Claims
- 1. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig on a carrier suspended from a ceiling of the elevator shaft, the carrier being mounted in place from the top floor.
- 2. The procedure as defined in claim 1, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 3. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the top floor has a landing and wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig on a carrier fixed to the landing of the top floor.
- 4. The procedure as defined in claim 3, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 5. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the elevator shaft has at least one wall and wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig on supporting elements attached to the at least one wall of the elevator shaft.
- 6. The procedure as defined in claim 5, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 7. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the top floor has a top floor door with jambs and wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig on the jambs of the top floor door.
- 8. The procedure as defined in claim 7, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 9. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the top floor has a top floor door and wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig on a front wall of the top floor door.
- 10. The procedure as defined in claim 9, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 11. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the step of positioning the various pieces of shaft equipment includes the step of using the plumb lines and a gauge which is placed between the plumb lines and the shaft equipment.
- 12. The procedure as defined in claim 11, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 13. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; fixing the various pieces in place after the step of positioning; and installing the shaft equipment by lifting the shaft equipment from the bottom of the shaft using an elevator car.
- 14. The procedure as defined in claim 13, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
- 15. A procedure for positioning and mounting shaft equipment in an elevator shaft, the elevator shaft having a top and a bottom, the top of the elevator shaft being adjacent to a top floor, the procedure comprising the steps of:mounting a plumbing jig in the elevator shaft, the step of mounting being carried out from the top floor and the plumbing jig being below the top of the elevator shaft; attaching plumb lines to the plumbing jig, the plumb lines being attached from the top floor; positioning various pieces of shaft equipment using the plumb lines attached to the plumbing jig; and fixing the various pieces in place after the step of positioning, wherein the step of mounting the plumbing jig and the step of attaching the plumb lines are carried out without scaffolds or ladders.
- 16. The procedure as defined in claim 15, wherein the step of mounting the plumbing jig comprises the step of mounting the plumbing jig above the top floor but below the top of the elevator shaft.
Priority Claims (1)
| Number |
Date |
Country |
Kind |
| 970970 |
Mar 1997 |
FI |
|
Parent Case Info
This application is the national phase under 35 U.S.C. §371 of prior PCT International Application No. PCT/FI98/00205 which has an International filing date of Mar. 6, 1997 which designated the United States of America, the entire contents of which are hereby incorporated by reference.
PCT Information
| Filing Document |
Filing Date |
Country |
Kind |
| PCT/FI98/00205 |
|
WO |
00 |
| Publishing Document |
Publishing Date |
Country |
Kind |
| WO98/40303 |
9/17/1998 |
WO |
A |
US Referenced Citations (8)
Foreign Referenced Citations (9)
| Number |
Date |
Country |
| 2194984 |
Mar 1988 |
GB |
| 54-138258 |
Oct 1979 |
JP |
| 5-139657 |
Jun 1993 |
JP |
| 5186160 |
Jul 1993 |
JP |
| 5-319729 |
Dec 1993 |
JP |
| 6009173 |
Jan 1994 |
JP |
| 6247661 |
Sep 1994 |
JP |
| 53-23447 |
May 1996 |
JP |
| 8-133623 |
May 1996 |
JP |
Non-Patent Literature Citations (1)
| Entry |
| Nakhov B.S. Skripka, B.F., “Montazh, naladka I ekspluatasiya liftov,” Izdatelstvo literatury po stroitelstvu, Moscow, 1973, p. 146, lines 1-6; with English translation. |