The present disclosure is directed to an arc welding process to create joints needed for the manufacturing of a double wall tube. More particularly, present disclosure is directed to a process that couples double wall pipes and associated couplings that allow leaked fluids to be transmitted to a suitable drain point.
Double wall pipes in gas turbine engines employ couplings that use high cost flanges that are associated with expensive and inefficient processing. Attachment of the flanges may involve several processing steps including, for example, welding, swaging, and brazing. Moreover, the processing costs account for the majority of the fabrication costs of doubled wall pipe configurations.
The joint for the double wall tube requires that the gap between the tube and the end fitting be fully sealed. Unfortunately, a brazing process is only capable of achieving 80% braze coverage, not 100% braze coverage. A risk exists that the potential 20% lack of coverage may form a path for leakage. In order to manage this risk, a specialized inspection method is needed to guarantee that there is no path for leakage. This specialized inspection method comes with the use of more expensive braze process. An inspection method such as X-ray or leak test is needed to capture any potential escape. The X-ray added significant cost as the double wall tube design is very difficult for meeting the inspection requirements. In many cases, multiple X-ray shots are required.
What is needed is a process of joining fittings to double walled tube without the need to braze the final inner tube to fitting joint to reduce production costs.
In accordance with the present disclosure, there is provided a process of welding fittings to ends of a double wall pipe, the process comprising forming a first welded joint between an inner pipe and an inner receiver of a first fitting; forming a second welded joint between an outer pipe and an outer receiver of the first fitting; forming a third welded joint between the outer pipe and an outer receiver of a second fitting; and forming a fourth welded joint between the inner pipe and an inner receiver of the second fitting.
In another and alternative embodiment, the fourth welded joint comprises a welded lap fillet joint or a full penetration groove welded joint.
In another and alternative embodiment, the process further comprises placing an assembly of the second fitting and the inner pipe and outer pipe into a fixture; the fixture comprising a set of collets configured to retain the assembly of the second fitting and the inner pipe and outer pipe; a backing plate coupled to the set of collets, the backing plate being fluidly coupled to the second fitting; and a conduit fluidly coupled to the backing plate; the conduit configured to fluidly couple a gas source to the backing plate.
In another and alternative embodiment, the gas source comprises an inert shielding gas, further comprising flowing the inert shielding gas through the conduit to a groove formed in the backing plate; flowing the inert shielding gas from the groove through the second fitting into a chamber formed between the inner pipe and the outer pipe to protect the fourth welded joint.
In another and alternative embodiment, the process further comprises installing the fixture within an orbital welding device; and aligning a welding electrode with the inner pipe and an inner receiver of the second fitting.
In another and alternative embodiment, the process further comprises clamping the assembly of the second fitting and the inner pipe and outer pipe in a biasing member formed by the set of collets and the backing plate.
In another and alternative embodiment, the process further comprises sealing the fourth welded joint between the inner pipe and an inner receiver of the second fitting by using an arc energy to melt either a full or a partial thickness of the fitting with the inner pipe.
In accordance with the present disclosure, there is provided a welding fixture comprising a set of collets configured to retain an assembly of a second fitting and an inner pipe and an outer pipe; a backing plate coupled to the set of collets, the backing plate being fluidly coupled to the second fitting; and a conduit fluidly coupled to the backing plate; the conduit configured to fluidly couple a gas source to the backing plate.
In another and alternative embodiment, the welding fixture further comprises a groove formed in the backing plate, the groove fluidly coupled to the conduit and fluidly coupled to the second fitting.
In another and alternative embodiment, the fixture is configured to mount into an orbital welding device.
In another and alternative embodiment, the orbital welding device includes a housing supporting an orbital welding head and adaptor configured to mount a welding electrode proximate an inner diameter of a joint between the inner pipe and an inner receiver of the fitting.
In another and alternative embodiment, the welding electrode is configured to form a welded lap fillet joint between the inner pipe and the inner receiver of the fitting.
In another and alternative embodiment, the welding electrode is positioned relative to the inner pipe inner diameter and configured for making a radially outward weld in a gap between the inner pipe and the fitting, wherein the gap is sealed by melting either a full or a partial thickness of the fitting with the inner pipe.
In accordance with the present disclosure, there is provided a process of joining a double walled pipe with a fitting, the process comprising placing an assembly of a fitting and an inner pipe and an outer pipe into a fixture, wherein the fitting and the outer pipe have a first welded joint; mounting the fixture into an orbital welding device; positioning a welding electrode relative to an inner diameter of the inner pipe proximate an inner receiver of the fitting; and forming a second welded joint between the inner pipe and the inner receiver.
In another and alternative embodiment, the second welded joint is formed with a radially outward weld in a gap between the inner pipe and inner receiver of the fitting.
In another and alternative embodiment, the second welded joint comprises a welded lap fillet joint or a full penetration groove welded joint.
In another and alternative embodiment, the fixture comprises a set of collets configured to retain the assembly of the fitting and the inner pipe and outer pipe; a backing plate coupled to the set of collets, the backing plate being fluidly coupled to the fitting; and a conduit fluidly coupled to the backing plate; the conduit configured to fluidly couple a gas source to the backing plate; flowing the inert shielding gas through the conduit to a groove formed in the backing plate; and flowing the inert shielding gas from the groove through the fitting into a chamber formed between the inner pipe and the outer pipe to protect the second welded joint.
In another and alternative embodiment, the process further comprises making the second weld as a radially outward weld in a gap between the inner pipe and the inner receiver of the fitting, wherein the gap is sealed by melting either a full or a partial thickness of the inner receiver of the fitting with the inner pipe.
In another and alternative embodiment, the second weld comprises one of an orbital welding technique or a manual gas tungsten arc welding technique.
Other details of the joining process are set forth in the following detailed description and the accompanying drawings wherein like reference numerals depict like elements.
Referring to
The turbine sections 20, 22 may comprise alternating rows of rotary airfoils or blades and static airfoils or vanes. Cooling air may be supplied to the turbine sections 20, 22 from the compressor sections 14, 16. A plurality of bearings 24 may support spools in the gas turbine engine 10.
The forward-aft positions of gas turbine engine 10 lie along axis of rotation A-A′. For example, fan 12 may be referred to as forward of turbine section 20 and turbine section 20 may be referred to as aft of fan 12. Typically, during operation of gas turbine engine 10, air flows from forward to aft, for example, from fan 12 to turbine section 29. As air flows from fan 12 to the more aft components of gas turbine engine 10, axis of rotation A-A′ may also generally define the direction of the air stream flow.
In various embodiments, double wall pipes 26 may be employed to transport fluids, and particularly, flammable fluids, through aircraft structures and in aircraft volumes (e.g., along the engine cage). These double wall pipes 26 typically are associated with expensive and resource intensive manufacturing processes. For example, typical double wall pipe assemblies may employ orbital welds, swaging, and brazing of flanges. However, these swaging and brazing processes may be expensive and time-consuming.
The double wall pipes 26 defined herein are described in the context of use in aerospace applications, and in particular, in the context of use in conjunction with gas turbine engines including, for example, gas turbine engine 10 as shown in
In various embodiments and with reference to
In various embodiments, gas turbine engine 10 and/or case 28 may comprise one or more double wall pipes 26 including, for example, double wall pipe 26 in
In various embodiments with reference to
The inner pipe 32 is configured to carry oil or fuel. The chamber 38 between the inner pipe 32 and the outer pipe 34 is the space to collect potential leakage from the inner pipe 32. Any fluid leaked from first pipe 32 may be contained in and/or conducted through the chamber 38 to a suitable drainage point.
In certain applications the geometry of the double wall pipe 26 may need to be bent to accommodate the needed complex configuration. A popular solution to address the required complex geometry is to connect multiple double wall pipe 26 into a long continuous pipe 26 and use the coupling 30 between two double wall pipes 26 to handle bending or any change of orientation. When multiple double wall pipes 26 connect into one, the inner pipe 32 as well as the spacing between the inner pipe 32 and the outer pipe 34 have to be connected to enable passage of the liquid. The chamber 38 between the inner pipe 32 and the outer pipe 34 would direct the liquid to a drainage location. The drainage provides evidence if leakage of the inner pipe 32 occurs.
The inner pipe 32, the outer pipe 34 and two end fittings 36, 30 (one at each end) are required to produce a single double wall pipe 26.
As illustrated in
As shown in
The arc welding process disclosed is configured to make all four joints needed for the manufacturing of the double wall pipe 26. The prior art brazing process is replaced by an arc welding process as schematically shown in
An arc torch 42 is positioned at the inner diameter 44 of the inner pipe 32. The arc weld 45 is formed and the gap between inner pipe 32 and the fitting 30 is sealed by using the arc energy to melt either full or partial thickness of the fitting 30 with the inner pipe 32. The full thickness of the fitting 30 is melted by the arc, the inner pipe 32 arc weld 45 indicated by a circle in
The radially outward weld 45 may be made by either using an orbital welding process or a manual gas tungsten arc welding method. The orbital welding process is a mechanized gas tungsten arc welding process designed in such a way that the gas tungsten arc welding torch 42 rotates while the fitting 30 and pipe 32 are kept stationary during welding. An orbital welding process is preferred over the manual arc welding process due to its superior process control and better consistency in the weld geometry and material properties. A manual gas tungsten arc welding process may be used when the use of an orbital welding process is not possible due to fitting 30 geometry.
Either the orbital welding process or the manual gas tungsten arc welding process requires the use of a fixture 46, as seen in
A cross section of the pipe/fitting assembly held by the fixture 46 is shown in
The fixture 46 includes the backing plate 56 and two pieces of the clamping collet 54.
A technical advantage of the process is the capability to use the orbital welding process to make the lap fillet weld or full penetration groove weld from the inside diameter surface of the inner tube.
Another technical advantage of the process is that the process significantly reduces the cost of producing the double wall tube as the cost of orbital welding is generally about one third of the brazing process.
Another technical advantage of the process is elimination of the post brazing inspection requirement and the risk of leakage is virtually eliminated.
There has been provided a joining process. While the process has been described in the context of specific embodiments thereof, other unforeseen alternatives, modifications, and variations may become apparent to those skilled in the art having read the foregoing description. Accordingly, it is intended to embrace those alternatives, modifications, and variations which fall within the broad scope of the appended claims.
Number | Name | Date | Kind |
---|---|---|---|
9829124 | Dill | Nov 2017 | B2 |
9982821 | Scheiferstein et al. | May 2018 | B1 |
20050011928 | Dick | Jan 2005 | A1 |
20060157536 | Wolf | Jul 2006 | A1 |
20100018599 | Ferrer et al. | Jan 2010 | A1 |
20170336007 | Rappitsch | Nov 2017 | A1 |
20180066781 | Sanchez | Mar 2018 | A1 |
Number | Date | Country |
---|---|---|
106041271 | Oct 2016 | CN |
208703373 | Apr 2019 | CN |
208703373 | Apr 2019 | CN |
2144799 | Dec 1972 | DE |
10303909 | Aug 2004 | DE |
2957804 | Dec 2015 | EP |
2957805 | Dec 2015 | EP |
3296053 | Mar 2018 | EP |
3296053 | Mar 2018 | EP |
2035871 | Jun 1980 | GB |
2009109950 | Sep 2009 | WO |
WO-2020156599 | Aug 2020 | WO |
Entry |
---|
Machine translation of CN-106041271-A, dated Dec. 2022. |
Machine translation of CN-208703373-U, dated Dec. 2022. |
Machine translation of WO-2020156599-A1, dated Dec. 2022. |
EP Search Report dated Nov. 2, 2020 issued for corresponding European Patent Application No. 20178106.9. |
Number | Date | Country | |
---|---|---|---|
20200384584 A1 | Dec 2020 | US |