The invention relates to a riser installation method wherein a riser is lowered from a first vessel, and is towed with its termination end by a tug over the sea bed to a termination point.
Such an installation method is known from WO 2004/035375 in the name of the applicant. This publication describes a Floating Production Unit (FPU) that is anchored to the seabed and that comprises one or more risers extending from the vessel to the seabed. The FPU comprises lifting means for assembling and lowering risers vertically towards the seabed. The lowered risers can be pulled out from the FPU by a tug boat towards a pre-drilled wellhead and be connected to it so that hydrocarbons can flow from the wellhead to the FPU were the hydrocarbons can be processed and/or stored temporarily.
Another installation method connects different segments of a pipeline on shore and tows the pipeline to the place where it is installed on the seabed. From Offshore Technology Conference OTC 11875, Houston, Tex., 1-4 May 2000 with the title “Hybrid Riser for Deepwater Offshore Africa”, a riser pipe for deep waters is described comprising a steel outer casing with a number of production risers, gas and water injection lines. The riser pipe is assembled on shore and towed to location where it is up righted and connected to the foundation on the seabed. The upper part of the riser is connected to a submerged buoy. After installation of the hybrid riser pipe, the submerged buoy is connected via flexible jumpers to the surface facility such as an FPSO, which may be located at a distance between 70 m-200 m from the submerged buoy. The known method has the disadvantage that during installation of the risers all at once, no hydrocarbon production and/or processing can take place. Furthermore, installation requires special and dedicated installation equipment. Specialised installation vessels are designed to work in as large as possible sea states and are hence, sizeable and costly equipment.
From U.S. Pat. No. 4,182,584 it is known to attach a freestanding marine production riser for use in deepwater between a base portion and a submerged buoy. With a derrick-equipped vessel, such as a semi-sub, the riser casing is lowered through the central part of the buoy and coupled to the bottom until the rigid riser part is completed. Next, a flexible hose is attached to a surface facility for hydrocarbon production and processing. Again, the use of separate, purpose build vessels for riser installation and for hydrocarbon production/processing requires scheduling and mobilising the installation vessel to site at large day rates and the demobilisation of the installation vessel after installation of the riser.
A deepwater field development may consist of several sub sea wells separated by long distances from a centralized FPU. These wells are tied back to the FPU via steel pipelines, and the risers may terminate on the production unit as SCRs. A large field scenario may take years to fully develop. Depending on drilling and completion schedules, construction vessels may be mobilized multiple times in order to connect the wells to the FPU. These vessels can cost millions of dollars to mobilize, and their working rates may exceed one or two hundred thousand dollars per day. It is therefore advantageous to minimize or eliminate the need for these vessels by self-installing the pipelines and risers from the drilling rig vessel.
The method of WO 2004/035375 describes a pipeline installation method without the use of a special pipe lay vessel, the termination part of the pipeline being installed on the sea bed or on a submerged buoy. When attaching the pipeline to a surface vessel, such as a FSU, the departure angle relative to the vertical should be accurately determined to prevent fatigue weakening during use, and should be for instance between 10° and 20°.
It is an object of the present invention to provide an installation method, which avoids the use of dedicated pipe-lay vessels and with which the departure angle of the risers attached to a surface vessel or to a submerged buoy can be accurately controlled.
Hereto the installation method according to the present invention comprises by the steps of:
By pulling the pipe-string, which may be a Steel Catenary Riser (SCRI) via the second vessel, such as a tug boat, across the sea bed to the third vessel (FSU), a simple installation method is achieved without the use of an expensive pipe lay vessel. The method provides increased flexibility in riser installation and hydrocarbon production and/or processing avoiding complex scheduling of the installation vessel and allowing riser installation at any suitable moment.
When pulling the pipe-string across the sea bed, the pulling angle relative to the vertical will be larger, in order to properly transmit the horizontal pulling force, than the required departure angle of the pipe-string form the third vessel or mooring buoy to which it is attached during use. By pulling the pipe-string further than the mooring point of the surface vessel or (submerged) buoy to which the termination end of the pipe-string is attached, the contact position of the pipe string with the sea bed is shifted towards the mooring position and the departure angle of the pipe-string is increased to the optimal value. As the pipe is not inspectable in this area the rules require the fatigue calculations to show a life of 10× the expected life of the pipe; i.e. for a 25 year field life the analysis must show a 250-year life. The designer will therefore take into account the vessel motions for 25 years and different angles of the pipe with soil parameters in the touchdown zone to determine what an acceptable angle is for the expected pipe motion. Generally a less vertical angle was found to increase the fatigue life. As less vertical angles result in larger loads on the vessel it is preferred to keep the angle as vertical as possible. 15 to 20 degrees from vertical are preferred angles, however in deeper water the angles may be smaller.
The pipe string can be handed over from the second vessel to the FSU, at the side nearest the first vessel, so that the vessel can sail around the FUSU to pick up the pipe string at the side away from the first vessel. In that position the pipe-string can be pulled underneath the FSU past its mooring point, so that the pipe departure point from the sea bed is shifted sufficiently close to the FSU in order to obtain the desired departure angle. Next, the second vessel can return to the FSU to connect the termination end of the pipe-string. In this step the second vessel does not exert a very large pulling force, and can hence approach the FSU at a relatively close distance without the risk of collision in view of varying soil resistance as occurs during pulling of the pipe-string across the sea bed.
In an alternative method, the pipe-string is pulled past its mooring position by temporarily changing the mooring position of the third vessel. A first set of anchor lines facing the first vessel is slackened while a second set of anchor lines situated at a side facing away from the first vessel is tensioned, whereafter the firs set is tensioned and the second set is slackened.
In one embodiment, the first vessel comprises a drilling and/or work over vessel that is situated over an offshore hydrocarbon well. After or during drilling or work over activities on a hydrocarbon well, the pipe string can be towed to the third vessel and be connected at its termination end, whereafter its initiation end can be connected to the newly drilled well. In this manner multiple pipe strings or risers can be connected during the drilling of several wells, wherein the pipe-string installation process can occur simultaneously with the drilling operations.
In an embodiment of a riser installation method, according to the present invention, the pulling force exerted by the second vessel is intermittently increased and lowered to tow the transfer duct across the sea bed by a predetermined distance, followed by resting the transfer duct in a stationary state by repeating steps d and e. In case the pipe-string is made up of segments, which may be welded together or connected by threaded connectors, the intermittent pulling force can be synchronised with the pipe-assembly rate of the segments, and with the lowering cycle of the pipe-string. The distance by which the pipe-string is pulled in each cycle can correspond to the length of one or more segments, a segment having a length of for instance between 10 and 50 m. As the pipe length resting on the sea bed increases, the required pulling force will increase, which can be more effectively transferred in short spans of high power than as a continuous force.
In case of supplying the pipe-string from a spool or in case of using a dual drilling vessel which can lower two drill strings at one time and on which a continuous assemblage of pipe-segments can take place, a slow and continuous pulling force may be utilised to tow out the pipeline. A “dual drilling” vessel can perform drilling and separately a work-over activity at two wells at the same time or have two drill strings with different diameters for efficient drilling of one well. Such drilling vessels can have two drilling towers or a simple drilling tower were at the same time two drill strings can be assembled for efficiency purposes and to reduce the offshore drilling time (single or double derrick MODU). These dual drilling vessels are well known and used in the industry and for example described in patents U.S. Pat. No. 6,047,781 and U.S. Pat. No. 6,068,069, with title “Multi-activity offshore exploration and/or development drilling method and apparatus”, which are both in the name of Transocean.
In order to accommodate for the bending of the transfer duct during installation, which assumes a catenary configuration, a guide member may be provided on the first vessel via which the transfer duct is guided along a curved path at an angle to the vertical from the first vessel in the direction of the sea bed. The guide member may for instance comprise a “stinger” that is placed near or below keel level of the first vessel, and comprising a number of bumpers of increasing diameter with distance below the rig. The series of bumpers forms a trumpet-like surface that has a radius (in the vertical plane) which limits the bend radius of the pipe-string and that keeps it from yielding when being pulled sideways to the angle required to deploy the pipe-string.
Adjustment of the take-off angle of the pipe-string or riser from the first vessel can also be effected by ballasting the first vessel to that its vertical centre line is tilted in the direction of the pipe-string. In this manner, no special provisions need to be taken for guiding the pipe string along a curved trajectory at the take-off point from the first vessel.
Some embodiments of a method according to the present invention will be explained in detail with reference to the accompanying drawings. In the drawings:
Installation of the pipe line 5 involves pulling the termination end 11 from the rig to the FPU 8 by way of a sub sea Pipe Line End Termination (PLET) or a Steel Catenary Riser (SCR) configuration near or directly to a Floating Production Unit (FPU) 8 which can be a FPSO, a Spar, a Semi-sub, a TLP, etc. The pipe line 5 is pulled across the sea bed 3 until the point of departure 10 is in the right position in order to obtain the desired angle of departure a. After installation, the initiation end 6 of the pipe line 5 may remain attached to the rig 1, or may be lowered, under ROV control, to be connected to hydrocarbon well 2. Once the pipe 5 is laid, the rig 1 can have the initiation end 6 of the pipeline 5 either attached to it or to the sub sea location 2.
During drilling or work over activities, the pipe line 5 or SCR can be assembled simultaneously at the drilling vessel 1 and be pulled out from the drilling vessel towards the FPU 8 with the help of a tugboat during stable weather conditions.
Drilling rig vessels 1 are normally used to drill or work-over wells 2. After the well 2 is drilled or as explained above even during the drilling of the new well, the assembling of a new SCR or pipe line 5 can start and the tugboat can drag the pipe line into the right position. This procedure can be repeated while one pipeline is already installed and there is a hydrocarbon flow from one wellhead to the FPU. When a pipeline or SCR is disconnected from the drilling rig 1 and connected to the wellhead 2, hydrocarbon production and processing can start at the FPU 8. Additional pipelines can be installed from new wellheads drilled at the same place or the drilling rig vessel 1 can be moved to a different place and start drilling a new well.
In the embodiment of
In
As can be seen from
A difficulty in the pipe pullout procedure when the pipeline 5 is dragged over the seabed 3 is the unknown of soil friction on the pipe 5. As the pipe is sometimes stopped or sliding this pullout is uncertain as there is a static and dynamic soil friction. The static soil friction being larger than the dynamic friction means once the pipe slides the amount of sliding is dependent on the ratio of static to dynamic friction and the catenary configuration of the pipe and cable being used by the pulling tug. It is necessary to keep a safe distance when the tugboat 20 pulls towards the FPU 8 to account for the vessel motion toward the FPU when the pipe slides and also in the event the pulling cable should break. In case sliding of the pipe occurs, the vessel will move forward as the tension in the pulling cable drops.
As can be seen in
The installation line 27 is then transferred back to the FPU 8 and taken up on a winch 30, which then pulls the pipe 5 into its final configuration in which it is connected to the FPU, as shown in
In the embodiment of
In the embodiment shown in
In
In the embodiment of
Number | Date | Country | Kind |
---|---|---|---|
05105983.0 | Jun 2005 | EP | regional |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/NL2006/050154 | 6/29/2006 | WO | 00 | 11/20/2009 |