1. Field of the Invention
The present invention relates generally to a rough-in box for creating penetrations in poured concrete flooring during the construction of high-rise buildings, and a method of using the device.
2. Background
Currently there are a number of solutions for creating penetrations in concrete slab flooring during the construction of high-rise buildings. The penetrations may then be utilized for the installation of plumbing, ducts or other mechanical systems between floors. It has been known to install plumbing or mechanical systems through concrete floors by knocking out holes in the floor or boring such holes after the floor has been formed, and then extending pipes or other conduits through the floors. After the conduits have been inserted into the holes, workers have to pour additional material such as more concrete or caulking material to seal up the spaces between the voids and the conduits extending through the penetrations. However, such attempts to use concrete or caulk to seal up the spaces has not been effective at preventing future problems such as water leaks that travel through any void spaces between the floors. These solutions fail to meet the needs of the industry because they are also time-consuming, labor intensive and wasteful of construction material.
Other solutions include the on-site fabrication of plywood boxes. The boxes are constructed so as to be placed over a roughed-in floor drain area or other location where a floor penetration is desired. The rough-in plywood construction is normally used in order to isolate and protect the rough-in drain at the time of the pouring of a concrete (or cement) floor. But these solutions are similarly unable to meet the needs of the industry because once the flooring is poured the framed openings must be covered with plywood to allow continued construction activity. The plywood creates an uneven floor surface which is a tripping hazard for construction workers and hinders the movement of pallet jacks and other wheeled devices used to deliver construction materials to the needed locations at the site. Furthermore, the wooden frames must be forcibly removed after the concrete is poured, a process which is time consuming and labor intensive.
Other solutions involve the use of metal boxes which are secured to the deck of the floor prior to pouring. This solution has many of the same problems as the use of wooden frames. For example; the metal boxes must be forcibly removed by workers before the concrete is completely cured, creating the need to repair damage to the floor caused by the removal process and the footprints of the workers. When the boxes are removed, the impression hole that is left also needs to be covered to prevent injuries incurred by falling in the hole.
Still other solutions seek to use cylindrical forms or tub-shaped, open-top boxes but these solutions also fail to meet industry needs because they do not provide a flush surface with the flooring. The tubs must be covered with plywood or filled with a foam insert to allow continued construction activity. The cylindrical forms typically protrude above the floor surface creating obstacles. If flush with the floor they must be covered with plywood which creates the problems discussed above.
However, none of the forms described above are suitable for bearing the weight of workers and construction vehicles/equipment/materials while at the same time not creating an uneven floor surface which could be a tripping hazard for construction workers and which could hinder the movement of wheeled devices. Moreover, none of the forms allow construction to continue without the need to remove or trim the forms or covers, such as plywood covers, placed over the forms during the pouring of concrete. There has been no suggestion that the cover to the form should be of a strength that can provide support for both workers and vehicles/equipment/materials that are moving and working on the floor.
With respect to the method of creating penetrations in poured concrete flooring during the construction of high-rise buildings, a typical current construction method using removable metal boxes generally includes the following steps:
(10) The cleaning debris is collected and removed from the floor for disposal.
(11) The cleaned boxes are then stacked, ready to be moved to the next floor.
(12) Before the supports and framing for the next floor can be erected, the open holes have to be covered to prevent injuries. Sheets of plywood are placed over the hole and nailed to the concrete to act as a cover.
This method does not meet the needs of the industry because it has many inherent problems and inefficiencies, some of which are now discussed.
Once the plumbing or mechanical penetrations in one floor are covered, the erection process for the next floor can begin. The support legs for the next floor are put in place and the wooden deck is installed. Due to the presence of the penetrations and wooden covers, the legs sometimes must be placed in different orientations to avoid having the legs being placed on a penetration cover which the leg could potentially puncture. During the erection and pouring process, the wooden penetration covers become dislodged by workers accidentally kicking or knocking the covers loose during the course of working on the erecting floor. Thus, the covers have to be refastened to the floor to prevent workers being injured by stepping into holes.
When a floor is set and ready to be worked on, the stripping and moving of materials and forms can begin on the floor below. This process involves heavy traffic on the floor with the covers in place, and often the covers are dislodged again and must be refastened.
Generally, while the covers are in place, the concrete contractor must maintain the covers for six floors until the general contractor assumes control of the floor to allow the other tradesmen to conduct their work. This maintenance typically consists of daily inspections of the penetration covers on each floor to ensure they are still correctly positioned and fastened to the floor, and refastening loose covers. Once the general contractor takes control of the floor they remove the wooden covers that were covering the penetrations and replace them with a thicker cover that has mitered edges. The old covers then need to be removed from the floor to prevent tripping hazards.
When the plumber or mechanical contractor is ready to begin installing pipes or other conduits in the penetration, it could be almost one month since the slab was poured. Since the holes become roughened from the prying process during removal of the boxes, the holes may need to be adjusted to fit the needs of the particular installation. Once the piping has been completed, the holes need to be filled with concrete to maintain the fire stopping ability of the concrete slab. Due to the fact that this is done at the stage when the units are having the finishing touches applied, it can lead to the some items being scuffed or damaged.
When the mechanical services are ready to run shafts and ducts, they must physically strip the wooden boxes from the cured concrete which is time consuming and also can roughen the sides of the penetration. The penetrations must also he filled with a material to maintain the fire stopping ability.
Suggestions have also been made to provide such cylindrical form or tube with lids to prevent concrete from being poured into the forms. Such forms are described, for example, in U.S. Patent Publication 2005/0055916 describing a plasticized form which is used to surround plumbing fixtures while concrete is being poured and has a lid secured to the form that provides an intermediate covering to the form assembly and until such time as the plumber completes the connection, U.S. Pat. No. 7,080,486 describes including intumescent material in a leave in place form which may be provided with a cap, the form being provided with frangible bands to allow adjustment of the form to the thickness of the floor. The cap is stated to be used to prevent concrete from being poured into the form. U.S. Pat. No. 4,823,527 describes a hollow form having a cover that can be coplanar with the top surface of a concrete floor and means for adjusting the height at which this form is located above the floor support. U.S. Pat. No. 4,077,599 describes an aperture-forming device for making openings, for example tubular openings in concrete. U.S. Pat. No. 7,073,766 describes a form work having a moveable outer frame linked to an inner rigid frame thereby permitting adjustment of its size. U.S. Pat. No. 4,666,388 describes a form for forming an opening such as a window or door which is adapted to collapse inwardly after use.
It would be desirable to have a device and method of using the device that can be used to retain an opening in concrete slab flooring during the pouring of the concrete which is capable of providing an upper surface flush with the concrete floor, has the structural strength to support the weight of workers and construction supplies, can remain in in place after construction and has waterproofing and fireproofing capabilities. This would eliminate the need to cover openings with plywood, which creates a tripping hazard for construction workers and impedes the movement of wheeled carts and trucks which are used to move materials around the construction site. Still further, it would be desirable to have a device that provides a waterproof and fireproof barrier. Still further, it would be desirable to have a device and method that provides for improved efficiency, increased safety, and reduced labor costs. Therefore, there currently exists a need in the industry for a device and associated method that provides for an opening in poured concrete flooring, with an upper surface which is flush with the surrounding floor, strong enough to support the weight of construction materials and workers, waterproof, fireproof, and cost effective. Therefore, there currently exists a need in the industry for a device and method of use that solves all the problems addressed above.
Specifically there is a need for a form that can be used to enable penetrations to be left in a concrete floor while concrete for the floor is being poured, that can permit work on the floor to continue without the need for removal of materials, that provides a. fireproof and waterproof barrier and desirably can easily accommodate different sized penetrations.
The present invention advantageously fills the aforementioned deficiencies by providing a rough-in box for creating penetrations in concrete flooring and a method of use which creates a penetration in the flooring while providing a flush surface with the floor which can support the weight of workers and equipment, can remain in place post-construction and provides waterproofing and fire proofing capabilities. The present invention further provides a method using such boxes.
The present invention provides a structure for forming openings in poured concrete slab flooring, which is made up of the following components: one or more boxes, for example two boxes, forming an opening of a desired shape. Rectangular side walls can be used for forming a box having the shape of a rectangular prism, and curved side walls can be used for forming a circular or elliptical box.
In a particularly useful embodiment, each box has a pair of short and long sides, a bottom side and top side. The top side is strong enough to permit workmen and their equipment to move over it without risk. The strength required of the top depends on the particular situation in which the box is being used. Conveniently, the box is formed on site from pre formed side pieces. It is usually desirable that the top piece is customized for a particular site. To facilitate on-site assembly of a box, the edges of each of the side pieces are designed to permit quick interlocking between them to form the four sides of the box and are preferably formed with a flange that once the sides have been assembled will be at the top of the assembly to provide support for the top.
In one embodiment, the boxes have four sides of equal height and a top side. If the penetration desired is for mechanical systems, a square box may be used, and if the penetration requires two boxes, then the boxes can be connected as follows: the boxes are connected with the short side of the first box attaching to the long side of the second box to form the shape of the letter T or letter L, or a linear shape. Where the sides of the boxes abut, there will be an opening in the wall of each box to allow access between the two boxes for subsequent plumbing installation. The top side of each box will be removable. One of the boxes may have a circular opening in the bottom side, through which a cylindrical frame may be extended downwards to provide a full penetration through the resulting slab floor. One box may have a height less than the thickness of the floor and be supported by legs of sufficient height to make the top surface flush with the floor surface. When the desired configuration has been created, the device is placed in the required position on the deck of the floor. Concrete is poured onto the deck and cured. The top sides of the boxes will sit flush with the floor surface to allow for pallet jacks and other wheeled carts to be moved over the covered openings without hindrance and without the need for plywood coverings which create tripping hazards.
The present invention may also have one or more of the following: The boxes may be constructed to he water tight to prevent water traveling through the floor penetration. The boxes may be constructed entirely or partially of a fireproof material. The boxes may also incorporate intumescent material as a means of fireproofing the penetration. Similarly, the method associated with the present invention may also include one or more of the following steps: installing waterproofing devices, installing fireproofing devices.
The present invention is unique when compared with other known devices and solutions because the invention provides: (1) a structure which creates a slab pass-through and a void space for plumbing, mechanical, or other access (2) which also has a closed top that is flush with the slab floor and can support the weight of construction workers and material; (3) provides waterproofing and fireproofing protection and (4) can remain in place after the concrete cures. Similarly, the associated method is unique in that it: (1) eliminates the time and labor of constructing and installing wooden covers on-site, (2) eliminates the time and labor removing frames from cured concrete, and (3) eliminates obstructions and tripping hazards at the construction site.
The present invention is unique in that it is structurally different from other known devices or solutions. More specifically, the present invention is unique due to the presence of (1) A solid top lid; (2) rectangular or square shaped structures for both the pass through section and plumbing connector as well as full penetration sections for shafts or mechanical systems; and (3) rigid construction which can support the weight of workers and material. Furthermore, the process associated with the aforementioned invention is likewise unique and different from known processes and solutions. More specifically, the present invention process owes its uniqueness to the fact that it: (1) achieves as good or better results than conventional methods in fewer steps, less time, less labor, less cost, and has safety advantages.
Among other things, it is an object of the present invention to provide plumbing boxes and mechanical boxes for creating penetrations in concrete flooring and method of use that does not suffer from any of the problems or deficiencies associated with prior solutions.
It is still further an objective of the present invention to create a device that is more economical to produce, easier to manufacture, easier to ship to the work site, easier to install and of sufficient durability to remain in place after construction is complete.
Further still, it is an objective of the present invention to create a device that is amenable to mass production in a variety of standard dimensions frequently encountered in the industry, thereby enabling the device to be more easily commercialized.
In a preferred aspect of the present invention, the boxes are of modular construction in which pre-formed components may be assembled on site to form boxes of the appropriate size for the desired penetration. Typically, the components form the side walls of the box and are fitted together by a specific interlocking mechanism as described below. The tops of these wall members provide a flange on which the cover may be placed.
The side walls may be formed of any strong, tough material which may vary in accordance with the particular application or circumstances under which the rough-in box is to be used. For example, the side walls may be made from metal alloys, fiberglass, and heavy duty plastics, or any combination thereof. Examples of heavy duty plastics include polyethylene, polyvinyl, and polypropylene. In one particular embodiment, the side walls are made from a magnesium aluminum alloy, such as the aluminum 5000 series, and may have a thickness in the range of 0.03 to 0.1, for example, 0.050 inches. Other properties such as weight can be relevant to the choice of material for the side walls of the rough-in box.
The top lid on the other hand needs to be strong enough to provide a working surface on the floor while construction is being carried out. As such, the top lid must be capable of supporting a weight of at least 2,000 pounds and in some applications of supporting weights of up to 20,000 pounds. The lid can be made from a broad range of fiberglass, and can also be made from heavy duty plastics such as polyethylene, polyvinyl, and polypropylene. Additionally, in some embodiments, the lid can be made from engineered wood. It is also possible that the lid is made from a combination of fiberglass, heavy duty plastics, and/or engineered wood.
In one embodiment, the top lid can be made of resin impregnated fiberglass with the density of fibers being determined by the weight that the closure has to bear. Generally, the number of piles or layers of fibers will affect the flexural strength of the lid as will be further discussed below. The resins used to impregnate the fiberglass may include epoxy resins as well as other types of thermosetting plastics such as polyester or vinylester resins and thermoplastics.
The lids may be custom made to have a fixed size for particular sized penetrations or can have an adjustable size as described below. Lids of adjustable size may be used, for example, by providing corrugations in defaces of different parts of the lid so that they can inter-lock with each other while maintaining a strong support. If desired, the lid can be supported by strut stretching across the box from an opening or vertical slot in one wall to an opening or vertical slot in the opposite wall.
In another aspect, the present invention provides a method for constructing a floor containing penetrations which comprises: assembling the walls of a box as described above, locating such boxes on a floor deck, placing a top being made of a material stronger than that of the sidewalk and being capable of supporting a weight of 2,000 pounds on to the top of said box, pouring concrete to form a floor around said boxes, performing work on said floor after pouring the concrete and subsequently removing said top, leaving the remaining parts of the box in situ in the concrete, and installing plumbing or electrical fittings within said box.
In a further embodiment, the walls of the box, irrespective of whether the walls are a fixed size or the wall lengths are adjustable, is provided with a groove into which fire proofing or fire retardant is injected or inserted.
In a yet further embodiment of the invention, the box components or the lid are provided with elements from which a guard rail may be provided to surround the perimeter of the penetration.
To comply with safety regulations, the upper surface of the lid will be a bright color (yellow and orange being typical) and will be provided with a non-slip upper surface.
In a preferred embodiment, the size of the box is adjusted to a predetermined size prior to being located on the floor deck. One way to accomplish this is by using sidewalk of adjustable length as described below.
The present invention will now be described more fully hereinafter with reference to the accompanying drawings, which are intended to be read in conjunction with both this summary, the detailed description, and any preferred and/or particular embodiments specifically discussed or otherwise disclosed. This invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided by way of illustration only so that this disclosure will be thorough, complete, and will fully convey the full scope of the invention to those skilled in the art.
The present invention is directed to a plumbing and mechanical rough-in box for creating penetrations in concrete flooring and a method of use.
In a first embodiment of the present invention, two boxes in the shape of rectangular prisms are constructed. The side walls of the boxes may be formed of any strong, tough material such as, for example, metal alloys, fiberglass, and heavy duty plastics such as polyethylene, polyvinyl, and polypropylene. In one embodiment, for example, the side walls can be made from an aluminum 5000 series alloy having a thickness of 0.050 inches. In another embodiment, the side walls can be made from high strength/low ductility plastic.
A first box is assembled from a panel consisting of the bottom (2) and long sides (1, 3) of the box shown in
A second box, is assembled in the same fashion as the first box with a bottom (7), long sides (6, 8), and a short side (9) except the bottom (7) and side panel (8) of the second box will have a circular opening in the bottom side (7) and rectangular opening on one of the long sides (8) as shown in
The boxes are connected by first having the metal feet (11) attached to the outer surface of the bottom of the first box, close to the closed end of the box. The open end of the first box is then aligned with the rectangular opening in the long side of the second box as shown in
This first embodiment of the present invention solves many of the labor inefficiencies and costs incurred when creating penetrations for plumbing boxes in concrete slabs. When the new boxes arrive on site they are assembled prior to installation in the slab. They are delivered to the floor to be poured, and from there they are installed in a prearranged spot on the deck. To fasten the boxes in place, they are simply nailed to the wooden deck and are then ready for the pouring process. No greasing is needed as they are a permanent fixture in the floor. When the pouring is taking place the workers can work faster because they do not have to worry about accidentally filling the boxes, and the smoothing tools can run over the lid of the box without concern of damaging the box or the hole. Also, the additional damage caused from workers walking on the concrete to pry out the boxes is avoided, thereby eliminating the need to perform additional surface finishing work. As the boxes are permanent fixtures, there is no additional time wasted in cleaning the boxes of excess concrete that may have overflowed into the box during the pouring of the concrete.
When the floor has hardened, the erecting process can begin. Like in conventional processes, when the legs are being erected to support the next floor they have to be placed so as to avoid the boxes, but the workers can easily identify the edges of the box and be assured that the leg is placed securely on concrete in a position that is as close as possible to the ideal placement orientation. During this stage, avoiding the use of plywood hole covers becomes a great benefit. Their absence from the floor (enabled by the structural lid component of the box) means that tripping hazards are eliminated, thereby eliminating job stoppages due to health and safety requirements. Their omission also increases the speed at which workers can operate as they can move carts and dollies freely about the floor to move materials without having to navigate around the hole covers sitting above the level of the concrete surface. When the floor is stripped (legs and deck removed), workers can perform tasks much more quickly and efficiently because they can use carts and dollies to move materials and forms, as opposed to moving everything by hand, as is often done in conventional processes. After the floor is stripped, tradesmen can begin working on the floor immediately because the holes will not need to be re-covered.
According to in conventional processes, the covers must be inspected once per day for each floor. The present invention would drastically reduce this requirement, if not eliminate it completely, as the structural capabilities of the lid would mean that the boxes would be able to withstand the loads and forces present on the site without failure. The reduction in inspection frequency would save on labor costs for the duration of the construction phase.
When the general contractor takes control of the floor, they do not need to add the additional covers for the holes. The plumber and mechanical services can immediately take responsibility for the boxes and run the pipework or shafts needed. Once complete, the plumber or other tradesman can lock the lid in place sealing the pipework or other components in position. Due to the stopping ability of the box, derived from its construction material, plugs and seals, the slab maintains its stopping ability. Therefore the holes do not need to be filled with concrete. This avoids any potential damage to the nearly finished unit caused by workers filling the hole with concrete and also reduces labor costs significantly.
The proposed method greatly improves existing methods by the fact that it increases productivity and reduces labor costs, while also reducing the potential trip or fall hazards present with existing methods, which in turn reduces job stoppages from falls and injuries.
In one embodiment, the walls are made of an aluminum 5000 series alloy having a thickness of 0.050 inches to keep the box as light as possible. The lid is from 18 to 40 fiber glass layer strands of fiber depending on the engineering requirements for the maximum weight required on said floor. This will insure 100% storage on the floor slab while being strong enough to hold any required weight for full axes to the complete floor.
In one embodiment of the invention, an attachment with concentric rings may be attached to the bottom of one of the box sections to provide full penetration of the slab. The rings may be internally and externally threaded to allow the rings to be threaded into each other to create variable height dimensions. Depending on the height of penetration needed the rings can be threaded into each other to correspond to the required dimension. The threaded design also gives the box vertical support in that the weight of the box could be supported without the need of additional bracing/legs.
In another embodiment, plugs or seals are incorporated into the two plates of the component that would fit tightly to the pipe to increase the water resisting abilities of the box. An intumescent based seal or plug can further increase the water resistance of the box.
As the penetrative height may be made adjustable via the concentric ring structure, so too may the leg supports that are supporting the box. Another embodiment of the invention incorporates adjustable legs as can be seen in
In another embodiment of the present invention, the components depicted in
In this second embodiment of the present invention, the components will be supplied with a male component (25) pre-positioned within a female component (22) for forming each side wall of the rough-in box (28). The male members (25) may be fully within the perimeter of the female members (22), and then the lengths of the side walls can be adjusted to the appropriate length by withdrawing the male member (25) from the female member (22). Once the appropriate side wall length is obtained, the male and female members (22, 25) are secured to each other to form one side wall of the rough-in box (28).
Both the female and male members (22, 25) are provided with a flange at the top (38, 39), and each flange (38, 39) is respectively provided with an outer rim (40, 41). The flange (38) on the female member (22) may be provided with a series of apertures (42) which may facilitate the adjustment of the length of the combination of female and male members (22, 25) by sliding the male member (25) into a desired position relative to the female member (22) so as to provide a side wall of an appropriate length. In this manner, each assembly of the female and male members (22, 25) forms a side wall of the rough-in box (28).
The rough-in box (28) is formed by joining four side walls together. The female member (22) and the male member (25) have corresponding mating faces that interlock when pushed together. Each male member (25) has an extending ridge (29) and a flange (30) on the right side of the internal side (26) as shown in
Each female member (22) has a slot (31) on the top left corner of the external side (23) as shown in
When two side walls of assembled female and male members (22, 25) are joined together, the extending ridge (29) of the male member (25) is fitted into the slot (31) of the female member (22) and the teeth (33) of the flange (30) engage the groves (32) running down the right side of the internal edge (24) of the female member (22). The joint interaction between the male member (25) and the female member (22) is shown in
As indicated above, before joining two side walls together, the length of each side wall can be adjusted by withdrawing the male member from within the female as shown in
Once the lengths of the sides have been appropriately adjusted, additional side walls are joined together in a similar fashion—i.e., the extending ridge (29) of each male member (25) is fitted into the slot (31) of each female member (22) and the teeth (33) of the flange (30) of each male member (25) engage the groves (32) running down the internal edge (24) of each female member (22).
In an embodiment different from the one described above, an alternative configuration may be used for adjusting the length and width of the rough-in box (28). This alternative configuration is shown in
The female members (22) and the male members (25) that form each side wall of the rough-in box (28) should be made from a strong, durable material for use in a construction site. Other properties such as the weight of the box can also be relevant to the choice of material for the female and male members (22, 25). For example, these components can be made from aluminum or an aluminum alloy such as, for example, an aluminum 5000 series alloy having a thickness of 0.050 inches.
In one embodiment, the side walls of the rough-in box (28) are rounded so that instead of a square, rectangular shape, the rough-in box (28) has a rounded, circular shape. In this embodiment, as shown in
There is no need to have a bottom surface on the rough-in box (28) as that would hinder the installation of plumbing, ducts, or other mechanical systems between floors. Thus, only a lid (34) needs to be opened so that these systems can be passed up from the floors below.
Once the four side walls of the rough-in box (28) are joined together, the lid (34) is attached to the rough-in box (28). Each side wall of the rough-in box (28) is formed with a flange (38, 29) at the top to provide support for the lid (34) so that the lid (34) can be attached to any of the side walls of the rough-in box (28).
The lid (34) is load bearing to permit workmen, equipment, vehicles, and materials to move over the lid (34) without risk of the lid (34) collapsing and caving in. Therefore, the lid (34) needs to be made from a strong enough material to provide a working surface on the floor while construction is being carried out. As such, the lid (34) must be capable of supporting a weight of at least 2,000 pounds and in some applications of supporting weights of up to 20,000 pounds. The lid (34) can he made from fiberglass or from heavy duty plastics such as polyethylene, polyvinyl, and polypropylene. Additionally, in some embodiments, the lid (34) can be made from engineered wood. It is also possible that the lid (34) is made from a combination of fiberglass, heavy duty plastic and/or engineered wood.
In one embodiment, the lid (34) can be made from resin impregnated fiberglass with the density of fibers being determined by the weight that the lid (34) has to bear. The resins used to make the lid (34) can include epoxy resins as well as other types of thermosetting plastics such as polyester or vinylester resins and thermoplastics. Table 1 compares the nominal flexural modulus and strength of several lids varying by the number of piles of fiberglass tape, area weight, and thickness.
The lid (34) may be custom made to have a fixed size for a particular sized penetration and hence rough-in box (28) or may be of an adjustable size in both the length and width directions. For example,
In an alternative embodiment, the length or width of the lid (34) can be adjusted by the turning of a screw (56). This embodiment is shown in
A fire rated rubber seal (36), such as the one shown in
Optionally, compressed fireproofing can be embedded into the side walls of the rough-in box (28). As shown in
If desired, the lid (34) can be supported by a strut stretching across the box from an opening or vertical slot in one wall to an opening or vertical slot in an opposite wall to provide additional load bearing strength.
The lid (34) may be equipped with hydraulic hinges (44) to control the speed that the lid (34) opens and to also keep the lid (34) in a vertical open position when the lid (34) is opened by a worker working on the hole. The hydraulic hinges (44) are shown in
The lid (34) can feature a grip and/or handle (45) for easy opening of the lid (34). An example of a handle (45) is shown in
Different locks/screw heads can be utilized so that only certain personnel from a particular trade can open the rough-in box (28). For example, some designated rough-in boxes (28) can be equipped with a special screw head that can only be opened by plumbers, whereas other designated rough-in boxes (28) can be equipped with a different screw head that can only be opened by electricians. Examples of the different types of locks/screw heads that can be used are shown in
As a safety measure, the lid (34) can have a non-slip surface (75) so that workers and equipment moving over the lid (34) do not slip on the rough-in box (28). A slip resistant surface (75) that can be applied to the lid (34) is shown in
As an additional safety measure, the lid (34) can also be equipped with a deployable safety rail (37). The deployable safety rail (37) is a series of tubular members that are connected together and fastened to the rough-in box (28) and the lid (34) when the lid (34) is open to prevent accidental trips and falls due to the hole being open. The deployable safety rail (37) can be collapsed/de-constructed and stored in pieces within the rough-in box (28) on the underside of the lid (34) for storage as shown in
A sensing system that would alert workers and staff on the jobsite as to when a particular rough-in box has been left open can be included in the rough-in box (28). For example, a pressure sensor can be integrated into the lid (34), side walls, or both the lid (34) and side walls of the rough-in box (28). When the lid (34) is closed, the sensor will register the applied pressure. When the lid (34) is open, no pressure will be detected by the sensor, and the sensor will then wirelessly relay to a visual display that the rough-in box (28) is open.
When installing the rough-in box (28), a numbering system can be used such that each box is numbered to match a corresponding hole at the jobsite. This ensures that the right rough-in box (28) goes over the correct hole. Also, if lids (34) are removed or placed over the wrong hole, this can be easily inspected and corrected.
The rough-in box (28) with the lid (34) attached allows holes to be covered prior to the pouring of concrete and stops leaks from entering the holes. When the concrete is poured to form the floor of a high-rise building, the lid (34) prevents over-pour from the concrete and creates a perfect edge that is level with the concrete when the concrete solidifies. Thus, there are no obstructions on the floor because the lid (34) will be flush with the concrete floor, allowing for the first time use of dollies, manlifts, modular scaffolding, and designated walkways because the lid (34) is load bearing and capable of handling loads from heavy machines and equipment. As a result, fewer safety personnel are needed and work shutdowns are eliminated.
The rough-in box (28) of the present invention is embedded in the concrete floor, and only the lid (34) needs to be removed during stripping. When the lids (34) are removed, the lids (34) can be easily stacked and removed all together.
For example, an assembled T shaped plumber's box (48) is shown in
A bottom (51) may be used to complete the plumber's box (48). The shape and size of the bottom (51) may be custom made to meet the particular shape and size created by the side walls (49) for a particular plumber's box (48). Slits (52) can be cut into the sides of the bottom (51) so that protrusions (64) extending from the bottom of the side walls (49) can be inserted thereby attaching the bottom (51) to the side walls (49), and adding stability and sturdiness to the assembled plumber's box (48).
The side walls (49) and bottom (51) are flat so that when they are loaded for transportation to a worksite, they can be easily stacked on top of another to reduce storage space. In this manner, a plumber's box (48) having a desirable size and shape can be easily and efficiently constructed from components that significantly reduce storage space.
While the present invention has been described above in terms of specific embodiments, it is to be understood that the invention is not limited to these disclosed embodiments. Many modifications and other embodiments of the invention will come to the mind of those skilled in the art to which this invention pertains, and which are intended to be and are covered by both this disclosure and the appended claims. It is indeed intended that the scope of the invention should be determined by proper interpretation and construction of the appended claims and their legal equivalents, as understood by those of skill in the art relying upon the disclosure in this specification and the attached drawings.
This application claims priority from U.S. provisional application 62/216,268 filed on Sep. 9, 2015, the contents of which are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
1507721 | Waite | Sep 1924 | A |
3593344 | Logsdon | Jul 1971 | A |
3625389 | Bartlow | Dec 1971 | A |
3854620 | Saidla | Dec 1974 | A |
4077599 | Oland | Mar 1978 | A |
4493173 | Kohaut | Jan 1985 | A |
4666388 | Kovasna et al. | May 1987 | A |
4823527 | Harbeke | Apr 1989 | A |
5305568 | Beckerman | Apr 1994 | A |
5309688 | Robertson | May 1994 | A |
5390465 | Rajecki | Feb 1995 | A |
5417019 | Marshall | May 1995 | A |
6088972 | Johanneck | Jul 2000 | A |
6786463 | Collum | Sep 2004 | B1 |
6848227 | Whitty | Feb 2005 | B2 |
7073766 | Schwoerer | Jul 2006 | B2 |
7080486 | Radke et al. | Jul 2006 | B2 |
7478503 | Milani | Jan 2009 | B2 |
7533499 | Daigger | May 2009 | B2 |
8001737 | Price | Aug 2011 | B1 |
8272082 | Price | Sep 2012 | B1 |
9046194 | Gandolfo | Jun 2015 | B2 |
9347217 | Feuer | May 2016 | B2 |
20040016191 | Whitty | Jan 2004 | A1 |
20050055916 | Daigger et al. | Mar 2005 | A1 |
20060096195 | Zierer | May 2006 | A1 |
20080217339 | Arn | Sep 2008 | A1 |
20090218130 | Monden | Sep 2009 | A1 |
20100084540 | Talley | Apr 2010 | A1 |
20130216759 | Lauro | Aug 2013 | A1 |
20150047276 | Gandolfo | Feb 2015 | A1 |
20150266260 | Fujioka | Sep 2015 | A1 |
20150300002 | Feuer | Oct 2015 | A1 |
Number | Date | Country |
---|---|---|
2752360 | Mar 2013 | CA |
Entry |
---|
International Search Report (ISR) and Written Opinion (WO) dated Nov. 29, 2016 for International Application No. PCT/US16/50708. |
Number | Date | Country | |
---|---|---|---|
20170067264 A1 | Mar 2017 | US |
Number | Date | Country | |
---|---|---|---|
62216268 | Sep 2015 | US |