The present invention relates to a runback backstructure access system. In particular, the present invention relates a personnel material hoist runback backstructure access system.
Backstructure systems provide access between building floors and construction hoists at building setbacks. Backstructures also provide a tie point for hoist masts.
Conventional backstructure systems are constructed from bolted or clamped connections for connecting both tower components and landing components. Landing gates and landing protection systems are traditionally constructed of pipes and clamps and/or site-built wood panels.
There is a need for a backstructure system that provides increased productivity, increased re-utilization of connection hardware and increased job safety.
In order to address the above drawbacks, a desired system should provide a more ergonomic and safer installation than previous systems.
According to the present invention, there is provided a runback backstructure access system for removably providing access between building floors of a building structure, the system comprising: a first tower leg comprising a first rosette attachment connector; a second tower leg comprising a second rosette attachment connector; a first landing beam mountable between the first and second tower legs; a first landing beam support connector connectable on a first end of the first landing beam, the first landing beam support connector comprising a first tethered pin for removably connecting to the first rosette attachment connector; a second landing beam support connector connectable on a second end of the first landing beam, the second landing beam support connector comprising a second tethered pin for removably connecting to the second rosette attachment; at least one building support connector for connecting the first landing beam to the building structure; a third tower leg comprising a third rosette attachment connector; a fourth tower leg comprising a fourth rosette attachment connector; a second landing beam mounted between the third and fourth tower legs; a third landing beam support connector connectable on a first end of the second landing beam, the third landing beam support connector comprising a third tethered pin for removably connecting to the third rosette attachment connector; a fourth landing beam support connector connectable on a second end of the second landing beam, the fourth landing beam support connector comprising a fourth tethered pin for removably connecting to the fourth rosette attachment connector; and at least one first strut member for connecting the first landing beam to the second landing beam.
Referring to
In an embodiment shown in
Referring to
Referring now to
Referring back to
The anchoring platform may further include a third landing beam 18″ mountable between to fifth and sixth tower legs 14. The third lading beam has a fifth and sixth landing beam support connector 32, 34 that work similarly as explained above. A series of second strut members 36 connect the second landing beam 18′ to the third landing beam 18″.
Referring back to
This design allows for the use of standard horizontal and diagonal braces for tower bracing. This feature allows for the repurposing of inventory items into a high capacity system while incorporating the quick connection feature of the wedge system and eliminating the possibility of hardware fall hazards. All of the leg connection hardware is tethered to its associated tower leg 14 to allow for a quick and safe connection, thus eliminating the material fall hazard of the leg connection hardware.
A landing beam support connection also engages leg rosettes or rosette attachment connectors 12 through tethered pins, as well as connecting the landing beam support to its corresponding landing beam. The tethered pin connection substantially increases connection efficiency which not only reduces hang time for all components, but also makes labor more efficient, thus reducing installation time and eliminating the potential for hardware fall hazards.
The landing deck beams include locking pins that offset the corresponding beam to minimize the risk of error in deck positioning and eliminating the requirement for measuring the beam offset.
The landing gate system incorporates the center infill panel into a modular frame that uses pins to connect the landing gate frame to the landing deck structure and the tower legs 14. The modular frame technology and pin connection provides for a safer system than conventional systems by reducing the required labor effort resulting from engineered fitted panels with pin connections. Modular frames also eliminate the labor effort required for job built systems, thereby increasing productivity and reducing material fall hazards.
A quickback tie or connector mechanism 16 laterally secures the runback backstructure access system 10 to the building structure. The quickback tie or connector mechanism 16 accepts the hoist mast tie, utilizes prefabricated fixed components internal to the system and has reduced bolted connections to localized tensile connections. The quickback tie or connector mechanism 16 allows for adjustability to accommodate building irregularities.
Each high capacity tower leg 14 is designed to exceed typical backstructure leg capacities. Each tower leg 14, in conjunction with standardize quick connections, allows for opportunities for repurposing of the tower material for other high capacity modular application such as shoring.
Although the present invention has been described hereinabove by way of specific embodiments thereof, it can be modified, without departing from the spirit and nature of the subject invention defined in the appended claims.
This application claims priority to U.S. Provisional Patent Application No. 62/532,626 filed on Jul. 14, 2017. The above document is incorporated herein in its entirety by reference.
Number | Date | Country | |
---|---|---|---|
62532626 | Jul 2017 | US |