The present invention relates to radiation monitoring equipment, and in particular, to the radiation monitoring equipment which measures a dose rate and the like, by detecting a current signal outputted from a radiation detector.
In order to measure a dose rate and others in the living space, radiation monitoring equipment is installed around a nuclear power plant, a nuclear fuel reprocessing plant, an institution for radiation application, their affiliated facilities and the like (see Patent Documents 1-6, for example). The radiation monitoring equipment needs to measure dose rates in a wide range, from the normal radiation level to the radiation level supposing an accident, with sufficient accuracy. In order to cover the current in a minute quantity and in a wide range, an ion chamber, for example, is used for the radiation detector of the radiation monitoring equipment. If radiation acts on the ion chamber of the radiation detector, a very small electric current with a broad range, on the order of from 10−14 A (Ampere) to 10−7 A, will be generated.
As for the radiation monitoring equipment which measures such a very small electric current, a current measurement means (operational amplifier) includes a capacitor which is connected between an inverting input terminal and an output terminal. Electric charge integration is carried on the input current which is supplied from the current measurement means of the radiation monitoring equipment, and the current is changed into voltage. When the voltage exceeds a fixed voltage, the current measurement means discharges the current automatically. Thereby, a saw-tooth wavelike pulse is generated repeatedly. The measurement part of the radiation monitoring equipment counts the number of the saw-tooth wavelike pulses within a set-upped period, and obtains a count. When the set-upped period is over, the measurement part measures the voltage of a saw-tooth wavelike pulse which is smaller than one pulse and obtains a voltage value. The measurement part of the radiation monitoring equipment has measured a very small electric current based on both of the count and the voltage value (see Patent Document 1, for example).
As mentioned above, this kind of radiation monitoring is treating a very small electric current. Since special consideration is required to a noise, the radiation monitoring equipment which is equipped with a noise rejection means is developed. The noise rejection means of the radiation monitoring equipment puts the measured values in a chronological order which are measured at a constant frequency. Thereby, an up-dated row of measured values is always created. The noise rejection means calculates a moving average of a fixed period from the row of measured values, which includes measured vales from a latest value to a previous value in the past. When the latest measured value is unusual, the noise rejection means eliminates it and performs an operation of moving averaging.
As a representative example of abnormality in measured values, the static electricity noise current in the apparatus can be mentioned. In the ion chamber, a high voltage line which supplies a high voltage as a bias voltage is arranged. This high voltage line is in touch with a common 0V through an insulator. Attributing to the insulation fall by moisture absorption or rise in temperature or the like, an electric charge is accumulated near the 0V contact part. When the insulator cannot bear the accumulation of charges, an electric discharge occurs, and at a next step a charge of current proceeds. In the ion chamber, the charge and discharge is repeated with an interval. If the condition for discharging is eased, the phenomenon in which the ion chamber returns to a normal state has happened.
Because the electric charge of discharge is offset by the electric charge of charge, a noise appears in sight. For example, the noise is in a shape where a mountain is overlapped at the plus side of a saw-tooth wavelike pulse, as a single shot. This mountain does not affect the basic shape of a saw-tooth wavelike pulse. For this reason, measurement is not affected, if the timing between the voltage measurement of a saw-tooth wavelike pulse and the noise invasion is out of synchronization. When the timing is in synchronization, unusual data are eliminated from the data for measurement (see Patent Document 2, for reference).
Patent Documents 1: JP S61-83967 A
Patent Documents 2: JP 2006-98081 A
Patent Documents 3: JP 2000-258537 A
Patent Documents 4: JP 2003-28963 A
Patent Documents 5: JP 2004-294193 A
Many of the radiation monitoring devices are constituted as mentioned above. In other words, the change in readings by the noise is prevented by eliminating the measurement data, in which a voltage sudden change by a noise current is overlapped on the fundamental wave form of a saw-tooth voltage based on a current signal. During the noise continuing period, the measurement data which contain noises are eliminated. After that, there is a period when noises are in disappearance and data used for the moving average are small in number. The moving average during the noise continuing period becomes large in the statistical variation of radiation and affects the accuracy in measurement. Moreover, when the data at the time of missing measurement are compensated by the standard data, exact measurement cannot be recovered, until the data at the time of missing measurement disappear from the moving average.
This invention is made to solve the subject pointed out in the above mentioned radiation monitoring equipment. The object of the invention is to obtain the radiation monitoring equipment which has high reliability and is capable of wide range measurement with no substantial influence from the noise.
Radiation monitoring equipment according to the present invention includes; a radiation detector outputting a current signal when a radiation is incident thereon, a first conversion unit converting the current signal outputted from the radiation detector into a voltage signal and forming a rectangular wave pulse based on the voltage signal, a second conversion unit sampling the voltage signal converted in the first conversion unit and outputting a digital voltage data, a calculation unit counting a number of rectangular wave pulses formed in the first conversion unit, an operation unit calculating a cumulated count from the digital voltage data outputted from the second conversion unit and the number of rectangular wave pulses outputted from the calculation unit, and obtaining a real count (this time) from a difference of a cumulated count (this time) at a this time operation cycle and a cumulated count (previous time) at a previous time operation cycle and memorizing the real count (this time) and a display unit displaying operational results carried out in the operation unit; wherein the calculation unit reads in a real count (this time) and a cumulated count (previous time) at every operation cycle, the calculation unit judges whether the real count (this time) which is read in is within a permissible range or not, if the calculation unit judges that the real count (this time) is within the permissible range, the calculation unit judges whether a number of times deviated from the permissible range is zero or not, if the calculation unit judges that the number of times deviated from the permissible range is zero, the calculation unit performs a regular processing, if the calculation unit judges that the real count (this time) is out of the permissible range, the calculation unit adds 1 to the number of times deviated from the permissible range and further judges whether an added number of times deviated from the permissible range is equal to 1 or not, if the calculation unit judges that the added number of times deviated from the permissible range is equal to 1, the calculation unit memorizes the cumulated count (previous time) as a cumulated count just before the deviation of real count from the permissible range, and further performs a first noise processing, if the calculation unit judges that the added number of times deviated from the permissible range is not equal to 1, the calculation unit judges whether the added number of times deviated from the permissible range is within a permissible number of times or not, if the calculation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the calculation unit performs the regular processing, if the calculation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the calculation unit performs the first processing, and; further wherein the regular processing includes; a step for calculating a moving average counting rate (this time) from a data row of real counts including the cumulated count (this time), and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value, and the first noise processing includes; a step for outputting an engineering value at the previous time operation cycle as an engineering value at the this time operation cycle.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the number of times deviated from the permissible range is not zero, the operation unit judges whether the number of times deviated from the permissible range is within the permissible number of times or not, if the operation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the operation unit performs the regular processing and further resets the number of times deviated from the permissible range, if the operation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the operation unit subtracts a cumulated count at an operation cycle just before the first noise processing from the cumulated count (previous time) to find a difference, and divides the difference with the number of times deviated from the permissible range+1 to find a first average real count, and judges whether the first average real count is within the permissible range or not, if the operation unit judges that the first average real count is within the permissible range, the operation unit performs a second noise processing and further resets the number of times deviated from the permissible range, and further wherein the second noise processing includes; a step for replacing a real count deviated from the permissible range with the first average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the first average real count is not within the permissible range, the operation unit performs a third noise processing and furthermore resets the number of times deviated from the permissible range, and further wherein the third noise processing includes; a step for obtaining a second average real count by averaging a real count (this time) and a latest real count within the permissible range, a step for replacing a real count deviated from the permissible range with the second average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate into an engineering value and outputting the value.
The radiation monitoring equipment according to the present invention includes; a radiation detector outputting a current signal when a radiation is incident thereon, a first conversion unit converting the current signal outputted from the radiation detector into a voltage signal and forming a rectangular wave pulse based on the voltage signal, a second conversion unit sampling the voltage signal converted in the first conversion unit and outputting a digital voltage data, a calculation unit counting a number of rectangular wave pulses formed in the first conversion unit, an operation unit calculating a cumulated count from the digital voltage data outputted from the second conversion unit and the number of rectangular wave pulses outputted from the calculation unit, and obtaining a real count (this time) from a difference of a cumulated count (this time) at a this time operation cycle and a cumulated count (previous time) at a previous time operation cycle and memorizing the real count (this time) and a display unit displaying operational results carried out in the operation unit; wherein the calculation unit reads in a real count (this time) and a cumulated count (previous time) at every operation cycle, the calculation unit judges whether the real count (this time) which is read in is within a permissible range or not, if the calculation unit judges that the real count (this time) is within the permissible range, the calculation unit judges whether a number of times deviated from the permissible range is zero or not, if the calculation unit judges that the number of times deviated from the permissible range is zero, the calculation unit performs a regular processing, if the calculation unit judges that the real count (this time) is out of the permissible range, the calculation unit adds 1 to the number of times deviated from the permissible range and further judges whether an added number of times deviated from the permissible range is equal to 1 or not, if the calculation unit judges that the added number of times deviated from the permissible range is equal to 1, the calculation unit memorizes the cumulated count (previous time) as a cumulated count just before the deviation of real count from the permissible range, and further performs a first noise processing, if the calculation unit judges that the added number of times deviated from the permissible range is not equal to 1, the calculation unit judges whether the added number of times deviated from the permissible range is within a permissible number of times or not, if the calculation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the calculation unit performs the regular processing, if the calculation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the calculation unit performs the first processing, and; further wherein the regular processing includes; a step for calculating a moving average counting rate (this time) from a data row of real counts including the cumulated count (this time), and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value, and the first noise processing includes; a step for outputting an engineering value at the previous time operation cycle as an engineering value at the this time operation cycle. By the above mentioned reasons, it becomes possible to obtain the radiation monitoring equipment which is capable of wide range and highly reliable measurement, with no substantial influence on measurement by a noise.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the number of times deviated from the permissible range is not zero, the operation unit judges whether the number of times deviated from the permissible range is within the permissible number of times or not, if the operation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the operation unit performs the regular processing and further resets the number of times deviated from the permissible range, if the operation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the operation unit subtracts a cumulated count at an operation cycle just before the first noise processing from the cumulated count (previous time) to find a difference, and divides the difference with the number of times deviated from the permissible range+1 to find a first average real count, and judges whether the first average real count is within the permissible range or not, if the operation unit judges that the first average real count is within the permissible range, the operation unit performs a second noise processing and further resets the number of times deviated from the permissible range, and further wherein the second noise processing includes; a step for replacing a real count deviated from the permissible range with the first average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value. Then, an average real count is calculated based on the cumulated counts just before and just after the noise invasion. The real counts among the invasion period are interpolated to up-date the data row having a preset number of real counts in chronological order. Thereby, it is possible to offer the radiation monitoring equipment which is capable of highly reliable measurement, with no substantial missing measurements. Besides that, prevented are fluctuations by the reduction in the number of data concerning the calculation of the moving average counting rate and the stable accuracy in measurement can be acquired.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the first average real count is not within the permissible range, the operation unit performs a third noise processing and furthermore resets the number of times deviated from the permissible range, and further wherein the third noise processing includes; a step for obtaining a second average real count by averaging a real count (this time) and a latest real count within the permissible range, a step for replacing a real count deviated from the permissible range with the second average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate into an engineering value and outputting the value. Then, an average real count is calculated based on the cumulated counts just before and just after the noise invasion. The real counts among the invasion period are interpolated to up-date the data row having a preset number of real counts in chronological order. Thereby, it is possible to offer the radiation monitoring equipment which is capable of highly reliable measurement, with no substantial missing measurements. Besides that, prevented are fluctuations by the reduction in the number of data concerning the calculation of the moving average counting rate and the stable accuracy in measurement can be acquired.
Hereinafter, the radiation monitoring equipment according to the embodiments of the present invention will be described with reference to drawings. Incidentally, the same reference numerals are given to those identical or similar to constitutional portions in respective drawings and the size and/or the scale size of the corresponding respective constitutional portions are respectively independent. For example, when the identical constitutional portions, which are not changed, are shown, the size and/or the scale size of the identical constitutional portions may different among sectional views in which a part of the configuration is changed. Furthermore, although the configurations of the radiation monitoring equipment are further actually provided with a plurality of members, for ease of explanation, only portions necessary for explanation will be described and other portions are omitted.
The current to voltage and frequency conversion unit 2 includes an electric charge integrating part 21, a voltage comparison section 22, an electric charge discharge section 23, and a rectangular wave pulse outputting part 24. The electric charge integrating part 21 has a capacitor 211 and an operational amplifier 212. As for the operational amplifier 212, the capacitor 211 is connected between an inverting input terminal and an output terminal. The output side of the operational amplifier 212 is connected to the input side of the voltage comparison section 22, and also to the input side of the analog to digital conversion unit 4. The output side of the voltage comparison section 22 is connected to the input side of the electric charge discharge section 23, and to the input side of the rectangular wave pulse outputting part 24. The electric charge discharge section 23 has a constant current source 231. The output side of the rectangular wave pulse outputting part 24 is connected to the input side of the calculation unit 3.
The output side of the calculation unit 3 is connected to the operation unit 5. The output side of the analog to digital conversion unit 4 is connected to the operation unit 5. The bias power supply unit 7 accepts instructions from the operation unit 5, and supplies, for example, a high voltage of some 600 to 800 V as a bias voltage, to the radiation detector 1. The operation unit 5 has an engineering value arithmetic processing means and a noise processing means, and the functions of those means are realized by the program carried out by a microprocessor 5a. The engineering value arithmetic processing means includes a real count calculation part 51, a real count memory 52, a moving average counting rate calculation part 54, and an engineering value conversion part 55. The noise processing means includes a noise processing part 53.
The operation unit 5 is connected with the display unit 6. The display unit 6 displays the data outputted from the operation unit 5, and furthermore carries out operations for set-ups and others of the operation unit 5. It should be noted that the current to voltage and frequency conversion unit 2, the calculation unit 3, the analog to digital conversion unit 4, the operation unit 5, the display unit 6, and the bias power supply unit 7 are contained in a box, for example. In other cases, all of the components including from the radiation detector 1 to the bias power supply unit 7 may be accommodated in one box.
As a radiation detector 1 which outputs a current signal, an ion chamber, a NaI (TI) scintillation detector, a plastic scintillation detector and the like may be adopted. Hereafter, it is assumed that the radiation detector 1 employs an ion chamber, which has an aluminum container with a rounded configuration, in which pressurized argon or nitrogen or those mixed gas is encapsulated. The ion chamber is capable of measuring a dose rate targeting an ionization current in the range from a background dose rate level on the order of 10−14 A to an accident dose rate level on the order of 10−7 A. At the accident dose rate level, monitoring is supposed to measure an accident of a nuclear power plant at the surrounding areas.
If an ion chamber is employed in the radiation detector 1, it is possible to measure a dose rate in a wide range of about 7 decades and with good (or flat) energy characteristics. The NaI (TI) scintillation detector and the plastic scintillation detector include a photo-multiplier as a detector constitute and have a large dark current on the order of 10−9 A. They are suitable for measuring the current signals in the high dose rate area, where the dark current can be ignored. Hereinafter, the ion chamber is employed as a representative of the radiation detector 1 and the operation of the radiation monitoring equipment 100 is explained as so.
In the response of a dose rate with respect to the incident radiation beams, the ion chamber (radiation detector 1) outputs a current proportional to the dose rate. The current to voltage and frequency conversion unit 2 takes in the current signal, and outputs a saw-tooth wavelike pulse with a repetition frequency proportional to the current and a rectangular wave pulse at the timing when the saw-tooth wavelike pulse is reversed from a top to a bottom of the pulse. The analog to digital conversion unit 4 samples the voltage signal which forms the saw-tooth wavelike pulse, and outputs a voltage value (digital converted data). The calculation unit 3 counts the number of rectangular wave pulses which are outputted from the rectangular wave pulse outputting part 24, and outputs a count. The count is reset at the set-up value (reset preset value), before the count results in overflow. The calculation unit 3 outputs also the reset information to the operation unit 5 as a special case, when the reset is inserted between the counting of numbers.
If the electric charge discharge section 23 discharges the accumulated electric charge, the voltage value of the capacitor 211 will fall from a top to a bottom of a pulse. The rectangular wave pulse outputting part 24 outputs a rectangular wave pulse of a fixed voltage and of a predetermined duration, corresponding to the above mentioned trigger signal.
When an ion chamber is employed as a radiation detector, the repetition frequency of the rectangular wave pulses, which are outputted from the rectangular wave pulse outputting part 24, is as low as some cpm on a background level, and the resolution of the detector is low. For this reason, it is necessary to count numbers for several 10 minutes, in order to carry out a high precision measurement by the ion chamber. So, in the radiation monitoring equipment 100 according to the present embodiments, the following ways are taken to shorten the time for measurement. In the operation unit 6 of the radiation monitoring equipment 100, the real count calculation part 51 handles the voltage value (voltage data to which digital conversion was carried out) received from the analog to digital conversion unit 4. In the real count calculation part 51, a count is scored for a voltage difference between the peak voltage and the bottom voltage in a saw-tooth wavelike pulse which is outputted from the electric charge integrating part 21.
The real count calculation part 51 samples a voltage value of this time operation cycle in every operation cycle and obtains a count c (this time) which is smaller than one count, based on the voltage value at a this time operation cycle. The count c (this time) is added to a count C (this time), which is inputted from the calculation unit 3, to make a cumulated count (this time) of this time operational cycle={count C (this time)+count c (this time)}. A cumulated count (previous time) of previous time operation cycle={count C (previous time)+count c (previous time)} is subtracted from a cumulated count (this time) of this time operation cycle to obtain a difference (this time). The difference [{count C (this time)+count c (this time)}−{count C (previous time)+count c (previous time)}] is referred to as a real count (this time).
The real count (this time) is memorized in the real count memory 52, and is stored in a newest position of the data row of real counts. The operation unit 5 discards a real count at an oldest position in the real count memory 52, and up-dates the data row of real counts. The moving average counting rate calculation part 54 calculates a moving average counting rate (this time) from the up-dated data row of real counts. First, a set-upped data number of real counts are accumulated. The accumulated data of real counts are divided by the integrated time corresponding to those accumulated data, to obtain the moving average counting rate (this time). The data in the set-upped data number are stored in the real count memory 52 and arranged serially from the newest to the oldest, by trace backing the data. In this way, a fractional count, which is smaller than one count, is embedded the real count. By doing so, the operation unit 5 can increase the resolution in measurement and shorten the time for measurement.
The engineering value conversion part 55 multiplies a moving average counting rate by an engineering value conversion factor, to output an engineering value, for example, a dose rate (unit: nGy/h). The display unit G displays the outputted engineering value. When a regular processing (D0) is performed, resetting may be inserted between the processing. In this case, the calculation unit 3 also outputs the reset information (reset preset value and the like) as a special case. If the real count calculation part 51 receives a count and the reset information from the calculation unit 3, the real count calculation part 51, based on this reset information, calculates the real count (this time) of this time operation cycle by the equation; [{count C (this time)+reset preset value+count c (this time)}−{count C (previous time)+count c (previous time)}]. At the following operation cycle, the process for obtaining a real count is switched to the regular process. Used is the following equation; [{count C (this time)+count c (this time)}−{count C (previous time)+count c (previous time)}].
Next, with reference from
The analog to digital conversion unit 4 carries out the sampling of the voltage value of a saw-tooth wavelike pulse for measurement and the real count calculation part 51 takes in the voltage value of the saw-tooth wavelike pulse at a constant frequency. At time A1, shown is the voltage value, which is in a normal state and is a value before the occurrence of a noise. At time A2 and at the subsequent time A3, it is shown that the real count calculation part 51 takes in the voltage value which is after the occurrence of a noise. The signal waveforms of time A1 and time A3 show that the inclination of a saw-tooth wavelike pulse is returned to a normal state, retaining the voltage change by a noise.
The ion chamber is manufactured with aluminum of a high purity, for example. On the inner surface of the ion chamber, a natural nuclide may be exposed to in a rare case. Or, a very small quantity of the radon, the TRON, or its progeny nuclide in the air may be remained or mixed in, during the time between from the filling processes of the ionization gas to the cleaning process of an ion chamber. For these reasons, a sudden change, as shown in the drawing, emerges on a signal waveform at a very rare frequency.
At the timing of time A1, the real count calculation part 51 reads in the voltage value which is a value before a noise is generated and in the normal state. At the timing of time A2, the real count calculation part 51 reads in the voltage value where electric charges by the noise are under discharge. At the timing of time A3, the real count calculation part 51 reads in the voltage value which is on the extension line of time A1 and has returned to the normal saw-tooth wavelike pulse.
Next, in reference to the flow chart of
If the judgment of step S02 is Yes, the process progresses to step S03. In step S03, it is judged whether Q is zero or not. Here, Q is referred to as a number of times deviated from the permissible range and represents the number of times that the real count (this time) has deviated from the permissible range. If the judgment of step S03 is Yes, the process progresses to step S04. In step S04, a regular processing (D0) is performed. First, the moving average counting rate calculation part 54 calculates a moving average counting rate (this time) of this time operation cycle, and outputs it. An engineering value is obtained in the engineering value conversion part 55, based on the moving average counting rate (this time) and is outputted. Further, the engineering value is displayed in the display unit 6. When a series of this regular processing (D0) is completed, the process will return to step S01 (see
If the judgment of step S02 is No, the process progresses to step S05. In step S05, the number of times deviated from the permissible range (Q), which represents a number of times that real count (this time) has deviated from the permissible range, is added 1, and the process progresses to S06. In step S06, it is judged whether Q is equal to 1 or not. If the judgment of step S06 is Yes, the process progresses to step S07. In step S07, the cumulated count (previous time) is memorized as a cumulated count just before the deviation of real count from the permissible range, and the process progresses to step S09. If the judgment of step S06 is No, the process progresses to step S08. In step S08, it is judged whether Q≤W is satisfied or not. Here, a permissible number of times (W) is set to Q.
If the judgment of step S08 is Yes, the process progresses to step S09. In stop S09, a noise processing (D1) is carried out. First, the engineering value conversion part 55 outputs the engineering value at the previous time operation cycle as an engineering value of this time operation cycle. The outputted engineering value is displayed in the display unit 6. When a series of the noise processing (first noise processing) is completed, the process returns to step S01 (see
If the judgment of step S03 is No, the process progresses to step S11. In step S11, it is judged whether Q is not greater than W or not (Q≤W). If the judgment of step S11 is Yes, the process progresses to step S12. In step S12, a first average real count is calculated and the process progresses to step S13 (see
In step S13, it is judged whether the first average real count is within the permissible range or not. In other words, it is judged whether the permissible lower limit (PL)≤the first average real count≤the permissible upper limit (PU) is satisfied or not. Here, the permissible lower limit (PL) and the permissible upper limit (PU) of the first average real count are the same with the permissible lower limit (PL) and the permissible upper limit (PU) of the real count (this time), respectively.
If the judgment of step S13 is Yes, the process progresses to step S14 (see
If the judgment of step S13 is No, the process progresses to step S15 (see
If the judgment of step S11 is No, the process progresses to step S17 (see
However, as a very rare phenomenon, the cumulated count comes back to a normal state, without the delay of a cycle in operation, when a cumulated count of previous time operation cycle sways in a certain direction by a noise, a cumulated count of this time operation cycle sways in the opposite direction, and the widths of swaying are equivalent. In this case, there is no substantial influence, although the noise processing (D2) or the noise processing (D3) will be carried out.
The noise processing part 53 detects the radiation of a measuring target as the deviation from the permissible range of a real count, if the radiation changes significantly on the basis of the normal background level. The deviation from the permissible range is generated also by the increase of the progeny nuclide of radon or TRON, at a near-by site of the radiation monitoring equipment, in connection with rain fall or snow fall in addition to a noise. This is also true in an accident at the institution on a watch list. These houses are targets of measurement. Accordingly, it is desirable to output the data in real time, in order to eliminate the response delay or missing in measurement as much as possible.
The deviation of real counts from the permissible range, which results from these above reasons, has a long duration time, compared with a general transient noise. For example, a transient noise ceases within 2 cycles of operation, when a cycle of the operation is set in 5 seconds. While the cumulated count makes a comeback to a normal state at 3 cycles of the operation, a real count makes a comeback to a normal state at 4 cycles of the operation. The permissible number of times (W) is a natural number and larger than one. For example, a delay of the response will be 20 seconds, if W is set as 4. The delay of this level is adequately settled in a tolerance level.
The static electricity noise in a radiation detector, the electromagnetism noise of air propagation and the like do not affect the inclination of saw-tooth wavelike pulses before and after the noise invasion. By performing the above mentioned noise processing (D2), a real count during a noise invasion period is replaced by the first average real count. Thereby, real data having a missing part can be restored.
Further, a sudden noise current is generated by an alpha ray emitted from the natural nuclide on the wall surface of an ion chamber, when the radiation detector 1 employs an ion chamber. The output of a saw-tooth wave at the electric charge integrating part 21 makes a sudden change rise and becomes discontinuous. Because the sudden change rise is a single shot phenomenon which occurs very rarely, the inclination of the saw tooth wave comebacks to a normal state at the following cycle of the operation. Missing in measurement which occurs with this phenomenon is 2 cycles of operation at maximum. By performing the above mentioned noise processing (D3), the real count of the concerned operation cycle is replaced by the second average real count. Thereby, the measurement is not influenced substantially.
A static electricity noise is one of the typical electromagnetism noises by which a radiation monitoring equipment 16 affected. A positive or negative noise current invades into the input of the electric charge integrating part 21 and an output signal is sent out from it. The static electricity noise is superimposed on a saw-tooth wavelike pulse of the output signal as a positive or negative sudden change voltage noise. Further, a noise current invades into the input of the electric charge integrating part 21 and vibrates alternately between a negative and a positive value. The electromagnetism noise is superimposed on a saw-tooth wavelike pulse of the output signal as an oscillating voltage noise. In both noises, the current signal component under the noise invasion is faithfully reflected on a saw-tooth wavelike pulse immediately after the cease of the noises. Because the fundamental wave form of a saw-tooth wavelike pulse, as an output signal of the electric charge integrating part 21, is not influenced, the above mentioned noise processing (D2) is applied to the process.
Further, the fundamental wave form of a saw-tooth wavelike pulse undergoes a step-like sudden change, as a single shot phenomenon, due to the alpha ray of the self-contaminated radioactive material in the radiation detector. The self-contaminated radioactive material does not influence the fundamental wave form (output signal of the electric charge integrating part 21) of a saw-tooth wavelike pulse. Accordingly, the above-mentioned noise processing (D3) is applied to the process, if the step-like sudden change is removed. In the noise processing (D3), the second average real count is calculated, based on the cumulated count of immediately just before and just after the noise invasion, and the values between are interpolated. The data row of real counts (row of the real counts in chronological order) is consist of a set-up number of data and is made to be up-dated. Accordingly, a high reliance and highly precise radiation monitoring equipment is obtained without missing in the measurement.
The radiation monitoring equipment according to this invention includes, a radiation detector which detects radiation and outputs a current signal; a current to voltage and frequency conversion unit which accumulates the electric charge of the current signal and changes it into a voltage signal, and discharges the electric charge accumulated when the voltage signal is beyond the preset voltage level, and outputs a rectangle wave pulse, and outputs the saw-tooth wavelike pulse of the repetition frequency proportional to a current signal, by repeating the accumulation and electric discharge of an electric charge; an analog to digital conversion unit which samples the voltage signal which forms the above-mentioned saw wavelike pulse, and outputs a voltage value; a calculation unit and an operation unit which calculate the above-mentioned rectangle wave pulse and outputs a count.
The above-mentioned operation unit has an engineering value operation processing means and a noise processing means. The above-mentioned engineering value operation processing means inputs the above-mentioned voltage value and the above-mentioned count at every operation cycle; calculates a count less than one based on the above-mentioned voltage value; adds the above mentioned count to the count less than one to calculate an addition count; calculates the real count as a difference of the above-mentioned cumulated counts of a this time operation cycle and a previous time operation cycle; takes in the above-mentioned real count of this time operation cycle, in the form to up-date the data row of the set-up number of data, as the serial row of the above-mentioned real count; finds a moving average counting rate, based on the data row; and changes the moving average counting rate into an engineering value, and outputs it.
When the above-mentioned real count of this time operation cycle is within a permissible range, the above-mentioned noise processing means performs a regular processing which outputs the engineering value based on the above-mentioned moving average count of this time operation cycle, to the above-mentioned engineering value operation processing means. When the above-mentioned real count of this time operation cycle is deviated from the above-mentioned permissible range, the above-mentioned noise processing means performs a series of the first noise processing, where the engineering value of an operation cycle just before deviating from the above-mentioned permissible range is made to output. When the number of times of performing the first noise processing continuously is less than a predetermined number, the first noise processing is made to continue. If the above-mentioned real count returns to the permissible range within the predetermined number, the above-mentioned noise processing means subtracts the above-mentioned cumulated count of the operation cycle just before the first noise processing from the above-mentioned cumulated count of this time operation cycle. The difference is divided by the number of times (Q+1) of performing first noise processing, and the first average real count is calculated.
When the first average real count is within the above-mentioned permissible range, the above-mentioned noise processing means replaces the above-mentioned real count with this first average real count, and finds the above-mentioned moving average counting rate. Furthermore, the above-mentioned noise processing means performs a second noise processing which changes the moving average counting rate into the above-mentioned engineering value, and outputs it. The number of times of performing the first noise processing is reset, and a series of the noise processing are terminated.
When the first average real count is deviated from the above-mentioned permissible range, the above-mentioned noise processing means replaces respective real counts (this time), which are deviated from the permissible range with the second average real count just before the real count (this time) and within the above-mentioned permissible range, and finds the above-mentioned moving average counting rate. The above-mentioned noise processing means performs the third noise processing which changes the moving average counting rate into the above-mentioned engineering value, and outputs it. The number of times of performing the first noise processing is reset, and a series of the noise processing are terminated. When the above-mentioned real count returns to the permissible range within the above-mentioned predetermined number of times, the noise processing is made to skip and the regular processing is performed. If the above-mentioned real count returns to the permissible range, the number of times of performing the first noise processing will be reset, and the skip of the noise processing is reset.
A radiation monitoring equipment according to the present invention includes; a radiation detector outputting a current signal when a radiation is incident thereon, a first conversion unit converting the current signal outputted from the radiation detector into a voltage signal and forming a rectangular wave pulse based on the voltage signal, a second conversion unit sampling the voltage signal converted in the first conversion unit and outputting a digital voltage data, a calculation unit counting a number of rectangular wave pulses formed in the first conversion unit, an operation unit calculating a cumulated count from the digital voltage data outputted from the second conversion unit and the number of rectangular wave pulses outputted from the calculation unit, and obtaining a real count (this time) from a difference of a cumulated count (this time) at a this time operation cycle and a cumulated count (previous time) at a previous time operation cycle and memorizing the real count (this time) and a display unit displaying operational results carried out in the operation unit; wherein the calculation unit reads in a real count (this time) and a cumulated count (previous time) at every operation cycle, the calculation unit judges whether the real count (this time) which is read in is within a permissible range or not, if the calculation unit judges that the real count (this time) is within the permissible range, the calculation unit judges whether a number of times deviated from the permissible range is zero or not, if the calculation unit judges that the number of times deviated from the permissible range is zero, the calculation unit performs a regular processing, if the calculation unit judges that the real count (this time) is out of the permissible range, the calculation unit adds 1 to the number of times deviated from the permissible range and further judges whether an added number of times deviated from the permissible range is equal to 1 or not, if the calculation unit judges that the added number of times deviated from the permissible range is equal to 1, the calculation unit memorizes the cumulated count (previous time) as a cumulated count just before the deviation of real count from the permissible range, and further performs a first noise processing, if the calculation unit judges that the added number of times deviated from the permissible range is not equal to 1, the calculation unit judges whether the added number of times deviated from the permissible range is within a permissible number of times or not, if the calculation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the calculation unit performs the regular processing, if the calculation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the calculation unit performs the first processing, and; further wherein the regular processing includes; a step for calculating a moving average counting rate (this time) from a data row of real counts including the cumulated count (this time), and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value, and the first noise processing includes; a step for outputting an engineering value at the previous time operation cycle as an engineering value at the this time operation cycle.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the number of times deviated from the permissible range is not zero, the operation unit judges whether the number of times deviated from the permissible range is within the permissible number of times or not, if the operation unit judges that the number of times deviated from the permissible range is out of the permissible number of times, the operation unit performs the regular processing and further resets the number of times deviated from the permissible range, if the operation unit judges that the number of times deviated from the permissible range is within the permissible number of times, the operation unit subtracts a cumulated count at an operation cycle just before the first noise processing from the cumulated count (previous time) to find a difference, and divides the difference with the number of times deviated from the permissible range+1 to find a first average real count, and judges whether the first average real count is within the permissible range or not, if the operation unit judges that the first average real count is within the permissible range, the operation unit performs a second noise processing and further resets the number of times deviated from the permissible range, and further wherein the second noise processing includes; a step for replacing a real count deviated from the permissible range with the first average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate (this time) into an engineering value and outputting the value.
Furthermore, the radiation monitoring equipment according to the present invention, wherein if the operation unit judges that the first average real count is not within the permissible range, the operation unit performs a third noise processing and furthermore resets the number of times deviated from the permissible range, and further wherein the third noise processing includes; a step for obtaining a second average real count by averaging a real count (this time) and a latest real count within the permissible range, a step for replacing a real count deviated from the permissible range with the second average real count, a step for obtaining a moving average counting rate (this time) based on a data row of real counts after replacement, and a step for converting the moving average counting rate into an engineering value and outputting the value.
A radiation monitoring equipment 100 in accordance with Embodiment 2 is explained based on
Further, as shown in the flow chart of
At the time of a periodic performance testing of the radiation monitoring equipment, investigation of the noise causes, like the contact resistance at a grounding wire connection place and others, is planned, depending on user's needs. These pieces of information can be used as the maintenance information for conducting the investigation of noise causes efficiently. The above-mentioned noise processing means memorizes the starting date (year, month, day and time) of the first noise processing, the execution date (year, month, day and time) of the second noise processing, and the execution date (year, month, day and time) of third noise processing, respectively. The engineering value arithmetic processing means displays these data, including year, month, day and time, on request.
A radiation monitoring equipment 100 in accordance with Embodiment 3 is explained based on
It is made to display those memorized contents on the display unit 6 by requesting from the display unit 6. The maintainability of the radiation monitoring equipment further improves, by providing the information about the state of the radiation monitoring equipment.
It is characterized in that the above mentioned noise processing means memorizes the accumulated number of times of the second above mentioned noise processing execution, and the accumulated number of times of the third above mentioned noise processing execution, respectively. Furthermore, the above mentioned engineering value arithmetic processing means displays those accumulated numbers of times by making a request.
A radiation monitoring equipment 100 in accordance with Embodiment 4 is explained based on
In the high radiation state, the noise processing is not expected and the repetition frequency of a saw-tooth wavelike pulse becomes high. The inclination of a saw-tooth wave becomes steep and the situation takes place where the count c (this time) of smaller than 1 count based on a voltage value (voltage data which are digitally converted) can be disregarded.
By skipping the noise processing in the high radiation state, the analog to digital conversion unit 4 can avoid a risk where the timing, at which the conversion unit reads in the output (voltage of a saw-tooth wavelike pulse) of the electric charge integrating part 21, induces malfunction in a noise processing capability. As a result, a highly reliable radiation monitoring equipment is obtained which covers an upper limit of the measurement range.
It should be noted that each embodiment of the present invention may be freely combined, or appropriately modified or omitted within the spirit and scope of the invention.
As mentioned above, this invention is on a radiation monitoring equipment which can control the changes of readings by noise current, by performing a first to third noise processing on the measurement data, where the voltage sudden change by noise current are overlapped on the fundamental wave forms of the saw-tooth wave voltage, based on the current signal from a radiation detector. The radiation monitoring equipment can be used as a radiation monitoring equipment for measuring a dose rate and others in the living space, which are installed around a nuclear power plant, a nuclear fuel reprocessing plant, an institution for radiation application, their affiliated facilities and the like.
1 Radiation Detector; 2 Current to Voltage and Frequency Conversion Unit; 21 Electric Charge Integrating Part; 211 Capacitor; 212 Operational Amplifier; 22 Voltage Comparison Section; 23 Electric Charge Discharge Section; 231 Constant Current Source; 24 Rectangular Wave Pulse Outputting Part; 3 Calculation Unit; 4 Analog to digital Conversion Unit; 5 Operation Unit; 5a Microprocessor; 51 Real Count Calculation Part; 52 Real Count Memory; 53 Noise Processing Part; 54 Moving Average Counting Rate Calculation Part 5; 55 Engineering Value Conversion Part; 6 Display Unit; 7 Bias Power Supply Unit; 100 Radiation Monitoring equipment; PL Permissible Lower Limit; PU Permissible Upper Limit
Number | Date | Country | Kind |
---|---|---|---|
JP2016-154200 | Aug 2016 | JP | national |
Number | Name | Date | Kind |
---|---|---|---|
4186307 | Tanaka | Jan 1980 | A |
4281382 | Knoll | Jul 1981 | A |
4301367 | Hsu | Nov 1981 | A |
4381450 | Cappelli | Apr 1983 | A |
4591984 | Mori | May 1986 | A |
4880981 | Johnston | Nov 1989 | A |
5012097 | Oda | Apr 1991 | A |
5113077 | Shimizu | May 1992 | A |
5477050 | Kronenberg | Dec 1995 | A |
5650616 | Iketaki | Jul 1997 | A |
6163029 | Yamada | Dec 2000 | A |
6181761 | Izumi | Jan 2001 | B1 |
6229377 | Hoggan | May 2001 | B1 |
8384004 | Rowland | Feb 2013 | B1 |
9229119 | Taguchi | Jan 2016 | B1 |
9423512 | Sato | Aug 2016 | B2 |
9494695 | Eguchi | Nov 2016 | B2 |
10422896 | Ianakiev | Sep 2019 | B1 |
10551721 | Sato | Feb 2020 | B2 |
20020117627 | Jimbo | Aug 2002 | A1 |
20020125999 | Cho | Sep 2002 | A1 |
20020146087 | Izumi | Oct 2002 | A1 |
20020149396 | Mizuhara | Oct 2002 | A1 |
20040200967 | Russell | Oct 2004 | A1 |
20080243404 | Banhegyesi | Oct 2008 | A1 |
20090140159 | Tomita | Jun 2009 | A1 |
20100102243 | Sakai | Apr 2010 | A1 |
20110113611 | Tonami | May 2011 | A1 |
20110144945 | Hayashi | Jun 2011 | A1 |
20130146767 | Seino | Jun 2013 | A1 |
20130248721 | Williams | Sep 2013 | A1 |
20130275087 | Scott | Oct 2013 | A1 |
20130284926 | Aiba | Oct 2013 | A1 |
20130327940 | Nagai | Dec 2013 | A1 |
20140114596 | Kobayashi | Apr 2014 | A1 |
20140172374 | Brady | Jun 2014 | A1 |
20140183359 | Tamaru | Jul 2014 | A1 |
20140188418 | Inoue | Jul 2014 | A1 |
20140203182 | Tsukiyama | Jul 2014 | A1 |
20140312228 | Moteki | Oct 2014 | A1 |
20150006112 | Gordon | Jan 2015 | A1 |
20150017092 | Costes | Jan 2015 | A1 |
20150025852 | Fukuchi | Jan 2015 | A1 |
20150198723 | Katayama | Jul 2015 | A1 |
20160109525 | Chau | Apr 2016 | A1 |
20160109586 | Eguchi | Apr 2016 | A1 |
20160170031 | Feller | Jun 2016 | A1 |
20160231436 | Tanaka | Aug 2016 | A1 |
20160238717 | Abraham | Aug 2016 | A1 |
20160252626 | Eguchi | Sep 2016 | A1 |
20160266054 | Cao | Sep 2016 | A1 |
20160356897 | Aoki | Dec 2016 | A1 |
20170160404 | Moteki | Jun 2017 | A1 |
20170280542 | Aiba | Sep 2017 | A1 |
20180356537 | Katayama | Dec 2018 | A1 |
20190154847 | Ohashi | May 2019 | A1 |
Number | Date | Country |
---|---|---|
1575148 | Sep 1980 | GB |
61-083967 | Apr 1986 | JP |
03195991 | Aug 1991 | JP |
10239440 | Sep 1998 | JP |
H10-239440 | Sep 1998 | JP |
2000-258537 | Sep 2000 | JP |
2001215279 | Aug 2001 | JP |
2003-028963 | Jan 2003 | JP |
2003-057354 | Feb 2003 | JP |
2004-294193 | Oct 2004 | JP |
2004294193 | Oct 2004 | JP |
2004333326 | Nov 2004 | JP |
2006-098081 | Apr 2006 | JP |
2007017374 | Jan 2007 | JP |
2007071760 | Mar 2007 | JP |
2007183118 | Jul 2007 | JP |
2007187682 | Jul 2007 | JP |
2008215907 | Sep 2008 | JP |
2011133454 | Jul 2011 | JP |
2013072675 | Apr 2013 | JP |
2013088266 | May 2013 | JP |
2013113648 | Jun 2013 | JP |
2013228285 | Nov 2013 | JP |
2014-112052 | Jun 2014 | JP |
2014112052 | Jun 2014 | JP |
2014112052 | Jun 2014 | JP |
2014219362 | Nov 2014 | JP |
2014235014 | Dec 2014 | JP |
2016114446 | Jun 2016 | JP |
2018004398 | Jan 2018 | JP |
Entry |
---|
Machine Translation for JP2001215279 (Year: 2001). |
Machine Translation for JP2004294193 (Year: 2004). |
Machine Translation for JP2004333326 (Year: 2004). |
Machine Translation for JP2007017374 (Year: 2007). |
Machine Translation for JP2007183118 (Year: 2007). |
Machine Translation for JP2007187682 (Year: 2007). |
Machine Translation for JP2008215907 (Year: 2008). |
Machine Translation for JP2011133454 (Year: 2011). |
Machine Translation for JP2013072675 (Year: 2013). |
Machine Translation for JP2013088266 (Year: 2013). |
Machine Translation for JP2013113648 (Year: 2013). |
Machine Translation for JP2014112052 (Year: 2014). |
Machine Translation for JP20140235014 (Year: 2014). |
Machine Translation for JP2018004398 (Year: 2018). |
Machine Translation for JPH03195991 (Year: 1991). |
Machine Translation for JP03195991A (Year: 1991). |
Machine Translation for JP10239440A (Year: 1998). |
Office Action (Notice of Reasons for Refusal) dated Aug. 20, 2019, by the Japanese Patent Office in corresponding Japanese Patent Application No. 2016-154200 and English translation of the Office Action. (8 pages). |
Number | Date | Country | |
---|---|---|---|
20180038965 A1 | Feb 2018 | US |