Claims
- 1. A method of forming a roof structure in an opening between side walls of a chamber comprising the steps of:
- installing at least one layer of bricks in said opening directly above said chamber;
- applying at least one layer of a first concrete in an unshaped form in said opening over said at least one layer of said bricks;
- tamping said at least one layer of said first concrete at at least a first predetermined temperature; and
- allowing said at least one layer of said first concrete to harden.
- 2. The method according to claim 1, further including the step of keeping said at least one layer of said first concrete moist for at least 30 hours after said applying.
- 3. The method according to claim 2, further including the steps of applying a layer of a second concrete in an unshaped form in said opening over said at least one layer of said first concrete, tamping said layer of said second concrete at a second predetermined temperature and allowing said layer of said second concrete to harden.
- 4. The method according to claim 3, further including the steps of applying another layer of said first concrete in an unshaped form in said opening over said layer of said second concrete, tamping said another layer of said first concrete at said second predetermined temperature and allowing said another layer of said first concrete to harden.
- 5. The method according to claim 4, wherein said chamber is a coke oven chamber, said first bricks are refractory bricks, said first concrete is a light refractory concrete, and said second concrete is an insulating concrete.
- 6. The method according to claim 4, wherein said tamping of said at least one layer of said first concrete is at said first predetermined temperature of about 50.degree. C. to about 60.degree. C. and said tamping of said layer of said second concrete and said tamping of said another layer of said first concrete are at said second temperature of about 850.degree. C. to about 950.degree. C.
- 7. The method according to claim 4, further including the step of laying a layer of common red brick over said another layer of said first concrete.
Priority Claims (1)
Number |
Date |
Country |
Kind |
3717015 |
May 1987 |
DEX |
|
CROSS REFERENCE RELATED APPLICATIONS
This application is a divisional application of U.S. patent application Ser. No. 07/258,549 filed on Oct. 17, 1988, now U.S. Pat. No. 4,929,179, which was a continuation-in-part application of International Application No. PCT/EP88/00461 filed on May 24, 1988, in which the U.S. was a designated state, which claims priority from Federal Republic of Germany Patent Application No. P 37 17 015.5 filed on May 21, 1987.
US Referenced Citations (10)
Divisions (1)
|
Number |
Date |
Country |
Parent |
258549 |
Oct 1988 |
|
Continuation in Parts (1)
|
Number |
Date |
Country |
Parent |
461 |
May 1988 |
|