The present invention relates to a regeneration control device for preventing degradation of a cell battery that may occur due to overvoltage during regeneration, which is used in a vehicle capable of performing braking using energy regenerated in a motor, such as an electric vehicle or a hybrid electric vehicle.
Conventionally, a technique has been known in which a motor that is a rotary electric motor is installed as a power source of an electric vehicle or a hybrid electric vehicle, for example, an inverter that is a motor drive unit is provided between the motor and an electric power supply unit, and a motor control unit which controls torque and the like of the motor is provided so that the inverter supplies a motor current that is a motor drive signal to drive the motor. The inverter converts direct current (DC) power from the electric power supply unit into alternate current (AC) power that is determined in accordance with a torque reference, and the motor is driven with the AC current. The motor control unit transmits a control signal to the inverter to control the inverter and generate an AC current for driving the motor.
The motor drive unit (inverter) which drives a motor as described above is driven by using an electric power supply unit as its energy source. For the electric power supply unit, a battery system in which a plurality of cell batteries constituted by a secondary battery and the like connected in series, for example, is used.
A battery system like this is installed on a vehicle as an electric power supply, and the battery system supplies electric power to drive the motor. The battery system is configured so that while the vehicle is decelerated or the like, regenerated energy generated by a regeneration operation of the motor is stored in the battery system and electric energy is exchanged between the battery system and the motor.
When the battery system performs power supply and regeneration of power, power that can be supplied and power that can be regenerated are limited in accordance with a state of the cell battery included in the battery system. For example, if the state of charge (SOC) of the cell battery is in the state of full charge, the battery system cannot receive the power regenerated by the motor. In addition, if the charged capacity of the cell batteries is small, power cannot be supplied to the motor. Cell batteries constituting the battery system may be affected by degradation of their performance, which may occur depending on their usage. For example, if the voltage across terminals of a cell battery reaches a predetermined charge/regeneration inhibiting voltage or above to cause overvoltage or is decreased to a predetermined voltage or below, degradation of the performance of the cell battery may occur. Because of this problem, battery systems are used with restrictions so that the voltage across terminals of the cell batteries would not exceed the predetermined voltage.
As an example of the above-described conventional technique, Patent Literature 1 discusses a technique in which when a battery system including serially connected cell batteries is used for regeneration, it is determined whether the voltage across terminals of the cell batteries constituting the battery system has exceeded a predetermined regeneration limiting voltage equal to or lower than a charge/regeneration inhibiting voltage, and if it is determined that the regeneration limiting voltage has been exceeded, then a total voltage to be achieved at a timing when the voltage across terminals of any of the cell batteries reaches the predetermined charge/regeneration inhibiting voltage (i.e., a sum of the voltages across terminals of the cell batteries constituting the battery system) is predicted, and the amount of regeneration is limited in accordance with deviation of an actual total voltage from the predicted total voltage.
In the above-described Patent Literature 1, if the voltage across terminals of any of the plurality of cell batteries constituting the battery system has exceeded the predetermined regeneration limiting voltage, a total voltage to be achieved at a timing when the voltage across terminals of the cell batteries reaches a regeneration inhibiting voltage for inhibiting regeneration is predicted, and regeneration is limited in accordance with deviation of an actual total voltage from the predicted total voltage value. In other words, the voltage across terminals of the cell batteries included in the battery system is detected and if the detected voltage across terminals has exceeded a predetermined regeneration limiting voltage, a total voltage at which the regeneration inhibiting voltage will be reached is predicted, and in detecting the voltages across terminals of multiple cell batteries, time delay for the detection may occur.
For example, if the battery system is constituted by lithium-ion battery cells, the opening voltage across terminals of the cell batteries is about 3.7 V, and to achieve a voltage of about 360 V for the voltage to be supplied to the motor and the inverter, ninety-six cell batteries are to be connected in series, for example. Because parameters for the multiple cell batteries constituting the battery system that represent the characteristics of the cell batteries such as the open circuit voltage (OCV) and internal resistance are uneven, the voltages across terminals of the cell batteries individually vary according to operation conditions (the current and the temperature). It is necessary to detect the voltages across terminals of the multiple cell batteries described above individually to suppress degradation of each of the cell batteries, and it therefore takes time to detect the voltages across terminals of all the cell batteries. Note that because it will require high costs to structure hardware for detecting the multiple voltages at the same time, the detection of voltages of multiple cell batteries is generally implemented by a method in which the voltages are serially detected.
In general, when regeneration is performed by a motor of a vehicle, the state of vehicle speed shifts from a high vehicle speed state to a low vehicle speed state and the regenerated energy is higher in a period in which the vehicle speed is high (i.e., a period in which the motor speed is high) than in a period in which the vehicle speed is low (i.e., a period in which the motor speed is low), and the amount of regeneration is therefore larger in the beginning of the regeneration. Namely, when regeneration is performed in a general way, the amount of regeneration is large in an initial stage of the regeneration, and it is therefore likely that overvoltage may occur, in which the voltage reaches the charge/regeneration inhibiting voltage.
Accordingly, in the technique discussed in Patent Literature 1 in which the total voltage that is the regeneration inhibiting voltage is predicted after a predetermined regeneration limiting voltage is reached, if any delay has occurred in detecting the voltages across terminals of the cell batteries due to the large amount of regeneration from the initial period of the regeneration, it is possible that the regeneration inhibiting voltage is reached before the total voltage that is the regeneration inhibiting voltage is predicted, and therefore inhibition of regeneration may be abruptly started when the regeneration inhibiting voltage is reached.
In other words, in vehicles, it is possible that a large amount of regeneration is generated from the initial period of regeneration, and if any delay has occurred in the detection of voltages across terminals of the cell batteries, it is therefore difficult in the method discussed in Patent Literature 1 to perform limit of regeneration power before the regeneration inhibiting voltage is reached.
In consideration of the above-described problems arising in the conventional technique, the present invention performs limit of regeneration power so that the regeneration inhibiting voltage would not be reached even if any delay has occurred in the detection of the voltages across terminals of cell batteries. In other words, a purpose of the present invention is to provide a battery system including plurality of cell batteries capable of quickly starting limit of regeneration power before voltages across terminals of the cell batteries reach a regeneration inhibiting voltage in order to suppress degradation of the cell batteries even if any delay has occurred in the detection of states such as the voltages across terminals of the plurality of cell batteries and also capable of increasing the amount of regeneration up to an upper limit amount close to the regeneration inhibiting voltage.
According to the present invention, a regeneration control device for a vehicle includes a motor capable of generating a vehicle braking force by regeneration, a battery system including a plurality of chargeable/dischargeable cell batteries, a battery monitoring device configured to detect a state of the battery system and states of the cell batteries, and regeneration limiting means configured to limit an amount of regeneration by the motor performed when a vehicle braking request is received within a predetermined regeneration power limiting amount, and in the regeneration control device, a period of a first limit of regeneration power starting when the vehicle braking request is received is provided, in which limit of regeneration power is performed by using a constant value or a regeneration power limiting amount set according to a last state of the battery system, and a period of a second limit of regeneration power in which limit of regeneration power is performed after the period of the first limit of regeneration power is provided, in which the regeneration power limiting amount is determined according to the states of the cell batteries acquired from the battery monitoring device during the regeneration performed in the period of the first limit of regeneration power.
The regeneration power limiting amount for the period of the first limit of regeneration power is set so that a total voltage of the battery system becomes lower than a predetermined total voltage limiting value, for example, and a relatively small amount of regeneration is set as the regeneration power limiting amount with a sufficient margin so as to securely protect the cell batteries. Accordingly, the cell batteries are securely prevented from reaching a regeneration inhibiting voltage even in an initial period of braking in which the vehicle speed is high.
Meanwhile, the regeneration power limiting amount for the period of the second limit of regeneration power is determined according to the states of the cell batteries that have been actually acquired during the regeneration in the period of the first limit of regeneration power, and a relatively large amount of regeneration that is close to the limit can therefore be set as the regeneration power limiting amount.
In one preferable embodiment, a cell battery that is likely to reach the regeneration inhibiting voltage during regeneration is identified according to the states of the cell batteries during the period of the first limit of regeneration power and the regeneration power limiting amount for the period of the second limit of regeneration power is determined so that the identified cell battery may not reach the regeneration inhibiting voltage. Accordingly, even if the multiple cell batteries have various different characteristics, no cell battery would reach the regeneration inhibiting voltage.
The states of the cell batteries acquired during the period of the first limit of regeneration power include at least one of a voltage across terminals, a current value, a state of charge (SOC), a state of health (SOH), and an internal resistance value of the cell batteries, for example.
For example, the amount of regeneration is varied into at least two different states during the regeneration in the period of the first limit of regeneration power, and a cell battery that reaches a maximum voltage during the regeneration can be identified according to the states of the cell batteries under each of the at least two different states.
According to the present invention, limit of regeneration power is started immediately after a braking request for a vehicle has been received according to a predetermined regeneration power limiting amount and before states of all cell batteries have been detected, and thereby the cell batteries are securely prevented from reaching a regeneration inhibiting voltage even in an initial period of braking in which the vehicle speed is high. Because the regeneration power limiting amount in the period of the second limit of regeneration power is determined according to detected states of the cell batteries that have been acquired during the period of the first limit of regeneration power, a relatively large amount of regeneration, which is close to an upper limit at which no cell battery would reach the regeneration inhibiting voltage, can be obtained in the period of the second limit of regeneration power. Accordingly, the present invention can securely prevent degradation of the cell batteries and recover larger regenerated energy at the same time.
The electric power-train system 100 includes a motor 200 which is a rotary motor, an inverter 400 which is a motor drive unit, a motor control unit 300 which outputs a control command for the inverter, and a battery system 500 which supplies power to the inverter 400.
The motor control unit 300 of the electric power-train 100 is installed in a vehicle, and is connected via a vehicle controller 600, which controls the entire vehicle, a brake controller 710, which operates a command for a brake operating device 700 which operates a friction brake 720, and a control area network 900.
The vehicle controller 600 which controls the entire vehicle receives detection signals from sensors such as an accelerator opening sensor 800, a brake pedal stroke sensor 810, and a vehicle speed sensor 820 and calculates a command for the electric power-train 100 according to operations by a driver and a state of the vehicle.
In addition, the brake controller 710 determines distribution of the friction brake and a regeneration brake of the electric power-train 100 and performs cooperation control of the friction brake 720 and the regeneration brake of the electric power-train 100.
The battery system 500 is constituted by a plurality of battery modules (531, 532, . . . ), each including a plurality of chargeable/dischargeable cell batteries (hereinafter referred to as “cell batteries” or “cells”) 560 such as a lithium-ion battery, cell monitoring devices (521, 522, . . . ) that detect states of the cell batteries 560 included in the battery modules (531, 532, . . . ) for each of the battery modules (531, 532, . . . ), a temperature sensor 540 which detects various types of temperatures in the battery system 500, and a battery monitoring device 510 which detects a state of the entire battery system 500 on the basis of information from the cell monitoring device (521, 522, . . . ) and information from the temperature sensor 540.
The motor control unit 300 includes a motor control command calculation unit 310, which calculates a command for driving the inverter 400, a motor drive control unit 320, which calculates a motor drive torque control command on the basis of a request for driving force and braking force transmitted from 600, and a motor regeneration control unit 330, which calculates a motor braking torque control command.
The motor control command calculation unit 310 of the motor control unit 300 acquires a rotation angle signal from a rotation angle sensor (not illustrated) installed in the motor 200 and a detection value of three phase AC current from a current sensor (not illustrated) installed in the motor 200, calculates a drive command for the inverter 400, which implements a motor torque command calculated by the motor drive control unit 320 or the motor regeneration control unit 330, and outputs the command to the inverter 400 to drive the inverter 400.
The motor drive control unit 320 calculates a drive torque command that can be output by the motor 200, the inverter 400, and the battery system 500 according to a driving force request from the vehicle controller 600 that is a higher-order controller and outputs a drive torque command to the motor control command calculation unit 310.
The motor regeneration control unit 330 calculates a brake torque command that can be output by the motor 200, the inverter 400, and the battery system 500 according to a braking force request from the vehicle controller 600 that is a higher-order controller or the brake controller 710 and outputs a drive torque command to the motor control command calculation unit 310. Note that details of a process performed by the motor regeneration control unit 330 will be described later below.
The inverter 400 controls driving of and regeneration operations by the motor 200 in accordance with a drive signal corresponding to pulse width modulation (PWM) output from the motor control command calculation unit 310 of the motor control unit 300 according to a torque command. For example, during driving of the motor 200, the inverter 400 converts DC power output from the battery system 500 into three phase AC power and supplies the power to the motor 200, and during regeneration of the motor 200, the inverter 400 converts three phase AC power output from the motor 200 into DC power and charges the battery system 500.
The motor 200 includes a permanent magnet type three phase AC synchronous motor and the like that uses a permanent magnet as a field magnet and is driven and controlled by the three phase AC power supplied from the inverter 400, and while the vehicle is decelerated, the driving force is transmitted from drive wheels to the motor 200, and as the motor 200 functions as a generator to generate regeneration braking force, the kinetic energy in the vehicle can be recovered as electric energy.
In the embodiment in
The determination means 331 of the motor regeneration control unit 330 receives a braking request signal from the vehicle controller 600, receives a state of the battery system 500 from the battery monitoring device 510 of the battery system 500, performs determination to carry out regeneration by the motor 200 and the inverter 400, and transmits regeneration limit information based on the state of the battery system 500 to the vehicle controller 600 and the brake controller 710.
Specifically, according to the braking request determined by the vehicle controller 600 based on an operation of the accelerator and an operation of the brake by the driver, the determination means 331 of the motor regeneration control unit 330 determines the presence of a regeneration request. According to the result of the determination, the battery information acquiring means 333 acquires battery information, such as states of the cell batteries 560 of the battery system 500, states of the battery modules (531, 532), temperature information, from the battery monitoring device 510 which monitors the state of the entire battery system 500. The battery information acquiring means 333 acquires the battery information output from the battery monitoring device 510 and interrupts the process to request the determination means 331 to transmit the battery information to the battery monitoring device 510 at a timing when it is determined that acquisition of the battery information is necessary.
The battery information acquiring means 333 acquires information such as a total voltage value and current signal values of all the batteries of the battery system 500, voltage values and current values of the cell batteries 560 included in each battery, estimation for internal resistance calculated within the battery system 500 and the cell monitoring device (521, 522), estimation for total opening voltage of all the batteries, estimation for opening voltage of each of the cell batteries 560, and a temperature detection value from the plurality of temperature sensor 540 installed within the battery system 500.
Various detection values and estimation values of the inside of the battery system 500 acquired by the battery information acquiring means 333 and the like are stored in the storing means 335. In the storing means 335, battery information to be stored in a short term for a predetermined time period and battery information to be stored for a long time period is classified from each other, and the determination means 331 determines the state of the battery system 500 according to the battery information stored on the storing means 335 and performs various processes.
If it is determined by the determination means of the motor regeneration control unit 330 that a regeneration request has been input according to the braking request having been determined by the vehicle controller 600 according to driver's operations of the accelerator and the brake, then the battery information acquiring means 333 acquires the battery information and the regeneration control means 332 performs regeneration control after the regeneration request.
If a regeneration request is received from the determination means 331, the regeneration control means 332 calculates a regeneration torque command based on the regeneration power limiting amount having been set by the regeneration limit calculating means 334. The regeneration torque command which has been calculated by the regeneration control means 332 is transmitted to the motor control command calculation unit 310, and the motor control command calculation unit 310 calculates a current command for the inverter on the basis of the transmitted regeneration torque command.
In the determination means 331, a torque command for regeneration control is calculated by the regeneration control means 332 according to the regeneration limit set by the regeneration limit calculating means 334, and the motor regeneration control unit 330 transmits the regeneration power limiting amount of the motor 200 and the inverter 400, as the regeneration amount that can be regenerated, to the vehicle controller 600 that is a higher-order controller and to the brake controller 710 for regeneration cooperation control. With respect to the regeneration power limiting amount, the regeneration power limiting amount is set by the regeneration limit calculating means 334 before the regeneration control torque command is calculated by the regeneration control means 332. Accordingly, the regeneration power limiting amount is transmitted to the vehicle controller 600 that is a higher-order controller and the brake controller 710 before the regeneration control torque command is calculated by the regeneration control means 332, and thereby the vehicle controller 600 and the brake controller 710 can acquire the amount of power that can be regenerated by the motor 200 and the inverter 400. Accordingly, distribution of braking between the regeneration brake and the friction brake can be determined according to the limit of regeneration power. Accordingly, excellent distribution and switching between the friction brake and the regeneration brake during the regeneration cooperation control can be implemented.
In one embodiment of the present invention, if a braking request is received, the determination means 331 first selects a regeneration power limiting amount with which none of the cell batteries 560 constituting the battery system 500 in the current state would cause overvoltage in which the charge/regeneration inhibiting voltage is reached from the regeneration limit calculating means 334, and the regeneration control means 332 calculates a regeneration torque command for controlling the regeneration amount to be equal to or lower than the regeneration power limiting amount according to the selected regeneration power limiting amount. The regeneration power limiting amount with which none of the cell batteries 560 constituting the battery system 500 in the current state would cause overvoltage in which the charge/regeneration inhibiting voltage is reached is set by using last information about the battery system 500 which has been stored in the storing means 335. For example, when the total state of charge (SOC) of the battery system 500 is high or when the temperature of the battery system 500 is low, overvoltage in which the overvoltage in which the charge/regeneration inhibiting voltage is reached may easily occur. In this case, a regeneration current with which the overvoltage in which the charge/regeneration inhibiting voltage is reached would not be reached can be set on the basis of an average internal resistance of the battery system 500 and the total open circuit voltage (OCV). For example, a limit of regeneration power is set with which the regeneration current becomes a regeneration current even lower than a limit regeneration current with which the above-described charge/regeneration inhibiting voltage would not be reached.
When a braking request is received, the regeneration control means 332 transmits, on the basis of the regeneration limit set by the regeneration limit calculating means 334, a regeneration torque command calculated based on the regeneration limit, and further, according to the command from the determination means 331, the battery information acquiring means 333 issues a request to the battery monitoring device 510 of the battery system 500 for transmission of the battery information. The battery information includes detection values or estimation values that denote the states of the cell batteries 560, such as the values of the voltage across terminals, the current values, and the internal resistance values of the cell batteries 560 constituting the battery system 500, values of temperature in the battery system 500, values of state of charge (SOC) of the cell batteries 560, values of state of health (SOH) of the cell batteries 560, and values of open circuit voltage (OCV) of the cell batteries 560, detection values or estimation values that denote the states of the modules, such as the values of the voltage across terminals, the current values, and the internal resistance values of the battery module (531, 532) including the plurality of cell batteries 560, temperature values of the module, an average value of states of charge (SOC) of the module, an average value of states of health (SOH) of the module, and an average value of open circuit voltages (OCVs) of the module, and values of the entire battery system, such as the value of the voltage across terminals (total voltage value), the current value, an average temperature value, an average value of states of charge (SOC), an average value of states of health (SOH), and an average value of open circuit voltages (OCVs) of the entire battery system.
The battery information acquiring means 333 transmits a battery information acquisition request to the battery monitoring device 510, receives the battery information transmitted from the battery monitoring device 510, and stores the received battery information in the storing means 335. If it is determined by the determination means 331 that the battery information acquiring means 333 has acquired a plurality of different pieces of battery information and the battery information has been stored in the storing means 335, then the determination means 331 determines that determination of the state of the battery system 500 has become possible, and the regeneration limit calculating means 334 performs calculation of the regeneration power limiting amount. According to the result of the determination by the determination means 331, the regeneration limit calculating means 334 reads the battery information that has been transmitted from the battery monitoring device 510 and stored in the storing means 335 and determines the state of the battery system 500. In particular, the regeneration limit calculating means 334 determines the state of each cell battery 560 included in the battery system 500 and identifies a cell battery that is likely to cause overvoltage in which charge/regeneration inhibiting voltage is reached during regeneration. In addition, the regeneration limit calculating means 334 acquires the values of the voltage across terminals, the current values, the values of state of charge (SOC), values of state of health (SOH), and the like including a plurality of sampling values and their average of the identified specific cell battery 560 that is likely to cause overvoltage in which the charge/regeneration inhibiting voltage is reached during regeneration, which are stored in the storing means 335, and sets an upper limit of the amount of regeneration with which the charge/regeneration inhibiting voltage would not be reached or an upper limit of the regeneration current. The information about the cell batteries 560 read by the regeneration limit calculating means 334 from the storing means 335 is information about the battery system 500 for a time period in which the regeneration limit has been performed by the regeneration control means 332 according to the braking request, and because the regeneration control means 332 continues to perform the regeneration limit while the information is acquired and read, the voltage of the cell batteries 560 of the battery system 500 would not reach charge/regeneration inhibiting voltage.
After the regeneration power limiting amount or the regeneration current limiting amount has been set by the regeneration limit calculating means 334, the determination means 331 stores the set regeneration power limiting amount or the regeneration current limiting amount in the storing means 335 and also transmits the regeneration power limiting amount that can be regenerated by the motor 200 and the inverter 400 to the vehicle controller 600 that is the higher-order controller or the brake controller 710. The higher-order controller 600 and the brake controller 710 can thereby acquire the amount available for regeneration braking and determine the distribution of braking between the regeneration brake and the friction brake.
After the regeneration power limiting amount has been set, the vehicle controller 600 that is the higher-order controller or the brake controller 710 calculates a regeneration braking request value according to the regeneration power limiting amount and outputs the calculated value to the motor control unit 300 as a regeneration braking command. The regeneration braking command is transmitted to the regeneration control means 332 to calculate a regeneration torque command there based on the regeneration power limiting amount or the regeneration current limiting amount.
First, the motor regeneration control unit 330 of the motor control unit 300 in
After the determination of the states of the cells has been completed (S1-5), the cell battery the cell batteries 560 that can cause overvoltage in which the charge regeneration inhibiting voltage is reached during regeneration (hereinafter referred to as a “constraint cell battery” or a “degraded cell battery”) can be identified, and the motor regeneration control unit 330 of the motor control unit 300 transmits the information about the specific degraded cell battery 560 (S1-6).
After the motor regeneration control unit 330 of the motor control unit 300 has transmitted the information about the degraded cell battery 560 that becomes a constraint during regeneration, limits of regeneration power to be set thereafter can be set on the basis of the transmitted information. Examples of the information about the degraded cell battery include information such as estimation of internal resistance, an upper limit value of current at which the overvoltage in which the charge/regeneration inhibiting voltage is reached is reached, and open circuit voltage values.
In the example illustrated in
In S2-5, the states of the cell batteries 560 are determined by using the information about the cell batteries 560 constituting the battery system 500, which has been acquired from the battery monitoring device 510. If the determination of the states of the cells has been completed, then the process proceeds to S2-9. At a timing immediately after the braking request has been received, the information about the cell batteries 560 constituting the battery system 500 may be yet to be received from the battery monitoring device 510 in some cases and thus the determination of the cell states is usually yet to be completed in such cases, and the process therefore proceeds to S2-8.
The cell battery information includes values of the voltage across terminals, concurrent current values, estimation for state of charge (SOC), estimation for state of health (SOH), estimation of internal resistance, and the like of the cell batteries 560, and physical quantities that denote the states of the cell batteries 560 correspond to the cell battery information. The determination of the state of the cells performed in S2-5 includes, for example, identification of a cell battery 560 with the highest voltage across terminals among the multiple cell batteries 560 constituting the battery system 500 as a cell battery that becomes a constraint during regeneration, identification of the cell battery that becomes a constraint by estimating the open circuit voltage values and the internal resistance of the cell batteries 560 from the values of the voltage across terminals and the current values of a plurality of states (e.g., states at a plurality of different battery current values) of the cell batteries 560, by determining whether the capacity has degraded from the open circuit voltage, and by determining whether the resistance has degraded from the internal resistance, and the like. In other words, with respect to the determination of the cell states, the cell battery information about all the cell batteries 560 is transmitted from the battery monitoring device 510 at least once or a plurality of times, and thereby it becomes possible to determine the cell states.
If it is determined that the determination of the cell states has not been completed yet in S2-5, then the process proceeds to S2-8 and a first limit of regeneration power is performed. Note that because the determination of the cell states is basically not completed for the first time of the determination as described above, then the process proceeds to S2-8 in this case.
The first limit of regeneration power in S2-8, which will be described later below, is a regeneration control performed within a time period after a timing at which a regeneration request has been received by the motor regeneration control unit 330 of the motor control unit 300 and before a timing at which the determination of the cell states is completed after having output a request for receiving the information about the cell batteries 560 constituting the battery system 500 is output to the battery monitoring device 510 and having acquired the cell battery information from the battery monitoring device 510 a plurality of times. In the first limit of regeneration power, because correct states of the cell batteries 560 constituting the battery system 500 have not been acquired yet, if the regeneration control is performed on the basis of the amount of regeneration requested from the higher-order vehicle controller 600 and the brake controller 710 as a command and if the amount of regeneration requested from the higher-order controller is large, then it is possible that a cell degraded battery 560 may exist that reaches a charge inhibiting voltage, for example, among the cell batteries 560 constituting the battery system 500. Accordingly, in the first limit of regeneration power, regeneration control is performed in which the amount of regeneration is limited to a small amount of regeneration with which the charge inhibiting voltage would not be reached. If the motor regeneration control unit 330 of the motor control unit 300 limits the amount of regeneration to a small amount of regeneration in the first limit of regeneration power, the requested braking cannot be implemented because the amount of regeneration requested from the higher-order vehicle controller 600 and the brake controller 710 cannot be achieved. However, since the first limit of regeneration power is a limit of regeneration power performed when a braking request has been received and in a period before the determination of the cell states, the requested braking can be implemented because the higher-order vehicle controller 600 and the brake controller 710 can set the distribution between the regeneration brake and the friction brake considering the limit of regeneration power by the first limit of regeneration power by previously setting an amount of regeneration performed in the first limit of regeneration power and transmitting the same to the higher-order vehicle controller 600 or the brake controller 710. Further, by performing a setting so that the regeneration current value in the first limit of regeneration power becomes constant, values of the voltage across terminals of the cell batteries 560 can be detected in the period of the first limit of regeneration power under the same current condition, which thereby enables stable detection of the cell battery states. In addition, alternatively to using the constant current value, it is possible to use a state of regeneration for the period in which the first limit of regeneration power is performed that is appropriate for detection of the states of the cell batteries 560.
After the first limit of regeneration power is started, a request for receiving the states of cell batteries is output (S2-3). In S2-3, the motor regeneration control unit 330 of the motor control unit 300 in
After the information about the cell batteries 560 is received from the battery monitoring device 510 of the battery system 500 (or after the acquisition timing has come even when the information has not been received), the process returns to S2-2. If the braking request (S2-2) has been continued, the determination of whether the determination of the cell states (S2-5) has been completed is repeated.
In transmitting the cell battery information from the battery monitoring device 510, it is necessary to detect the states of the plurality of cell batteries included in the battery system 500, and if it takes a long time to detect the states, delay may occur until the determination of the cell states is completed. Therefore, in some cases, the period of receiving the cell battery information may be delayed in relation to the control period in which the motor regeneration control unit 330 of the motor control unit 300 performs the regeneration control. Accordingly, before the determination of the cell states in S2-5 is completed after having received the cell battery information, the motor regeneration control unit 330 of the motor control unit 300 proceeds to S2-8 to perform the first limit of regeneration power and repeat the request for receiving the cell battery information and the receiving of the cell battery information.
In the cell state determination process of S2-5, after the motor regeneration control unit 330 of the motor control unit 300 has acquired the cell battery information from the battery monitoring device 510 for a plurality of times, the states of the cell batteries 560 constituting the battery system 500 is determined on the basis of the acquired cell battery information. As described above, the cell battery information includes values of the voltages across terminals, concurrent current values, estimation for state of charge (SOC), estimation for state of health (SOH), estimation of internal resistance, and the like of the cell batteries 560, and physical quantities that denote the states of the cell batteries 560 correspond to the cell battery information. The determination of the cell states include identification of the constraint cell battery that becomes a constraint during regeneration.
After the determination of the cell states in S2-5 is completed, the process proceeds to the second limit of regeneration power (S2-9). In the second limit of regeneration power in S2-9, because the determination of the cell states has been completed in S2-5 and thus the cell battery that becomes a constraint during regeneration has been identified, an upper limit regeneration amount or an upper limit value of regeneration current for preventing the voltage of the identified cell battery from reaching the charge inhibiting voltage can be set as the regeneration power limiting amount. Accordingly, in the second limit of regeneration power, regeneration control is performed on the basis of information about the constraint cell battery acquired as a result of the completion of the determination of the cell batteries and the upper limit regeneration amount or the upper limit value of regeneration current.
If the motor regeneration control unit 330 of the motor control unit 300 arbitrarily limits the upper limit regeneration amount or the upper limit regeneration current in the second limit of regeneration power, the requested braking cannot be implemented in some cases because the amount of regeneration requested from the higher-order vehicle controller 600 and the brake controller 710 cannot be achieved. However, since the value for the limit of regeneration power such as the upper limit regeneration amount or the upper limit value of regeneration current is set after the determination of the cell states is completed when a braking request has been received in the second limit of regeneration power, the requested braking can be implemented because the higher-order vehicle controller 600 and the brake controller 710 can set the distribution between the regeneration brake and the friction brake considering the limit of regeneration power by the second limit of regeneration power by previously transmitting the set limit of regeneration power to the higher-order vehicle controller 600 or the brake controller 710.
After the second limit of regeneration power is started, the process returns to S2-2 and repeats the determination of the braking request (S2-2) and the determination of completion of the determination of the cell states (S2-5).
By performing the above-described process, when a braking request is received, the first limit of regeneration power for limiting the amount of regeneration with which the charge/regeneration inhibiting voltage is not reached is immediately performed, detailed information about the cell batteries 560 constituting the battery system 500 is acquired while the first limit of regeneration power is being performed, the states of the cell batteries 560 are determined, and the upper limit regeneration amount or the upper limit value of regeneration current with which the voltage across terminals of the cell battery that becomes a constraint during the regeneration would not reach the charge inhibiting voltage is set to perform the second limit of regeneration power, and thereby upper limit regeneration can be performed in which the cell battery that is likely to reach the charge inhibiting voltage and most likely to become a constraint among the cell batteries 560 constituting the battery system 500 would not reach the charge/regeneration inhibiting voltage.
Next,
In the example illustrated in
In other words, in S3-10, in order to perform the first limit of regeneration power in the following S3-8, the already acquired information about the battery system 500 is acquired from the motor regeneration control unit 330. The information about the battery system 500 includes information which indicates the states of the battery system 500 that has been transmitted from the battery monitoring device 510 before the braking request, such as values of state of charge (SOC) of the entire battery system 500, a total voltage value of the entire battery system 500, and variation of the voltages across terminals and the internal resistances of the cell batteries 560 constituting the battery system 500. Based on this information, an approximate value of the regeneration power limiting amount or a regeneration current limiting value with which the voltages across terminals of the cell batteries 560 would not become overvoltage in which the charge/regeneration inhibiting voltage is reached can be set, and further, if a limit lower than the setting value is set, the limit of regeneration power can be performed in which no cell battery would cause overvoltage in which the charge/regeneration inhibiting voltage is reached.
After the battery information has been read in S3-10, the process proceeds to S3-5. In S3-5, by using the information about the cell batteries 560 acquired from the battery monitoring device 510, the states of the cell batteries 560 constituting the battery system 500 is determined. If the determination of the cell states has been completed, the process proceeds to S3-9. Similarly to S2-5 in
If it is determined in S3-5 that the determination of the cell states has not been completed yet, then the process proceeds to S3-8 and the first limit of regeneration power is performed. The first limit of regeneration power in S3-8, as described above with reference to
Note that as described above with reference to
After the first limit of regeneration power (S3-8) is started, a request for receiving the states of cell batteries is output (S3-3). In S3-3, the motor regeneration control unit 330 of the motor control unit 300 in
After the information about the cell batteries 560 is received from the battery monitoring device 510 of the battery system 500 (or after the acquisition timing has come even when the information has not been received), the process returns to S3-2. If the braking request (S3-2) has been continued, the determination of whether the determination of the cell states (S3-5) has been completed is repeated.
In transmitting the cell battery information from the battery monitoring device 510, it is necessary to detect the states of the plurality of cell batteries included in the battery system 500, and if it takes a long time to detect the states, delay may occur until the determination of the cell states is completed. Therefore, in some cases, the period of receiving the cell battery information may be delayed in relation to the control period in which the motor regeneration control unit 330 of the motor control unit 300 performs the regeneration control. Accordingly, before the determination of the cell states in S3-5 is completed after having received the cell battery information, the motor regeneration control unit 330 of the motor control unit 300 proceeds to S3-8 to perform the first limit of regeneration power and repeat the request for receiving the cell battery information and the receiving of the cell battery information.
In the cell state determination process of S3-5, after the motor regeneration control unit 330 of the motor control unit 300 has acquired the cell battery information from the battery monitoring device 510 for a plurality of times, the states of the cell batteries 560 constituting the battery system 500 is determined on the basis of the acquired cell battery information. As described above, the cell battery information includes values of the voltages across terminals, concurrent current values, estimation for state of charge (SOC), estimation for state of health (SOH), estimation of internal resistance, and the like of the cell batteries 560, and physical quantities that denote the states of the cell batteries 560 correspond to the cell battery information. The determination of the cell states include identification of the constraint cell battery that becomes a constraint during regeneration.
After the determination of the cell states in S3-5 is completed, the process proceeds to the second limit of regeneration power (S3-9). In the second limit of regeneration power in S3-9, because the determination of the cell states has been completed in S3-5 and thus the cell battery that becomes a constraint during regeneration has been identified, an upper limit regeneration amount or an upper limit value of regeneration current for preventing the voltage of the identified cell battery from reaching the charge inhibiting voltage can be set. Accordingly, in the second limit of regeneration power, regeneration control is performed on the basis of information about the constraint cell battery acquired as a result of the completion of the determination of the cell batteries and the upper limit regeneration amount or the upper limit value of regeneration current.
As described above with reference to
After the second limit of regeneration power is started, the process returns to S3-2 and repeats the determination of the braking request (S3-2) and the determination of completion of the determination of the cell states (S3-5).
In the present embodiment, by performing the above-described process, when a braking request is received, the first limit of regeneration power in which the amount of regeneration, with which the charge/regeneration inhibiting voltage is not reached is limited, is securely performed on the basis of the already acquired information about the battery system 500, detailed information about the cell batteries 560 constituting the battery system 500 is acquired while the first limit of regeneration power is being performed, and the upper limit regeneration amount or the upper limit value of regeneration current with which the voltage of the cell battery that becomes a constraint during the regeneration would not reach the charge inhibiting voltage is set to perform the second limit of regeneration power, and thereby upper limit regeneration can be performed in which the cell battery that is likely to reach the charge inhibiting voltage and most likely to become a constraint among the cell batteries 560 constituting the battery system 500 would not reach the charge/regeneration inhibiting voltage.
Next,
In the example illustrated in
If it is determined in S4-2 that a braking request signal has been received, the process proceeds to S4-10 and the information about the battery system 500 and the cell batteries 560 included therein, which has been already acquired from the battery monitoring device 510 of the battery system 500, is read from the storing means 335 of the motor regeneration control unit 330 (S4-10).
In other words, in S4-10, in order to perform the first limit of regeneration power in S4-8, the already acquired information about the battery system 500 is acquired from the motor regeneration control unit 330. This process is the same as that in S3-10 in
In S4-11, it is determined whether limit of regeneration power is necessary based on the read battery information. For example, if the value of the total state of charge (SOC) of the battery system 500 is low and if it is determined that overvoltage in which the charge/regeneration inhibiting voltage would not occur in any of the cell batteries 560, then it is determined that it is not necessary to perform limit of regeneration power. If the value of the state of charge (SOC) is high, it is determined that it is necessary to perform the limit of regeneration power because it is likely that overvoltage in which the charge/regeneration inhibiting voltage is reached occurs. If the temperature of the parts of the battery system 500 is low, the voltages across terminals would increase even at the same regeneration current value because the internal resistance of the cell batteries 560 constituting the battery system 500 becomes high, and therefore it is determined that overvoltage in which the charge/regeneration inhibiting voltage is reached is likely to occur and that it is necessary to perform the limit of regeneration power. On the other hand, if the temperature of the battery system 500 is normal temperature, the internal resistance is low, and it is therefore determined that overvoltage in which the charge/regeneration inhibiting voltage is reached would not occur and that it is not necessary to perform the limit of regeneration power. Further, if it is determined that the state of health (SOH) of the cell batteries 560 constituting the battery system 500 has become worse and that the battery system has been degraded, then it is determined that it is necessary to perform the limit of regeneration power because the internal resistance is high and overvoltage in which the charge/regeneration inhibiting voltage is reached is likely to occur in this case. If the vehicle speed is low, the amount of regeneration that can be regenerated becomes small, and thus it is determined that overvoltage in which the charge/regeneration inhibiting voltage is reached would not occur and that it is not necessary to perform the limit of regeneration power. As described above, whether limit of regeneration power is necessary can be determined by using the battery states and the vehicle states at a relatively latest time before the regeneration.
If it is determined in S4-11 that the limit of regeneration power is unnecessary, then the process proceeds to S4-12 and normal regeneration control is performed. On the other hand, it is determined in S4-11 that the limit of regeneration power is necessary, then the process proceeds to S4-5.
In S4-5, similarly to S3-5 described above with reference to
If it is determined in S4-5 that the determination of the cell states has not been completed yet, then the process proceeds to S4-8 to perform the first limit of regeneration power.
The first limit of regeneration power in S4-8, as described above with reference to
Note that as described above with reference to
After the first limit of regeneration power (S4-8) is started, a request for receiving the states of cell batteries is output (S4-3). In S4-3, the motor regeneration control unit 330 of the motor control unit 300 in
After the information about the cell batteries 560 is received from the battery monitoring device 510 of the battery system 500 (or after the acquisition timing has come even when the information has not been received), the process returns to S4-2. If the braking request (S4-2) has been continued, the determination of whether the determination of the cell states (S4-5) has been completed is repeated.
In transmitting the cell battery information from the battery monitoring device 510, it is necessary to detect the states of the plurality of cell batteries included in the battery system 500, and if it takes a long time to detect the states, delay may occur until the determination of the cell states is completed. Therefore, in some cases, the period of receiving the cell battery information may be delayed in relation to the control period in which the motor regeneration control unit 330 of the motor control unit 300 performs the regeneration control. Accordingly, before the determination of the cell states in S4-5 is completed after having received the cell battery information, the motor regeneration control unit 330 of the motor control unit 300 proceeds to S4-8 to perform the first limit of regeneration power and repeat the request for receiving the cell battery information and the receiving of the cell battery information.
In the cell state determination process of S4-5, after the motor regeneration control unit 330 of the motor control unit 300 has acquired the cell battery information from the battery monitoring device 510 for a plurality of times, the states of the cell batteries 560 constituting the battery system 500 is determined on the basis of the acquired cell battery information. As described above, the cell battery information includes values of the voltages across terminals, concurrent current values, estimation for state of charge (SOC), estimation for state of health (SOH), estimation of internal resistance, and the like of the cell batteries 560, and physical quantities that denote the states of the cell batteries 560 correspond to the cell battery information. The determination of the cell states include identification of the constraint cell battery that becomes a constraint during regeneration.
After the determination of the cell states in S4-5 is completed, the process proceeds to the second limit of regeneration power (S4-9). In the second limit of regeneration power in S4-9, because the determination of the cell states has been completed in S4-5 and thus the cell battery that becomes a constraint during regeneration has been identified, an upper limit regeneration amount or an upper limit value of regeneration current for preventing the voltage of the identified cell battery from reaching the charge inhibiting voltage can be set as the regeneration power limiting amount. Accordingly, in the second limit of regeneration power, regeneration control is performed on the basis of information about the constraint cell battery acquired as a result of the completion of the determination of the cell batteries and the upper limit regeneration amount or the upper limit value of regeneration current.
As described above with reference to
After the second limit of regeneration power is started, the process returns to S4-2 and repeats the determination of the braking request (S4-2) and the determination of completion of the determination of the cell states (S4-5).
In the present embodiment, by performing the above-described process, whether limit of regeneration power is necessary is determined after a braking request has been received, and it is determined that the limit of regeneration power is necessary, then the first limit of regeneration power in which the amount of regeneration, with which the charge/regeneration inhibiting voltage is not reached is limited, is securely performed, detailed information about the cell batteries 560 constituting the battery system 500 is acquired while the first limit of regeneration power is being performed, and the upper limit regeneration amount or the upper limit value of regeneration current with which the voltage of the cell battery that becomes a constraint during the regeneration would not reach the charge inhibiting voltage is set to perform the second limit of regeneration power, and thereby upper limit regeneration can be performed in which the cell battery that is likely to reach the charge inhibiting voltage and most likely to become a constraint among the cell batteries 560 constituting the battery system 500 would not reach the charge/regeneration inhibiting voltage. In the present embodiment, in particular, it is determined that limit of regeneration power is not necessary, then the regeneration control involving extra limit of regeneration power is not performed and upper limit regeneration is performed starting from the initial stage of the regeneration, and thus the amount of regeneration can be maximized.
Next,
In the example illustrated in
If it is determined in S5-2 that a braking request signal has been received, the process proceeds to S5-10 and the information about the battery system 500 and the cell batteries 560 included therein, which has been already acquired from the battery monitoring device 510 of the battery system 500, is read from the storing means 335 of the motor regeneration control unit 330 (S5-10).
In other words, in S5-10, in order to perform the first limit of regeneration power in S5-8, the already acquired information about the battery system 500 is acquired from the motor regeneration control unit 330. The information about the battery system 500 includes information which indicates the states of the battery system 500 that has been transmitted from the battery monitoring device 510 before the braking request, such as the state of charge (SOC) of the entire battery system 500, a total voltage value of the entire battery system 500, and variation of the voltages across terminals and the internal resistances of the cell batteries 560. Based on this information, an approximate value of the regeneration power limiting amount or a regeneration current limiting value with which the voltages across terminals of the cell batteries 560 would not become overvoltage in which the charge/regeneration inhibiting voltage is reached can be set, and further, if a limit lower than the setting value is set, the limit of regeneration power can be performed in which no cell battery would cause overvoltage in which the charge/regeneration inhibiting voltage is reached. Further, in S5-10, in order to determine whether the limit of regeneration power in the subsequent step S5-11, necessary information about the battery system 500 is also read from the storing means 335 of the motor regeneration control unit 330 included in the motor control unit 300. The battery information to be read includes information such as the total voltage value, the total charged capacity, and the state of health (SOH) of the entire battery system 500, the vehicle speed value, and temperature values of parts of the battery system 500. This process is the same as that in S4-10 in
In S5-10, in addition to the process described above, necessary information about the battery system 500 is read from the storing means 335 for determination in S5-13 as to whether determination of the cell states is necessary. The battery information to be read is information about the states of the battery and the regeneration power limiting amount acquired and used during past limits of regeneration power. Specifically, the battery information to be read includes information acquired when a degraded cell battery that becomes a constraint during regeneration among the cell batteries 560 constituting the battery system 500 has been identified in past limits of regeneration power, such as the total voltage values and the total charged capacity of the entire battery system 500, temperature values and states of health (SOH) of parts of the battery system 500, and further, the regeneration current limiting values and regeneration power limiting amounts. This information may be information necessary for determining whether the current states of the battery system 500 and the cell batteries 560 are in a state similar to the states detected in limits of regeneration power performed before.
After the battery information has been read in S5-10, the process proceeds to S5-11.
In S5-11, it is determined whether limit of regeneration power is necessary based on the read battery information. For example, if the value of the total state of charge (SOC) of the battery system 500 is low and if it is determined that overvoltage in which the charge/regeneration inhibiting voltage would not occur in any of the cell batteries 560 constituting the battery system 500, then it is determined that it is not necessary to perform limit of regeneration power, while if the value of the state of charge (SOC) is high, it is determined that it is necessary to perform the limit of regeneration power because it is likely that overvoltage in which the charge/regeneration inhibiting voltage is reached occurs. If the temperature of the parts of the battery system 500 is low, the voltages across terminals would increase even at the same regeneration current value because the internal resistance of the cell batteries 560 constituting the battery system 500 becomes high, and therefore it is determined that overvoltage in which the charge/regeneration inhibiting voltage is reached is likely to occur and that it is necessary to perform the limit of regeneration power. On the other hand, if the temperature of the battery system 500 is normal temperature, the internal resistance is low, and it is therefore determined that overvoltage in which the charge/regeneration inhibiting voltage is reached would not occur and that it is not necessary to perform the limit of regeneration power. Further, if it is determined that the state of health (SOH) of the cell batteries 560 constituting the battery system 500 has become worse and that the battery system has been degraded, then it is determined that it is necessary to perform the limit of regeneration power because the internal resistance is high and overvoltage in which the charge/regeneration inhibiting voltage is reached is likely to occur in this case. If the vehicle speed is low, the amount of regeneration that can be regenerated becomes small, and thus it is determined that overvoltage in which the charge/regeneration inhibiting voltage is reached would not occur and that it is not necessary to perform the limit of regeneration power. As described above, whether limit of regeneration power is necessary can be determined by using the battery states and the vehicle states at a relatively latest time before the regeneration.
If it is determined in S5-11 that the limit of regeneration power is unnecessary, then the process proceeds to S5-12 and normal regeneration control is performed. On the other hand, it is determined in S5-11 that the limit of regeneration power is necessary, then the process proceeds to S5-13.
In 5-13, whether determination of the cell states is necessary is determined. The determination as to whether determination of the cell states is necessary is performed by using the information about the battery system 500 acquired in S5-10. Specifically, it is determined whether the current states of the battery system 500 and the cell batteries 560 included therein, such as the voltage, the current, the temperature, the charged capacity, and the state of health (SOH), are similar to the battery states acquired at timings of braking requests of second limit of regeneration power performed before. Alternatively to using the above-described information, any information that enables the determination as to similarity to the state of the battery system 500 or the cell batteries 560 obtained in the second limit of regeneration power performed before can be used. For example, if appropriate conditions have been satisfied, i.e., if, with respect to the temperature of the battery system 500, for example, a difference between the current and the past values is within a predetermined value, if a difference between the current and the past charged capacity values is within a predetermined value, if a difference between the current and the past total voltages is within a predetermined value, if a difference between the current degree of health denoting the state of health (SOH) and the past degree of degradation is within a predetermined value, etc., between the current value and the value obtained when the second limit of regeneration power has been performed before for each such condition, then it is determined that the current state is similar to the state in the second limit of regeneration power performed before and determination of the cell states is determined to be not necessary. In this case, as will be discussed below, the regeneration current limiting value and the regeneration power limiting amount used in the second limit of regeneration power performed before can be used as limiting values for the second limit of regeneration power to be performed in the current state.
If it is determined in S5-13 in the above-described manner that the current state of the battery system 500 is similar to the state thereof in the second limit of regeneration power performed before at the time of the braking request, then it is determined that the determination of the cell states is not necessary and the process proceeds to S5-9 for the second limit of regeneration power without performing S5-5. On the other hand, if it is determined in S5-13 that the current state of the battery system 500 is not similar to the state thereof in the second limit of regeneration power performed before, then it is determined that the determination of the cell states is necessary and the process proceeds to S5-5.
In S5-5, similarly to S4-5 described above with reference to
If it is determined in S5-5 that the determination of the cell states has not been completed yet, then the process proceeds to S5-8 to perform the first limit of regeneration power.
The first limit of regeneration power in S5-8, as described above with reference to
Note that as described above with reference to
After the first limit of regeneration power (S5-8) is started, a request for receiving the states of cell batteries is output (S5-3). In S5-3, the motor regeneration control unit 330 of the motor control unit 300 in
After the information about the cell batteries 560 is received from the battery monitoring device 510 of the battery system 500 (or after the acquisition timing has come even when the information has not been received), the process returns to S5-2. If the braking request (S5-2) has been continued, the determination of whether the determination of the cell states (S5-5) has been completed is repeated.
In transmitting the cell battery information from the battery monitoring device 510, it is necessary to detect the states of the plurality of cell batteries included in the battery system 500, and if it takes a long time to detect the states, delay may occur until the determination of the cell states is completed. Therefore, in some cases, the period of receiving the cell battery information may be delayed in relation to the control period in which the motor regeneration control unit 330 of the motor control unit 300 performs the regeneration control. Accordingly, before the determination of the cell states in S5-5 is completed after having received the cell battery information, the motor regeneration control unit 330 of the motor control unit 300 proceeds to S5-8 to perform the first limit of regeneration power and repeat the request for receiving the cell battery information and the receiving of the cell battery information.
In the cell state determination process of S5-5, after the motor regeneration control unit 330 of the motor control unit 300 has acquired the cell battery information from the battery monitoring device 510 for a plurality of times, the states of the cell batteries 560 constituting the battery system 500 is determined on the basis of the acquired cell battery information. As described above, the cell battery information includes values of the voltages across terminals, concurrent current values, estimation for state of charge (SOC), estimation for state of health (SOH), estimation of internal resistance, and the like of the cell batteries 560, and physical quantities that denote the states of the cell batteries 560 correspond to the cell battery information. The determination of the cell states include identification of the constraint cell battery that becomes a constraint during regeneration.
After the determination of the cell states in S5-5 is completed, the process proceeds to the second limit of regeneration power (S5-9). In the second limit of regeneration power in S5-9, because the determination of the cell states has been completed in S5-5 and thus the cell battery that becomes a constraint during regeneration has been identified, an upper limit regeneration amount or an upper limit value of regeneration current for preventing the voltage of the identified cell battery from reaching the charge inhibiting voltage can be set. Accordingly, in the second limit of regeneration power, regeneration control is performed on the basis of information about the constraint cell battery acquired as a result of the completion of the determination of the cell batteries and the upper limit regeneration amount or the upper limit value of regeneration current.
If it is determined in S5-13 that the determination of the cell states is not necessary also, the process proceeds to the second limit of regeneration power (S5-9). In this case, because it has been determined in S5-13 that the current state of the battery system 500 is similar to the state of the battery system 500 acquired when the second limit of regeneration power has been performed before, the similar regeneration current limiting value and the similar regeneration power limiting amount used in the second limit of regeneration power performed before are set as limiting values for the second limit of regeneration power to be performed in the current state.
As described above with reference to
After the second limit of regeneration power is started, the process returns to S5-2 and repeats the determination of the braking request (S5-2) and the determination of completion of the determination of the cell states (S5-5).
In the present embodiment, by performing the above-described process, whether limit of regeneration power is necessary is determined after a braking request has been received, and it is determined that the limit of regeneration power is necessary, then the first limit of regeneration power in which the amount of regeneration, with which the charge/regeneration inhibiting voltage is not reached is limited, is securely performed, detailed information about the cell batteries 560 constituting the battery system 500 is acquired while the first limit of regeneration power is being performed, and the upper limit regeneration amount or the upper limit value of regeneration current with which the voltage of the cell battery that becomes a constraint during the regeneration would not reach the charge inhibiting voltage is set to perform the second limit of regeneration power, and thereby upper limit regeneration can be performed in which the worst cell battery that is likely to reach the charge inhibiting voltage among the cell batteries 560 constituting the battery system 500 would not reach the charge/regeneration inhibiting voltage. In the present embodiment, in particular, it is determined that limit of regeneration power is not necessary, then the regeneration control involving extra limit of regeneration power is not performed and upper limit regeneration is performed starting from the initial stage of the regeneration, and thus the amount of regeneration can be maximized. Further, if the current states of the battery system 500 and the cell batteries 560 are similar to the state in the second limit of regeneration power performed before, the second limit of regeneration power with the large amount of regeneration can be immediately performed without requesting a new regeneration power limiting amount for performing limitation in the second limit of regeneration power and without performing the first limit of regeneration power with a small amount of regeneration, and thus a larger amount of regeneration can be secured.
Referring to
In the example illustrated in
In
In
In
After the time t0, the regeneration control is performed at or below the regeneration current limit for the first limit of regeneration power, which is illustrated in
After upper limit regeneration amount and the upper limit value of regeneration current (the regeneration current limit for the second limit of regeneration power) with which the identified degraded cell battery would not cause overvoltage in which the charge/regeneration inhibiting voltage is reached have been calculated, it is determined that the determination of the cell states has been completed, and the process proceeds from the first limit of regeneration power to the second limit of regeneration power. In
After the degraded cell battery 560 has been identified and the regeneration current limit for the second limit of regeneration power corresponding thereto has been calculated, the value of the regeneration current limit for the second limit of regeneration power is transmitted to the vehicle controller 600. Thus, the vehicle controller 600 acquires the upper limit value at which the electric power-train system 100 can perform the regeneration. Consequently, in the period of the second limit of regeneration power, distribution between the regeneration brake and the friction brake is determined so that regeneration control is performed at the regeneration current limit for the second limit of regeneration power or below and the second limit of regeneration power is performed according to the distribution.
In
In the period from the time t0 and the time t1 in which the first limit of regeneration power is performed, the regeneration control is performed at the regeneration current limit for the first limit of regeneration power or below, at which none of the cell batteries 560 constituting the battery system 500 would reach the charge inhibiting voltage. In the example illustrated in
Assuming that the regeneration current value for the period from the time t0 to the time t2 be Ib1, the voltage across terminals (Vb_ci) of the cell battery 560 that has been acquired during this period can be expressed by the following expression [1].
Vb
—
ci[k]=Eb
—
ci[k]+Rb
—
ci[k]×Ib1[k] [1]
where
Vb_ci[k]: voltage across terminals (closed circuit voltage (CCV) of an i-th cell battery at time k
Eb_ci[k]: open circuit voltage (OCV) of an i-th cell battery at the time k
Rb_ci[k]: internal resistance of an i-th cell battery at the time k
Ib1[k]: battery current at the time k
If the regeneration current between the period of the time t0 to the time t2 is constant, the voltage across terminals of the cell battery 560 becomes substantially constant, and the constant voltage is advantageous in detecting the voltage across terminals of the cell battery 560 at high accuracy. Specifically, even if detection values of the voltage of the cell battery 560 have been varied, the voltage across terminals can be detected at high accuracy by detecting and using an average value thereof.
Next, assuming that the regeneration current value for the period from the time t2 to the time t1 be Ib2, the voltage across terminals (Vb_ci) of the cell battery 560 that has been acquired during this period can be expressed by the following expression [2].
Vb
—
ci[j]=Eb
—
ci[j]+Rb
—
ci[j]×Ib2[j] [2]
where
Vb_ci[j]: voltage across terminals (closed circuit voltage (CCV) of an i-th cell battery at time j
Eb_ci[j]: open circuit voltage (OCV) of an i-th cell battery at the time j
Rb_ci[j]: internal resistance of an i-th cell battery at the time j
Ib1[j]: battery current at the time j
The period from the time t0 to the time t1 is a short period of time of several hundred msecs to 1 second, for example, and therefore it can be supposed that the state of charge (SOC), the temperature, the state of health (SOH), and the like are the same for the period from the time t0 to the time t2 and the period from the time t2 to the time t1. Accordingly, the relationship expressed by the following expressions [3] and [4] holds.
Eb
—
ci[k]=Eb
—
ci[j] [3]
Rb
—
ci[k]=Rb
—
ci[j] [4]
Therefore, the relationship expressed by the following expression [5] holds from the expressions [1] to [4].
Vb
—
ci[k]−Vb
—
ci[j]=Rb
—
ci×(Ib1[k]−Ib2[j]) [5]
where
Rb
—
ci=Rb
—
ci[k]=Rb
—
ci[j]
From the expression [5], the internal resistance (Rb_ci) and the open circuit voltage (OCV) (Eb_ci) of the cell batteries 560 are calculated by the following expressions [6] and [7].
Rb
—
ci=(Vb—ci[k]−Vb—ci[j])/(Ib1[k]−Ib2[j]) [6]
Eb
—
ci=Vb
—
ci[k]−(Vb—ci[k]−Vb—ci[j])/(Ib1[k]−Ib2[j])×Ib2 [7]
where
Eb
—
ci=Eb
—
ci[k]=Eb
—
ci[j]
As described above, by detecting and using the voltages across terminals and the battery current values of the cell batteries 560 at two different regeneration currents for the period from the time t0 to the time t2 and the period from the time t2 to the time t1, the internal resistance and the open circuit voltage (OCV) of the cell batteries 560 in the current states can be estimated at high accuracy.
Further, assuming that the regeneration inhibiting voltage be Vb_cmax, the upper limit value of regeneration current (Ibmax_i) at which the cell batteries 560 reach the regeneration inhibiting voltage can be calculated by the following expression.
From the expression [8], after calculating the respective upper limit values of regeneration current (Ibmax_i) of the cell batteries 560 constituting the battery system 500, a lowest upper limit value of regeneration current among the calculated values is set as the upper limit value of regeneration current for the battery system 500. The cell battery 560 that has become a constraint is identified as a worst cell battery.
By performing the above-described process, identification of the worst cell battery and the calculation for the upper limit value of regeneration current can be performed in the period of the first limit of regeneration power, and thereby an upper limit value of regeneration current for the period of the second limit of regeneration power at and after the time t1 can be set.
Similar to
As will be described below, Case 1 and Case 2 are different in a point that the degraded cell battery among the cell batteries 560 constituting the battery system 500 is different. Compared with Case 1, the voltages across terminals of the degraded cell battery during the period of the first limit of regeneration power is higher for Case 2.
Similar to
Similar to
Similar to
In
In
The voltage across terminals of the cell battery 560 is determined depending on the open circuit voltage (OCV) of the cell battery, the output current, and the voltage drop occurring in relation to the internal resistance of the cell battery. The two examples in
After the braking request has been transmitted at the time t0 and the first limit of regeneration power has been started, regeneration control is performed as illustrated in
As illustrated in
As described above with reference to
By applying the present invention as described above, the upper limit regeneration amount in the second limit of regeneration power is limited to a smaller value or the absolute value of the upper limit of regeneration current is limited to a smaller value as the voltages across terminals of the cell batteries 560 detected in the first limit of regeneration power become greater.
The determination about whether limit of regeneration power is necessary in (A) is a determination about whether the voltages across terminals of the cell batteries 560 would apparently not reach the regeneration inhibiting voltage due to the regeneration based on outline information. Accordingly, the total voltage, the temperature, the state of charge (SOC), and the state of health (SOH) of the entire battery system 500, for example, is information necessary for the process.
The determination as to whether cell state determination is necessary in the above item (B) is a determination performed, if any history of the second limit of regeneration power having been performed before or in a latest occasion, as to whether the second limit of regeneration power used therein is available for the current state of the battery system 500. Accordingly, information such as the total voltage, the temperature, the state of charge (SOC), the state of health (SOH), as well as estimation for internal resistance and time elapsed since the last second limit of regeneration power of the entire battery system 500, is information necessary for the process.
Further, the information to be read in S5-10 includes the information for determining the regeneration power limiting amount for the first limit of regeneration power mentioned in the above item (C). The information necessary for this process includes information such as the total voltage, the temperature, the state of charge (SOC), and the internal resistance of the entire battery system the battery system 500.
The temperature of the battery system 500 includes a temperature included in a battery temperature signal detected by various temperature sensors 540 installed in the battery system 500. The total state of charge (SOC) of the battery system 500 includes a signal of the state of charge (SOC) of the entire battery system calculated by the battery monitoring device 510, and the internal resistance of the entire battery system 500 includes an average value of the internal resistance of the entire battery system 500 calculated by the battery monitoring device 510, the total voltage of the entire battery system 500 includes the total voltage value of the entire battery system 500 detected by the battery monitoring device 510, and the state of health (SOH) of the battery system 500 includes the state of health (SOH) of the battery system 500 calculated by the battery monitoring device 510. These pieces of information indicate the states of the entire battery system 500, and in the next step, whether limit of regeneration power can be performed is determined by using these pieces of information.
1) The battery temperature is equal to or below a predetermined value. Specifically, “battery temperature<BAT_Temp_limit” (BAT_Temp_limit is a setting value).
2) The battery state of charge (SOC) is equal to or higher than a predetermined value. Specifically, “SOC>BAT_SCO_limit” (BAT_SCO_limit is a setting value).
3) The battery internal resistance is equal to or higher than a predetermined value. Specifically, the “battery internal resistance>BAT_R_limit” (BAT_R_limit is a setting value).
4) The battery total voltage is equal to or higher than a predetermined value. Specifically, the “battery total voltage>Vall_max” (Vall_max is a setting value).
5) The battery state of health (SOH) is equal to or higher than a predetermined value. Specifically, “SOH>BAT_SOH_Limit” (BAT_SOH_Limit is a setting value).
If any one of the five conditions described above holds, it is determined that limit of regeneration power is necessary, while none of them holds, it is determined that limit of regeneration power is not necessary.
1) By performing setting according to the battery temperature. For example, by using signals from the temperature sensor 540 installed to the battery system 500 as inputs, the regeneration current limiting values are stored in a table, and thereby the regeneration current limiting value is set according to the signals from the temperature sensors 540. In this case, the regeneration current limiting value is decreased as the temperature is lower, for example.
2) By performing the setting according to the battery SOC. For example, by using the states of charge (SOCs) of the battery system 500 as inputs, the regeneration current limiting values are stored in a table, and the regeneration current limiting value is set according to an average charged capacity. In this case, the regeneration current limiting value is decreased as the charged capacity is larger, for example.
3) By performing the setting according to the battery internal resistance. For example, by using the average internal resistance values of the cell batteries 560 constituting the battery system 500 as inputs, the regeneration current limiting values are stored in a table, and thereby the regeneration current limiting value is set according to the average internal resistance value. In this case, the regeneration current limiting value is decreased as the internal resistance value is larger, for example.
4) By setting a predetermined value. Specifically, a previously set fixed value is set as the regeneration current limiting value. In this case, a value smaller than that in the other methods is set as the regeneration current setting value.
After the regeneration current limiting value for the first limit of regeneration power has been set in S5-81, a regeneration control preprocess is performed in S5-82. In the regeneration control preprocess, the amount of regeneration requested from the vehicle controller 600 that is the higher-order control system or the brake controller 710 is received, and any one of the following processes is performed according to the received requested amount of regeneration.
1) If the received requested amount of regeneration is equal to or below the regeneration current limiting value used in performing the first limit of regeneration power, the process proceeds to a process in which the regeneration current limiting value or the regeneration power limiting amount for the first limit of regeneration power is transmitted to the vehicle controller 600 that is the higher-order control system or the brake controller 710 and the regeneration control is performed based on the received amount of regeneration.
2) If the received requested amount of regeneration is larger than the regeneration current limiting value used in the first limit of regeneration power, the process proceeds to a process in which the regeneration current limiting value or the regeneration power limiting amount for the first limit of regeneration power is transmitted to the vehicle controller 600 that is the higher-order control system or the brake controller 710 and the regeneration control is performed based on the regeneration current limiting value used in performing the first limit of regeneration power.
In addition, if it is determined in S5-80 that the process is not a first process of the first limit of regeneration power, the process proceeds to S5-82 because the regeneration power limiting amount has already been set, and the first limit of regeneration power is performed there as described above.
Next,
Compared with the example illustrated in
The battery system 500 includes a plurality of cell batteries 560, and the cell batteries 560 are managed not individually and are usually managed by handling a certain number of cell batteries 560 as one module. For example, four cell batteries 560 constitute one module 531, 532. In this case, for one module 531, 532, one cell monitoring device 521, 522 respectively monitors the four cell batteries 560 included in each module. For example, voltages across terminals of the four cell batteries 560 are detected by one cell monitoring device 521, 522. The cell monitoring device 521, 522 is connected to the battery monitoring device 510 via a communication system not illustrated in
The cell monitoring device 521, 522 is usually constituted by a plurality of cell monitoring devices that is connected with the battery monitoring device 510 by daisy chain connection, and results detected by the cell monitoring device 521 are transmitted to a subsequent cell monitoring device 522 and are then transmitted from the cell monitoring device 522 to a further subsequent cell monitoring device, for example. All the states of the cell batteries 560 detected by the cell monitoring devices are transmitted to the battery monitoring device 510 via the plurality of cell monitoring devices as described above. Accordingly, it takes time until all the states of all the cell batteries 560 are transmitted to the battery monitoring device 510. The method for transmitting the states of all the cell batteries 560 via the communication system described above is implemented by the first detection means 511 in the example illustrated in
Meanwhile, in a case where the state of the battery system 500 is detected while performing the first limit of regeneration power after the braking request to set the limit of regeneration power for the second limit of regeneration power, it is preferable to immediately detect the states of the cell batteries 560 constituting the battery system 500. If the detection is performed immediately, the period of the first limit of regeneration power can be shortened, and thus as the period becomes shorter, the regeneration can be performed more times. Accordingly, in the example illustrated in
To describe an example of the second detection means 512, differently from the example using the first detection means 511 in which the states of all the cell batteries 560 constituting the modules 531, 531 detected by the cell monitoring devices 521, 522 are transmitted, the second detection means 512 includes a method in which each of the cell monitoring devices 521, 522 transmits the state of a cell battery 560 with the highest voltage across terminals among the plurality of cell batteries 560 being monitored only. In other words, for each of the modules 531, 532, information about the cell battery 560 likely to reach the regeneration inhibiting voltage during the regeneration only is transmitted. Thus, the amount of data to be transmitted can be reduced, and information about a worst cell battery included in the modules can be transmitted to the battery monitoring device 510 in a period shorter than that for the first detection means 511. Accordingly, an effect can be achieved such that the process can proceed to the second limit of regeneration power at a timing earlier than the case in which the detection depends on the first detection means 511.
Another example of the second detection means 512 includes a method in which, for example, one cell monitoring device 521 transmits the state of a cell battery 560 with the highest voltage across terminals among the plurality of cell batteries included in the module 531 being monitored only to a subsequent cell monitoring device 522, and the cell monitoring device 522 compares, among the plurality of cell batteries included in the module 532 being monitored, the voltage across terminals of the cell battery 560 having the highest voltage across terminals with the highest voltage across terminals among those detected from the module 531 that have been transmitted from the cell monitoring device 521 and transmits the information about the cell battery with the higher voltage across terminals to a subsequent cell monitoring device. As described above, the cell monitoring devices serially transmits the information about the cell battery with the highest voltage across terminals only instead of transmitting all information, and thereby the amount of data to be transmitted can be reduced and the information about the worst cell battery of the modules can be transmitted to the battery monitoring device 510 in a period shorter than that for the first detection means 511.
Further, a different another example of the second detection means 512 includes a method in which, for example, the cell monitoring devices 521, 522 transmit the state of the cell battery 560 with the highest voltage across terminals only, among the plurality of cell batteries of the module 531 being monitored, directly to the battery monitoring device 510. The cell monitoring devices 521, 522 transmit minimum data only, such as a detection value of voltage of the cell battery 560 with the highest voltage across terminals among the modules, directly to the battery monitoring device 510, and thereby the amount of data to be transmitted can be reduced and the information about the worst cell battery of the modules can be transmitted in a period shorter than that for the first detection means 511.
The second detection means 512 is not limited to the above-described example, and any configuration or any method may be employed in which the battery monitoring device 510 is enabled to immediately collect information such as the voltage across terminals of the cell battery 560 with the highest voltage across terminals among the modules 531, 532.
As described above, in the example illustrated in
Specifically, in the example illustrated in
As described above, at least two different detection means (the first detection means 511, the second detection means 512) are provided, and thus if it is desired to detect the state of the battery system 500 in a short period such as the period of the first limit of regeneration power, the battery monitoring device 510 can transmit to the control area network specific information about the battery system 500 (e.g., information such as the voltage across terminals, state of charge, the current value of the cell battery 560 with the highest voltage across terminals among the cell batteries 560 constituting the battery system 500) only, by using the second detection means 512 that performs detection in a short period. Accordingly, because the worst cell battery 560 likely to reach the regeneration inhibiting voltage in the first limit of regeneration power can be immediately identified and thus the upper limit value of regeneration current or the upper limit regeneration amount for regeneration with which the worst cell battery 560 would not reach the charge inhibiting voltage can be immediately set, the period of the first limit of regeneration power can be shortened, and thereby a large amount of regeneration can be achieved.
In the example illustrated in
The cell monitoring device 521, 522 is usually constituted by a plurality of cell monitoring devices that is connected with the battery monitoring device 510 by daisy chain connection, and results detected by the cell monitoring device 521 are transmitted to a subsequent cell monitoring device 522 and are then transmitted from the cell monitoring device 522 to a further subsequent cell monitoring device, for example. All the states of the cell batteries 560 detected by the cell monitoring devices are transmitted to the battery monitoring device 510 via the plurality of cell monitoring devices as described above. Accordingly, it takes time until all the states of all the cell batteries 560 are transmitted to the battery monitoring device 510. In the example illustrated in
As described above, the state of the battery system 500 and the states of the cell batteries 560 constituting the battery system 500 are detected by the battery monitoring device 510 in a predetermined period. Accordingly, even before the first limit of regeneration power of the present invention is performed, the state of the battery system 500 and the states of the cell battery 560 at a timing earlier by predetermined length of time can be generally determined. Or rather, which cell battery of which module (531, 532, . . . ) has been the worst cell battery that would have reached the charge inhibiting voltage in the first limit of regeneration power and the second limit of regeneration power performed before can be recognized. In this example, candidates of the degraded cell battery that is likely to reach the regeneration inhibiting voltage or candidates of a module including the worst cell battery likely to reach the regeneration inhibiting voltage from among the cell batteries 560 constituting the battery system 500 can be extracted based on the states of the modules 531, 532 of the battery system 500 being continuously monitored by the first detection means 511 and the states of the cell batteries 560 constituting the same in the state in which the first limit of regeneration power is not currently performed.
Specifically, a method can be employed in which the voltages across terminals and the current values or the voltage between modules and the current of the cell batteries that are being continuously monitored for detection are acquired and cell batteries 560 or modules with a low voltage across terminals at the timing of driving are determined as candidates of the worst cell battery likely to reach the regeneration inhibiting voltage during regeneration or the module including the worst cell battery likely to reach the regeneration inhibiting voltage. In addition, another method can be employed in which a cell battery 560 or a module with the largest difference of voltages across terminals between the voltage across terminals at the time of driving and that at the time of the regeneration is determined as a candidate of the worst cell battery likely to reach the regeneration inhibiting voltage or the module including the worst cell battery likely to reach the regeneration inhibiting voltage.
In the example illustrated in
As described above, candidates of the cell batteries 560 or modules (531, 532, . . . ) likely to reach the regeneration inhibiting voltage among the cell batteries 560 or modules constituting the battery system 500 are identified according to previously acquired information and stored in the storage means 550, the second detection means 512 preferentially detects the states of the candidate cell batteries 560 and the candidate modules stored in the storage means 550 only, and thereby the worst cell battery likely to reach the regeneration inhibiting voltage can be immediately identified within short time and in a short period and the upper limit value of regeneration current or the upper limit regeneration amount for regeneration with which the worst cell battery would not reach the charge inhibiting voltage can be immediately set. Accordingly, the period of the first limit of regeneration power can be shortened and a large amount of regeneration can be achieved.
Number | Date | Country | Kind |
---|---|---|---|
2012-225575 | Oct 2012 | JP | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/JP2013/075787 | 9/25/2013 | WO | 00 |