottom end plate 704. The precast panel 310 also has one or more ducts 724 extending from the top end plate 702 of the panel 310 to the bottom plate 704 of the panel 312. The top end plate 702 and the bottom end plate 704 of the precast panel 310 each has one or more openings 726 extending through the respective end plate 702 and 704 and in axial alignment with a respective duct 724 of the precast panel 310.
In the implementation shown in FIG. 3B, to anchor the precast panel 310 to the cast-in-place foundation 50 or wall 60, a top portion 312 of the foundation 50 or wall 60 (which is the last portion to be formed from concrete poured to from the cast-in-place foundation 50 or wall 60) includes a cap plate 314 that serves as a base for vertically connecting precast panels 310. The top portion 312 may correspond to the approximately 10 feet of the foundation 50 or wall under the cap plate 314. The last or top portion 312 of the cast-in-place foundation 50 or wall 60 may be formed to include one or more support posts 316 upon which the cap plate 314 may be disposed before pouring concrete to encase the support posts 316 and forming the top portion 312. Plates 318 having jacking bolts 320 may be disposed on the top of the support posts 316. Prior to pouring the concrete for the top portion 312 of the foundation 50 or wall 60, shims or jacking bolts 320 may be used (by individually threading each bolt 320 through the respective support plate 318) to adjust the level of the cap plate 314 of the foundation 50 or wall 60. Shims (e.g., 308 in FIG. 3A) may also be employed to level the bottom end plate 704 of the precast panel 310 relative to the cap plate 314.
The precast panel 310 may be further aligned to the top portion 312 of the cast-in-place foundation 50 or wall 60 using erection aids as described herein, such as in reference to FIG. 24.
The bottom end plate 704 and the cap plate 314 may be connected or affixed via high strength welding or bolting as described in further detail herein for vertical panel-to-panel connections, such as in reference to FIGS. 13A-13B and 14A-14E.
Alternatively, or in addition to welding or bolting the bottom end plate 704 of the precast panel 310 to the cap plate 314 of the foundation 50 or wall 60, the precast panel 310 may be vertically connected to the cap plate 314 using one or more vertical reinforcing bars or bar segments 728a in a manner similar to the vertical panel-to-panel connection described herein for precast panel 700. In this implementation, each of a first plurality of reinforcing bar segments 728a and 728b may have one end 323 anchored or embedded in the cast-in-place foundation 50 or wall 60 and another end 322 that extends through a respective opening 324 drilled through the cap plate 314. If the reinforcing bar segment 728a is not long enough to extend from the foundation 50 or wall 60 through the duct 724 in the precast panel 310, a bar-to-bar coupler 326 (such as a DYWIDAG THREADBAR® Coupler commercially available from Dywidag-Systems International) may be affixed or threaded to the end 322 of the respective reinforcing bar segment 728a extending through the cap plate 314 before the precast panel 310 is lowered into position atop the cap plate 314 of the foundation 50 or wall 60. Once the cap plate 314 is aligned with the precast panel 310, a second reinforcing bar segment 728b may then be disposed through a respective opening 726 in the top plate 702 of the precast panel 310 and into a respective duct 724 aligned with the opening 726 so that the second reinforcing bar segment 728b may be affixed or threaded to a corresponding coupler 326 to effectively affix the two reinforcing bar segments 728a and 728b together to form one continuous vertical reinforcing bar 728 through the precast panel 310 and anchored in the cast-in-place foundation 50 or wall 60. Additional vertical reinforcing bars 728 may be employed in the same manner to further vertically interconnect the precast panel 310 to the cast-in-place foundation 50 or wall 60 for transfer of forces from upper tier precast panels similarly connected to the precast panel 310 to the foundation 50 or wall 60. Additional precast panels 102, 104, 106, 108 and 110 may be anchored to the cast-in-place foundation 50 or wall 60 in a similar manner as precast panel 310 and horizontally interconnected to from the first group 112a or precast panels in the precast wall system 100 as further described herein.
Turning to FIG. 5, a top view is shown of an exemplary story or floor 500 of the precast wall system 100, in which the precast wall system 100 is employed as all or a portion of the core walls of a building having perimeter walls 502, 504, 506 and 508 connected to the precast panels 102, 104, 106, 108 and 110 corresponding to at least the story or floor 500 of the precast wall system 100. In the implementation shown in FIG. 5, the perimeter walls 502, 504, 506 and 508 are constructed using steel frames 510 and may be interconnected to the back side 720 of the precast panels 102, 104, 106, 108 and 110 employed as core walls of the story or floor 500 of the precast wall system 100 via a floor slab or floor beam spanning from the respective perimeter wall to the precast panel. The floor slab or floor beam is interconnected to the respective precast panel using one of the slab-to-panel connections or beam-to-panel connections further described herein.
FIG. 6 is an exemplary view of the internal side (e.g., side 512 in FIG. 5) of the precast wall system 100 that illustrates exemplary embodiments of interior precast panels 102, corner precast panels 104, and opening precast panels 106, 108 and 110 and horizontal and vertical panel-to-panel connections 602 and 604 between such panels consistent with the present invention. The internal side 512 of the precast wall shown in FIG. 6 also depicts a link beam connection 606 and embedded plates (1102 in FIG. 11) on the front side 718 of the precast panels 102, 106, 108 or 110 employed to implement a beam-to-panel connection 608 (e.g., for supporting an interior floor slab) as further discussed herein. The internal side 512 of the precast wall system 100 further depicts a brace-to-panel connection 610 employed to interconnect to a support frame 120, 122, or 124 for bracing opposing pairs of vertically interconnected precast panels of the precast wall system 100. The internal structure of embodiments of an interior precast panel 102 and opening precast panels 106, 108 and 110 are described in detail with reference to the figures to follow. Except as noted herein, the internal structure and horizontal and vertical interconnections of a corner precast panel 102 may correspond to the embodiments described for an interior precast panel 102.
FIG. 7 is a vertical cross-sectional view of one exemplary embodiment 700 of an interior precast panel 102 that may be employed to construct the precast wall system 100. FIG. 7 also illustrates implementations of a horizontal panel-to-panel connection and implementations of a vertical panel-to-panel connection between an interior precast panel 102 and adjacent precast panels 102, 104, 106 or 108 consistent with the present invention. As shown in FIG. 7, the interior precast panel 700 includes a top end plate 702, a bottom end plate 704, and a plurality of vertical bars 706 disposed between and attached to the end plates 702 and 704 and a cementitious material 708 encasing the vertical bars 706 and defining the right side 714, left side 716, front side 718 and back side 720 of the panel 700 between the top end plate 702 and the bottom end plate 704. The precast panel 700 may also include a plurality of horizontal bars or transverse ties 709, each of which is connected to at least two vertical bars 706 disposed adjacent to opposing sides 714 and 716 of the panel 700.
In the implementation shown in FIG. 7, the interior precast panel 700 has one or more side plates 720a-720f (which may transfer shear, tension, moment, compression, or other forces or some combination thereof) to implement a horizontal panel-to-panel connection with one or two precast panels 750 that are horizontally adjacent to the right side 714 and/or left side 716 of the interior precast panel 700. Each precast panel 750 that is disposed adjacent to and has a horizontal panel-to-panel connection with the interior precast panel 700 may be another interior panel 102, a corner panel 104, or an opening panel 106 or 108. Note, as discussed below, an opening panel 110 has link beams 114 and 116 on both sides of the panel 110 that may be but are not typically interconnected to a side plate 720 as discussed herein for a horizontal panel-to-panel connection.
Each side plate 720a-720f may include one or more shear studs 715 embedded in the cementitious material 708 to further enable the side plate (and, thus, the respective interconnected panels 700 and 750) to resist and transmit shear and other forces that typically are imposed on high-rise buildings. Each side plate 720a-720f may be embedded in the cementitious material 708 of the respective precast panel 700 or 750 such that the plate 720a-720f is approximately flush with the side 714 or 716 of the panel 700 or 750, enabling two adjacent panels 700 and 750 to have no or a minimal spacing between the panels. A fire resistant sealant or grout may be applied to any spacing or joint between the precast panels to inhibit smoke from a fire outside the precast wall system 100 from passing through spacing between precast panels interconnected as disclosed herein. Accordingly, the precast wall system 100 may provide additional safety and security for a fire stairs constructed within the precast wall system 100, such as in conjunction with the bracing system 118 (FIG. 1) of the precast wall system 100.
As shown in FIG. 7, the interior precast panel 700 may have one or more side plates 720a-720c affixed to the left side of the precast panel 700 (e.g., the first precast panel) and the other precast panel 750 (e.g., the second precast panel) has a corresponding one or more side plates 720e-720f affixed to the right side 714 of the other precast panel 750 that is adjacent to the interior precast panel 700. In the implementation shown in FIG. 7 for a horizontal panel-to-panel connection, each side plate 720a-720c on the left side 716 of the interior precast panel 700 is affixed to a corresponding one of the side plates 720d-720f on the right side 714 of the other adjacent precast panel 750 via a respective weld 722, such as a high-strength weld having a strength in a range of 60 ksi to 110 ksi.
In an alternative implementation for a horizontal panel-to-panel connection, each side plate 720a-720f of two adjacent precast panels 700 and 750 (or 102, 104, 106, or 108) has a width (into the page in FIG. 7) that is greater than the thickness of the respective panel 700 or 750, such that each side plate 720a-720f has lip on the front side 718 and back side 720 relative to the respective panel similar to the end plates 1306 and 1308 discussed in reference to FIGS. 13A and 13B below. In this implementation, the lips of each side plate 720a-720f on a first side (e.g., right side 714 or left side 716) of a first precast panel 700, (or 102, 104, 106, or 108) and the lips of each corresponding side plate 720d-720f on an adjacent second side (e.g., left side 716 or right side 714) of a second precast panel 750 may be clamped or bolted together so that the respective side plates of the two adjacent precast panels are affixed to each other to transfer shear, tension, moment, compression or other forces (or some portion thereof) between the two adjacent panels 700 and 750. For example, ¾ inch diameter A325 bolts spaced at 12 inches on center to 1 inch diameter A490 bolts spaced at 4 inches on center may be used to affix together the respective side plates of the two adjacent precast panels.
One implementation of a vertical panel-to-panel connection between the interior precast panel 700 and a vertically adjacent precast panel (e.g., another interior precast panel 102b, an opening precast panel 104b, or a type of opening precast panel 106b, 108b or 110b) is depicted in and described in reference to FIG. 13. In this implementation, the top end plate 702 of the interior precast panel 700 is clamped or bolted to the bottom end plate 704 of the vertically adjacent precast panel (not shown in FIG. 7).
A vertical panel-to-panel connection implemented as described herein using a top end plate and a corresponding bottom end plate of vertically adjacent panels 102, 104, 106, 108 or 110 may be positioned at a floor level of the building, or above the floor level (for example about one to four feet above floor level.
In another implementation of a vertical panel-to-panel connection between the interior precast panel 700 and a vertically adjacent precast panel (e.g., 102b, 104b, 106b, 108b or 110b), the top end plate 702 of the interior precast panel 700 is welded to the bottom end plate 704 of the vertically adjacent precast panel (not shown in FIG. 7).
In yet another implementation of a vertical panel-to-panel connection, the precast panel 700 corresponds to a first interior precast panel 102a of the first group 112a of precast panels in the precast wall system 100. In this implementation, the precast panel 700 has one or more ducts 724 extending from the top end plate 702 of the panel 700 (e.g., the first panel 102a) towards the bottom plate 704 of the respective panel 700. The top end plate 702 of the precast panel 700 (e.g., 102a) has one or more openings 726 extending through the top end plate 702 and in axial alignment with a respective duct 724 of the precast panel 700. A second precast panel (e.g., 102b, 104b, 106b, 108b or 110b in FIG. 1 or 6) of the second group 112b of precast panels also has a duct 724 extending from the top end plate 702 of the second precast panel to the bottom plate 704 of the second panel (e.g., 102b, 104b, 106b, 108b or 110b), such as shown for the panel 700 in FIG. 7. The two end plates 702 and 704 of the second panel (e.g., 102b, 104b, 106b, 108b or 110b) each has one or more openings 726 extending through the respective plate and in axial alignment with a respective duct 724 of the second panel (e.g., 102b, 104b, 106b, 108b or 110b). Each opening 726 of the two end plates 702 and 704 of the second panel 102b, 104b, 106b, 108b or 110b may be the same size or larger than the opening 726 of the top plate 702 of the precast panel 700 (e.g., 102a) to which the second panel is to be vertically connected.
In this implementation of a vertical panel-to-panel connection, the precast wall system also includes one or more vertical reinforcing bars 728. Each reinforcing bar 728 is disposed in and extends through a respective one of the ducts 724 of the second panel 102b, 104b, 106b, 108b or 110b, a respective opening 726 of the bottom end plate 704 of the second panel 102b, 104b, 106b, 108b or 110b, a respective opening 726 of the top end plate 702 of the first panel 700 or 102a and a respective duct of the first panel 700 or 102a. As described in further detail herein, each reinforcing bar 728 may be formed from coupled vertical reinforcing bar segments 728a and 728b to define a single continuous vertical reinforcing bar 728 for implementing a vertical panel-to-panel connection among multiple vertically adjacent precast panels employed in separate tiers 112a, 112b and 112c of the precast wall system 100.
In one implementation, each duct 724 of each of the first panel 700 or 102a and the second panels 102b, 104b, 106b, 108b or 110b is wider than the vertical reinforcing bar 728. In this implementation, a grout or other cement material may be disposed in each duct 724 of each of the first panel 700 or 102a and the second panel 102b, 104b, 106b, 108b or 110b to secure or affix the vertical reinforcing bar 728 to the first and second panels that are vertically connected via the respective reinforcing bar 728. Each end of each vertical reinforcing bar 728 may be anchored to the top side 710 of the second or last precast panel (e.g., 102b or 102c) to be vertically connected via the respective reinforcing bar 728.
In addition, each reinforcing bar 728 may have a length sufficient to extend through three or more vertically adjacent precast panels (e.g., 102a, 102b and 102c) of the precast wall system 100. Thus, each reinforcing bar 728 may have a length corresponding to or greater than the six-story section of the precast wall system 100 depicted in FIG. 1, where each precast panel 102, 104, 106, 108 and 110 has a respective length corresponding to two stories or floors of a building. Because the reinforcing bars 728 bars (which may be formed from coupled bar segments 728a and 728b) extend continuously through multiple vertically aligned precast panels (e.g., 102a, 102b and 102c), they provide vertical continuity throughout the building formed using the precast panels. The bars 728 may comprise or be made entirely of mild or high-strength steel (for example, steel having a strength in a range of 60 ksi to 150 ksi), and used to resist significant tension forces on the walls. The bars 728 may be post-tensioned or not, depending on the expected force levels on the walls formed by the precast panels. The size or diameter of each vertical panel-to-panel reinforcing bar 728 is preferably in the range of about 1 inch to 2½ inch in diameter. However, smaller or larger diameter vertical panel-to-panel reinforcing bar 728 may be used depending on the vertical reinforcement requirements (e.g., axial loads) of the respective precast panel. The number and location of the vertical panel-to-panel reinforcing bars 728 within a precast panel 102, 104, 106, 108 and 110 may vary. However, each precast panel to be vertically interconnected with an adjacent precast panel preferably has two or more bars 728 per panel (to provide redundancy). The vertical panel-to-panel reinforcing bars 728 may be arranged symmetrically about the vertical centerline of the respective panel 102, 104, 106, 108 and 110. In the one implementation shown in FIG. 11, the bars 728 are preferably disposed within the outer quarters of the respective panel with a horizontal bar 709 wrapped around the reinforcing bars 728 to provide lateral support of the bars 728. Each of the vertical reinforcing bars or bar segments 728a and 728b may be a rod or other reinforcing member. In particular, tensioning cables may be used as an alternative to reinforcing bars 728. Tensioning cables may be anchored to a foundation 50 or wall 60 in a similar manner as described herein for reinforcing bars 728 (for example, as described in reference to FIG. 3B). Tensioning cable may also be anchored within or to a precast panel in a similar manner as described for reinforcing bars 728 (for example, as described in reference to FIG. 16B). In addition, tensioning cables or cable segments may be joined via a coupler to form a continuous panel-to-panel vertical reinforcing member as described herein for reinforcing bars 728.
The precast panel 700 (as well as other precast panels 102, 104, 106, 108 and 110 described herein) may be manufactured using forms (not shown in figures) that temporarily hold or retain the end plates 702 and 704 relative to the vertical bars 706 and hold or retain the one or more side plates 720a-720f while the cementitious material 708 is poured inside the forms and allowed to set or cure. In one implementation, tubes or pipes, such as metal or plastic pipes, having a diameter greater than the vertical reinforcing bars 728 may be inserted in and extend between the openings of the end plates 702 and 704 to form the vertical ducts 724 in the precast panel 700 before the cementitious material 708 sets or cures to form the precast panel 700. The tubes or bars are preferably corrugated to aid in the transfer of forces to the respective precast panel 700.
Turning to FIG. 8, a vertical cross-sectional view is shown of an exemplary embodiment 800 of a “left” opening precast panel 106 (as viewed from the internal or front side 718 of the panel) that may be employed to construct the precast wall system 100. Except as noted herein, the opening precast panel 800 may have an internal structure corresponding to an interior precast panel 700. In particular, the opening precast panel includes a top end plate 702, a bottom end plate 704, and a plurality of vertical bars 706 disposed between and attached to the end plates 702 and 704 and a cementitious material 708 encasing the vertical bars 706 and defining the right side 714, left side 716, front side 718 and back side 720 of the panel 800 between the top end plate 702 and the bottom end plate 704. The precast panel 800 may also include a plurality of horizontal bars or transverse ties 709. The precast panel 800 may also be formed to include vertical ducts 724 to receive vertical reinforcing bars 728 for a vertical panel-to-panel connection with a vertically adjacent precast panel 102, 104, 106, 108 or 110.
In the implementation shown in FIG. 8, the opening precast panel 800 has side plates 720d-720f affixed to the right side 714 of the panel 106 to enable the panel 106 to form a horizontal panel-to-panel connection with an adjacent precast panel 102, 104 or 108 in a similar manner as described for the interior precast panel 700. As shown in FIG. 8, the opening precast panel 106 also includes one or more link beams 114a and 114b affixed to the left side 716 of the panel 106. Each link beam 116a and 116b defines a respective passage or opening 802a, 802b, and 802c above and/or below the respective link beam 114a and 114b relative to an adjacent precast panel 108 or 110 to which the link beam 114a and 114b is interconnected. Each link beam 114a and 114b may be spaced along the side 716 of the panel 106 to permit the passage or opening 802a, 802b, and 802c to accommodate persons, plumbing, ducts or other mechanical systems required to pass through the wall formed by the respective panel 106. As discussed in further detail herein, the link beams 114a and 114b may each be employed to support a floor slab for a respective story or level of the building erected using the precast wall system 100.
Note, a “right” opening precast panel 108 as shown in FIGS. 1 and 6 has a similar structure to the opening precast panel 106 except that the panel 108 has side plates 720a-720c affixed to the left side 716 of the respective opening panel 108 and one or more link beams 116a and 116b affixed to the right side 714 of the panel 108 such that each link beam 116a and 116b defines a respective passage or opening 802a, 802b, and 802c above and/or below the respective link beam 114a and 114b relative to an adjacent precast panel 106 or 110 to which the link beam 116a and 116b is interconnected. Similarly, a “left and right” opening precast panel 110 as shown in FIGS. 1 and 6 has a similar structure to the opening precast panel 108 except that the panel 110 has one or more link beams 116a and 116b affixed to the right side 714 of the panel 110 and one or more link beams 114a and 114b affixed to the left side 716 of the panel 110. For clarity and brevity in the discussion, the description herein of link beams 114a and 114b for a left opening precast panel 106 (consistent with panel 800) is applicable to the link beams 116a and 116b of a right opening precast panel 108 and a left and right opening precast panel 110.
As shown in FIG. 8, each link beam 114a and 114b has a first end 804a or 804b encased in the cementitious material 708 of the left opening precast panel 800 or 108 and a second end 806a or 806b extending from the left side 716 of the opening precast panel 800. Similarly, each link beam 116a and 116b of a right opening precast panel 108 (or 902 shown in FIG. 9) has a first end 804a or 804b encased in the cementitious material 708 of the respective panel 108 or 902 and a second end 806a or 806b extending from the right side 716 of the opening precast panel 106. A right opening precast panel 108 (or the right side 714 of an opening panel 110) may be disposed adjacent to a left opening precast panel 106 (or to the left side 716 of an opening panel 110) such that the second ends 806a and 806b of the link beams 116a and 116a of the right opening precast panel 108 (or the right side 714 of the opening panel 110) and the second ends 806a and 806b of the link beams 114a and 114b of the left opening precast panel 106 or 800 (or the left side 716 of the opening panel 110) are disposed in proximity to each other and substantially axially aligned as shown in FIGS. 1 and 7. The second ends 806a and 806b of the link beams 114a and 114b of the left opening precast panel 106 or 110 may then be interlinked or connected to the second ends 806a and 806b of the link beams 116a and 116b of the right opening precast panel 108 or 110, for example, via a respective bolted or welded shear splice plate 808a or 808b. In this implementation, when the first link beam 114a and/or 114b of the left opening precast panel 106 or 110 is disposed in proximity to the second link beam 116a and/or 116b of the right opening precast panel 108 or 110, the respective two link beams 114 and 116 define the gap or opening 802a, 802b, or 802c between the left side 714 (or first side) of the left (or first) opening precast panel 106 or 110 and the right side 716 (or second side) of the right (or second) opening precast panel 108 or 110.
In one implementation, the link beams 114 and 116 may comprise or be made of steel or other high-strength metal or material. In another implementation, the link beams 114 and 116 may be made of the same cementitious material 708 as the precast panel and reinforced using vertical bars 706 and/or horizontal bars 709 in a manner similar to the precast panel 700. The link beams 114 and 116 may have a standard I beam shape or other shape that enables the first end 804a or 804b of the beam 114 or 116 to be embedded and/or anchored in the respective opening precast panel 106, 108 or 110 with enough length to transfer the forces from the link beam 114 or 116 to the precast panel 106, 108 or 110. Each of the link beams 114 and 116 may also have one or more shear studs 715 extending from the portion of the link beam 114 or 116 embedded in the panel to effectively further reinforce the link beam 114 or 116 connection to the precast panel 700 and assist in the transfer of forces from the link beam 114 or 116 to the precast panel 700.
FIG. 9 is a vertical cross-sectional view of two or more exemplary precast panels 900 and 902 that may be employed to construct the precast wall system 100. The precast panels 900 and 902 each has one or more horizontal ducts 904 adapted to receive a respective panel-to-panel horizontal reinforcing bar 906 for horizontally connecting the precast panels 900 and 902 to each other to implement another panel-to-panel horizontal connection alternative in accordance with the present invention. Although the two precast panels 900 and 902 illustrated in FIG. 9 are opening precast panels 106 and 108, this panel-to-panel horizontal connection may be employed to horizontally interconnect any combination of interior, corner, or opening precast panels 102, 104, 106, 108 or 110. In the implementation shown in FIG. 9, each precast panel 900 and 902 of a group of precast panels (e.g., group 112a, 112b or 112c) has a duct 904 extending through a left side 714 to right side 716 width of the respective panel 900 or 902 and in axial alignment with the duct 904 of a horizontally adjacent precast panel 902 or 900. A horizontal reinforcing bar 906 (which may be a rod or other reinforcing member) is disposed in and extends through each of the axially aligned ducts 904 of the horizontally adjacent precast panels 900 and 902. Because the reinforcing bars 906 bars extend continuously through multiple horizontally aligned precast panels 900 and 902, they provide horizontal continuity throughout the building formed using the precast panels. The bars 906 may comprise or be made entirely of mild or high-strength steel, such as steel having a strength of 60 ksi to 150 ksi. The horizontal reinforcing bars 906 are anchored at each end of the group of precast panels 900 and 902 through which the respective bar 906 extends. In the implementation shown in FIG. 9, each horizontal reinforcing bar 906 may have a bar anchor 910 attached to at least one end of the horizontal reinforcing bar 906. The bar anchor 910 has a shape adapted to inhibit the movement of the horizontal reinforcing bar 906 in at least one direction within the ducts 906 of the panels 900 and 902 through which the respective bar 906 extends. In one implementation, the bar anchor 910 has a greater width than the horizontal reinforcing bar 906 to inhibit movement of the reinforcing bar 906 beyond the side 714 or 716 of the precast panel 900 or 902 to which the bar anchor 910 is adapted to engage. The bar anchor 910 may be, for example, a high-strength nut that is affixed to a threaded end 908 of the respective horizontal reinforcing bar 906. In one implementation, a plate functioning as a washer may be placed between the nut and the edge of the precast panel 900 or 902 to further inhibit the movement of the horizontal reinforcing bar 906 beyond the side 714 or 716 of the respective panel.
When the horizontal reinforcing bars 906 are anchored at each end of the group of precast panels 900 and 902 through which the respective bar 906 extends, the ducts 904 through which each bar 906 extends do not need to be grouted. The number (and size) of horizontal reinforcing bars 906 extend through a group of horizontally adjacent panels 900 and 902 and level of post-tensioning of the bars 906 are derived based on a predetermined horizontal compressive (clamping) stress on the panels 900 and 902 that enables the shear forces on the plane of the horizontal connection to be transferred by friction between the panels 900 and 902. The horizontal reinforcing bars 906 may each be a rod or other reinforcing member. In particular, tensioning cables may be used as an alternative to horizontal reinforcing bars 906. Tensioning cables may be anchored at each end of the group of precast panels 900 and 902 in a similar manner as described herein for horizontal reinforcing bars 906. In addition, tensioning cables or horizontal reinforcing bars 906 may be joined via a coupler to form a continuous panel-to-panel horizontal reinforcing member in a similar manner as described herein for reinforcing bars 728.
Turning to FIG. 10, a vertical cross-sectional view of another two or more exemplary, horizontally adjacent precast panels 1000 and 1002 that may be employed to construct the precast wall system 100. The precast panels 1000 and 1002 each has a side 714 or 716 and one or more shear keys 1004 or 1006 disposed or formed on the side of the respective panel for horizontally mating or aligning the respective panel 1000 or 1002 to another precast panel 1002 or 1000. In the example shown in FIG. 10, the first panel 1000 (e.g., an opening precast panel 108) has a first shear key (or set of shear keys) 1004 attached to the right or first side 714 of the first panel 1000. The second panel 1002 (e.g., an interior precast panel 102) has a second shear key (or set of shear keys) 1006 disposed or formed on the left or second side 716 of the second panel 1002 facing the right or first side 714 of the first panel 1000. The second shear key or key set 1006 is formed to complementary mate the first shear key or key set 1004 such that the one or more horizontal ducts 904 of the first panel 1000 are each axially aligned with the corresponding one or more horizontal ducts 904 of the second panel 1002 when the first shear key or key set 1004 is mated to the second shear key or key set 1006. In this implementation of a panel-to-panel horizontal connection shown in FIG. 10 employing mating shear keys 1004 and 1006, the combination of friction (due to a compressive clamping stress) and shear keys 1004 and 1006 enables the transfer of vertical shear forces between the precast panels 1000 and 1002. Employing mating shear keys 1004 and 1006 as described also provides the additional advantage that the required amount of horizontal post-tensioned reinforcement is reduced, as compared to the implementation in which the horizontal reinforcing bars 906 are used to connect adjacent panels 900 and 902 that do not have mating shear keys 1004 and 1006.
Although the two precast panels 1000 and 1002 illustrated in FIG. 10 are depicted as an opening precast panel 108 and an interior precast panel 102, respectively, the mating shear keys 1004 or 1006 may be employed on any two abutting sides 714 and 716 of any combination of interior, corner, or opening precast panels 102, 104, 106 or 108.
FIG. 11 is a horizontal cross-sectional view of an exemplary precast panel 1100 that may be employed to construct the precast wall system 100 in accordance with the present invention. The precast panel 1100 corresponds to an opening precast panel 108 having a link beam 116 embedded a length (L) within the panel 1100. However, the precast panel 1100 also has a plate 1102 embedded on the front side 718 of the panel 1100 for implementing a beam-to-panel connection 608 or a floor slab-to-panel connection 1904 in FIG. 19A as further described herein for opening precast panels as well as interior precast panels 102. As shown in FIG. 11, each plate 1102 has shear studs 1104 embedded in the cementitious material 708 of the precast panel 1100 to enable the respective plate to transfer forces between the precast panel 1100 and the beam or floor slab connected to the precast panel 1100 via the embedded plate 1102. Note, although the embedded plate 1102 is also referenced as a shear plate 1102 herein, one of ordinary skill in the art would recognize that the plate 1102 enables forces in addition to shear forces (e.g., compression, moment or tension forces) to be transferred between the respective precast panel 1100, 102, 104, 106, 108 or 110 and the beam or floor slab to which the precast panel is connected via the embedded plate 1102.
The precast panel 1100 further has a first arrangement of horizontal bars 709, vertical bars 706 connected between the two end plates 702 and 704 of the panel 1100 and vertical panel-to-panel reinforcing bars 728 extending through the precast panel 1100. In this first arrangement, a respective horizontal bar 709 transverses or wraps around a respective set of at least two and preferably four vertical bars 706 or the set of two and preferably four vertical panel-to-panel reinforcing bars 728.
The number of horizontal bars 709, the number of vertical bars 706 and the number of vertical panel-to-panel reinforcing bars 728 are based on the predetermined strength required to resist and transfer the predicted forces and moments on the respective precast panel 1100, 102, 104, 106, 108 or 110. As previously described herein, because the precast wall system 100 may be employed to construct a high-rise building, the precast panels 1100 (and other embodiments of the precast panels 102, 104, 106108 and 110) may be subjected to high axial forces due to gravity loads (such as the self-weight of the structure and imposed loads) and lateral loads (such as wind). For this reason and due to the proportions of panels required for high-rise buildings, the vertically adjacent precast wall panels 102, 104, 106, 108 and 110 may be considered as individual columns. Therefore, the amount of vertical reinforcement (i.e., the number of vertical bars 706 and the number of vertical panel-to-panel reinforcing bars 728) is based on the predetermined strength required to resist and transfer the imposed forces and moments. For precast panels 102, 104, 106, 108 and 110 in which the predicted axial and moment load force levels are relatively small, minimum amounts of reinforcement are required, and the number of vertical bars 706 and vertical panel-to-panel reinforcing bars 728 may be based on applicable building codes for reinforced concrete walls or foundation. Thus, the amount of vertical reinforcement (i.e., the combination of vertical bars 706 and vertical panel-to-panel reinforcing bars 728) may range from approximately 0.12 percent to 8 percent of the horizontal cross section of the precast panel as shown in FIG. 11.
Horizontal bars 709 may be provided to enclose and laterally support the vertical bars 706. Horizontal bars 709 also provide additional strength to the precast panel 1100, 102, 104, 106, 108 and 110 for resisting horizontal shear forces and torsional moments (moments acting in the direction of the vertical axis of the respective panel). For precast panels 1100, 106, 108 and 110 with embedded steel link beams (i.e., opening precast panels), small openings 1106 are formed through the beam web 1108 to allow passing of the horizontal bars 709.
As previously noted, grout or other cement material may be inserted into the vertical ducts 726 through which the vertical panel-to-panel reinforcing bars 728 extend in order to affix the bars 728 within the ducts 726 of the respective precast panels 102, 104, 106, 108 and 110.
FIG. 12 is a horizontal cross-sectional view of another exemplary precast panel 1200 (e.g., an interior precast panel 102) that may be employed to construct the precast wall system 100 in accordance with the present invention. The precast panel 1200 has a support member or column 1202 disposed vertically within the precast panel 1200 and encased in the cementitious material 708 between the two end plates 702 and 704 (not shown in FIG. 11) of the panel of the panel to provide additional strength to the precast panel 1200. The support member 1202 may have a non-circular shape that is different than the vertical bars 706 or 728 and extends vertically within the panel 1200. In the implementation shown in FIG. 12, the support member 1202 has an I shape and includes headed shear studs 1204 extending laterally from the I shape portion of the support member 1202. Although not shown in FIG. 12, respective ends of the support member or column 1202 may be welded or bolted to the top and bottom end plates 702 and 704 of the precast panel 1200. The support member or column 1202 may comprise or be made of steel or other high-strength material (e.g., having a yield strength of 36 ksi to 65 ksi) to provide the panel 1200 with additional strength. The non-circular shape of the support member or column 1202 provides further reinforcement to the precast panel 1200. Therefore, the support member or column 1202 reduces the amount of vertical bars 706 needed in the precast panel 1200 to meet the same predetermined strength as required for the precast panel 1100. Thus, employing the support member or column 1202 in the precast panel 1200 as shown and described is particularly useful when the predicted axial stresses on the panel are significant (e.g., service stresses up to 6,000 psi), and the amount of vertical reinforcement required is rather large.
Building codes may specify the location and minimum amounts of vertical and horizontal rebar reinforcement for cast-in-place concrete columns with encased steel members (i.e., composite columns). The combination of vertical bars 706 and vertical reinforcing bars 728 of the precast panel 1200 comprises an area of at least 0.4% of the horizontal cross sectional area of the panel 1200. The support member 1202 (when employed) preferably comprises an area of at least 1% of the horizontal cross sectional area of the panel 1200. In the implementation shown in FIG. 12, the vertical reinforcing bars 728 are disposed at every corner of the panel 1200 and vertical bars 706 are spaced apart no further than one-half the thickness (T) of the precast panel 1200. In this implementation, the precast panel 1200 has a total area of vertical reinforcement (grouted reinforcing bars 728 and vertical bars 706) of at least 0.4% of the panel's 1200 cross sectional area. Horizontal bars 709 may be provided to enclose and laterally support the vertical bars 706 and the vertical panel-to-panel reinforcing bars 728.
FIGS. 13A and 13B depict one implementation for a vertical panel-to-panel connection 604 between two exemplary precast panels 1302 and 1304 of the precast wall system 100. The two precast panels 1302 and 1304 are representative of any vertically adjacent combination of an interior panel 102, a corner panel 104, and an opening panel 106, 108 or 110. The lower precast panel 1302 has a top end plate 1306 that is aligned with and affixed to a bottom end plate 1308 of the upper precast panel 1304. In this implementation, the top end plate 1306 and the bottom end plate 1308 each has a width (Wplate) that is greater than the thickness (TU or TL) of the respective vertically adjacent upper panel 1304 and lower panel 1302 such that each end plate 1306 and 1308 has a lip 1312 or 1314 on the front side 718 and back side 720 relative to the respective panel 1306 and 1308. In this implementation of a vertical panel-to-panel connection 604, the lips 1312 of the bottom end plate 1306 and the lips 1314 of the top end plate 1308 are affixed to each other using high-strength bolts 1310 that are inserted through bores in the lips 1312 and 1314 of the end plates 1306 and 1308. The end of each bolt 1310 may be affixed to a corresponding nut (not shown in the figures) to further secure the ends plates 1306 and 1308 to each other.
FIGS. 14A and 14B depict a vertical cross-sectional view of two exemplary precast panels 1402 and 1404 of the precast wall system 100 that may employ one of the vertical panel-to-panel connections depicted in FIGS. 14C, 14D and 14E to vertically interconnect the panels 1402 and 1404. The two precast panels 1402 and 1404 are representative of any vertically adjacent combination of an interior panel 102, a corner panel 104, and an opening panel 106, 108 or 110. The lower precast panel 1402 has a top end plate 1406 that may be affixed to a bottom end plate 1408 of the upper precast panel 1404 in accordance with one of the implementations depicted in FIG. 14C, 14D or 14E. In the implementation depicted in FIG. 14C, the top end plate 1406 of the lower precast panel 1402 is longer than the bottom end plate 1408 of the higher precast panel 1404, defining a gap 1410 between the two end plates 1406 and 1408 to support a high strength weld joint 1412 that affixes the two end plates 1406 and 1408 to each other.
In the implementation depicted in FIG. 14D, the bottom end plate 1408 and the top end plate 1406 are the same size. In this implementation, a lap plate 1414 is disposed partially over both the bottom end plate 1406 and the top end plate 1408 to at least cover a joint 1416 between the two end plates 1406 and 1408. The lap plate 1414 is then welded to both the bottom end plate 1406 and the top end plate 1408 to affix the two end plates to each other.
In the implementation depicted in FIG. 14E, the bottom end plate 1408 and the top end plate 1406 are the same size. In this implementation, one of the end plates (e.g., the bottom end plate 1408 of the upper precast panel 1404) is beveled at one end 1420 to enable a weld joint 1422 penetration between the two end plates 1406 and 1408 to affix the two end plates to each other.
Turning to FIG. 15, a magnified view is shown of a vertical bar 706 encased in an exemplary precast panel 1500 and connected to a top or bottom end plate 1502 consistent with one aspect of the present invention. The precast panel 1500 is representative of each embodiment of an interior precast panel 102, corner precast panel 104, or opening precast panel 106, 108, or 110 that employs a vertical bar 706 affixed between end plates 702 and 704 as discussed herein. As shown in FIG. 15, the vertical bar 706 is attached to an internal surface 1504 of the end plate 1502 of the precast panel 1500 via a coupler 1506 that is welded to the respective end plate 1502. The coupler 1506 has one end 1508 adapted to receive an end of the vertical bar 706 and another end 1510 that is welded (via a weld joint 1512) to the end plate 1502. In one implementation, the vertical bar 706 is retained in the coupler 1506 using one or more bolts or screws 1514 that are threaded through openings in the side of the coupler 1506 until the bolts or screws engage the vertical bar 706. In another implementation, the one end 1508 of the coupler 1506 may be threaded to receive and retain the end of the vertical bar 706. When rebar is employed to implement the vertical bar 706, the coupler 1506 may be a standard Type I or Type II rebar coupler, such as a model D-250 Bar Lock Structural Steel Connector commercially available from Dayton Superior.
FIG. 16 illustrates a vertical cross-sectional view of two exemplary precast panels 1602 and 1604 vertically connected in accordance with the present invention. The two precast panels 1602 and 1604 are representative of any vertically adjacent combination of an interior panel 102, a corner panel 104, and an opening panel 106, 108 or 110. As shown in FIG. 16, the top one 1604 of the two precast panels may be thinner than the bottom precast panel 1602. In this implementation, the bottom end plate 704 of the top precast panel 1604 may be shorter (in the thickness direction or front side 718 to back side 720) than the top end plate 702 of the bottom precast panel 1602, enabling the two end plates 702 and 704 to be welded together via a lap weld joint 1606 and/or a lap plate welded to both end plates 702 and 704. In an alternative implementation, the end plates 702 and 704 each may be longer in the thickness direction of the two panels 1602 and 1604 so that each end plate 702 and 704 has a respective lip through which the end plates 702 and 704 may be bolted using high strength bolts as discussed herein, for example, in reference to FIG. 13.
FIG. 16B is a vertical cross-sectional view of another two precast panels 1650 and 1652 vertically connected in accordance with the present invention. The two precast panels 1650 and 1652 are representative of any vertically adjacent combination of an interior panel 102, a corner panel 104, and an opening panel 106, 108 or 110. Similar to the precast panels 1602 and 1604 in FIG. 16A, the upper or top one of the two precast panels is thinner than the lower or bottom precast panel 1650. In this implementation, each panel 1650 and 1652 has one or more vertical ducts 724 adapted to receive a respective reinforcing bar segment 728a or 728b that are connected via a bar-to-bar coupler 326 to form a single continuous vertical reinforcing bar 728 that vertically connects the two panels to each another. Since the lower precast panel 1650 is thicker than the upper precast panel 1652, the lower precast panel 1650 may include more ducts 724 than the upper precast panel 1652 or have one or more ducts (e.g., duct 724x in FIG. 16B) that does not align with corresponding duct in the upper precast panel 1652. In this implementation, the additional duct 724x in the lower precast panel 1650 may have a bar anchor 1654 at one end of the duct 724x to anchor a vertical reinforcing bar segment 728b that extends from the lower precast panel 1650 to a vertically adjacent precast panel in a tier (e.g., 112a) below the panel 1650 or to a foundation wall (not shown in FIG. 16B). Similarly, if there is no duct 724 in a panel or foundation wall below the panel 1650 that is in axial alignment with a duct 724y in the upper precast panel 1652, the lower precast panel 1650 may be cast to have a duct 724z that does not extend through the bottom end plate 704 of the panel 1650 and is axially aligned with the duct 724y of the upper precast panel 1652. In this implementation, the duct 724z may have a bar anchor 1656 at the one end of the duct 724z that is closest to the bottom end plate 704 of the lower precast panel 1650.
FIG. 17 depicts an exploded view of two precast panels 106a and 108a (depicted in the precast wall shown in FIG. 6) that are horizontally connected in accordance with a horizontal panel-to-panel connection 602 and vertically connected to two other precast panels 106b and 108b in accordance with a vertical panel-to-panel connection 604. An internal surface or front side 718 of at least one of the precast panels (e.g., precast panel 108a) includes an embedded beam segment 1702 for connecting to a beam disposed orthogonal to the panel 108a and an embedded gusset plate 1704 for connecting a brace member (of a support frame 120, 122, or 124 of the precast wall system 100) at an angle diagonal to the internal surface 718 of the precast panel 108a as described in further detail herein and, in particular to FIGS. 20 and 21. Each of the precast panels 108a and 106a also include one or more embedded plates 1102 for implementing a beam-to-panel connection 608 to support, for example, a respective floor slab 1706 and 1708.
Although the embedded beam segment 1702 and embedded gusset plate 1704 are depicted in FIG. 17 as included in a left opening precast panel 108, each may be employed in a similar manner in an interior panel 102, a corner panel 104, or another type of opening precast panel 106 or 110 in order to interconnect to a support frame 120, 122, or 124 of the precast wall system 100. In addition, although each embedded plate 1102 is depicted in FIG. 17 as included in an opening precast panel 106 or 108, each may be employed in a similar manner in an interior panel 102, a corner panel 104, or another type of opening precast panel 110 in order to implement a beam-to-panel connection 608 to support, for example, a respective floor slab 1706 and 1708.
Turning to FIG. 18A, a vertical cross-sectional view is shown of a portion of one of the precast panels (e.g., 108a) in FIG. 17 that is referenced generally as the precast panel 1800. FIG. 18A illustrates one implementation for a beam-to-panel connection 608 in accordance with one aspect of the present invention. As shown in FIG. 18A, the precast panel 1800 includes a shear tab 1802 that is affixed (via a high-strength weld or other bond) to an embedded plate 1102 of the precast panel 1800 so that the shear tab 1802 is orthogonal to the front side 718 of the precast panel. In one implementation, the shear tab 1802 may be affixed or welded to the beam 1804. In another implemation, the shear tab 1802 may have one or more bolt openings 1806 for bolting (via high-strength bolts 1808) the shear tab 1802 to the end of the beam 1804.
The embedded plate 1102 of each panel 102, 104, 106, 108 and 110 may have shear studs 1104 attached to the shear plate 1102 and embedded in the cementitious material 708 of the respective precast panel 102, 104, 106, 108 and 110. In an alternative implementation of a beam-to-panel connection 608, the beam 1804 may be welded directly to the embedded plate 1102 of the precast panel 1800.
Once the beam-to-panel connection 608 has been formed, a metal deck or web 1810 may then be disposed on the beam 1804 and a horizontally adjacent beam (not shown in FIG. 18A). A floor slab 1812 may then be formed (e.g., using concrete or another cementitious material) over the metal deck 1810 and floor beam 1804.
To attach the floor slab 1812 to the precast panel 1800 (i.e., to form one implementation of a floor slab-to-panel connection), the precast panel 1800 may be precast to include a plurality of horizontal bars 1814 as shown in FIGS. 18B and 18C. In the implementation shown in FIG. 18B, each horizontal bar 1814 is attached to one end 1818 of a respective Type I or Type II coupler 1816 that has a socket 1820 at the other end 1822 of the coupler 1816. When the precast panel 1800 shown in FIG. 18B is precast or formed, the couplers 1816 are disposed along a lateral (side 714 to side 716) axis of the panel 1800 relative to a predetermined floor slab level and encased in the cementitious material 708 of the precast panel 1800. Before or after the precast panel 1800 is set in place to form the precast wall system 100 of the building, another horizontal end bar 1824 may be inserted or threaded in the socket 1820 of each coupler 1816 of the panel 1800. Once each horizontal bar 1824 is engaged in a respective coupler socket 1820, concrete or other cementitious material may be poured over the metal deck or web 1810 and the horizontal bars 1824 to form the floor slab 1812 and to encase the horizontal bars 1824 in the floor slab 1812, connecting the floor slab 1812 to the panel 1800.
In an alternative implementation for a floor slab-to-panel connection shown in FIG. 18C, the horizontal bars 1814 of the precast panel 1800 are not connected to a respective coupler 1816. Instead, each horizontal bar 1814 has one end 1826 encased in the cementitious material 708 of the precast panel 1800 and another end 1828 that extends though a trench 1830 running in a lateral axis (e.g., side 714 to side 716) of the panel 1800 and extending beyond the front side 718 of the panel. The trench 1830 has a depth sufficient to enable the end 1828 of each of the horizontal bars 1814 to be bent within the trench 1830 towards the right side 714 or the left side 716 of the panel 1800 such that the portion of each horizontal bars 1814 that extends beyond the front side 718 of the panel 1800 before bending are disposed within the trench or extend to the right or left sides 714 and 716 of the panel as shown in FIG. 18C. After the precast panel 1800 is set in place to form the precast wall system 100 of the building, each of the horizontal bars 1814 may be bent back or straightened so that the end 1828 extends beyond the front side 718 of the panel 1800 in a plane corresponding to the plane of the floor slab 1812 to be formed. In this implementation, concrete or other cementitious material may then be poured over the metal deck or web 1810 and the portion of the horizontal bars 1814 extending beyond the trench 1830 to form the floor slab 1812 and to encase the portion of the horizontal bars 1814 extending beyond the trench 1830 in the floor slab 1812, connecting the floor slab 1812 to the panel 1800.
FIG. 19A is a vertical cross-sectional view of the portion of another exemplary precast panel 1900, illustrating one implementation for connecting the precast panel 1900 to a floor slab 1902 that is not disposed over a floor beam. FIG. 19B is a perspective view of the precast panel 1900 and the floor slab-to-panel connection 1904 between the floor slab 1902 and the precast panel 1900. The precast panel 1900 is representative of an interior panel 102, a corner panel 104, and an opening panel 106, 108 or 110 that may be required to support a floor slab. As shown in FIGS. 19A and 19B, the precast panel 1900 may include one or more plates 1102 embedded on the front side 718 of the panel 1900 for implementing a respective floor slab-to-panel connection rather than a beam-to-panel connection. Each embedded plate 1102 may have one or more shear studs 1104 extending into and embedded in the cementitious material 708 of the precast panel 1900. As previously noted, each embedded plate 1102 as employed in a precast panel 1900 (or other precast panel embodiment 102, 104, 106, 108 or 110) is adapted to transfer shear forces as well as tension or other forces that may be imposed on the respective panel to another precast panel interconnected via the embedded plate 1102.
In the implementation shown in FIGS. 19A and 19B, a bracket or L-shaped angle 1906 is affixed to each embedded plate 1102 such that a shelf 1907 defined by the bracket or angle 1906 is disposed parallel to a lateral (or side 714 to side 716) axis of the panel 1900. A metal deck or web 1910 may then be disposed on the shelf 1907 of the panel 1900 as well as the shelf 1907 or beam 1804 connected to other panels 1900 or 1800 of the group 112a, 112b or 112c of precast panels 102, 104, 106, 108 or 110 that are horizontally interconnected to form a floor of the stories of the building defined by the respective group 112a, 112b or 112c of precast panels. One or more headed shear studs 1908 may be welded or otherwise attached to the bracket or angle 1902 through the metal deck or web 1910 so that each shear stud 1908 extends from the shelf 1907 of the bracket or angle 1906. A floor slab 1902 may then be formed (e.g., using concrete or another cementitious material) over the metal deck 1910 and the shear studs 1908 of the bracket or angle 1906 supporting the metal deck 1910.
Turning to FIG. 20A, an exemplary support frame 2000 is depicted that may be employed between and connecting opposing precast panels 102, 104, 106, 108 or 110 in the precast wall system 100 in accordance with the present invention. FIG. 20B depicts one embodiment of the support frame 2000 in which temporary posts 2055a and 2055b are employed to support the support frame 2000 when attached to a foundation 50 or foundation wall 60 before a first of the precast panels in the first tier 112a is erected to form the precast wall system 100.
In the implementation shown in FIGS. 20A and 20B, when erected in the precast wall system 100, the support frame 2000 is used as the permanent core floor framing. The exemplary support frame 2000 is representative of one embodiment of the support frames 112a, 112b, or 112c that may be employed to brace opposing precast panels 102, 104, 106, 108 or 110. Each support frame 2000 is disposed between and attached to a respective first pair of vertically interconnected precast panels and a second pair of vertically interconnected precast panels that are disposed opposite to the first pair in the precast wall system 100. For example, referring to FIG. 6, the first pair of vertically interconnected precast panels may correspond to the first pair of vertically interconnected interior panels 102a and 102b, where the interior panel 102a is one of the first group 112a of horizontally connected precast panels 102, 104, 106, 108 and 110 and the interior panel 102b is one of the second group 112b of horizontally connected precast panels 102, 104, 106, 108 and 110 employed in the precast wall system 100. In this example, the second pair of vertically interconnected precast panels may be a pair of vertically interconnected opening panels 106a and 106b that disposed opposite to the first pair of vertically interconnected interior panels 102a and 102b of the precast walls system as reflected in FIGS. 1 and 6. However, the first pair of precast panels 102a and 102b and the second pair of precast panels 106a and 106b may be any vertical pair combination and opposing vertical pair combination of the precast panels 102, 104, 106, 108 and 110 of the precast wall system 100, where the vertical pair of precast panels are formed to have connections to the support frame 2000 as described herein.
As depicted in FIGS. 6, 17, 20A and 20B, each support frame 2000 includes one or more cross beams 2002, 2032, and 2034 that provide bracing support for opposing walls of a tier of precast panels to be erected as well as function as floor framing when installed in the precast wall system 100. In the implementation shown in the figures, each precast wall panel (e.g., panels 102b and 106b) is connected to two cross beams (e.g., 2002 and 2034) to provide floor framing for two respective levels or floors of the precast wall system 100 and the building erected using the precast wall system 100. However, without deviating from the scope of the invention, each precast wall panel 102b and 106b may be precast to be connected to one respective cross beam (e.g., to provide floor framing corresponding to one floor of a single story precast wall system 100 and building).
In the implementation shown in FIGS. 20A and 20B, the cross beam 2032 may be erected or installed first and may be connected to the opposing foundation walls 60 or previously erected opposing precast panels (e.g., lower precast panels 102a and 106a in FIGS. 20A and 20B) of a first tier 112a of the precast wall system 100. Although support frame connections to opposing lower precast panels 102a and 106a are shown in FIGS. 20A and 20B, opposing foundation walls 60 may be formed in accordance with the present invention to have the same support frame connections. Thus, opposing foundation walls 60 or each of the lower one (e.g., 102a and 106a) of the opposing pairs of vertically interconnected precast panels (e.g., 102a & 102b and 106a & 106b) includes a beam segment 1702 having a first end 2018 encased in the cementitious material 708 of the respective panel 102b or 106b (or foundation wall 60) and a second end 2020 extending from an internal or front side 718 of the respective panel 102b or 106b (or foundation wall 60). The cross beam 2032 is connected to the beam segment 1702 of each of opposing lower precast panels 102a and 106a (or opposing foundation walls 60). As shown in FIG. 21, the end segment 1702 of each precast panel 102a and 106b may be affixed to the cross beam 2032 via a web splice plate 2022 that may affixed to the respective end segment 1702 and the cross beam 2032 via a high strength weld 2024 or high strength bolts 2026 or rivets, or a combination thereof. In one implementation, the connecting end 2020 of the respective end segment 1702 has two flanges 2030a and 2030b that define an opening through which a respective end of the cross beam 2032 may be inserted. In this implementation, each flange 2030a and 2030b may be bolted or welded to the respective end of the cross beam 2032 to provide additional reinforcement to the connection between the beam segment 1702 and the cross beam 2032.
In addition, in one implementation as shown in FIG. 21, each precast panel 102a, 102b, 106a and 106b that has a beam segment 1702 for connecting to a support frame 2000 may also include a support member or column 1202 centrally and vertically encased in the cementitious material 708 of the respective precast panel. In this implementation, the embedded end 2018 of the beam segment 1702 may be affixed to the support member or column 1202 via a high strength weld 2028 or bolts (not shown in FIG. 21) to provide further strength to the beam-to-panel connection formed using the embedded beam segment 1702.
As shown in FIG. 20B, the support frame 2000 may include one or more removable temporary posts 2055a and 2055b or false works that are used to aid in the erection of the one or more cross beams 2002 and 2034, which will then be connected between the opposing upper precast panels 102b and 106b as each of these panels are erected. As shown in FIG. 20C, each temporary post 2055a and 2055b may include two inner posts 2056a and 2056b each having a top and a bottom, a top cross member 2057a removably attached to the top of each inner post 2056a and 2056b, and a bottom cross member 2057b removably attached to the bottom of each inner post 2056a and 2056b. The cross members 2057a and 2057b may be removably attached to the inner posts 2056a and 2056b via bolts (not shown in the figures) or other removable fasteners standard to the construction industry. In one implementation, the inner posts 2056a and 2056b and the top cross member 2057a and bottom cross member 2057b define a space 2060a to enable the passage of a brace member 2004 or 2012 of the support frame 2000 through the respective temporary post 2055a or 2055b as further described herein. Each temporary post 2055a or 2055b may also have 2058 an intermediate cross member 2058a removably attached to and disposed between (or external to) the inner posts 2056a and 2056b at the elevation of the underside of the beam 2034 so that the intermediate cross member 2058 may be used to aid in the positioning and temporary support of a portion of beam 2034 (e.g., beam segment 2034a). The inner posts 2056a and 2056b, the top cross member 2057a and the intermediate cross member 2058 define an upper space 2060b to enable the passage of a portion of beam 2034 (e.g., beam segment 2034a). In this implementation in which each temporary post 2055a and 2055b includes an intermediate cross member 2058 as shown in FIG. 20C, the inner posts 2056a and 2056b, the bottom cross member 2057b and the intermediate cross member 2058 define a lower space 2060a to enable the passage of a brace member 2004 or 2012 of the support frame 2000 through the respective temporary post 2055a or 2055b.
As shown in FIGS. 20B and 20C, one of the temporary posts 2055a may be erected and positioned at one end of beam 2032. Another temporary post 2055b may then be erected on the opposite end of beam 2032. Each of the temporary posts 2055a and 2055b are oriented on the beam 2032 interconnected between the lower precast panels 102a and 106a so that the opening or spaces 2060a and 2060b between the inner posts 2056a and 2056b of each of the temporary posts 2055a and 2055b are axially aligned with the beam 2032 and with the beam 2034 to be interconnected between the upper precast panels 102b and 106b as further described below. Once the temporary posts 2055a and 2055b are oriented on the beam 2032, the beam 2002 may be erected and supported on top of the temporary posts 2055a and 2055b.
To provide additional support and stiffening to the support frame 2000 and, in particular, to the cross beams 2002 and 2034 to be connected between the opposing upper precast panels 102b and 106b, the support frame 2000 may include one or more diagonal brace members 2004 and 2012. In this implementation, each of the lower precast panels 102a and 106a (or opposing foundation walls 60) has a gusset plate 1704 extending from an internal or front side 718 of the respective lower precast panel (or foundation wall 60). The lower end of each brace member 2004 and 2012 is inserted through the space 2060a between the inner posts 2056a and 2056b of a respective temporary post 2055a or 2055b and then connected to the gusset plate 1704 of a respective one of the lower precast panels 102a and 106a (or opposing foundation walls 60). The top end of each brace member 2004 and 2012 is connected to a gusset plate 2008 that is affixed to and extends from the cross beam 2002 as shown in FIGS. 20A and 20B. The gusset plate 1704 of each of the lower precast panels 102a and 106a may be supported by or rest on (and be welded to) the beam segment 1702 of the respective lower precast panel 102a or 106a to connect to the diagonal brace member 2004 or 2012.
In the implementation shown in FIGS. 20A and 20B, the beam 2034 comprises beam sections 2034a, 2034b and 2034c, which are interconnected via splicing plates 2038 and 2040 so that the diagonal brace members 2004 and 2012 pass diagonally through the beam 2034. The first beam section 2034a may be inserted through the space 2060b between the inner posts 2056a and 2056b of the temporary post 2055a and supported on the intermediate cross member 2058 of the same temporary post 2055a. Similarly, the third beam section 2034c may be inserted through the space 2060b between the inner posts 2056a and 2056b of the temporary post 2055b and supported on the intermediate cross member 2058 of the same temporary post 2055b. In one implementation, to connect the second beam section 2034b to the first beam section 2034a, a splicing plate 2038 may be affixed to and between facing ends of the first beam section 2034a and the second beam section 2034b so that the brace member 2004 passes between the first and second beam sections 2034a and 2034b. Similarly, to connect the second beam section 2034b to the third beam section 2034c, a splicing plate 2040 may be affixed to and between facing ends of the second beam section 2034b and the third beam section 2034c so that the brace member 2012 passes between the second and third beam sections 2034b and 2034c. In the implementation shown in FIGS. 20A and 20B, each splicing plate 2038 and 2040 is affixed to a web portion of the ends of the beam sections 2034a and 2034b or 2034b and 2034c such that the brace member 2004 or 2012 (which is offset from the center or web axis of the beam 2034 by at least the width of the gusset plate 1704 to which the brace member 2004 or 2012 is affixed) passes along side the respective splicing plate 2038 or 2040. The splicing plates 2038 and 2040 may be affixed to respective beam sections 2034a, 2034b and 2034c via mild or high strength bolts and/or welds (not shown in FIG. 20A or 20B).
To support a floor slab on the cross beam 2034 and to effectively reduce the span of the cross beam 2034, the support frame 2000 may also include a column 2036 connected (e.g., via welding or bolting) between the cross beam 2034 and the lower cross beam 2032 as shown in FIG. 20A. Optional column 2036 may also be used to assist in the erection of beam section 2034c.
FIG. 20D depicts another exemplary support frame 2050 that may be employed between and connecting opposing precast panels (102a & 102b and 106a & 106b) in the precast wall system 100 in accordance with the present invention. Except as described below, the support frame 2050 has components (such as cross beams 2002, 2032, and 2034 and brace members 2004 and 2012) that are erected consistent with the support frame 2000. However, in the implementation shown in FIG. 20D, instead of temporary posts 2055 extending between cross beams 2002 and 2032, the support frame 2050 includes one or more removable or temporary posts 2054a and 2054b mounted between the cross beam 2032 and the next higher cross beam 2034 to be connected between the opposing upper precast panels 102b and 106b. In this implementation, the diagonal brace members 2004 and 2012 are each comprised of brace member sections 2004a, 2004b and 2012a, 2012b. The lower end of each brace member 2004a and 2012a is connected to the gusset plate 1704 of a respective one of the lower precast panels 102a and 106a (or opposing foundation walls 60). The top end of each brace member 2004a and 2012a is connected to another respective gusset plate 2005a or 2005b that is affixed to and extending from the cross beam 2034 as shown in FIG. 20D.
After the cross beam 2034 is braced to the lower cross beam 2032 using the temporary posts 2054a and 2054b and/or brace members 2004a and 2012a, one or more temporary posts 2052a and 2052b may be mounted between the cross beam 2034 and the next higher cross beam 2002 to be connected between the opposing upper precast panels 102b and 106b to be erected as shown in FIG. 20D. To provide additional support and stiffening to the support frame 2050 (and, in particular, to the cross beam 2002 to be connected between the opposing upper precast panels 102b and 106b), the lower end of each brace member 2004b and 2012b is connected to a respective gusset plate 2005c or 2005d that is affixed to and extending from the cross beam 2034 as shown in FIG. 20D. The top end of each brace member 2004b and 2012b is connected to the cross beam 2002, via the gusset plate 2008 attached to the cross beam 2002 at a center portion thereof.
As shown in FIGS. 1 and 5, multiple support frames 120, 122 and 124 (consistent with frames 2000 or 2050) may be constructed and arranged in a parallel manner across respective pairs of opposing precast panels of the first or current tier of the precast wall system 100. The support frames 120, 122, and 124 may have interconnecting members (not numbered in FIGS. 1 and 5). Once the members of each support frame 120, 122 and 124 are erected, plumbed and bolted, opposing pairs of precast panels 102b and 106b in the next tier may be erected to connect to a respective support frame 120, 122, or 124.
In the example shown in FIGS. 20A and 20D, the cross beam 2034 of the respective support frame 2000 or 2050 is connected to a shear plate 1102 embedded in the internal or front side 718 of the higher one 102b of the first pair of precast panels 102a and 102b and to a shear plate 1102 embedded in the internal or front side 718 of the higher one 106b of the second pair of precast panels 106a and 106b. The beam-to-panel connection 608 that may be employed to connect the cross beam 2034 to the respective precast panels 102b and 106b may correspond to the beam-to-panel connection described in reference to FIG. 18A. In particular, as shown in FIG. 18A, a shear tab 1802 may be affixed (via a high-strength weld or other bond) to the embedded shear plate 1102 of the precast panel 102b and 106b so that the shear tab 1802 is orthogonal to the front side 718 of the precast panel 102b and 106b. The shear tab 1802 may be affixed or welded to the beam 2034. In another implementation, the shear tab 1802 may have one or more bolt openings 1806 for bolting (via high-strength bolts) the shear tab 1802 to the end of the cross beam 2034.
The cross beam 2002 of the respective support frame 2000 or 2050 is connected (e.g., in the same manner as described for cross beam 2032) to a beam segment 1702 embedded in the upper one 102b of the first pair of precast panels 102a and 102b and a beam segment 1702 embedded in the upper one 106b of the second pair of precast panels 106a and 106b.
Once the precast panels (e.g., panels 102b and 106b in FIG. 20B or FIG. 20D) for the current tier (e.g., group 112b) of the precast wall system 100 are vertically connected to respective lower tier panels (e.g., panels 102a and 106a of group 112a) and horizontally connected to respective adjacent panels in the same tier (e.g., group 112b), the temporary posts 2055a and 2055b of the support frame 2000 and the temporary 2052a, 2052b, 2054a and 2054b of the support frame 2050 may be removed as shown in FIG. 20A and used for erection of the next tier of support frames 120, 122, and 124. The column 2036 may remain as part of the support structure 2000 and 2050 and the bracing system 118 to support the span of beam 2034 for floor framing. Cross beams 2032, 2034 (including splicing plates 2038 and 2040 in support frame 2000) and 2002 also remain as permanent framing members for the bracing system 118 to support the core floor decking and concrete slab.
The support frame 2000 and 2050 as described provides bracing support for the first group 112a of panels horizontally interconnected to the opposing lower precast panels 102a and 106a and to the second group 112b of panels that are or are being set in place to be interconnected to the opposing higher precast panels 102b and 106b that are vertically interconnected to the lower precast panels 102a and 106a.
As depicted in FIG. 1, each support frame 120, 122 and 124 (constructed consistent with support frame 2000 or 2050) may be expanded or vertically interconnected to another similarly formed support frame 2000 or 2050 to continue to construct or erect the precast wall system 100 for the building. The next or other support frame 2000 or 2050 would similarly support opposing pairs of precast panels that include the opposing higher precast panels 102b and 106b and the next opposing higher precast panels (e.g., 102c and 106c) that are vertically connected to the precast panels 102 and 106b.
FIG. 22A depicts a horizontal cross-sectional view of another two exemplary precast panels 2200 and 2202 that may be employed to construct the precast wall system 100 in accordance with the present invention. Similar to precast panels 1000 and 1002 depicted in FIG. 10, the precast panels 2200 and 2202 each has a side 714 or 716 and one or more shear keys 1004 or 1006 disposed or formed on the side of the respective panel for horizontally mating or aligning the respective panel 2200 and 2202 to the other precast panel 2202 and 2200. The second shear key or key set 1006 is formed to complementary mate the first shear key or key set 1004 such that the one or more horizontal ducts 904 of the first panel 2200 are each axially aligned with the corresponding one or more horizontal ducts 904 of the second panel 2202 when the first shear key or key set 1004 is mated to the second shear key or key set 1006. In this implementation of a horizontal panel-to-panel connection 602, the precast wall system 100 includes one or more post-tensioned horizontal reinforcing bars 2204 disposed in the respective ducts 904 with a bar anchor 910 attached to each end of the respective horizontal reinforcing bar 2204. The combination of friction (due to the compressive clamping stress of the post-tensioned horizontal reinforcing bars 2204) and the shear keys 1004 and 1006 enables the transfer of horizontal shear forces between the two precast panels 2200 and 2202 such that the panels are able to resist large horizontal shear forces perpendicular to the plane of the wall defined by the precast panels 2200 and 2202, for example due to blast loading. In addition, the combination of the post-tensioned horizontal reinforcing bars 2204 and shear keys 1004 and 1006 enables the precast panels 2200 and 2202 to inhibit the passage of flame or hot gases through the shear key joint 2206 between the two panels 2200 and 2202.
FIG. 22B is a horizontal cross-sectional view of another two exemplary precast panels 2210 and 2212 that may be employed to construct the precast wall system 100 in accordance with the present invention. When the precast panels 2210 and 2212 (or walls formed from these panels) are used as a part of a fire-resistant-rated system, the joints (e.g., 2214) between the precast panels 2210 and 2212 inhibit the passage of flame or hot gases in compliance with the ASTM E 1966 standard for testing and rating fire-resistance joint systems made in or between fire-resistance-rated assemblies. As shown in FIG. 22B, one of the precast panels 2210 has a pocket or indentation 2216 on and extending the vertical height of the side 714 of the panel 2210 that is to be connected with the side 716 of the adjacent panel 2212. The side 716 of the adjacent panel 2212 may be planar or also have a vertical indentation 2216. After the two precast panels are aligned and connected side 714 by side 716 in accordance with a horizontal panel-to-panel connection 602 disclosed herein, the indentation 2216 is then filled with grout 2218 to create a seal that inhibits the passage of flame or hot gases between the joint 2214. In another implementation, the joint 2214 between the two precast panels 2210 and 2212 may be fire and smoke sealed using a flexible non-combustible material, such as a ceramic fiber blanket that is tested and fire-resistance rated in accordance with the applicable standard, for example ASTM E 1966.
Turning to FIG. 23A, a vertical cross-sectional front view of another exemplary precast panel 2300 is shown, which may be employed to construct the precast wall system 100 in accordance with the present invention. FIG. 23B depicts a left side view of the precast panel 2300 and FIG. 23C depicts a horizontal cross-sectional view of the same precast panel 2300. As shown in FIGS. 23A-23C, the precast panel 2300 has a plurality of structural angles 2302a-2302d comprised or made entirely of mild or high-strength metal (for example, steel having a yield strength in a range of 36 ksi to 50 ksi). In the implementation shown in FIGS. 23A-23C, each angle 2302a-2302d is disposed along a corner edge 2306a, 2306b, 2306c or 2306d of the precast panel 2300 and may extend between a top corner 2308a, 2308b, 2308c or 2308d and a bottom corner 2310a, 2310b, 2310c or 2310d of the precast panel 2300 such that each angle 2302a-2302d is adapted to connect (for example, via a high strength weld) the precast panel 2300 to another horizontally adjacent precast panel 2300 and/or to another vertically adjacent precast panel 2300. In an alternative implementation, each angle 2302a-2302d may comprise two or more angle segments spaced apart on a respective corner edge 2306a-2306d of the panel 2300.
As best shown in FIG. 23C, each angle 2302a-2302d has a first portion or leg 2304a that extends along and is embedded in either the right side 714 or left side 716 of the panel 2300 and a second portion or leg 2304b that extends along and is embedded in either the front side 718 or the back side 720 of the panel 2300. Each angle 2302a-2302d may have one or more shear studs 1104 affixed to (e.g., welded to) and extending from each leg of the respective angle into the cementitious material 708 of the precast panel 2300 so that the respective angle is further effective to transfer forces between the precast panel 2300. In addition, to further aid in the transfer of vertical forces, the legs 2304a and 2304b at each end of each angle 2302a-2302d (or one end of an angle segment) may be affixed to (e.g., via a high strength weld) to the end plates 702 and 704 of the panel 2300. In this implementation, each leg 2304a and 2304b at each end of each angle 2302a-2302d may be connected to a respective end plate 702 or 704 via a stiffening plate 2312 or 2314 embedded in the same side 714, 716, 718 or 720 of the panel 2300 as the leg 2304a or 2304b of the respective angle 2302a-2302d.
The precast panel 2300 may also include one or more horizontal side plates 2316. Each horizontal side plate 2316 is embedded in the front side 718 or back side 720 of the precast panel 2300 and connects one leg of one angle (e.g., 2302a or 2302d) to one leg of another angle (e.g., 2302b or 2302c). Each horizontal side plate 2316 may have one or more shear studs 1104 affixed to and extending into the cementitious material 708 of the precast panel.
Although the precast panel 2300 is depicted as an opening precast panel 108 in FIG. 23, structural angles 2302a-2302d may be employed in any interior panel 102, corner panel 104, and opening panel 106, 108 or 110 embodiment disclosed herein. Furthermore, the structural angles 2302a-2302d may be employed in lieu of or in addition to side plates 720a-720f to implement a horizontal panel-to-panel connection 602 and in lieu of or in addition to end plates 702 and 704 to implement a vertical panel-to-panel connection 604 between two precast panels 2300, 102, 104, 106, 108 or 110.
For example, to implement a horizontal panel-to-panel connection 602 between a first precast panel 2300 as shown in FIG. 23 and a second precast panel formed similar to the first precast panel 2300 to employ structural angles 2302a-2302d (e.g., an interior precast panel 102 not shown in FIG. 23), each angle of the first precast panel 2300 having a leg embedded on the right side 714 of the precast panel 2300 (e.g., angles 2302b and 2302c) is horizontally aligned with and affixed to a corresponding angle (e.g., angles 2302a and 2302d) on the left side 716 of the second precast panel 102. Each pair of horizontally aligned angles of the two precast panels (e.g., angle 2302b of the first precast panel 2300 and angle 2302a on the second interior precast panel 102) define a respective joint running vertically along the front side 718 or the back side 720 of the two panels that may be welded to affix the two angles together to effectively implement the horizontal panel-to-panel connection 602.
Similarly, to implement a vertical panel-to-panel connection 604 between a first precast panel 2300 and a second precast panel formed similar to the first precast panel 2300 to employ structural angles 2302a-2302d (e.g., an interior precast panel 102 not shown in FIG. 23), each angle 2302a-2302d disposed in proximity to a respective top corner 2308a, 2308b, 2308c or 2308d of the first precast panel 2300 is vertically aligned with and affixed to a corresponding angle 2302a-2302d disposed in proximity to a respective bottom corner 2310a, 2310b, 2310c or 2310d of the second precast panel 102. In this implementation, the first and second panels may be formed without end plates 702 and 704. Instead, each pair of vertically aligned angles of the two precast panels (e.g., angle 2302a of the first precast panel 2300 and a corresponding angle 2302a on the second interior precast panel 102) define a respective corner joint running horizontally along the front side 718 or the back side 720 of the two panels, bending around a respective corner of each panel and continuing along the right side 714 or the left side 716 of the two panels. Each such corner joint may be welded to affix the respective pair of vertically aligned angles together to effectively implement the vertical panel-to-panel connection 604.
As discussed in further detail below, each structural angle 2302a-2302d of a precast panel 2300 may be used to attach temporary lifting lugs to the precast panel 2300 to enable the panel 2300 to be hoisted into position within a building via a crane or other hoisting rig.
Turning to FIG. 24, a precast panel erection aid platform 2400 is shown, which may be employed to construct a precast wall system 100 in accordance with the present invention. The erection aid platform 2400 comprises one or more sets 2402a, 2402b and 2402c of beam members 2404a-2404d. Each set 2402a, 2402b and 2402c of beam members 2404a-2404d is connected to four or more columns 2406a-2406d such that each set 2402a, 2402b and 2402c defines a respective floor of the erection aid platform 2400. The columns 2406a-2606d have a sufficient height (H) such that, when the erection aid platform 2400 is disposed relative to a top corner of a foundation 50, wall 60, or lower tier (e.g., group 112a in FIG. 1) of horizontally interconnected precast panels 102, 104, 106, 108 or 110, two beam members (e.g., 2404a & 2404d) of each floor or set 2402a, 2402b and 2402c are each positioned to temporarily brace a respective one or more precast panels 102, 106, 108, or 110 of one wall 2408a or 2408b of a next tier or group (e.g., 112a, 112b or 112c) erected on top of the foundation 50, the wall 60, or the lower tier (e.g., group 112a) of precast panels before the one wall 2408a or 2408b is horizontally connected to an adjacent wall 2408b or 2408a via a corner precast panel 106. In the example implementation shown in FIG. 24, each column 2406a-2406d is disposed in a respective corner of the erection aid platform 2400 and has a height approximately equal to the height of a precast panel 102b1, 102b2, 102b3, 102b4, or 102b5 of a next tier or group 112b to be erected upon a lower tier or group 112a of precast panels employed to construct the precast wall system 100 of a building. In this implementation, two beam members 2404a and 2404d of each floor or set 2402a, 2402b and 2402c are each positioned to respectively brace precast panels 102b1 and 102b2 that define the wall 2408a and precast panels 102b3, 102b4, and 102b5 that define the wall 2408b of the next tier or group 112b precast panels to be erected, enabling these precast panels 102b1, 102b2, 102b3, 102b4, and 102b5 to be aligned relative to each adjacent precast panel and horizontally interconnected before the walls 2408a and 2408b are horizontally connected via a corner precast panel 106b. Thus, the erection aid platform 2400 enables adjacent walls 2408a and 2408b of one tier of precast panels to be erected before the adjacent walls 2408a and 2408b are interconnected so that any alignment error between the two walls 2408a and 2408b may be limited and corrected via the erection of the precast corner panel 104 used to horizontally interconnect the two walls 2408a and 2408b of precast panels.
As shown in FIG. 24, each beam member 2404a and 2404d positioned to brace one or more precast panels 102b1, 102b2, 102b3, 102b4, or 102b5 may be temporarily attached to the braced precast panel via one or more right angle brackets 2410a-2410e (Note, right angle brackets attached to beam members 2404d are not shown in FIG. 24 for clarity and to avoid obscuring other features of the erection aid platform 2400 depicted in FIG. 24). The right angle brackets 2410a-2410e may be erection stiffened angles 2504b as described further described herein that have one plate 2506 affixed to the respective beam member 2404a or 2404d and another plate 2508 bolted to the respective precast panel 102b1, 102b2, 102b3, 102b4, or 102b5.
An upper end 2412 of each column 2406a-2406d includes an attachment point 2414 for connecting a crane or other hoisting rig to each column 2406a-2406d to lift the erection aid platform into position relative to a top corner of a foundation 50, a cast-in-place wall 60 system, or a lower tier (e.g., group 112a or 112b) of horizontally interconnected precast panels 102, 104, 106, 108 or 110. A lower end of 2416 of each column 2406a-2406d is attached to a respective support bracket 2418a-2418d. When the erection aid platform is lifted into position, two of the support brackets 2414c-2414d are each temporarily attached (e.g., via bolts and nuts not in view in FIG. 24) to the internal face of the foundation 50, the cast-in-place wall 60, or a respective precast panel (e.g., 102a3 or 102a5 in FIG. 24) of a previously erected lower tier or group (e.g., 112a) of precast panels. In addition, when the erection aid platform is lifted into position, another two of the support brackets 2414a-2414b are temporarily attached (e.g., via bolts not in view in FIG. 24) to a cross beam 2440 connected between two opposing walls of the foundation 50, the cast-in-place walls 60, or the lower tier (e.g., 112a or 112b) of precast panels 102, 104, 106, 108 or 110. The cross beam 2440 may be a primary cross beam 2032 employed in a support frame 120, 122, 124 or 2000 of the bracing system 118 as discussed herein.
Planks or deck members 2420 may be disposed over a respective set of beam members 2404a-2404d to form a floor deck for construction workers to work inside the precast wall system 100 as it is being erected. Working on a floor deck of the erection aid platform 2400, construction workers may complete tasks, including but not limited to: (1) a vertical panel-to-panel connection 604 (e.g., by welding end plates 702 and 704 or bolting end plates 1306 and 1308 of vertically adjacent precast panels 102a1 and 102b2), (2) a horizontal panel-to-panel connection 602 (e.g., by welding side plates 720 or structural angles 2302 of horizontally adjacent precast panels 102a1 and 102b2), (3) a link beam connection 606 between two opening panels 106, 108 and 110, (4) a beam-to-panel connection 608 (e.g., for supporting an interior floor slab 1704, 1706 or 1812), (5) a slab-to-panel connection 1904, or (6) other construction activities required to erect structures internal to the precast wall system 100.
As shown in FIG. 24, the erection aid platform 2400 may also include a monorail system 2422 supported from two or more of the beam members 2404b and 2404d of the lowest set 2402a of beam members defining the first floor of the platform 2400. The monorail system 2422 may be used to erect elevator divider beams and floor beams that support the metal deck on a floor or floors of the foundation 50, the cast-in-place wall 60 system, or the lower tiers of precast wall system 100 below the erection aid platform 2400.
An erection aid platform 2400 may be employed in each corner of the precast wall system 100 to be erected. Once each of the precast panels for the current or upper most tier of the precast wall system 100 are erected and secured (e.g., via a vertical panel-to-panel connection 604 and a horizontal panel-to-panel connection 602 or link beam connection 606 as described herein), each erection aid platform 2400 may be lifted via a hoisting rig to the top of the panels 102b1, 102b2, 102b3, 102b4, or 102b5 that the respective platform 2400 braced during the erection sequence for those panels 102b1, 102b2, 102b3, 102b4, or 102b5. As discussed in further detail herein, the process of lifting each platform 2400 in position to brace precast panels to be erected, erecting the precast panels, completing panel-to-panel connections for the braced precast panels, and forming floor beam and floor slab structures relative to the braced precast panels is repeated over and over again until each planned tier or group 112a, 112b, and 112c of the precast wall system 100 is erected to construct the building as designed. Once the precast wall system 100 is fully erected, the erection aid platforms 2400 may be removed and lowered to the street for dismantling and shipping off-site.
FIG. 25 depicts angle brackets 2500a-2500d that may be temporarily attached to ends of precast panels 2502a and 2502b (which each represent any embodiment of a precast panel 102, 104, 106, 108, or 110 disclosed herein) to aid in vertically aligning the precast panels 2502a and 2502b as the upper panel 2502b (e.g., included in an upper tier or group 112b or 112c of precast panels) is lifted into position atop the lower panel 2502a (e.g., included in a lower tier or group 112a or 112b of precast panels) during the construction process of the precast wall system 100. Each angle bracket 2500a-2500d includes a first plate 2504 and a second plate 2506 that is affixed (or integral) to and extends at a right angle from the first plate 2504. Each angle bracket 2500a-2500d may include one or more stiffening side plates 2508 affixed to both the first plate 2504 and second plate 2506 of the respective bracket 2500a-2500d to further strengthen the bracket. The second plate 2506 of each angle bracket 2500a-2500d is affixed (e.g., via a bolt 2510) to the end of the respective precast panel 2502a or 2502b so that the first plate 2504 is aligned with and in the same plane as the end plate 702 or 704 of the respective precast panel 2502a or 2502b to which the second plate 2506 of the angle bracket 2500a, 2500b, 2500c or 2500d is attached. The first plate 2504 of each angle bracket 2500a-2500b of the upper precast panel 2502b may be temporarily aligned with and affixed to the first plate 2504 of a corresponding angle bracket 2500c-2500d of the lower precast panel 2502a via a respective bolt 2512 inserted through a bore 2514 in each of the first plates and threaded in a respective nut (not shown in FIG. 25). The bore 2514 of each angle bracket 2500c and 2500d attached to and aligned with the top end plate 702 of a precast panel may be used as an attachment point for a hoisting rig to lift the precast panel into position within the precast wall system 100 being erected.
As an alternative to using angle brackets 2500a-2500d, FIGS. 26A through 26D depict one embodiment of lifting lugs 2600a-2600d that may be affixed to a precast panel 2602a, 2602b or 2602c (each of which are representative of any embodiment of a precast panel 102, 104, 106, 108 or 110 described herein) to aid in lifting the precast panel (e.g., 2602b) and for guiding the precast panel (e.g., 2602b) into alignment with another vertically adjacent precast panel (e.g., 2602a) that was previously erected during the construction process of the precast wall system 100. As best shown in FIG. 26D, each lifting lug 2600a-2600d includes a body 2604 that is configured to be removably attached to one end of a respective precast panel 2602a-2602d and a first end 2606 extending from (and integral to) the body 2604 and having an attachment point 2608 for a hoisting rig (e.g., a crane) to lift the respective precast panel. Each lifting lug 2600a-2600d may also have a second end 2610 that extends from (and is integral to) the body 2604 opposite from the first end 2606, where the second end 2610 has another attachment point 2612 for the hoisting rig to lift the respective precast panel. In the implementation shown in FIG. 26, the attachment point 2608 or 2612 is an orifice through the respective end 2606 or 2610 of the lifting lug 2600a-2600d that is sized to enable a bolt or cable to pass for connecting to a hoisting rig. However, other attachment points 2608 or 2612 may be employed such as a ring or clip that a hoisting rig may connect to in order to lift the precast panel 2602a, 2602b or 2602c via the lifting lug 2600a-2600d.
The first end 2606 of each lifting lug 2600a-2600d may be bent or curved relative to the body 2604 of the lifting lug 2600a-2600d so that, when the body 2604 of the lifting lug 2600a-2600d is attached to the precast panel (e.g., 2602b), the first end 2606 of the lifting lug 2600a-2600d is effective to capture and guide another vertically adjacent precast panel (e.g., 2602a or 2602c) towards the panel 2602b that the lifting lug 2600a-2600d is attached.
In one implementation, to removably attach the lifting lug 2600a-2600d to a respective precast panel 2602a, 2602b or 2602c, each lifting lug 2600a-2600d has one or more bore holes 2614 for receiving a respective stud 2616 mounted on or embedded in the front side 718 or back side 720 of the precast panel in proximity to one end 710 or 712 of the panel 2602a, 2602b or 2602c. Each stud 2616 may be secured to the respective lifting lug 2600a-2600d via a nut or other type of anchor threaded on or affixed to the end of the stud 2616 extending out of the bore hole 2614 in the body 2604 of the respective lifting lug 2600a-2600d.
Each precast panel 2602b may have a first plurality of lifting lugs 2600a and 2600b (“top lugs 2600a and 2600b”) attached in proximity to and spaced about the top end 710 or top end plate 704 so that the first end 2606 of each lifting lug 2600a and 2600b extends beyond and curves away the top end 710 or top end plate 702. As shown in the example depicted in FIGS. 26A-26D, two top lugs 2600a and 2600b are each attached to a respective structural angle 2302a and 2302b on the front side 718 of the precast panel 2602b and two additional top lugs 2600a (not in view in FIGS. 26A-26D) and 2600b are each attached to a respective structural angle 2302c and 2302d (not in view in FIGS. 26A-26D) on the back side 720 of the precast panel 2602b. The four lifting lugs 2600a and 2600b spaced about the top end 710 or top end plate 702 of the precast panel 2602b enable the precast panel 2602b to be lifted without being substantially tilted by a hoisting rig connected to the attachment points 2608 of the first end 2606 of each of four lifting lugs 2600a and 2600b so that the precast panel 2602b may be positioned atop and vertically aligned with a lower precast panel 2602a that was previously erected as one of a lower tier (e.g., group 112a) of precast panels in the precast wall system 100 being constructed.
Each precast panel 2602b may also have a second plurality of lifting lugs 2600c and 2600d (“bottom lugs 2600c and 2600d”) attached in proximity to and spaced about the bottom end 712 or bottom end plate 704 so that the first end 2606 of each lifting lug 2600c and 2600d extends beyond and curves away the bottom end 712 or bottom end plate 704. As shown in the example depicted in FIGS. 26A-26D, two bottom lugs 2600c and 2600d are each attached to a respective structural angle 2302a and 2302b on the front side 718 of the precast panel 2602b and two additional bottom lugs 2600c and 2600d (not in view in FIGS. 26A-26D) are each attached to a respective structural angle 2302c and 2302d (not in view in FIGS. 26A-26D) on the back side 720 of the precast panel 2602b. As the upper precast panel 2602b is lifted and lowered towards the lower precast panel 2602a, the first end 2608 of the four bottom lifting lugs 2600c and 2600d spaced about the bottom end 712 or bottom end plate 704 of the upper precast panel 2602b effectively capture the top end 710 of the lower precast panel 2602a and guide the upper precast panel 2602b towards the top end 710 of the lower precast panel 2602a such that the bottom end 712 (or bottom end plate 704) of the upper precast panel 2602b is substantially aligned with the top end 710 (or top end plate 702) of the lower precast panel 2602a.
As previously noted, the lower precast panel 2602a may also have a first plurality of lifting lugs 2600a and 2600b attached in proximity to and spaced about the top end 710 or top end plate 704 of the lower precast panel 2602 so that the first end 2606 of each lifting lug 2600a and 2600b extends beyond and curves away the top end 710 or top end plate 702 of the lower precast panel 2602a. In this implementation, as the upper precast panel 2602b is lifted and lowered towards the lower precast panel 2602a, the first end 2608 of the four top lifting lugs 2600a and 2600b spaced about the top end 710 or top end plate 702 of the lower precast panel 2602a effectively capture the bottom end 714 of the upper precast panel 2602b and guide the upper precast panel 2602b towards the top end 710 of the lower precast panel 2602a such that the bottom end 712 (or bottom end plate 704) of the upper precast panel 2602b is substantially aligned with the top end 710 (or top end plate 702) of the lower precast panel 2602a.
As best shown in FIGS. 26A and 26C, when the bottom end 712 of the upper precast panel 2602b is positioned atop and substantially aligned with the top end 710 of the lower precast panel 2602a, each top lug 2600a and 2600b attached in proximity to the top end 710 or the top end plate 702 of the lower precast panel 2602a is disposed relative to and horizontally aligned with a corresponding one of the bottom lugs 2600c and 2600d attached in proximity to the bottom end 712 or the bottom end plate 704 of the upper precast panel 2602b. When a top lug 2600a or 2600b is horizontally aligned with a corresponding bottom lug 2600c or 2600d, the orifice 2614 in the first end 2606 of the top lug 2600a attached to the lower precast panel 2602a is aligned with the orifice 2614 in the second end 2610 of the bottom lug 2600c attached to the upper precast panel 2602b and a bolt 2620 or other removable fastener may be inserted through the aligned orifices 2614 of the two horizontally aligned lugs 2606 and 2610 of the vertically adjacent panels 2602a and 2602b to maintain the alignment between the two panels. Similarly, when a top lug 2600a or 2600b is horizontally aligned with a corresponding bottom lug 2600c or 2600d, the orifice 2614 in the first end 2606 of the bottom lug 2600b attached to the upper precast panel 2602b is also aligned with the orifice 2614 in the second end 2610 of the top lug 2600c attached to the bottom precast panel 2602a and another bolt 2620 or other removable fastener may be inserted through these aligned orifices 2614 of the two horizontally aligned lugs 2606 and 2610 of the vertically adjacent panels 2602a and 2602b to further maintain the alignment between the two panels 2602a and 2602b.
Once the upper precast panel 2602b is positioned and interconnected to the lower precast panel 2602a, the hoist rig may be disconnected from the attachment point 2608 of each of the top lugs 2600a and 2600b of the upper precast panel 2602b and connected to the attachment point 2608 of each of the top lugs 2600a and 2600b of the next precast panel 2602c to be positioned in the precast wall system 100.
FIGS. 27A-27C depict a flow chart illustrating an exemplary process 2700 for constructing a precast wall system 100 in accordance with the present invention. For brevity and clarity in the discussion of the process 2700 to follow, an exemplary sequence is shown in FIG. 28 of erecting precast panels 102, 104, 106, 108 and 110 in a first tier 112a of the precast wall system 100 in accordance with the process 2700. Unless otherwise specified herein, the precast wall system construction or erection process 2700 may be performed by construction workers utilizing one or more hoisting rigs (such as cranes suitable for high-rise building construction) and standard construction tools (such as a welder, manual or power socket wrenches, or other standard tools). The precast panels 102, 104, 106, 108 and/or 110 employed in the precast wall system 100 to be erected may vary depending on the design of the building without deviating from the scope of the disclosed process 2700. In addition, the precast panels 102, 104, 106, 108 and/or 110 employed in the precast wall system 100 are preferably casted or formed off site in accordance with the embodiments described in detail herein.
Initially, construction workers may form a footing or foundation 50 and foundation walls 60 upon the footing or foundation 50 using standard cast-in-place techniques (step 2702 in FIG. 27A). In an alternative implementation, the foundation walls 60 may be omitted and the initial tier 112a of precast panels 102, 104, 106, 108 and 110 may be erected directly on the footing or foundation 50 as described herein. If any of the first tier 112a of precast panels are to be vertically connected to the foundation 50 or the foundation walls 60 using a vertical reinforcing bar 728, a top portion (e.g., 312 in FIG. 3B) of the foundation 50 or wall 60 (which is the last portion to be formed from concrete poured to from the cast-in-place foundation 50 or wall 60) is formed to include a cap plate 314 that serves as a base for vertically connecting precast panels 102, 104, 106, 108 or 110 (precasted consistent with the panel 310 in FIG. 3B) and to include vertical ducts 724 for inserting and retaining a continuous reinforcing bar 728 or coupled reinforcing bar segments 728a and 728b. The last or top portion 312 of the cast-in-place foundation 50 or wall 60 may be formed to include one or more support posts 316 upon which the cap plate 314 may be disposed before pouring concrete to encase the support posts 316 and forming the top portion 312. Plates 318 having jacking bolts 320 may be disposed on the top of the support posts 316. Prior to pouring the concrete for the top portion 312 of the foundation 50 or wall 60, shims or the jacking bolts 320 may be used (by individually threading each bolt 320 through the respective support plate 318) to adjust the level of the cap plate 314 of the foundation 50 or wall 60. Shims (e.g., 308 in FIG. 3A) may also be employed to level the bottom end plate 704 of the precast panel 310 relative to the cap plate 314.
Next, using a hoisting rig, construction workers may install one or more support frames 120, 122, 124 (consistent with the support frame 2050) for a first tier 112a of precast panels (step 2704). Each support frame 120, 122, 124 may be previously constructed (consistent with the support frame 2050) to include removable or temporary posts 2052a and 2052b and 2054a and 2054b to connect cross beams of the precast panels as shown and described, for example, in reference to FIGS. 20A and 20B. In this implementation, the temporary posts 2052a and 2052b and 2054a and 2054b are used to support the respective support frame 120, 122, 124 when the primary cross beam (i.e., the lowest cross beam of the support frame 2050) is attached to a foundation 50 or wall 60 before a first tier 112a precast panel is erected to form the precast wall system 100. At this stage in the process 2700, additional beams 2802a and 2802b as shown in FIG. 28 may be installed and connected between the support frames 120, 122, and 124 to complete the structural framing for the first tier 112a of the precast wall system 100.
Using a hoisting rig, an erection aid platform 2400 may next be installed at each top corner of the foundation walls 60 (step 2706) as described in reference to FIG. 24. Although not shown in FIG. 28 to avoid obscuring other aspects of the first tier 112a of the precast wall system 100 to be constructed, each erection aid platform 2400 functions to brace precast panels on two respective walls (2806 & 2808, 2808 & 2810, 2810 & 2812 and 2812 & 2806 in FIG. 28) before installation of a corner precast panel 104 that horizontally connects the two respective walls as previously described and shown in reference to FIG. 24. Thus, the erection aid platforms 2400 enable each wall 2806, 2808, 2810 and 2812 of the current tier 112a, 112b or 112c of precast panels 102, 104, 106, 108 or 110 to be erected and aligned and plumbed relative to the foundation 50 or wall 60 or lower tier (e.g., 112a or 112b) of precast panels before the precast panel walls 2806, 2808, 2810 and 2812 of the current tier 112a, 112b or 112c are interconnected via precast corner panels 106. Accordingly, alignment errors between adjacent precast panel walls 2806, 2808, 2810 and 2812 is limited or avoided.
Returning to FIG. 27A, a precast panel is selected to be erected (step 2708). In a preferred selection sequence, the first precast panel selected to be erected requires a connection to a previously erected support frame 120, 122 or 124 and the next precast panel to be erected is the precast panel designed to be disposed opposite to the first precast panel and connected to the other end of the respective support frame 120, 122, or 124. In the example erection sequence depicted in FIG. 28, the interior precast panel referenced as “1” is selected as the first precast panel to be erected since the precast panel 1 requires a connection to the support frame 120. The next precast panel that will be selected to be erected is the opening precast panel referenced as “2” in FIG. 28, which is disposed opposite to the interior precast panel 1 and is to be connected to the same support frame 120.
Next, a hoisting rig is connected to the selected precast panel (step 2710). In one implementation, each precast panel 102, 104, 106, 108 and 110 to be erected in each tier 112a, 112b and 112c of the precast wall system 100 has angle brackets 2500c and 2500d (as shown in FIG. 25) attached to and aligned with the top end plate 702 of the precast panel. The bore 2514 of each bracket 2500c and 2500d may then used as attachment points for the hoisting rig to lift the selected precast panel into position within the precast wall system 100. Alternatively, each precast panel may be formed consistent with the precast panels 2602a and 2602b depicted in FIGS. 26A-26D to have a first plurality of lifting lugs 2600a and 2600b (“top lugs 2600a and 2600b”) attached in proximity to and spaced about the top end 710 or top end plate 704 so that the first end 2606 of each lifting lug 2600a and 2600b extends beyond and curves away from the top end 710 or top end plate 702. The hoisting rig may connect to the attachment points 2608 of the top lugs 2600a and 2600b to lift the selected panel into position within the precast wall system 100. A second plurality of lifting lugs 2600c and 2600d (“bottom lugs 2600c and 2600d”) may be attached in proximity to and spaced about the bottom end 712 or bottom end plate 704 of the selected precast panel (consistent with the precast panel 2602b in FIG. 26A) so that the first end 2606 of each of the bottom lifting lugs 2600c and 2600d is able to effectively capture the outside edges of the foundation walls 60 (or the top end 710 of a lower tier precast panel such as 2600a in FIG. 26A) and guide the selected (or upper) precast panel towards the foundation wall 60 (or the top end 710 of the lower tier precast panel 2602a) such that the bottom end 712 (or bottom end plate 704) of the selected or upper precast panel (2600b in FIG. 26A) is substantially aligned with the top end 710 (or top end plate 702) of the lower precast panel (2600a in FIG. 26A).
If in step 2712 it is determined that the design of the precast system 100 specifies that a vertical reinforcing bar is not required to complete the vertical connection of the selected precast panel to the foundation 50, wall 60, or a lower tier precast panel, then the erection process continues at step 2726. If a vertical reinforcing bar is required and it is determined in step 2714 that a first vertical reinforcing bar or segment 728a is not present in the foundation 50 or foundation wall 60 or lower tier precast panel, then a first vertical reinforcing bar segment 728a is inserted in a duct of the foundation 50, foundation wall 60, or lower tier panel (2716). The selected precast panel is then lowered via the hoisting rig to within a predetermined distance (e.g., approximately 18 inches) above the foundation 50 or foundation wall 60 (or to a lower tier precast panel once the first tier 112a is erected) (step 2718).
If vertical bar-to-bar couplers 326 are to be used to connect vertical reinforcing bar segments 728a and 728b to form a continuous vertical reinforcing bar 728 and a first vertical reinforcing bar segment 728a is present in the foundation or lower tier panel, then a vertical bar-to-bar coupler 326 is attached to the first vertical reinforcing bar segment 728a (step 2720). A second vertical reinforcing bar segment 728b is then inserted in a duct 724 of the selected precast panel that is aligned with the first vertical reinforcing bar segment 728a (step 2722). Step 2722 may be omitted if the second vertical reinforcing bar segment 728b was previously installed in the duct 724 of the selected precast panel before the panel was connected to the hoist rig and lowered into place in step 2714. The second vertical reinforcing bar segment 728b is attached to the vertical bar-to-bar coupler 326 (step 2724) to incrementally form a continuous vertical reinforcing bar 728 through each vertically adjacent precast panels in a plurality or all tiers 112a, 112b or 112c of the precast wall system 100 to be erected. If the selected precast panel has more than one duct 724 and corresponding vertical reinforcing bar segment 728b, steps 2720, 2722 and 2724 may be repeated to align and couple each vertical bar segment 728b in the selected precast panel to a corresponding vertical bar segment 728a present in the foundation or lower tier panel.
Next, the selected precast panel is lowered to its final position atop the foundation 50, wall 60 or lower tier precast panel (step 2726). In the implementation in which bottom lugs 2600c and 2600d are attached in proximity to and spaced about the bottom end 712 or bottom end plate 704 of the selected precast panel, the first end 2606 of each of the bottom lifting lugs 2600c and 2600d is able to effectively capture the outside edges of the foundation walls 60 (or the top end 710 of a lower tier precast panel such as 2600a in FIG. 26A) and guide the selected (or upper) precast panel towards the foundation wall 60 (or the top end 710 of the lower tier precast panel 2602a) such that the bottom end 712 (or bottom end plate 704) of the selected or upper precast panel (2600b in FIG. 26A) is substantially aligned with the top end 710 (or top end plate 702) of the lower precast panel (2600a in FIG. 26A). However, the selected precast panel may be further aligned, plumbed and shimmed (as necessary) relative to the foundation wall 60 or lower tier precast panel (step 2728) using standard bore sighting equipment or alignment tools.
Next, it is determined whether the selected precast panel requires a connection to one of the erection aid platforms (step 2728). If selected precast panel does not require connection to an erection aid platform, then processing continues at step 2732. Otherwise, the selected precast panel is temporarily attached to one of the erection aid platforms (step 2730). As previously noted, each erection aid platform 2400 functions to brace precast panels on two respective walls (2806 & 2808, 2808 & 2810, 2810 & 2812 and 2812 & 2806 in FIG. 28) before installation of a corner precast panel 104 that horizontally connects the two respective walls. For example, precast panels 4 and 6 of wall 2810 and precast panels 31 and 33 of wall 2808 may be braced by one erection aid platform 2400 before the corner precast panel 35 is installed and horizontally interconnected to adjacent panels 6 and 33 using one of the disclosed horizontal panel-to-panel connections 602. As previously described in reference to FIG. 24, the selected precast panel may be temporarily attached, via one or more right angle brackets 2410a-2410e, to one of the beam members 2404a or 2404d of the erection aid platform 2400 that is bracing the selected precast panel. The right angle brackets 2410a-2410e are not over tightened to enable the selected precast panel to be aligned, plumbed, and shimmed (as necessary) relative to the foundation 50, wall 60 or lower tier precast panel in step 2732.
Once the selected precast panel is lowered to its final position, aligned, plumbed, and shimmed as necessary, the vertical panel-to-panel connection 604 between the selected panel and foundation wall 60 or lower tier precast panel is completed (step 2734). For example, if the selected precast panel is formed with end plates consistent with the precast panels disclosed herein, the bottom end plate 302, 704, 1308, or 1408 of the selected precast panel is connected (for example, via welding, bolting or clamping) to the cap plate 314 embedded in the foundation wall 60 or to the top end plate 702, 1306 or 1406 of a previously erected lower tier precast panel.
Alternatively or in addition to connecting end plates between vertically adjacent precast panels, if the precast panels are formed to include structural angles 2302a-2302d, the structural angles 2302a-2302d of the selected precast panel may be welded or affixed to the cap plate 314 of the foundation 50 or wall 60 or to corresponding structural angles 2302a-2302d of a lower tier precast panel as previously described herein.
In addition, once the erection, pluming and alignment of the selected panel is completed, the ducts 724 of the selected panel are filled with grout to lock the vertical reinforcing bar segment 728b in place. Alternatively, the grouting of the ducts 724 of each precast panel in the current tier may be performed after step 2748 after the erection, pluming and alignment of all the precast panels in the current tier is completed. The grouting may be performed on the first two tiers of precast panels after the two tiers of panels have been erected to facilitate bar 728a to bar 728b alignment.
Next, it is determined whether the selected precast panel requires a connection to the support frame (step 2736). For example, in the exemplary erection sequence depicted in FIG. 28, the precast panels 1 and 2 require a connection to the support frame 120, the precast panels 10 and 11 require a connection to the support frame 122, and the precast panels 16 and 17 require a connection to the support frame 124. Other precast panels 3, 8, 9, 26 and 27 require an indirect method (e.g., a beam-to-panel connection) to connect a structural beam (e.g., a floor beam) to one of the support frames 120, 122, or 128 as part of the bracing system 118 of the precast wall system 100. Such connections to precast panels 3, 8, 9, 26 and 27 may be performed in step 2738.
If the selected precast panel does not require a connection to a support frame 120, 122 or 124, then processing continues at step 2740. Otherwise, the selected precast panel is connected to the respective support frame 120, 122 or 122 as required (step 2738). For example, each of the precast panels 1, 10, and 16 may be connected to cross beams 2002 and 2034 and brace member 2004 of the respective support frame 120, 122 or 124 consistent with the manner in which the precast panel 102b is connected to the support frame 2000 or 2050 as previously described in reference to FIGS. 20A-20D. Similarly, each of the precast panels 2, 11, and 17 may also be connected to cross beams 2002 and 2034 and a brace member 2004 or 2012 of the respective support frame 120, 122 or 124 consistent with the manner in which the precast panel 106b is connected to the support frame 2000 or 2050 as previously described herein. Precast panels 3, 8, 9, 26 and 27 may be formed to implement any one of the beam-to-panel connections 608 in described herein, such as depicted and described in reference to FIG. 18A.
It is then determined whether the selected precast panel requires a horizontal panel-to-panel connection that can be completed with a previously precast panel horizontally adjacent to the selected precast panel (step 2740). If no such horizontal connections are required, then processing continues at step 2744. Otherwise, the horizontal panel-to-panel connection or connections 602 between the selected panel and each horizontally adjacent precast panel is completed (step 2742). For example, if the selected precast panel and adjacent precast panels are formed to include embedded side plates 720 consistent with the panels 700 or 702, the horizontal panel-to-panel connection 608 may be implemented by welding or bolting the corresponding aligned side plates of the two precast panels. Alternatively or in addition, if the selected precast panel and adjacent precast panels are each formed to include embedded structural angles 2302a-2302d on the edges 2306a-2306d of the panels consistent with the panel 2300 or 2602a depicted in FIGS. 23 and 26, the horizontal panel-to-panel connection 608 may be implemented by welding the corresponding aligned structural angles of the selected precast panel and each adjacent precast panel. In addition or alternatively, the selected precast panel and adjacent precast panels may be formed with horizontal ducts 904 to accommodate a horizontal reinforcing bar 906 inserted in the axially aligned ducts 904 of the selected precast panel and the adjacent precast panel as described, for example, in reference to FIG. 9.
Once the selected precast panel is horizontally interconnected to previously erected adjacent precast panels, in step 2750 it is determined whether there are more precast panels are required to complete current tier 112a, 112b or 112c of the precast wall system 100 (step 2744). If there are more precast panels required to complete the current tier (e.g., tier 112a in FIG. 18), the processing continues at step 2708 until each panel, including corner precast panels 104 (e.g., panels 34, 35, 36 and 37 in FIG. 28) are horizontally interconnected to complete the erection of the current tier (e.g., 112a).
If all the precast panels in the current tier have been erected and horizontally connected, then each of the temporary posts 2052a and 2052b and 2054a and 2054b employed in the support frames may be removed (step 2746). Once the precast panels requiring a connection to a respective support frame 120, 122, or 124 are actually connected to the respective support frame 120, 122, or 124 in accordance with the present invention, the temporary posts 2052a and 2052b and 2054a and 2054b are no longer needed to stabilize the secondary cross beam 2034 to one of the primary cross beams 2002 or 2032 of support frame 120, 122, or 124.
Similarly, once all the precast panels in the current tier have been erected and horizontally connected, then the connections between panels and erection aid platforms via the right angle brackets 2410 may be removed (step 2748).
If it is determined in step 2750 that more tiers (e.g., 112b and 112c) of precast panels need to be erected to complete the construction of the precast wall system 100, then each support frame 120, 122, and/or 124 for the next tier of precast panels (e.g., 112b or 112c) is installed relative to the last tier of precast panels (step 2752). For example, as shown in FIG. 20A, the brace members 2004 and 2012 of the support member 2000 (or the brace members 2004a and 2012a of the support member 2050) for a next tier 112b are connected to the gusset plate 1704 of a lower precast panel (e.g., the gusset plates of panels 102b and 106b that are disposed above the cross beam 2002 of the lower tier support frame 2000 depicted in FIG. 20A or the lower tier support frame 2050 in FIG. 20D) before the next tier precast panel (e.g., erected atop panels 102b and 106b) is lifted into position and connected to this next tier support member 2000 or 2050.
In addition, each erection aid platform 2400 is lifted to respective top corner of the previously erected tier of precast panel walls (step 2754) and processing is then continued at step 2708. In the example shown in FIG. 28, each erection aid platform 2400 is lifted to a respective top corner of the tier 112a of precast walls, where each top corner is defined by the corner precast panels 34, 35, 36, and 37 in FIG. 28. The erection aid platforms 2400 may each be lifted and supported relative to the top corner of the previously erected tier 112a as described in reference to FIG. 24.
If no more tiers (e.g., 112b and 112c) of precast panels need to be erected to complete the construction of the precast wall system 100, then each erection aid platform 2400 may be disconnected from the precast wall system and removed (step 2756). The erection aid platforms 2400 may be disassembled and stored or shipped to another site for use in erecting another precast wall system for another high-rise building.
The precast wall system 100 and precast panels 102, 104, 106, 108 and 110 as described herein retain the advantages of a cast-in-place concrete core wall while eliminating the field labor intensity associated with layout, formworks, field installed rebar, field locating and placement of embedded plates, concrete pouring, curing, forms stripping or jacking in the case of a mechanized forming system. A precast wall system consistent with the present invention is also able to serve as the main lateral bracing system of the building as well as the support for the gravity loads or function in combination with typical systems used for high-rise buildings (e.g., perimeter frame with outriggers). Thus, a precast core or perimeter wall system consistent with the present invention is a more efficient, cost effective and viable alternate to cast-in-place construction.
The foregoing description of an implementation of the invention has been presented for purposes of illustration and description. It is not exhaustive and does not limit the invention to the precise form disclosed. Modifications and variations are possible in light of the above teachings or may be acquired from practicing the invention. Accordingly, while various embodiments of the present invention have been described, it will be apparent to those of skill in the art that many more embodiments and implementations are possible that are within the scope of this invention. Accordingly, the present invention is not to be restricted except in light of the attached claims and their equivalents.