Claims
- 1. A method of controlling an elevator group including two or more elevators driven by hoisting machines and collectively controlled by a group control that adaptively assigns elevators to calls comprising:a) receiving a new landing call; b) simulating probable future landing calls responsive to activating the new landing call; c) allocating the probable future landing calls to the elevator group on the basis of the simulation of step b); and d) reallocating the elevator group to one or more old calls based on the simulation if a time period for reserving the one or more old calls has not been exceeded.
- 2. The method of claim 1, wherein said step (c) of allocating generates a statistical simulation of virtual passenger traffic generated on the basis of distribution and intensity of the passenger traffic prevailing at the moment.
- 3. The method of claim 1, wherein said step (c) of allocating generates the statistical simulation including calls, car commands, elevator states and elevator movements.
- 4. The method of claim 3, wherein, said simulation further includes that, passengers are generated for different floors in proportion to the arrival intensities and distributions, car commands are generated in accordance with probable intensities of passengers leaving the elevators, an arrival time, arrival floor and destination floor are assigned for each simulated person, the simulated persons give simulated landing calls and car commands, and elevator traffic is simulated according to the next stopping floor used in the simulation, selected by the control system.
- 5. The method of claim 4, wherein for each new landing call is registered in said step (a), simulation is immediately carried out in said step (b) for different elevators and the call is allocated to the one that gives minimum costs.
- 6. The method of claim 1 wherein the allocation is determined on the basis of computed elevator-specific cost for the call including a predicted cost of serving the new landing call and an additional cost due to the virtual traffic.
- 7. The method of claim 1 further including performing simulation and call reallocation even for old calls that are only going to be served after a certain length of time (TLim), and performing simulation of future operation regarding these calls using even calls that, one mode subsequent to a call assignment have to a elevator of said group.
- 8. The method of claim 1 wherein said simulation in said step b) is also based on forecast landing destinations.
- 9. The method of claim 8 wherein said step c) of allocating assigns the best car to answer all of the received elevator calls so that said group control produces a reduced average time between elevator call and delivery to destination floor.
Priority Claims (2)
| Number |
Date |
Country |
Kind |
| 973927 |
Oct 1997 |
FI |
|
| 973928 |
Oct 1997 |
FI |
|
Parent Case Info
This application is a Continuation of PCT International Application No. PCT/FI98/00791 filed on Oct. 10, 1998, which designated the United States, and on which priority is claimed under 35 U.S.C. § 120, the entire contents of which are hereby incorporated by reference.
US Referenced Citations (11)
Foreign Referenced Citations (3)
| Number |
Date |
Country |
| 0565864 |
Mar 1993 |
EP |
| A1565864 |
Oct 1993 |
EP |
| 331173 |
Aug 1991 |
JP |
Continuations (1)
|
Number |
Date |
Country |
| Parent |
PCT/FI98/00791 |
Oct 1998 |
US |
| Child |
09/547054 |
|
US |