The present invention relates generally to precast concrete floor systems and, more specifically, to a precast concrete floor system that has a shallow flat soffit and uses no corbels to reduce the floor height while maximizing useable space.
Conventional hollow-core floor systems consist of hollow-core planks supported by inverted-tee (IT) precast prestressed concrete beams, which are, in turn, supported on column corbels or wall ledges. These floor systems provide a rapidly constructed solution to multi-story buildings that is economical, fire-resistant, and with excellent deflection and vibration characteristics. The top surface of hollow-core floor systems can be a thin non-structural cementitious topping or at least 2 inch thick concrete composite topping that provides a levelled and continuous surface. Despite the advantages of conventional precast hollow-core floor systems, they have the two main limitations of a low span-to-depth ratio and the presence of floor projections, such as column corbels and beam ledges. For a 30 ft bay size, conventional precast hollow-core floor system would require a 28 inch deep IT plus a 2 inch topping, for a total floor depth of 30 inches, which results in a span-to-depth ratio of 12 (PCI, 2010). In addition, this floor would have a 12 inch deep ledge below the hollow-core soffit and a 16 inch deep column corbel below the beam soffit.
On the other hand, post-tensioned cast-in-place concrete slab floor systems can be built with a span-to-depth ratio of 45 and flat soffit, which results in a structural depth of 8 inches for the 30 ft bay size (PTI, 2006). If the structural depth of precast floor systems can come close to that of post-tensioned cast-in-place concrete slab system, then precast concrete systems could be very favorable due to their rapid construction and high product quality. Reducing the depth of structural floor results in reduced floor height, which in turn makes savings in architectural, mechanical and electrical (AME) systems and may allows for additional floors for the same building height. The cost of AME systems is about 75 to 80% of the total initial and operation cost, and any small savings in these systems would have a significant impact on the building life cycle cost.
Low, et al. (1991 and 1996) developed a shallow floor system for multi-story office buildings. The system consists of hollow-core planks, 8 ft wide and 16 inch deep prestressed beams, and single-story precast columns fabricated with full concrete cavities at the floor level. The column reinforcement in this patented system is mechanically spliced at the job site to achieve the continuity (Tadros and Low, 1996). The beam weight and the complexity of the system design and detailing were discouraging to producers.
Thompson and Pessiki, (2004) developed a floor system of inverted tees and double tees with openings in their stems to pass utility ducts. This floor system is appropriate and economical for parking structures as it does not provide either shallow floor or flat soffit required for residential and office buildings.
Hanlon, et al. (2009) developed a total precast floor system for the construction of the nine-story flat-slab building. This system consists of precast concrete stair/elevator cores, prestressed concrete beam-slab units, prestressed concrete rib-slab floor elements; variable-width beam slab; and integrated precast concrete columns with column capital. The need for special forms to fabricate these components and the need for high capacity crane for erection are the main limitations of this system.
Composite Dycore Office Structures (1992) developed the Dycore floor system that consists of shallow soffit beam, Dycore floor slabs, and continuous cast-in-place/precast columns with block outs at the beam level. In this system, precast beams and floor slabs act primarily as stay-in-place forms for major cast-in-place operations required to complete the floor system, which is costly and time consuming.
Simanjuntak, J. H. (1998) developed a shallow ribbed slab configuration without corbels. This is accomplished by threading high tensile steel wire rope through pipes imbedded in the floor system and holes in the columns. The main drawback of that system is the need for false ceiling to cover the unattractive slab ribs.
Wise, H., H. (1973) introduced a method for building reinforced concrete floors, and roofs employing composite concrete flexural construction with little formwork. The bottom layer of the composite concrete floor is formed by using thin prefabricated concrete panels laid side by side in place with their ends resting on temporary or permanent supports. The panels are precast with one or more lattice-type girders or trusses extending lengthwise from each panel having their bottom chords firmly embedded in the panel and with the webbing and top chords extending above the top surface of the panel. The main drawback of that system is the need for shoring during construction, in addition to the limitations of the panel dimensions.
Filigree Widesslap System was presently used under the name of OMNIDEC (Mid-State Filigree Systems, Inc. 1992). It consists of reinforced precast floor panels that serve as permanent formwork. The panels are composite with cast-in-place concrete and contain the reinforcement required in the bottom portion of the slab. They also contain a steel lattice truss, which projects from the top of the precast unit. One of the main advantages for this system is a flat soffit floor which does not required a false ceiling. However, this system requires extensive techniques to produce (Pessiki, et al. 1995).
Bellmunt and Pons (2010) developed a new flooring system which consists of a structural grid of concrete beams with expanded polystyrene (EPS) foams in between. The grid has beams in two directions every 32 inches. The floor is finished with a light paving system on top and a light ceiling system underneath. This system has many advantages, such as lightweight, flat soffit, and thermal insulation. However, some of its disadvantages include the floor thickness, unique fabrication process of EPS forms due to the special connections required.
The Deltabeam (Peikko Group, Peikko News (2010)), is a hollow steel-concrete composite beam made from welded steel plates with holes in the sides. It is completely filled with concrete after installation in site. Deltabeam acts as a composite beam with hollow-core, thin shell slabs, and in-situ casting. Deltabeam can have a fire class rating as high as R120 without additional fire protection. The Deltabeam height varies based on the required span. For a 32 ft span, the Deltabeam can be as shallow as 23 inch (21 inch deep beam+2 inch topping). Although this is 5 inches less than the precast/prestressed concrete inverted tee, it requires shoring for erection, adding shims to the base plate to rise up hollow core to match the level of the top plate, and additional fire protection operations if higher ratings are required.
Although the use of column corbels and beam ledges is the common practice in parking structures and commercial buildings, it is not aesthetically favourable in residential buildings, such as hotels. False ceiling is used in these applications to hide the unattractive floor projections, which results in reduced vertical clearance. Elimination of floor projections combined with shallow structural depth will improve the building aesthetics and overall economics.
The present invention provides a flat soffit shallow precast floor system for multi-story residential and office buildings. The system minimizes the limitations of existing precast floor systems with regard to span-to-depth ratio and floor projections, while maintaining speed of construction, simplicity, and economy. More specifically, the present system has a span-to-depth ratio of at least 30 to reduce the floor height and save in architecture, mechanical, and electrical costs. In addition, the present system eliminates the column corbels and beam ledges to provide additional space and flat soffit for residential and office buildings. Further, it consists of easy-to-produce and erect precast/prestressed components with minimal cast-in-place operations to ensure practicality, economy, quality, and speed of construction.
a-d are transverse cross-sectional views through two alternative beams, wherein
The present floor system consists of precast continuous columns, precast rectangular beams, precast hollow core planks, and cast-in-place composite topping. The precast components can be easily fabricated using the facilities readily available to pre-casters in the United States.
The construction sequence consists of the following steps in order:
a) Multi-story continuous precast columns are erected and temporary corbels are installed at each floor level. The temporary corbels can be steel angles with stiffeners that are anchored to the column using high strength threaded rods through holes in the precast columns.
b) Precast rectangular beams are placed on temporary corbels. Steel angles are welded to the steel plates on top of beams and plates on column sides to stabilize beams during hollow-core erection.
c) Temporary beam ledges are installed for supporting hollow-core planks. These ledges can be steel tubes or angles anchored to the beam soffit using bolts and pre-installed coil inserts.
d) Hollow-core planks are placed on the temporary ledges for the entire floor.
e) Specially-shaped steel bars (called hat bars) are placed in hollow-core keyways. Also, beam continuity reinforcing bars are placed in beam recess and through the column opening.
f) Grout or flowable concrete is used to fill hollow-core keyways, beam recess, shear keys between hollow-core planks and beam sides, and gaps between beam ends and column sides.
g) An additional layer of beam continuity reinforcement is placed on top of the beam through the column opening and on each side of the column. Also, topping reinforcement is installed.
h) Cast-in-place topping is placed to provide levelled floor surface.
i) Temporary corbels and ledges are removed after the topping concrete reaches the required strength to provide a flat soffit.
Referring to the figures, there is depicted in
The precast interior columns 24 have a reduced width section, generally at 32 (
Precast rectangular beams 26a and 26b are placed on the temporary corbels 38a and 38b (
Temporary beam ledges 46 are installed on the bottom side of the beams 26. The ledges 46 are preferably steel tubes or angles anchored to the beam 26 soffit using bolts and pre-installed inserts (not shown). The hollow-core planks 28 are placed on the temporary ledges 46 for the entire floor (
In a preferred embodiment of the hollow-core planks 28, keyways 48 in the top surface are formed (
Grout or flowable concrete is used to fill the hollow-core keyways 48, beam recesses 54 and 56, shear keys 58 between the hollow-core planks 28 and beam 26 sides, and gaps between the beam 26 ends and column 24 sides (
Three key concepts were used to achieve the shallowness, flat soffit, and structural capacity of the proposed floor system under gravity loads. First, the width of the beams 26 was increased to accommodate a larger number of prestressing strands while minimizing its depth. Also, larger diameter strands than are commonly used in inverted tee beams were used to allow for higher prestressing force and eccentricity despite the shallow depth. In a constructed embodiment, 0.6 inch diameter strands were used instead of 0.5 inch diameter used in the art. Second, increasing beam 26 continuity for topping weight and live loads improves the beam resistance to gravity loads and eliminates the need for permanent corbels on the column 24. This continuity necessitates having an opening 36 in the precast column 24 at the beam 26 level to allow the reinforcement in the beam recesses 54 and 56 to go through the column 24 in addition to the reinforcement in the cast-in-place topping 64. Beam continuity reinforcement will also provide adequate support for the beam 26 as it creates a hidden corbel. Third, eliminating beam ledges by using temporary ledges 46 during construction. The hollow-core plank 28 to beam 26 connection is made using shear keys 58 or hidden corbels and reinforcing bars to transfer the vertical shear from the hollow-core planks 28 to beam 26 under ultimate loads after the removal of the temporary ledges 46.
The experimental investigation presented was carried out to evaluate the shear capacity of four different hollow-core-beam connections as well as the flexural capacity of the shallow rectangular beam. The shear capacity of beam-column connection (i.e., hidden corbel) was evaluated in an earlier investigation (Morcous and Tadros, 2011). The full-scale test specimen shown in
Eight strain gages were attached to the topping reinforcement (two in each connection). Finally concrete topping was poured and temporary ledges were removed after reached the specified strength. Table 1 summarizes the specified and attained concrete strength at the time of testing for precast, grout and topping concrete.
Two tests were performed, testing the hollow-core-beam connection in the four different configurations (hidden ledge with angle, shear key with angle, hidden ledge without angle, shear key without angle, and hidden ledge without angle by loading the hollow-core as cantilever), and testing the beam flexural capacity.
A. Testing hollow-core-Beam Connection
The purpose of this test is to evaluate the shear capacity of the hollow-core-beam connections under gravity loads. The hollow-core planks were loaded at their mid-span in one side while clamping the other side of the beam to maintain specimen stability. Testing was performed using two jacks applying two concentrated loads to a spread steel beam to create uniform load on the hollow-core planks at 3 ft away from the hollow-core-beam connection. Loading continued to failure while measuring the deflection under the load using potentiometer attached to the soffit of the middle hollow-core plank. The hollow-core-beam connection was tested in two stages. In the first stage, hollow-core planks were loaded up to 100 kips (50 kips each side), which creates a shearing force at the connection of 16.5 kips. This value is the ultimate shearing force due to factored dead and live loads. In the second stage, hollow-core planks were loaded up to the failure. The factored load applied to shear the hollow-core-beam connection using shear friction theory was predicted to be 209 kip (104.5 kip each side, which is 34.9 kip per hollow-core). Also, the factored loads applied to fail the composite hollow-core planks in flexure and shear were predicted to be 315 kip (157.5 kip each side, which is 52.5 kip per hollow-core) and 240 kip (120 kip each side, which is 40 kip per hollow-core) respectively.
1. Hidden Ledge with Angle
Two 130 kip jacks were used to test the connection. In the first stage of loading, the specimen performed well under ultimate design load with no signs of failure or cracking. In the second stage, hollow-core planks were loaded up to 258 kip (129 kip each side). The test was stopped after reaching the ultimate load capacity of the used jacks. The applied load creates a shearing force at the hollow core-to-beam connection of 43 kips. This value is almost 2.6 times the demand and 12% more than the design capacity of the connection. At that load, the connection did not crack, while small shear cracks were observed in the other end of hollow-core.
2. Shear Key with Angle
Two 400 kips jacks were used in this test. The specimen performed well under ultimate design load with no signs of failure or cracking. In the second stage, hollow-core planks were loaded up to 240 kip (120 kip each side) without even cracking the connection. The test was stopped due to the shear failure of hollow-core planks. The applied load created 40 kip shearing force on each hollow-core. This value is almost 2.4 times the demand and 15% more than the design capacity of the connection.
3. Hidden Ledge without Angle
Two 400 kips jacks were used in this test. The specimen performed well under ultimate design load with no signs of failure or cracking. In the second stage, hollow-core planks were loaded up to 204 kips (102 kips in each side) without even cracking the connection. The test was stopped because of the shear failure of hollow-core planks. The applied load created 34 kip shearing force on each hollow-core. This value is almost 2.1 times the demand and equal to the design capacity of the connection.
4. Shear Key without Angle
Two 130 kips jacks were used in this test. The specimen performed well under ultimate design load with no signs of failure or cracking. In the second stage, hollow-core planks were loaded up to 227 kips (113.5 kips each side) without even cracking the connection. The test was stopped due to the shear failure hollow-core planks. The applied load created 37.8 kip shearing force on each hollow-core. This value is almost 2.3 times the demand and 8% more than the design capacity of the connection.
5. Testing Beam-hollow-core Connection by Loading the Hollow-core as Cantilever In the entire previous the tests were done by applied the load at the mid span of the hollow-core, and the failure occurred in the hollow-core without even cracking the connections. Therefore, in order to investigate the full shear capacity of the connection, the hollow-core was loaded as a cantilever.
B. Testing the Beam Flexural Capacity
The purpose of this test is to evaluate the positive moment capacity at the mid-section of the composite beam. One 400-kip jack was used to apply a concentrated load on the beam at 13.75 ft from the center line of roller supports, up to failure, while measuring the deflection under the load.
The only option for constructing flat soffit shallow floors in multi-story buildings is using post-tensioned cast-in-place concrete flat slab, which is complicated, costly, and time-consuming. Current precast concrete floor systems require the use of beam ledges to support hollow core planks and column corbels to support beams, which result in projections that further reduce the clear floor height in addition to the already low span-to-depth ratio. The present floor system solves this problem by developing a shallow precast concrete floor system that eliminates the need for beam ledges and column corbels and provides a flat soffit. Economy, structural efficiency, ease and speed of construction, quality, and aesthetics are the main advantages of the proposed system. Full-scale testing of four ledge-less hollow-core-beam connections was conducted to evaluate the behaviour and shear capacity of these connections. Based on the test results, the following conclusions can be made:
1. All proposed ledge-less hollow-core-beam connections (shear key and hidden ledge with and without angles) performed very well as their shear capacity exceeded the predicted values and significantly exceeded the demand. None of these connections has failed as the tested hollow-core planks failed in shear prior to the failure of the connections
2. The capacity of the proposed ledge-less hollow-core-beam connections can be accurately predicted using shear friction theory.
3. Since the shear capacity of the hollow-core-beam connections without steel angle was adequate, steel angles are considered as temporary ledges that do not affect the fire rating of the building
4. The results of testing full-scale specimen do not only indicate the efficiency of the proposed system but also the consistency of its performance.
5. The flexural capacity of the shallow prestressed beam exceeded the demand and was accurately predicted using strain compatibility.
It should be appreciated from the foregoing description and the many variations and options disclosed that, except when mutually exclusive, the features of the various embodiments described herein may be combined with features of other embodiments as desired while remaining within the intended scope of the disclosure. It is to be understood that the above description is intended to be illustrative, and not restrictive. Many other embodiments and combinations of elements will be apparent to those skilled in the art upon reviewing the above description and accompanying drawings. The scope of the invention should, therefore, be determined with reference to the appended claims, along with the full scope of equivalents to which such claims are entitled
This application claims priority to U.S. Patent Application Ser. No. 61/468,642, filed Mar. 29, 2011, which is incorporated herein in its entirety by this reference.
Number | Date | Country | |
---|---|---|---|
61468642 | Mar 2011 | US |