The present invention relates to a procedure for the construction of underground transport infrastructures, mainly lines for the urban and metropolitan mass transport performed underground in double pipe configuration, each with a unidirectional single transport way.
As is known, the greater demand for mobility, the growing urbanization of the territory, pressing technological development, the increasing value of urban land and the investment capacity of institutions have resulted in considerable development as regards the construction of mass transport infrastructures, of the road, motorway, railway and underground railway type.
Such infrastructures mainly occupy underground space which offers areas available for sustainable development of infrastructures.
This development has also been strongly facilitated by the exponential technological development of excavating equipment which makes it possible to do works once prohibitive, in reliable times and at reliable costs, while respecting and totally safeguarding safety, the territory and pre-existences.
This has given rise to and permitted the building, planning and design of major infrastructures in terms of complexity and efficiency, aimed at minimizing risks and maximizing user safety.
Furthermore, the quest for continuous improvements to transport infrastructures, not only in terms of operating capacity and management but also of the safety of users during operation, involves further developments in technological installations and fittings which increase the value of the work.
In this respect, the fact is underlined that underground transport infrastructures stretching for long distances (over 2,000 m) base their safety concept during operation on the double pipe configuration, each of which unidirectional, connected to transversal passages called “bypasses” or “cross passages”.
In case of an accident, fire or other catastrophic event involving one of the two pipes, the transversal passages make it possible to place all the environments of the tunnel in communication to use the other pipe as a safe place and/or escape route.
The construction of the bypass tunnel is usually carried out after the two main pipes, which are excavated using special mechanical boring machines to support the balanced front, have been made.
This equipment makes excavating the main pipes of the tunnels efficient and safe with reliable and low building costs.
Building bypass tunnels on the other hand has no comparable excavation alternative using mechanized systems similar to the boring machines for excavating the main tunnels.
The building of the “cross passages”, in the majority of installations, requires the completion of excavations using traditional method, i.e., removing the earth with appropriate mechanical means (excavators, rippers, bucket excavators, . . . ) following a preliminary treatment of the soil so as to improve its mechanical characteristics.
The excavation operations are performed following a defined time sequence which envisages:
after the demolition of part of the tunnel lining, bypass excavation, which is performed using excavators and other machines for recesses of about one metre followed by the installation of the first-phase lining, generally consisting of shotcrete reinforced with metal profile sections, known as centring;
Such infrastructures are habitually used in the following two ambits:
It is therefore easy to appreciate that the construction of underground transport infrastructures complete with bypass tunnels is a very complex and problematic activity, in particular when performed in urban and metropolitan contexts, and the need is strongly felt to find cutting edge technology and innovative solutions such as to allow building the above installation parts in an efficient, safe and easily repeatable way, so as to maximize the benefits and minimize risks, above all where reference is made to the bypass tunnel building phase. The excavation and bypass building method most widely used to date in fact certainly does not achieve the level of mechanization and industrialization applicable for the excavation of the main tunnels.
The procedures used, above all in the case of work excavations and consequently cross passages involving loose soils, underneath the water table, in particularly sensitive urban contexts, are rather complex, localizing in the areas of reference particularly difficult soil consolidation and impermeabilization jobs (freezing, injections by means of concrete and/or chemical mixes) in order to allow excavating bypass tunnels in conditions of safety for the workers and the urban context.
The above jobs involve a number of difficulties/critical situations, listed below:
The main aim of the present invention is to provide a procedure for the construction of underground transport infrastructures which permits introducing strongly developed and technologically advanced excavation methods which have an industrial type approach to therefore ensure quality and safety.
A further object of the present invention is to provide a procedure for the construction of underground transport infrastructures wherein it is possible to control, in a constant and rigorous way, the work erection process in terms of structural stability, minimize the impacts and interferences on the context, maximize safety for workers and everything that interferes with the excavation, and ensure compliance with deadlines and costs.
Another object of the present invention is to provide a procedure for the construction of underground transport infrastructures which allows overcoming the mentioned drawbacks of the state of the art within the ambit of a simple, rational, easy, effective to use and low cost solution.
The above mentioned objects are achieved by the present procedure for the construction of underground transport infrastructures having the characteristics mentioned in the enclosed claim 1.
Other characteristics and advantages of the present invention will become better evident from the description of a preferred but not exclusive embodiment of a procedure for the construction of underground transport infrastructures, illustrated by way of an indicative, but not limitative, example in the accompanying drawings in which:
By means of the procedure in accordance with the present invention, for example, transport infrastructures can be built such as roads, motorways, railways and underground railways, which are constructed underground in the double pipe configuration, each pipe being dedicated to a unidirectional single transport way.
The procedure, in particular, comprises a first step which consists in excavating at least an underground transport tunnel 1, 2, i.e., a tunnel able to house one of the above transport infrastructures.
The underground transport tunnel 1, 2 comprises a first pipe 1 and a second pipe 2 substantially parallel to one another.
The excavation of the pipes 1, 2 can be done using traditional methods (by means of the use of dynamite and/or roadheader) but preferably it is done using the mechanized method (using tunnel boring machines of the TBM or EPB type).
The adoption of the mechanized method permits conforming the pipes 1, 2 with a substantially constant circular section, with a diameter approximately equal to the diameter of the boring machine unless the inner lining 3 of the pipes themselves.
By way of example only, it is specified that the excavation of the pipes 1, 2 can be done with boring machines having a diameter of around 6-9 metres.
In the embodiment shown in the illustrations, for example, the diameter of the boring machine used for the excavation of the pipes 1, 2 is preferably equal to about 6.5 m.
The excavation of the two pipes 1, 2 is done so as to define a longitudinal direction D1, D2 for each pipe 1, 2, i.e., a path that can be rectilinear, curvilinear or mixed rectilinear-curvilinear.
More in detail, the excavation of the two pipes 1, 2 is done so these extend substantially horizontally; in other words, the inclination of the longitudinal directions D1, D2 with respect to a horizontal plane is substantially equal to 0° or in any case contained in a rather reduced interval, e.g., between 0° and 25°.
It must not be forgotten in fact that the pipes 1, 2 are part of a transport infrastructure of the road or railway type and, therefore, the possibility of the underground transport tunnel 1, 2 having a very accentuated gradient or, absurdly, vertical gradient, must be totally ruled out.
Once the construction of the first pipe 1 and of the second pipe 2 has been completed, the procedure according to the invention provides the step of making at least a bypass tunnel 4 connecting the first pipe 1 and the second pipe 2.
With reference to the embodiment shown schematically in
The construction phase of each bypass tunnel 4 comprises the following steps:
The launching chamber 5 comprises a first base platform 8 on which is fitted a thrust system 13, 14.
The first base platform 8 has a first side 8a which, in use, is turned towards a first portion 1a of the first pipe 1 through which the tunnel boring machine 6 will pass to excavate the bypass tunnel 4.
The first base platform 8 also has a second side 8b, opposite the first side 8a.
The thrust system 13, 14 has two linear actuators 13, of the type of two hydraulic jacks fitted horizontally at a predefined height with respect to the first base platform 8, and a pusher block 14, fittable on the linear actuators 13 and movable with them.
The linear actuators 13 are associated with the first base platform 8 in correspondence to the second side 8b, wherein the launching chamber 5 also has a shaped reaction wall 9 substantially matching a second portion 1b of the first pipe 1.
The second portion 1b consists in a stretch of the first pipe 1 which is diametrically opposite the first portion 1a and is that which, in use, is adjacent to the second side 8b of the first base platform 8.
In practice, depending on the conformation of the first pipe 1 in correspondence to the first predefined portion P1, the reaction wall 9 has a corresponding outline.
In the embodiment shown in the illustrations, in which the first pipe 1 has a tube shape with a circular cross section, the reaction wall 9 consists of a circular cylinder stretch.
The arrival chamber 7 essentially consists of a second base platform 16 having a third side 16a which, in use, is turned towards a third portion 2a of the second pipe 2 through which the tunnel boring machine 6 will pass to excavate the bypass tunnel 4.
The second base platform 16 also has a fourth side 16b, opposite the third side 16a and designed to be positioned in the proximity of a fourth portion 2b of the second pipe 2, diametrically opposite the third portion 2a.
The tunnel boring machine 6 consists of an outer metal shield 21 shaped like a straight cylinder and having, at an axial extremity, a rotating head 22 bearing the actual excavation tools 23.
The tunnel boring machine 6 is sized so as to allow to be introduced and moved along the pipes 1, 2.
In the embodiment shown in the illustrations, for example, where the cross section of the pipes 1, 2 has an approximate diameter of 6.5 m, the tunnel boring machine 6 has an approximate diameter of 4 m and a length in axial direction of below 3 m, more precisely about 2.7 m.
Inside the outer metal shield 21 is a compartment 24 in which the excavated material is collected and which is designed to be transported outside the underground transport tunnel 1, 2.
The material excavated by the tunnel boring machine 6 can be extracted as it is or be mixed to a carrier fluid, of the bentonite mud type.
It is however underlined that, preferably, the discharge of the excavated material is obtained by means of a system 25 of the “slurry” type, i.e., a system that permits pumping the carrier fluid outside the outer metal shield 21 directly onto the material to be excavated.
During the excavation, the carrier fluid is mixed to the excavation material outside the tunnel boring machine 6, fills the space between the outer metal shield 21 and the profile of the land and is kept at a pressure such as to ensure the stability of the front and prevent the penetration of ground water, if present, ensuring the excavatability and safety of the excavation.
The excavated material mixed to the carrier fluid is therefore discharged through a system of tubes, not shown in the illustrations.
Before starting the actual excavation phase, therefore, the procedure according to the invention involves an additional phase which consists in the impermeabilization of the launching chamber 5 to the first pipe 1.
In practice, in correspondence to the first side 8a of the first base platform 8 the construction is envisaged of a first impermeabilization structure 10, which prevents the carrier fluid pumped by the tunnel boring machine 6 from flooding the first pipe 1.
The first impermeabilization structure 10 consists, e.g., of a first shaped wall 11 substantially matching the first portion 1a of the first pipe 1.
The first wall 11 has a first seal 12, of circular shape, through which the tunnel boring machine 6 passes.
With the first wall 11, furthermore, a first pressurization system can be usefully associated, not shown in detail in the illustrations, which pressurizes the first impermeabilization structure 10 to ensure its seal during the crossing of the tunnel boring machine 6.
Similarly, the procedure envisages an identical additional phase which consists in the impermeabilization of the arrival chamber 7 to the second pipe 2, which is implemented by envisaging the construction, in correspondence to the third side 16a of the second base platform 16, of a second impermeabilization structure 17, which prevents the carrier fluid pumped by the tunnel boring machine 6 from flooding the second pipe 2.
The second impermeabilization structure 17 consists, e.g., of a second shaped wall 18 substantially matching the third portion 2a of the second pipe 2.
The second wall 18 has a second seal 19, of circular shape, through which the tunnel boring machine 6 passes.
With the second wall 18, furthermore, a second pressurization system can be usefully associated, not shown in detail in the illustrations, which pressurizes the second impermeabilization structure 17 to ensure its seal during the crossing of the tunnel boring machine 6.
The excavation phase of the bypass tunnel 4 occurs by pushing the tunnel boring machine 6 along the transversal direction T by means of the thrust system 13, 14 present in the launching chamber 5.
For this purpose, the tunnel boring machine 6 is fitted on the first base platform 8 with the rotating head 22 turned towards the first portion 1a (
The excavation of the bypass tunnel 4 also comprises an additional phase which consists in conveying a plurality of precast segments 26 along the first pipe 1 up to the launching chamber 5 and placing the precast segments 26 one by one between the tunnel boring machine 6 and the thrust system 13, 14.
The precast segments 26 have a cylindrical ring shape with a central axis A.
The precast segments 26 have a fairly reduced length and diameter slightly below that of the tunnel boring machine 6; in the embodiment shown in the illustrations, for example, the length of the precast segments 26 is equal to about 1.2-1.5 m while the diameter is 3.96 m.
When the precast segments 26 are interposed between the tunnel boring machine 6 and the thrust system 13, 14, they are arranged coaxially to one another to form a tube which extends along the transversal direction T.
The excavation procedure thus continues with gradual forward movements substantially equal to the length of the precast segments 26 (as said equal e.g. to 1.2-1.5 m) operated by the thrust system 13, 14 which pushes both the precast segments 26 and the tunnel boring machine 6 (
Thanks to the system 25 of the “slurry” type, during the forward movement of the tunnel boring machine 6 along the transversal direction T, a pumping phase is envisaged of the carrier fluid on the material to excavate through the tunnel boring machine 6 and a discharge phase of the material to excavate mixed to the carrier fluid.
When the tunnel boring machine 6 reaches the second pipe 2, it breaks through the third portion 2a of the second pipe and rests on the second base platform 16.
The excavation of the bypass tunnel 4 is thus completed, the chambers 5, 7 and the tunnel boring machine 6 are removed by making them run along the pipes 1, 2 as far as the outside of the underground transport tunnel 1, 2, or until they are repositioned in approach to the next bypass tunnel 4.
Each bypass tunnel 4 excavated this way is designed to accommodate the future finishing and connecting works to the lining of the pipes 1, 2.
It has been found in practice how the described invention achieves the intended objects.
In particular, the fact is underlined that the procedure according to the invention permits: