This application claims priority of Taiwanese Patent Application No. 106104229, filed on Feb. 9, 2017.
The disclosure relates to a method of production planning.
A goal of production planning systems is to satisfy the costumer's demands on time and to optimize certain performance measures, such as maximizing revenue or minimizing cost. To reach this goal, the production planning system should effectively allocate the limited capacity of various resource types among different operations of different products by calculating the raw material releases, finished goods inventory/backorder levels of various products, production input quantities and work-in-process (WIP) inventory levels of the operations on the route of various products in future periods within the planning horizon.
According to the disclosure, a method of production planning is implemented by a computer device, and includes steps of: (a) collecting sample data points for a resource type, each of the sample data points representing an individual relationship among arrival workloads, initial work-in-process (WIP) workloads and input workloads of the resource type; and (b) establishing a capacity model that models a relationship among arrival workloads, initial WIP workloads and expected input workloads of the resource type according to the sample data points collected in step (a), a first predetermined objective function, and a first set of predetermined constraints.
According to the disclosure, a method of production planning for a group of products is proposed to include steps of: (a) receiving, by a processor, a plurality of sample data pieces for a resource type from at least one of a storage device or an input device, each of the sample data pieces representing an individual relationship among arrival workloads, initial work-in-process (WIP) workloads and input workloads of the resource type; and (b) generating, by a processor, capacity model data representing a capacity model that models a relationship among arrival workloads, initial WIP workloads and expected input workloads of the resource type according to the sample data pieces received in step (a), first pre-stored objective function data representing a first predetermined objective function, and first pre-stored constraint data representing a first set of predetermined constraints.
According to the disclosure, a computer system for production planning for a group of products is proposed to include an input device, a storage device and a processor. The input device is for input operation of a user. The storage device stores first pre-stored objective function data representing a first predetermined objective function, and first pre-stored constraint data representing a first set of predetermined constraints. The processor is coupled to the input device, the storage device, and is configured to: receive a plurality of sample data pieces for a resource type from at least one of the storage device or the input device, each of the sample data pieces representing an individual relationship among arrival workloads, initial work-in-process (WIP) workloads and input workloads of the resource type; and generate capacity model data representing a capacity model that models a relationship among arrival workloads, initial WIP workloads and expected input workloads of the resource type according to the sample data pieces, the first pre-stored objective function data, and the first pre-stored constraint data.
Other features and advantages of the disclosure will become apparent in the following detailed description of the embodiment (s) with reference to the accompanying drawings, of which:
Before the disclosure is described in greater detail, it should be noted that where considered appropriate, reference numerals or terminal portions of reference numerals have been repeated among the figures to indicate corresponding or analogous elements, which may optionally have similar characteristics.
Referring to
Terminologies used in the description are defined as follows. A resource type is a group of similar tools that are used to perform similar value-added activities on materials. A lot is a group of materials that are transported together between various resource types and processed together on a unit of a particular resource type. An operation is an activity (for instance, processing on a machine of a workstation or transportation between workstations or factories) performed on a lot by a tool of a particular resource type (a machine or a transport equipment). To be transformed into finished goods, a lot of raw materials has to undergo a pre-specified route, which defines a sequence of operations. An operation is defined by a required resource type, required processing time per product unit (in work-hours), and time lag between input and output (or, input-output time lag) of the operation. Note that two or more operations of various products may share the same resource type, where input of a lot means a beginning of the processing on materials of the lot by a tool of the required resource type, and output of a lot means the end of the processing on materials of the lot by a unit of the required resource type. Also, the input-output time lag of an operation for a lot may be longer than the actual processing time of the operation on the lot because it may take extra time, during which the tool is not occupied, to complete the operation. Lead time of an operation (or called operation lead time) consists of waiting time for an available tool of the required resource type of the operation and the input-output time lag of the operation. Release means that a lot of materials is ready and allowed to begin its first operation. Thus, total lead time of a lot is the time between the release and the completion of the lot, which is also equal to the sum of the operation lead times of all the operations of the lot. Arrival means that materials reach the required resource type of an operation and are ready to be processed by a tool of the resource type. Arrival time of a lot to an operation may not be equal the input time of the lot to the operation because all of the tools of the required resource type may be busy with other lots or may have broken down and the arrival lot has to wait. The difference in the arrival time and the input time of a lot is the waiting time for the lot.
Work-in-process (WIP) refers to materials that are not in the form of finished goods and that are waiting for a tool to be processed or transported. A workload on a resource type refers to an aggregate processing time that is usually measured in work-hours and that is requested by a group of lots for various operations. WIP in this embodiment refers to materials that are waiting for a particular resource type at a particular time point. The WIP workload at a particular time point (or, called epoch) refers to total processing time (in work-hours) of all lots that wait for required resource types for various operations at that time.
In general, a resource type has limited available capacity and a lot of materials has to wait in queue of the resource type when all tools of the resource type are unavailable. Input quantity to a resource type is constrained due to the limited capacity. Materials that can be input for processing or transport in a period come from two possible portions: one is the initial WIP (the materials waiting in the queue) at the beginning of the period and the other is the materials that arrive in the period. Under the condition of no arrival material to a resource type in a period (where the arrival material refers to material that arrives the resource type during the period), the materials of the initial WIP at the beginning of the period can be inputted to the resource type for processing/transport as long as their total capacity requirement is less than the available capacity in the period of the resource type since these materials are ready at the beginning of the period. Hence, when there is no arrival material in a period, the relationship between initial WIP workload and input workload (i.e., workload for material that is inputted to the resource type) is that as shown in
The following indices are used to precisely and concisely describe the embodiment, and are defined as follows. An index value denotes a unique entity. For example, g denotes an index of a product. Then, g=1 denotes product No. 1, g=2 denotes product No. 2, g=3 denotes product No. 3, etc. The indices used herein include:
g: an index of a product;
G: a set of all products;
p,q: an index of a period, p=1, . . . , P, q=1, . . . , P, where P denotes the last period;
t: an index of a period in a historical database or simulation, or an index of a sample data point;
l: an index of an operation;
L(g): the last operation of a product g;
k: an index of a resource type;
K: a set of all resource types;
i: an index of an end point on an x-axis, an index of an approximate plane, or an index of a triangle on an x-y plane of z=0 for empirical capacity model of a resource type, where i=0, 1, . . . , I, where I is a predetermined parameter which will be described later; and
j: an end point index on a y-axis, where j=0 or 1.
Various notations are defined in the following presentation. A notation represents a data table or file in computer database systems. For example, ugl denotes processing time per product unit of an operation l of a product g. For example, a data table of ugl may look like Table 1, which shows that the processing time per product unit of operations 1, 2 and 3 of a product 1 are 2.0, 1.5, and 1.8 hours, respectively, and the processing time per product unit of the operations 1, 2 and 3 of a product 2 are 1.0, 1.2, and 1.6 hours, respectively.
The embodiment of the production planning method uses an LPPP model including a sample data point collection module, an approximate surface fitting module, a plane parameter calculation module, a plane reduction module, an input coefficient calculation module, and an LPPP calculation module, which may be realized by a processor executing a software program.
The sample data point collection module collects sample data points for each resource type to build a relationship among initial WIP workloads, arrival workloads and input workloads of a period for the resource type. Each of the sample data points has an individual relationship among arrival workloads, initial WIP workloads and input workloads of the resource type. The sample data points may be collected from a manufacturing database system which may be built in the storage device, from a simulation program that simulates the actual manufacturing system, or from user input through the input device.
The sample data point collection module calculates the initial WIP workload, the arrival workload and the input workloads in a period by multiplying their respective quantities (in product units) by the processing time per product unit of the associate operation. The procedure to calculate three-coordinate values of sample data points is described as follows.
The sample data point collection module has module input data, module output data, and a module procedure listed as follows.
The module input data of the sample data point collection module includes:
ugl: processing time (in work-hours) per product unit of an operation l of a product g;
Qgtl: an arrival quantity (in product units) to an operation l of a product g in a period t;
Mgtl: a WIP level (in product units) of an operation l of a product g at the beginning of a period t;
Egtl: an input quantity (in product units) to an operation l of a product g in a period t; and
k′gl: a resource type required by an operation l of a product g.
The module output data of the sample data point collection module includes:
{tilde over (x)}kt: arrival workload (in work-hours) of a resource type k in a period t;
{tilde over (y)}kt: WIP workload (in work-hours) of a resource type k at a beginning of a period t; and
{tilde over (z)}kt: input workload (in work-hours) of a resource type k in a period t.
The module procedure of the sample data point collection module is that:
For a resource type k, the values of the three coordinates of a data point t are ({tilde over (x)}kt, {tilde over (y)}kt, {tilde over (z)}kt). Then, the available capacity model of the resource type k is empirically constructed from ({tilde over (x)}kt, {tilde over (y)}kt, {tilde over (z)}kt) ∀t.
Referring to
In the following description, ck denotes an available capacity (in work-hours) in a period of a resource type k, ai denotes an x-value (arrival workload) of an i-th end point on the x-axis (i=0, 1, . . . , I), and Tki denotes an expected input workload of resource type k in a period when the arrival workload is ai and the initial WIP workload is zero.
Furthermore, there is only one segment on the y-axis (no arrival workload). The y-value of the approximate plane-wise surface of the resource type k corresponds to the end point of the segment and equals ck, also denoted as s1, for the resource type k. The approximate plane-wise surface of the resource type k consists of (I+1) lines that can also be indexed by i and i=0, 1, . . . , I. Line i is obtained by connecting the point (0,ck,ck) and the point (ai,0,Tki). Then, two neighboring lines i and i+1 obtained in this way determine a plane, and thus a total of (I+1) such planes can be constructed to approximate available capacity of a resource type k under different combinations of initial WIP workload and arrival workload in a period. These planes are concave because the intersection of these plane-wise surfaces and plane y=0 is a piece-wise curve that is enforced to be concave by the constraint in the surface fitting linear programming model, as described later. Concavity is essential to the LPPP model in this embodiment. Projecting the boundary line between two neighboring planes to the x-y plane of z=0 generates I triangles on the x-y plane. Note that the last plane (the (I+1)-th plane with index I) is not a triangle. The triangles on the x-y plane of z=0 and their corresponding approximate planes can both be indexed by i, which is also used to index the end points on the x-axis.
In addition, this model enforces the last plane (i.e., the (I+1)-th plane with index I) to be equal to plane z=ck, in which ck is the available capacity (in work-hours) in a period of a resource type k and is the maximum possible input workload for a resource type k in a period.
Let Ψki be a set of all data points whose (x,y) values belong to a triangle i on the x-y plane of z=0 for a resource type k. The z-values (expected input workload) of all the data points in a triangle are projected by the corresponding plane of the approximate surface.
In this embodiment, a plane i of a resource type k is defined by three points (0,ck,ck), (ai,0,Tki), and (ai+1,0,Tk,i+1) and it is used to project the expected input workload from a pair of arrival workload (x value) and initial WIP workload (y value) in a period that is in a triangle i. In addition, parameters Dki, Aki, and Bki are required to describe plane i of resource type k in LPPP model and are calculated from the three points, (0,ck,ck), (ai,0,Tki), and (ai+1, 0, Tk,i+1).
For each resource type k of all resource types, linear programming problem LPk outlined as follows can be formulated and solved to obtain the plane-wise surface to approximate the empirical capacity limits for resource type k.
The surface fitting linear programming problem LPk may be formulated by:
parameters of:
{tilde over (y)}kt: initial WIP workload (in work-hours) at a beginning of a period of a data point t, ∀t;
{tilde over (z)}kt: input workload (in work-hours) in a period of a data point t, ∀t;
ck: available capacity (in work-hours) of resource type k in a period;
ai: an x-value of the i-th end point on the x-axis, i=0, . . . , I; and
sj: a y-value of the j-th end point on y-axis, where s0=0 and s1=ck;
θki: the number of data points in Φki;
sets of:
Ψki:{(x,y)|ckx+aiy−aick>0 and ckx+ai+1y−ai+1ck≤0}i=0, . . . ,I−1; and
ΨkI:{(x,y)|ckx+aIy−aIck>0};
Φki:{t|({tilde over (x)}kt,{tilde over (y)}kt)∈Ψki},i=0, . . . ,I;
decision variables of:
Tki: expected input workload that can be inputted for being processed when the y-value (initial WIP workload) is zero and the x-value (arrival workload) is ai, i=0, . . . , I;
Dki: a z-intercept of a plane i, which is defined by the three points (ai,0,Tki), (ai+1,0,Tk,i+1), and (0,ck,ck), i=0, . . . , I−1, and a plane I is defined as a plane of z=ck;
Okt: over-estimated input workload of a data point t in LPk, ∀t;
Ukt: under-estimated input workload of a data point t in LPk, ∀t;
kt: an expected z-value (input workload) of a data point t whose x-value is {tilde over (x)}kt and y-value is {tilde over (y)}kt and is projected by plane-wise approximation of the empirical capacity surface, ∀t;
an objective function of
which is subject to constraints of:
Function (1) is an objective function that minimizes a sum of the absolute deviation between the expected input workload (
The approximate surface fitting module has module input data, module output data, and a module procedure listed as follows.
The module input data of the approximate surface fitting module includes:
{tilde over (x)}kt: arrival workload (in work-hours) in a period of a data point t, ∀t;
{tilde over (y)}kt: initial WIP workload (in work-hours) at a beginning of a period of a data point t, ∀t;
{tilde over (z)}kt: input workload (in work-hours) in a period of a data point t, ∀t;
ck: available capacity (in work-hours) of resource type k in a period;
ai: an x-value of an i-th end point on the x-axis, i=0, . . . , I; and
sj: a y-value of a j-th end point on the y-axis, where s0=0 and s1=ck.
The module output data of the approximate surface fitting module includes:
Tki: expected input workload that can be inputted for being processed when the y-value (initial WIP workload) is zero and the x-value (arrival workload) is ai, i=0, . . . , I; and
Dki: a z-intercept of plane i, which is defined by three points (ai, 0,Tki), (ai+1,0,Tk,i+1), and (0,ck,ck); and
The module procedure of the approximate surface fitting module is that:
After the approximate surface fitting module solves the linear programming module LPk for a resource type k, plane i of resource k is defined by the equation z=Dki−Akix-Bkiy, and the plane parameter calculation module is used to calculate the parameters Aki and Bki.
The plane parameter calculation module has module input data, module output data, and a module procedure listed as follows.
The module input data of the plane parameter calculation module includes:
ck: available capacity of a resource type k in a period;
ai: an x-value of the i-th end point on x-axis, i=0, . . . , I;
Tki: expected input workload that can be inputted for being processed when the y-value (initial WIP workload) is zero and the x-value (arrival workload) is ai, i=0, . . . , I; and
Dki: a z-intercept of a plane i, which is defined by three points (ai,0,Tki), (ai+1,0,Tk,i+1), and (0,ck,ck).
The module output data of the plane parameter calculation module includes:
Aki: a coefficient of arrival workload of a plane i of a resource type k; and
Bki: a coefficient of initial WIP workload of a plane i of a resource type k.
The module procedure of the plane parameter calculation module is that:
The plane reduction module reduces complexity of the empirical capacity constraints of the LPPP model, thereby reducing time required for calculation. In detail, the plane reduction module determines whether or not a difference between arbitrary two of the planes of the plane-wise surface, which is constructed by the approximate surface fitting module, satisfies a predetermined condition; and modifies the plane-wise surface by removing one of said arbitrary two of the planes from the plane-wise surface when the difference between said arbitrary two of the planes satisfies the predetermined condition. For instance, when the plane reduction module determines that the values of Dk,i1, Ak,i1, and Bk,i1, respectively, of plane it of a resource type k are very close to Dk,i2, Ak,i2, and Bk,i2, respectively, of plane i2 of the resource type k, the plane reduction module adds only the plane i1 to the empirical capacity constraint of the resource type in the LPPP model. As an example, if each of the absolute values of the fractions
is less than a very small value (for instance, 10−6), plane i2 is removed from the approximate plane-wise surface of the empirical capacity of the resource type k. In some embodiments, the plane reduction module may be omitted.
The plane reduction module has module input data, a function, a variable, module output data, and a module procedure listed as follows.
The module input data of the plane reduction module includes:
Aki: a coefficient of arrival workload variable of a plane i of a resource type k, •i;
Bki: a coefficient of initial WIP workload variable of a plane i of a resource type k, •i; and
δ: a predetermined value which is very small, for instance 10−6.
The function of the plane reduction module is that:
|x|: an absolute value of x; i.e., |x|=x, if x≥0; |x=−x, if x<0.
The variable of the plane reduction module is:
i′: an index of currently added plane.
The module output data of the plane reduction module is:
Ī(k): a set of all planes that are used in the LPPP model to approximate the empirical capacity surface of resource type k.
The module procedure of the plane reduction module is that:
The input coefficient calculation module determines, for each target period of each operation of each product, an input-output relationship between an output quantity in a target period and input quantity or input quantities in at least one period which is not later than the target period according to a predetermined input-output time lag of an operation by calculating input coefficients to express an output quantity in the target period of an operation as a linear function of input quantities in various periods of the operation. Input quantity to an operation in a given period will lead to output quantity of the operation, which may spread over several periods. In addition, the output quantity from an operation in a period will also be equal to the arrival quantity to its downstream operation in the same period. Under a uniform assumption of input rates in a period, the input-output time lag of an operation can be used to determine a fraction of the input quantity in each of the previous periods that contribute to the output quantity of the operation in a particular period.
The input-output relationship is expressed as:
Y
gpl=Σq=1peglpqXgql,l=1, . . . ,L(g),p=1, . . . ,P,g∈G
eglpq: a coefficient for a period q and a target period p of an operation l of a product g, and represents a fraction of an overlapping period between the previous period q and a target input period of the period p to the period q, where the target period has a length equal to that of the target input period, which is obtained by shifting the target period by the predetermined input-output time lag;
L(g): a final operation of the product g;
Xgql: an input quantity to an operation l of the product g in the period q; and
Ygpl: an output quantity from an operation l of the product g in the target period p.
In more detail, the input coefficient calculation module has module input data, a function, program variables, module output data, and a module procedure listed as follows.
The module input data of the input coefficient calculation module includes:
τp: a number of working days from the beginning of period 1 (time 0) until the end of period p, p=1, . . . , P, and τ0=0; and
fgl: an input-output time lag of operation l of product g.
The function of the input coefficient calculation module is:
{tilde over (p)}(τ): the smallest period index p such that τp>τ.
The program variables of the input coefficient calculation module include:
q−: a period that covers the left input epoch of an output period; and
q+: a period that covers the right input epoch of an output period.
The module output data of the input coefficient calculation module includes:
eglpq: the coefficient of Xgql in expressing Ygpl, where Xgql represents an input quantity to an operation l of a product g in a period q, which is limited by the empirical capacity constraint; and Ygpl represents an output quantity from operation l of product g in a period p (i.e., the target period), which is equal to an arrival quantity from an operation l to an operation l+1 of a product g in the period p.
An input epoch of an operation is obtained by shifting a corresponding output epoch by the input-output time lag of the operation fgl. Let q−={tilde over (p)}(τp-1−fgl) and q+={tilde over (p)}(τp−fgl). Two possible cases are described as follows.
In a first case, the input epoch, i.e., the time interval [τp-1−fgl, τp−fgl], is contained in the same period, as shown in
That is,
In a second case, the time interval [τp-1−fgl, τp−fgl] spans over more than one period, as shown in
and the coefficient of Xg,q
For q=q−+1, . . . , q+−1, the coefficient of variable Xgql is 1; that is, all the input quantity in each of these periods can be finished as part of the output quantity in period p. To summarize, Ygpl can be expressed by
That is,
The module procedure of the input coefficient calculation module is that:
The LPPP calculation module solves an LPPP problem using an LPPP model with empirical capacity constraint that formulates the joint effect of the workloads from the initial WIP and the arrival in a period of a resource type to constrain the input workload to the resource type in the period, thereby determining a release quantity to a first operation of the product in a period.
The LPPP model with empirical capacity constraint has parameters, decision variables, and an objective function listed as follows.
The parameters of the LPPP model include:
ε: a number of working days per period;
ugl: processing time (in work-hours) per product unit of an operation l of a product g;
vgp: unit revenue for a product g in a period p;
hgp: unit inventory holding cost per working day for a product g in a period p;
bgp: unit backorder cost per working day for a product g in a period p;
wgp: unit WIP cost per working day for a product g in a period p;
Wg,0,l: an initial WIP level of an operation l of a product g at planning calculation time (current time);
k′gl: a resource type required by an operation l of a product g;
dgp: demand quantity (in product units) for a product g during a period p;
eglpq: a coefficient of Xgql in expressing Ygpl;
Dki: a z-intercept of a plane i of a resource type k;
Aki: a coefficient of an arrival workload variable (x variable) in the equation of a plane i for a resource type k;
Bki: a coefficient of an initial WIP workload variable (y variable) in the equation of a plane i for a resource type k; and
Ī(k): a set of planes that are used to approximate an empirical capacity surface of a resource type k.
The decision variables of the LPPP model include:
Xgpl: input quantity (in product units) to an operation l of a product g in a period p, which is constrained by the empirical capacity constraint of a resource type of the operation l of the product g;
Xgql: input quantity (in product units) to an operation l of a product g in a period q, which is constrained by the empirical capacity constraint of a resource type of the operation l of the product g;
Ygpl: output quantity (in product units) from an operation l of a product g in a period p, which is equal to arrival quantity to an operation l+1 of a product g in a period p;
Ŷgp: output quantity (in product units) of a finished product g in a period p, which is equal to output quantity (in product units) from an operation L(g) of the product g in the period p (i.e., Ŷgp=Yg,p,L(g));
Rgp: release quantity (in product units) to the first operation of a product g in a period p;
Wgpl: a WIP level (in product units) of an operation l of a product g at the end of a period p;
Igp: a finished goods inventory level (in product units) of a product g at the end of a period p; and
Jgp: a finished goods backordered level (in product units) of a product g at the end of a period p.
The objective function of the LPPP model is that:
which is subject to the following constraints (14)-(21):
WIP balance constraint:
W
gpl
W
g,p-1,l
+R
gp
−X
gpl
,l=1,p=1, . . . ,P,g∈G. (14)
W
gpl
=W
g,p-1,l
+Y
g,p,l-1
−X
gpl
,l=2, . . . ,L(g),p=1, . . . ,P,g∈G. (15)
Input Output Relation Equation:
Y
gpl=Σq=1peglpqXgql,l=1, . . . ,L(g),p=1, . . . ,P,g∈G (16)
Finished Goods Inventory Balance:
I
g,p-1
−J
g,p-1
,Ŷ
gp
−I
gp
+J
gp
=d
gp
,p=1, . . . ,P,g∈G.
(i.e., Ig,p-1−Jg,p-1+Ŷgp−dgp=Igp−Jgp,p=1, . . . ,P,g∈G.) (17)
Empirical Capacity Constraint:
Σ{(g,l)|k′
Final Output Constraint:
Ŷ
gp
=Y
g,p,L(g)
,p=1, . . . ,P,g∈G (19)
Non-Negativity Constraint:
W
gpl
,X
gpl
,Y
gpl≥0,l=1, . . . ,L(g),p=1, . . . ,P,g∈G. (20)
Ŷ
gp
,R
gp
,I
gp
,J
gp≥0,p=1, . . . ,P,g∈G. (21)
Objective function (13) is to maximize the revenue minus WIP inventory cost and finished goods inventory and backorder costs. Constraints (14) and (15) are both WIP inventory balance constraints. Constraint (14) used for operation l=1 enforces that the WIP level of the first operation of product g at the end of period p (Wgpl) is equal to the WIP level at the beginning of the period (Wg,p-1,l) plus the release quantity to the first operation (Rgp) and minus the input quantity to the first operation in the period (Xgpl). Similarly, Constraint (15) used for operation l=2, . . . , L(g) enforces that the WIP level of product g for operation l at the end of period p (Wgpl) is equal to the WIP level at the beginning of the period (Wg,p-1,l) plus the arrival quantity from preceding operation (Yg,p,l-1) and minus the input quantity to the operation in the period (Xgpl). The difference between Constraints (14) and (15) is the arrivals: one is the new release quantity into the factory for the first operation; and the other is the output quantity from the preceding operation. Constraint (16) is an input-output equation for an operation of a product in a period. Constraint (17) is an inventory balance constraint on finished products which ensures that the inventory-minus-backorder level at the end of a period is equal to the inventory-minus-backorder level at the beginning of the period plus the finished product output in the period ({tilde over (Y)}gp) and minus the demand in the period (dgp) Constraint (18) is an empirical capacity constraint of a resource type in a period that limits the workload of all input quantities (Xgpl) under the plane-wise surface developed in previous modules (i.e., the approximate surface fitting module, the plane parameter calculation module and the plane reduction module). The limitation on input workload of a resource type in a period is jointly expressed by the workload from the arrival quantity in the period (output quantity from the preceding operation, Yg,p,l-1) and the workload from the initial WIP of the period (Wg,p-1,l) of various operations that use the resource type. Constraint (19) makes the output quantity of a finished product equal the output from the last operation of the product. Constraints (20) and (21) are non-negative constraints for all continuous variables.
The LPPP calculation module has module input data, module output data, and a module procedure listed as follows.
The module input data of the LPPP calculation module includes:
ε: a number of working days per period;
ugl: processing time (in work-hours) per product unit of an operation l of a product g;
vgp: unit revenue for a product g in a period p;
hgp: unit inventory holding cost per working day for a product g in a period p;
bgp: unit backorder cost per working day for a product g in a period p;
wgp: unit WIP cost per working day for a product g in a period p;
Wg,0,l: an initial WIP level of an operation l of a product g at planning calculation time (current time); k′gl: a resource type required by an operation l of a product g;
dgp: a demand quantity (in product units) for a product g during a period p;
eglpq: a coefficient of Xgql in expressing Ygpl;
Dki: a z-intercept of a plane i of a resource type k;
Aki: a coefficient of an arrival workload variable (x variable) in the equation of a plane i for a resource type k;
Bki: a coefficient of an initial WIP workload variable (y variable) in the equation of a plane i for a resource type k; and
Ī(k): a set of planes that are used to approximate the empirical capacity surface of a resource type k.
The output data of the LPPP calculation module includes:
Xgpl: input quantity to an operation l of a product g in a period p, constrained by the empirical capacity constraint of its resource type;
Rgp: release quantity to the first operation of a product g in a period p;
Igp: a finished goods inventory level of a product g at the end of a period p; and
Jgp: a finished goods backordered level of a product g at the end of a period p.
The module procedure of the LPPP calculation module is to solve the LPPP problem.
Finally, the computer system may display information of the above calculations, which may include module input data, module output data, parameters, graphs that correspond to the established model, and each piece of user desired data, to the user through the user interface device (e.g., by displaying the information on a screen, printing the information on paper, etc.), so that the user may execute production plans accordingly, thereby optimizing the production.
In summary, the empirical capacity model developed in this disclosure maps the joint workload effects from the initial WIP and arrival of a resource type in a period to the input workload of the resource type in the period. This relationship is extrapolated from the two primitive relationships: one relates initial WIP workload of a resource type in a period to the input workload of the resource type in the period when there is no arrival to the resource type in the period; and the other relates the arrival workload of a resource type in a period to the input workload of the resource type in the period when there is no initial WIP of the resource type in the period. By virtue of the six modules introduced in the embodiment and using the empirical capacity model, production plans may thus be optimized.
In the description above, for the purposes of explanation, numerous specific details have been set forth in order to provide a thorough understanding of the embodiment (s). It will be apparent, however, to one skilled in the art, that one or more other embodiments may be practiced without some of these specific details. It should also be appreciated that reference throughout this specification to “one embodiment,” “an embodiment,” an embodiment with an indication of an ordinal number and so forth means that a particular feature, structure, or characteristic may be included in the practice of the disclosure. It should be further appreciated that in the description, various features are sometimes grouped together in a single embodiment, figure, or description thereof for the purpose of streamlining the disclosure and aiding in the understanding of various inventive aspects.
While the disclosure has been described in connection with what is (are) considered the exemplary embodiment(s), it is understood that this disclosure is not limited to the disclosed embodiment(s) but is intended to cover various arrangements included within the spirit and scope of the broadest interpretation so as to encompass all such modifications and equivalent arrangements.
| Number | Date | Country | Kind |
|---|---|---|---|
| 106104229 | Feb 2017 | TW | national |