The present invention relates generally to the construction industry, and relates more specifically to a lift-slab construction system and method for constructing multi-story buildings using pre-manufactured structures.
Conventional pre-manufactured building construction has typically focused on single-story buildings or building room modules or components for incorporation into new or pre-existing building structures. Conventional pre-manufactured building structures have been promoted based on the purported cost, timing, and efficiency advantages of having construction pre-manufactured at manufacturing plants or factories prior to delivery and installation at a building site. Conventional pre-manufactured building structures may be delivered either as complete structures that require minimal installation, e.g., mobile homes, or may be partial building structures or components that require labor and costly on-site installation. Installation of these pre-manufactured structures generally occur using conventional construction techniques.
It is not always cheaper, faster and more efficient to pre-manufacture building structures at manufacturing plants or factories to be delivered to the building site for further installation and/or integration and finishing on site. Handling of such structures can be extremely difficult, time-intensive and cost-prohibitive due to weight, bulk, and craning issues. Shipping modular structures or spaces can raise transportation issues due to weight and space problems. Due to the size of some building structures, transport may be inefficient as trucks may only fit one to two modules for delivery to a construction site. Huge cranes may be required to lift the modules to and from the trucks, or other transport means, at the manufacturing plants as well as the building sites.
With regard to multi-story building construction, on-site construction is conventionally preferred over use of pre-manufactured constructs because pre-manufactured structures are not typically adapted for building multi-story structures.
Conventional lift-slab construction for building multi-story buildings involves the lifting of heavy slabs by strand jacks located on top of columns. After the slab is lifted into position, it must be secured to the supporting columns which are typically located underneath a lifted slab. Securing such lifted slabs requires construction workers to undesirably and unsafely engage in the dangerous activity of working underneath heavy unsecured slabs in order to adequately secure the slabs to the columns. Such unsecured slabs may fall and crush or kill persons located underneath the slab.
The present invention utilizes pre-manufactured structures together with a lift-slab building process to overcome the limitations of utilizing pre-manufactured structures when constructing multi-story buildings.
The present invention offers several advantages over known construction systems and methods in addition to adapting the concept of pre-manufactured structures for use in multi-story building construction.
Advantages of the present invention include increased ease and efficiency of construction, reduced construction time, reduced construction cost, minimal use of scaffolding, minimal use of field welding, safer construction, higher quality construction, construction of a consistent quality, the practice of more environmentally sound construction practices including “green” building construction, reduced maintenance costs, increased ease of access to intelligently designed building spaces for residential, institutional and/or commercial use, the ready ability to permit limited interior space and finishing details customization by the governments, municipalities, townships, builders, consumers, occupants and/or other purchasers or users of these buildings, the ready ability to manage the cost, delivery, timing, and experience expectations of governments, municipalities, townships, builders, consumers, occupants and/or other purchasers or users of these buildings due to the buildings' familiar and repeated pre-manufactured components and the ability to use experience gained by virtue of constructing other similar buildings in accordance with the present invention.
The present invention integrates the use of pre-manufactured structures with minimal on-site installation and lift-slab construction to achieve the construction of multi-story building, while at the same time making building construction easier, more efficient, faster, cheaper, safer, of higher quality and consistency, environmentally advantaged, energy-efficient, easier to maintain, intelligently designed, and customizable. The buildings of the present invention also result in an enhanced building experience for all those involved in the purchase, construction and use of the buildings due, at least in part, to the ability to manage cost, delivery, timing, and experience expectations based on experiences garnered from other similar buildings constructed according to the present invention.
The present invention comprises a set of pre-manufactured structures designed for ready integration with each other and with limited on-site lift-slab construction. The present invention incorporates use of innovative lift-slab construction techniques. The pre-manufactured structures themselves are designed so that they may be arranged to create buildings and interior building units of various sizes and functionality. The pre-manufactured structures are designed so as to be readily integrated with both horizontal and vertically adjacent building components, including lift-slab components and/or other pre-manufactured structures, so that multiple building stories may be readily and securely stacked, one on top of the other. The pre-manufactured components permit development of flexible design plans for institutional, residential, office and other types of buildings, and may be provided with various finish packages customized to order.
The pre-manufactured structures preferably involve the use of as many repetitive and self-sustaining construction methods and as many preassembled and prefinished structures as possible. Preassembled and prefinished structures are constructed in a manufacturing facility, transported to the construction site and installed within and/or on the lift-slab structure in conjuction with other components to create a fully finished, comfortable and weather-tight living environment. The present invention also contemplates use of semi- or largely prefinished components that may be fully and finally finished at the construction site. The pre-manufactured structures are preferably sized and packaged to eliminate wasted shipping space to facilitate efficiency of transport.
Standardizing the pre-manufactured structures and constructing them in a manufacturing facility provides the advantages of, among other things, reduced materials waste, reduced energy costs, quality control, faster production, consistent production, safer production, and increased labor productivity. The initial assembly of the components may eventually become automated. However, another advantage of the present invention is that construction may be carried out by less skilled labor under the supervision of qualified managers. Given that assembly will occur in an environmentally controlled setting, the potential for mold or materials damage due to exposure may also be reduced.
As will be explained in greater detail below, the lift-slab construction involving the pre-manufactured structures of the present invention provides for “top-down” construction. That is, once the building's foundation and any parking or floors below or at grade and the supporting external columns and/or beams are in place, the buildings of the present invention may be built from the top down, starting with the roof and moving sequentially down through each level until construction is complete. Roof slabs and floor slabs are lifted into place using multiple strand jacks located on top of the external columns and/or beams. The external columns and/or beams may be located around the exterior perimeter of the building slabs. Once a slab is lifted into place, connections located at the slab edge are used to secure the slab to the external columns and/or beams. The slab may be connected by various means, including but not limited to, bolted or pinned connections and/or the use of welding. The preferred method of the current invention is the use of bolts and/or pins to secure the slabs to the columns and/or beams to allow for an efficient and quick installation method. The slabs may be readily secured to the external columns and beams via access created by the exterior walkways of the present invention, or by using a man-lift or other similar means. This means of connection eliminates the potential unsafe and hazardous activity of workers being underneath an unsecured slab utilized in previous conventional lift-slab construction.
The present invention advantageously reduces, and in some cases, completely eliminates the need for exterior scaffolding. The exterior walkways are utilized for access to the utility walls, while the window walls are securely attached to the lifted slabs from the interior of the unit. The end walls at each end of a multi-story building are the only location where exterior scaffolding might be necessary. This need can potentially be eliminated if the end walls are fully prefinished with the exterior components installed prior to being set in place. In this case, a man-lift or other similar means may be used to install final panels to the exterior wall. The lift-slab construction system also reduces, and in some cases, largely eliminates the need for construction cranes. By reducing the need for, and or eliminating entirely, the need for scaffolding and construction cranes, the present invention significantly and advantageously reduces the time and costs involved in multi-story building construction. Furthermore, the present invention limits or eliminates the time consuming and costly practice of field welding. The structural steel may arrive at the site shop welded where necessary and ready for installation. All field connections, whether between the structural members themselves, or between the structural steel and the floor slab, may be bolted and/or pinned connections.
The present invention's top-down lift-slab construction beneficially provides enclosure of the buildings from roof to grade during construction, thus protecting the building's interior space and construction workers from the elements such as rain, snow and wind. Construction of the multi-story building from the top-down also increases the security and safety of partially constructed multi-story buildings as access to the upper building doors is limited during construction. Further, the present invention also permits multiple construction crews to be actively working on completing building construction with, for example, one crew finishing installation and/or final finishing of pre-manufactured building structures on floor slabs that have been secured into place and another crew dedicated to preparing floor slabs and/or pre-manufactured structures to be lifted.
The present invention may reduce construction time by approximately 50%, or one-half. That is, a building constructed according to the present invention that has about 100 units on five or six floors, may be completed in six (6) to eight (8) months from the podium level to the roof. By contrast, construction of a similarly sized building using conventional construction techniques would be expected to take about twelve (12) to sixteen (16) months. The present invention is well-suited for the construction of many types of multi-story buildings, including mid-rise buildings.
The present inventions comprises, in no particular order: pre-manufacturing a plurality of finished, or mostly finished, non-weight bearing walls; pre-manufacturing a plurality of finished, or mostly finished, interior components adapted to connect to the non-weight bearing walls; pre-manufacturing finished, or mostly finished, exterior components adapted to attach to the exterior building surfaces; transporting the pre-manufactured non-weight bearing walls, interior components, and exterior components to a building site; preparing a multi-story building foundation at the building site to support a plurality of load-bearing structural columns and/or beams; forming a plurality of floor slabs and a roof slab to attach to the structural columns and/or beams at each building level; constructing the load-bearing structural columns and beams at the building site; lifting the roof slab and each floor slab to attach to structural columns and/or beams at each level; installing stairs and elevators which attach to the structural columns, beams and/or slabs; installing the non-weight bearing walls and the interior components at each building level; and installing the plurality of exterior components on exterior building surfaces. The non-weight bearing walls, interior component, and exterior components are assembled and installed to provide the multi-story building with the plurality of units which may be identical or have different floor plans and may, optionally, include a retail level with amenity space and underground parking.
The present invention may be used to construct various buildings with a plurality of institutional, office, commercial, and/or residential units including, for example, studio units, one or multiple bedroom units, and/or a mix of such units.
The non-weight bearing walls of the present invention may include: demising walls that are pre-manufactured, pre-wired, pre-plumbed, prefinished, pre-bundled, preassembled, and may me include preassembled sections, electrical wiring and electrical radiant heat, acoustic insulation, studs for framing, fire rated sheathing, interior finish material, and may include plumbing for sprinklers; end walls that are pre-manufactured, pre-wired, pre-plumbed, prefinished, pre-bundled, preassembled, and may include preassembled sections, electrical wiring and electrical radiant heat, acoustic insulation, studs for framing, fire-rated sheathing, interior finish material, vapor barrier, thermal insulation, fire rated exterior sheathing, weather resistive barrier, an exterior cladding system, and may include plumbing for sprinklers; exterior walls that are pre-manufactured, pre-wired, pre-plumbed, prefinished, pre-bundled, preassembled, and may include preassembled sections, electrical wiring and electrical radiant heat, acoustic insulation, studs for framing, fire-rated sheathing, interior finish material, vapor barrier, thermal insulation, fire rated exterior sheathing, weather resistive barrier, an exterior cladding system, and may include plumbing for sprinklers and an optional window or door; utility walls that are pre-manufactured, pre-wired, pre-plumbed, prefinished, pre-bundled, preassembled, and may include features that permit stacking of the utility walls, heating, ventilating, and air conditioning (HVAC) electrical and communications wiring for adjacent walls, an electrical service panel, kitchen and bath plumbing, including kitchen and/or bath supply and waste lines and vent ducting, exhaust vents/fans and vent trims, and toilet mounting support with a water-resistant, interior surface, interior sheathing, vapor barrier, acoustic insulation, plumbing chase, studs for framing, exterior sheathing, weather resistive barrier, and an exterior cladding system, and exterior window walls that are pre-manufactured prefinished, preassembled, pre-bundled and that may be pre-glazed and pre-bundled with a unitized wall system, and may include windows, insulation, insulated aluminum or glass and weather seal. Optionally, pre-manufactured, pre-wired, prefinished and preassembled ceiling panels that may include electrical wiring and acoustical paneling may also be used as part of the present invention. Each of the above components may also be pre-manufactured so as to be only partially prefinished and/or preassembled, with complete finishing and assembly to be done upon or after installation.
The present invention may optionally incorporate several environmentally friendly and/or green building practices. The present invention may utilize recycled products and materials, use low volatile organic compounds (VOC) finishes for improved indoor air quality, provide an abundance of natural day lighting for user comfort and well-being, provide operable windows for natural cross ventilation, incorporate use of alternative energy sources such as solar panels and wind powered turbines, provide solar thermal panels for domestic hot water and radiant heating, aid water and collection retention with green and vegetated roofs and water cisterns, utilize gray water recycling methods, provide water features and landscaping within the courtyard, and may increase cooling by introduction of green walls. The present invention optionally includes the use of external rain screen system on the building itself. The rain screen system may be located directly adjacent to the building exterior and or may include an air gap of, for example, between about 1″ to 3,″ between the insulation and the cladding to allow for air movement within the cavity to provide a means of drying potential moisture behind the cladding material. The external cladding may be comprised of various materials allowed by code, such as, but not limited to, composite panels, phenolic resin panels, metal panels, cement board, lightweight precast concrete panels, wood siding, gypsum fiber reinforced cement panels, ceramic tile, and stone panels, and may be attached to metal or wood furring channels set apart from the insulation with an air gap.
The precise sequence of steps involved in the lift-slab method used to produce a multi-story building according to the present invention may be re-ordered and executed in various different sequence steps, including, for example, those methods disclosed in U.S. patent application Ser. Nos. 12/796,625 and 12/796,603, the contents of which are fully incorporated by reference herein.
The methods and sequence of construction steps disclosed in connection with production of identical unit and mixed unit residential buildings described in detail immediately below are provided as exemplary embodiments of the present invention only and are, in no way, intended to be limiting.
One method of constructing a multi-story building with a plurality of units comprises: (a) pre-manufacturing a plurality of non-weight bearing walls with a finished exterior including all electrical, insulating, plumbing and communications components; (b) pre-manufacturing a plurality of interior components adapted to connect to the non-weight bearing walls; (c) pre-manufacturing a plurality of exterior components adapted to attach to the building's exterior surfaces; (d) transporting the non-weight bearing walls, the interior components, and the exterior components to a building site; (e) preparing a multi-story building foundation at the building site to support a plurality of load-bearing structural columns and/or beams; (f) forming and pouring a plurality of floor slabs and a roof slab to attach to the structural columns and beams at each building level; (g) constructing the load-bearing structural columns and/or beams at the building site (h) installing the exterior walkways to the structural columns and/or beams; (i) installing stairs and elevators to attach to the structural columns, beams and/or slabs, (j) loading the plurality of exterior components on the first slab; (k) lifting and securing the first slab from the poured slabs up to top of the building; (l) loading the plurality of non-weight bearing walls, the interior components, and the exterior components to the second slab; (m) lifting and securing the second slab to the structural columns and beams forming the top door, (n) repeating steps (l) through (m) until all building levels are completed; (o) installing exterior components on exterior building surfaces; (p) installing demising walls in a direction perpendicular to the longitudinal direction of the slab and partially enclosing each of the units; (q) installing end walls on the exterior sides of the units at building's ends in a direction parallel to the demising walls and partially enclosing each of the units located at the building's ends; (r) installing utility walls on the interior sides of the units in a perpendicular direction interfacing with the demising walls and connecting with the demising walls to partially enclose each of the units; (s) installing exterior window walls on exterior sides of the units and substantially enclosing each of the units; (t) installing entry doors in line with the utility walls and completely enclosing each of the units; (u) installing kitchen and bathroom components to the utility walls; and (v) installing interior partitions within each of the units for separating rooms and configuring each of the units. Using this method of construction, the non-weight bearing walls, the interior components, and the exterior components may be assembled and installed to provide the multi-story building with units having identical or different floor plans and, optionally, a retail level with underground parking.
Another method of constructing a multi-story building with a plurality of units comprises, (a) pre-manufacturing a plurality of non-weight bearing walls with a finished exterior including all electrical, insulating, plumbing and communications components: (b) pre-manufacturing a plurality of interior components adapted to connect to the non-weight bearing walls; (c) pre-manufacturing a plurality of exterior components adapted to attach to the building's exterior surfaces; (d) transporting the non-weight bearing walls, the interior components, and the exterior components to a building site; (e) preparing a multi-story building foundation at the building site to support to a plurality of load-bearing structural columns and/or beams; (f) forming and pouring a plurality of floor slabs and a roof slab to attach to the structural columns and beams at each building level; (g) constructing the load-bearing structural columns and/or beams at the building site; (h) installing stairs and elevators to attach to the structural columns, beams and/or slabs; (i) installing exterior roof components on the top slab surface; (j) lifting and securing the first slab from the poured slabs up to top of the building; (k) installing the non-weight bearing walls other than exterior window walls and some of the interior components on a second slab located beneath the first slab; (l) loading the exterior window walls and rest of the interior component on the second slab; (m) lifting the second slab with the non-weight bearing walls and the interior components whether installed or loaded to the floor level immediately beneath the first slab; (n) attaching the second slab securely to load-bearing structural columns and/or beams to form a top floor; (o) installing the remaining non-weight bearing walls, exterior window walls, the rest of the interior components on the second slab to complete the top level; (p) repeating steps (k) through (o) until all building levels are secured. Using this method of construction, the non-weight bearing walls, the interior components, and the exterior components may be assembled and installed to provide the multi-story building with units having identical or different floor plans and, optionally, a retail level with underground parking.
The foregoing and other objectives, features, and advantages of the invention will be more readily understood upon consideration of the following detailed description of the invention, taken in conjunction with the accompanying drawings.
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate various exemplary embodiments.
Before describing the invention and the figures, some of the terminology should be clarified. Please note that the terms and phrases may have additional definitions and/or examples throughout the specification. Where otherwise not specifically defined, words, phrases, and acronyms are given their ordinary meaning in the art. Exemplary embodiments may be better understood with reference to the drawings, but these embodiments are not intended to be of a limiting nature.
As used herein, “prefinished” refers to a component or components that arrive at the building site partially or fully completed and ready to be installed, and may include application of both the interior and exterior finish materials to the component(s).
As used herein, “pre-bundled” refers to a pre-manufactured component or components that are partially or fully protected, packaged, secured or otherwise made ready for transportation to the building site.
As used herein, “preassembled” refers to the partial or full assembly of a pre-manufactured component or components that occurs wholly or in part at a location other than the building site.
The exterior window wall may be an aluminum and glass panel with the possibility of containing an operable window unit. The exterior window wall may include the use of spandrel or fritted glass, as well as metal panel within the frames. The exterior window wall may also include an integral sliding door and railing to create an open wall with a flush ‘Juliet’ balcony or a full balcony bolted onto the structural frame. A first type of exterior window wall may be used in a straight configuration. A second type of exterior window wall may be used in corner units located adjacent to a building's corners. All of the exterior window walls may be fully weather-sealed and may be able to provide a U-factor of at least about 0.40. A U-factor measures the rate of heat transfer through a building element over a given area.
The entry doors may be a pre-fabricated, pre-bundled entry door unit with operable transom panel above, inner and outer frames, and all associated door hardware with preassembled sections that may include electrical wiring and may include plumbing for sprinklers. The entry door may be set in place at the final exterior wall or adjacent to the utility walls. A threshold may be provided for installation after the entry door is in place.
The kitchen unit may be a pre-fabricated and preassembled kitchen unit and may include cabinets, preinstalled plumbing, plumbing connections, electrical wiring, vent ducting, countertops, at least one sink, exhaust vents/fans and light fixtures that may be installed on, or connected to, the kitchen on the utility walls.
The cabinets may be pre-manufactured and preassembled cabinets that may include integral exhaust fans, light fixtures, refrigerator and/or washer and dryer to be installed on, or connected to, the utility walls.
The bathroom vanity may include at least one sink and preinstalled plumbing that may be installed on, or connected to, the bathroom on the utility walls.
The parapet wall may be a pre-manufactured, prefinished, and preassembled wall at the top portion of the exterior window wall, end wall, exterior wall, or utility wall that may connect to a roof slab and accommodate a building's roofing and/or garden roof conditions.
The exterior walkway may be a pre-fabricated, pre-bundled walkway with preassembled sections that may support railing and decking for rapid installation. The exterior walkway may be used in place of scaffolding during construction. Specifically, the exterior walkway may be used to provide access to secure slabs to the structural columns and/or beams and to provide ease of access for connecting utilities.
It should be noted that although these embodiments are described in relative terms as prefinished, preassembled and/or pre-bundled, the present invention is not limited to pre-manufactured building structures that are completely prefinished, preassembled and/or pre-bundled in the factory or at a site other than the building site. The present invention also encompasses the final finishing or assembly of the pre-manufactured structures and/or the use of non-pre-bundled components at the building site. The use of partially prefinished, preassembled and/or pre-bundled pre-manufactured structures may be determined on a project by project basis.
Referring now in detail to the drawing figures,
The lift-slab construction of the multi-story building 100 is described in detail for the load bearing assembly of the structural frame 400 and floor slabs 450. More specifically,
For preconstruction and excavation prior to building the structural frame 400, conventional methods of surveying, excavation and shoring may be utilized that are appropriate for the existing soil/ground conditions and preferred depth required for excavation. For example, deeper excavations may require shoring and possible below-grade waterproofing. Shoring may be constructed using concrete or wood, or other suitable material, depending on the best option for the area. Locating, trenching and extending the existing utilities to the new structure may utilize conventional methods of construction and may occur in conjunction with excavation and construction of the foundation.
For foundation construction, including basements if applicable, footings are first applied, spread and matted evenly. Any forming, reinforcing, and casting of footings and foundation walls may utilize conventional methods of concrete construction. For basements, formwork and reinforcing of below-grade walls may utilize conventional slip-form concrete construction. Slip-form construction refers to a method by which large towers or bridges are built front concrete by pouring concrete into a form and moving the hardened concrete. Typically, slip-form construction minimizes the materials used in formwork and labor, reduces the amount of concrete waste produced, and also allows for the foundation walls to be erected with the rapid speed. Unlike other concrete methods, slip-form construction does not produce over-shot concrete structures and requires very little cleanup or hauling away of waste concrete product. All site utilities may be extended to the building's service points while staged and protected for future connections. Similarly for elevator and stair foundation, excavation and forming of the foundation for the elevator and stair systems may be carried out in conjunction with the rest of the building's excavation and forming. Formwork may be properly placed, reinforcement added, and the foundation concrete may be placed and finished.
For concrete slab-on-grade construction, conventional construction practices may be utilized. A slab-on-grade may occur either at the basement level or at grade level if no basement is built. Utilities may be extended so that they are about 6 to 8 feet above the top of the slab either at the basement level or at grade level. Once this step is finished, the steps of placing the backfill, providing compaction, installing gravel, positioning vapor barrier, if required for local geotechnical review, and securing the slab reinforcement may be followed by placing and finishing the concrete slab. If a particular design incorporates below grade parking, the step of constructing a ramp may be implemented. Alternatively, the step of constructing a ramp may occur after the slab-on-grade is positioned into place. Typically, the ramp's formwork may be placed and followed by the step of securing and installing of the slab reinforcement. After these steps, the ramp's concrete slab may be placed and finished.
Assuming that only one level of parking is constructed below grade, the steps of positioning the shoring and forming the slab-on-grade level may be carried out after the basement slab and ramp are placed. Afterwards, the steps of securing slab reinforcement, any block-outs or sleeves required for the building's mechanical, plumbing, electrical, communications, site planter drainage, irrigation, parking control systems and electrical connections for security and lighting may be implemented. The steps of pouring, finishing and sealing concrete may then be implemented. If a commercial or retail level is being considered for the at grade level, then the concrete slab at the second story may be placed by conventional shoring and forming methods.
For constructing a plaza 110 for retail at the street level with an exterior courtyard, a residential terrace may be constructed at the level immediately above the retail level as shown in
As noted earlier, the forming and pouring of the floor slabs and roof slab 450A-F may occur prior to or after the building's structural frame 400 is erected. If using the plaza/retail level 110 slab as a base, the building's typical floor slabs and the roof slab 450A-F are poured one on-top-of the other, using the slab 450A below as the formwork for the slab 450B above. All of the slabs 450A-F will remain stacked on the plaza/retail level 110 surface until the slabs 450A-F have cured and reached the desired design strength. Upon curing, the slabs 450A-F are ready to be hoisted or lifted up to their finished elevation via a series of strand jacks strategically located atop the support columns and/or beams. The number of strand jacks used is dependent on the length and shape of the floor slabs to be hoisted. Upon the forming, pouring and curing of all of the slabs 450A-F, each of the floor slabs and roof slab 450A-F will then be loaded with a plurality of non-weight bearing walls, a plurality of exterior window walls, a plurality of interior components, and a plurality of exterior components, followed by lifting or hoisting up to the appropriate elevation level so that every slab 450A-F is securely positioned and attached at every building level so that non-weight bearing walls, exterior window walls, interior components, and exterior components may be installed at every level in-between floor slabs and roof slab 450A-F. Each hoisted floor slab contains numerous concrete embedded steel plates that will align with steel plates securely attached to the structural beams and/or columns 405, 406 as the slabs are hoisted into position. Upon reaching the appropriate position and the plates become aligned, a bolted or pinned connection may be used to securely attach the slabs 450A-F to the structural frame 400. The exterior walkways, exterior beams 410A-F and/or the use of man lifts may be used as a means of accessing the connections points, thereby eliminating any unnecessary hazards of having workers located under the unsecured slabs to access the connection points.
An alternate method may include installing exterior roof components on the cured top or roof slab 450F and lifting the top or roof slab 450F all the way to the top of the building via a series of strand jacks strategically located atop the support columns and/or beams. The number of strand jacks used is dependent on the length and shape of the floor slabs to be hoisted. Immediately after securing the top slab 450F, a plurality of non-weight bearing walls, exterior window walls, and some of the interior components, including the shower pan, kitchen and bathroom components are installed on a second slab 450E beneath the first slab 450F that is not yet lifted. Upon installation of the non-weight bearing walls and some of the interior components, and upon loading of the exterior window walls and rest of the interior components on the second slab 450E below, the second slab 450E with non-weight bearing walls, exterior window walls, and interior components, is lifted or hoisted up under the first slab at the top 450F and securely attached to the load bearing structural frame 400 to make the top floor or level. Each hoisted floor slab contains numerous concrete embedded steel plates that will align with steel plates securely attached to the structural beams and/or columns 405, 406 as the slabs are hoisted into position. Upon reaching the appropriate position and the plates become aligned, a bolted or pinned connection may be used to securely attach the slabs 450A-F to the structural frame 400. The exterior walkways, exterior beams 410A-F and/or the use of man lifts may be used as a means of accessing the connections points, thereby eliminating any unnecessary hazards of having workers located under the unsecured slabs to access the connection points.
The next sequence of steps involves installation of elevators and stairs. The pre-fabricated, pre-bundled stairs with preassembled sections is delivered to the site. Lower sections of the stairs are set and anchored into place simultaneously with the placement of the street level slab or at grade slab 430. Installation of the stairs will track closely with the installation of the building's structural frame 400. Installation of the structural framing for the elevator enclosure will track in conjunction with installation of the rest of the building's vertical columns 405.
Upon securely attaching the second slab 450E to the load bearing structural columns and beams 405, 410E, the loaded exterior window walls and the rest of the interior components including the entry doors and interior partitions are installed to the second slab 450E to complete the building's top level. Non-weight bearing walls, the exterior window walls, kitchen and bathroom components are next installed on a third floor slab 450D beneath second slab 450E. Similar to the previously described process for constructing the top level, the exterior window walls and the rest of the interior components are loaded on the third slab 450D below, and the third slab 450D with the non-weight bearing walls and the interior components, whether installed or loaded, is lifted up or hoisted under the second slab 450E and securely attached to the load-bearing structural columns and beams 405, 410E to make a level beneath the top level. This process of loading and installing the non-weight bearing walls, the exterior windows, and the interior components is repeated until all the building levels are completed.
Upon suspending the slabs 450A-F at their appropriate elevation levels, each slab 450A-F is bolted or pinned to the vertical columns 405 and horizontal beams 410A-F which make up the load bearing steel framing 400. For example, the roof slab 450F is securely attached to the vertical columns 405 and the top horizontal beam 410F. The top floor slab 450E is securely attached to the vertical column 405 and the fifth horizontal beam 410E. The fourth floor slab 450D is securely attached to the vertical columns 405 at the fourth horizontal beam 410D. The third floor slab 450C is securely attached to the vertical columns 405 at the third support beam 410C. The second floor slab 450B is securely attached to the vertical columns 405 at the second support beam 410B. The first floor slab 450A is securely attached to the vertical columns 405 at the first support beam 410A. The present invention limits or eliminates the time consuming and costly process of field welding, however the use of field welding is not prohibited in the present invention.
Conventional steel reinforcing bars and post tensioned cables may be used in the slabs 450A-F. The span of the slab 450A-F is set at a distance that can be supported within the depth and width of the slab 450A-F. Upon placing the slabs 450A-F at appropriate elevation levels, they will fully support their spans without the use of supplemental beams or columns. Electric radiant heat coils may be incorporated into the concrete floor slabs 450A-F to heat each unit. The structural floor slabs 450A-F may act as the finished floor slab for the unit above or the finished ceiling for the unit below. Acoustical and impact isolation at the slab 450A-F is required and may either be accomplished by coverage on the floor and/or by including optional pre-fabricated ceiling panels which may also include acoustical paneling.
Each of the demising walls 500A-B are positioned directly opposite of each other in a parallel direction to enclose the studio unit 300A. The shower 612A (later shown in
As shown in
Each of the demising walls 500A-B are positioned directly opposite of each other in a parallel direction to enclose the studio unit 300B. The shower 612A (later shown in
As shown in
Each of the demising walls 500A-B are positioned directly opposite of each other in a parallel direction to enclose the one bedroom unit 300C. The shower 612B (later shown in
Alternatively, the exemplary two bedroom unit can be configured in a number of various ways. Any of the layouts are flexible and walls as well as components can be changed around. For example, the entry door 540 can be positioned adjacent to storage cabinet 630B and kitchen unit 600C moved adjacent to storage cabinet 630C; storage cabinets 630B-C can be interchanged; sliding bedroom door 640 and entertainment wall 642 are completely interchangeable with each other.
In an effort to keep the construction as efficient as possible for on-site staging, storage of materials, walls and components are minimal. All of the building's fundamental elements are delivered to the site as pre-fabricated and prefinished components. These pre-fabricated and prefinished components include all exterior walls, demising walls, interior partitions, all kitchen and bathroom units, and other components. Walls are typically delivered in a minimum of ten foot lengths and may be as large as 20 foot lengths or more unless noted otherwise, and may be hoisted directly from the truck or other transport means to their final location for immediate installation.
The floor slabs and roof slab 450A-F are either lifted and secured to the load bearing structural frame 400 or the floor slabs and roof slab 450A-F are loaded, lifted and secured to the load bearing structural frame 400. The step of constructing a building for the present invention may involve placing or installing the demising walls 500A-B as shown in
The first step of installing the demising wall 500A utilizes prefinished, acoustically sealed L-shaped support members 706A-B and fasteners 707 which are secured to the top and undersides of the floor slab 450. As shown in
As shown in
As shown in
The next step of constructing a building using the present invention may be installing end walls 510, particularly when a unit is not located in the middle of a building. A living unit that is located in the middle of a building is enclosed between two demising walls 500A-B that are parallel to one another. In this case, both demising walls 500A-B are placed one after the other. However, for a living unit that is located at the end of a building, the end unit requires installation of an end wall 510 in lieu of a second demising wall 520B or an exterior window wall 530A-C. The preferred sequence is to install the end wall 510 with its structural members immediately following installation of the demising walls 500A-B as described in previous figures. This sequence helps to enclose the construction as soon as possible.
The exterior side of the end wall 510 receives exterior sheathing 803, a weather resistive barrier 802, furring channels 804, preferably metal or similar material, rigid insulation 805, associated flashing pieces 806, exterior fasteners 807 and an exterior cladding material 800. A section of exterior cladding 800, metal furring channels 804, rigid insulation 805, associated flashing pieces 806, and exterior fasteners 807 is temporarily left off the end wall 510 at the slab edge 450 as a means of providing the connection of the end wall 510 to the floor slab 450 as described below.
The steps to attach the end wall 510 to the floor slab 450 are illustrated in
Upon attachment of the plates 808A-B to the slab 450 with fasteners 807, the end wall 510 is moved into place with the exterior wall sheathing 803 abutting the base and head plates 808A-B. Fasteners 807 are installed in the horizontal direction along the end wall 510 through the weather resistive barrier 802 and into the exterior sheathing 803 to securely attach the end wall 510 to the floor slab 450. The next step is to attach a “peel and stick” weather resistive barrier 809 over the base and head plates 808A-B at the base and head of the wall and the floor slab 450 of the end wall 510. The final step involves attaching the final exterior cladding 800, metal furring channels 804, rigid insulation 805, and associated flashing pieces 806 with fasteners 807 that was temporarily left off allowing access to attachment points of the end wall 510 to floor slab 450. The installation of this final panel 800 completes the installation of the end walls 510 creating a weather-tight and watertight system.
After the demising walls and end walls are secured in place, the next step involved in constructing the building using the present invention may be to attach utility wall 520 as to further enclose the unit. Each unit 300A-H and 300J as shown in
As shown in
Upon attachment of the plates 808A-B to the slab 450 with fasteners 807, the utility wall 520 is moved into place with the exterior wall sheathing 803 abutting the base and head plates 808A-B. Upon connection of the utilities through the exterior side of the utility wall 520 utilizing the exterior walkway for access, or by other means, the portion of exterior sheathing 803 that was previously left off is attached using fasteners 807. The utility wall 520 is then securely fastened to the head and base plates 808A-B with fasteners 807 installed in the horizontal direction along the utility wall 520 through the weather resistive barrier 802 and into the exterior sheathing 803 to securely attach the utility wall 520 to the floor slab 450. The next step is to attach a “peel and stick” weather resistive barrier 809 over the base and head plates 808A-B at the base and head of the wall and the floor slab 450 of the utility wall 520. The final step involves attaching the final exterior cladding 800, metal furring channels 804, rigid insulation 805, and associated flashing pieces 806 with fasteners 807 that was temporarily left off allowing access to attachment points of the utility wall 520 to floor slab 450 as well as to allow for a connection point of utilities within the utility wall 520. The installation of this final panel 800 completes the installation of the utility wall 520 creating a weather-tight and watertight system.
After the demising walls 500A-B, end walls 510, and utility wall 520 are secured in place, the next step involved in contracting the building using the present invention may be to attach the exterior window wall 530A-D to substantially enclose the unit. Window wall sections are installed in a linear arrangement starting at the end wall as shown in
A slip member 825A is then anchored firmly to the underside of the slab 450 at the ceiling, or head, portion of the exterior window wall 530B. The slip member 825A is shimmed so that it is perfectly level to receive the bottom exterior window wall 530B with the head support member 826 and rests at its exact elevation. The exterior window walls 530A-B are constructed to allow approximately ⅝″ of shim space at the top and bottom for leveling and alignment. A third fastener 823 is used to attach a head blocking 827 to the underside of the slab 450. The small flashing 828 is used to seal the head blocking 827. Upon anchoring the slip member 825A to its proper position under the slab 450, the exterior window wall 530B with the head support member 826 is inserted into the slip member 825A. Upon securing the head portion of the exterior window wall 530B with the slip member 825A, the bottom portion of the exterior window wall 530A is positioned tightly against the anchor 822 and at the bottom side of the exterior window wall 530A. As shown in
The final step in completely enclosing exemplary units 300A-H and 300J involves the installation of the entry door 540. The entry door 540 is a preassembled, pre-glazed, and prefinished component.
Upon anchoring the head frame 846 to its proper position under the slab 450, the transom 843 is inserted into the head frame 846. Upon securing the head portion of the transom 843 with the head frame 846, the bottom portion of the entry door 540 is positioned tightly against the anchor at the bottom side of the entry door 540. A closure trim piece 848 is snapped into place into the transom head 846. An electrical closure chase 845 adjacent to the transom head 846 is snapped into place following the installation of cleats 705 and fasteners 707 on the blocking 847 and the underside of the floor slab 450. The electrical chase 845 is preferably made of aluminum, however, other types of materials can be used to enclose the conduit. The electrical chase 845 is preferably made of the same material as the entry door frame 842.
After the exemplary units 300A-H and 300J are fully enclosed utilizing the steps outlined above, the next step of constructing a building is connecting utility components and installing fixtures. All of the unit's utility connections occur at the utility wall 520. The electrical and communications main lines run vertically in the utility wall 520. At each unit, the electrical service feeds directly into the utility wall's 520 breaker panel. Wiring connections to other wall components occur via pre-installed wiring. Electrical and communications connections are carried out at the time of installation of each adjacent utility wall 520. In
The shower pan 612A and integral drain 613 are set on the slab or into a recess within the floor slab 450. In
The next step of construction is installing interior bathroom partitions 620A-B, and 621 as shown on
The bottom portions of the shower and bathroom partitions 620A-B and 621 are used to attach to the floor slab 450. A rigid C-shaped bottom receptor channel 732 is attached to the floor slab 450 by a bottom anchor 736 to insert the glass partition 730 as illustrated in
The next step of construction is installing interior bedroom partitions 640, 642 for separating rooms or configuring rooms with different layouts as shown in
As illustrated in
To complete the installation of the entertainment wall 642 as illustrated in
The final step of construction may be assembling the parapet for the roof as shown in
As illustrated in
Upon attachment of the plate 808A to the slab 450 with fasteners 807, the parapet wall is moved into place with the exterior wall sheathing 803 abutting the base plate 808A. Fasteners 807 are installed in the horizontal direction along the parapet wall through the weather resistive barrier 802 and into the exterior sheathing 803 to securely attach the parapet wall to the floor slab 450. The next step is to attach a “peel and stick” weather resistive barrier 800 over the base plate 808A at the base of the wall and the floor slab 450 of the parapet wall. The exterior cladding 800, metal furring channels 804, rigid insulation 805, and associated flashing pieces 806 with fasteners 807 are then applied to the exterior portion of the parapet wall 760 and integrally flashed with the window wall 530B or end wall.
As shown in
The majority of the building's roof is a flat membrane roof. In one of the exemplary applications, the roof area has a garden roof system. The garden roof system is a low-maintenance, vegetated roof system which helps reduce heat island effects, retains storm water runoff, and provides insulation benefits. This vegetated roof system may include recycled material in either a complete vegetated system, or a modular vegetated system. The cover provided by the planting minimizes the impact from UV and varying temperatures on the surrounding environment and increases the life of the roof system. In one of the exemplary applications, an Inverted Roof Membrane Assembly (IRMA) also called a Protected Roof Membrane (PRM) system may be installed after the parapet wall is installed. A monolithic, thermoplastic roofing membrane 860 is placed directly on the concrete roof slab 450. This monolithic, thermoplastic roofing membrane 860 is a fully adhered, seamless, self-healing membrane that can be mopped onto the top of the roof slab 450. Upon applying the roofing membrane 860, the roof is covered with a fiberglass-reinforced protective layer or roof barrier, and additionally covered with a layer of CFC-free, closed cell rigid insulation 864 as an air barrier. The thickness of the insulation layers 864 are determined by the local environment and governing thermal design values.
As shown in
Sloped roofing may be used in selective locations such as independent walkways, areas with stairs and elevator landings. Translucent roof panels may be used at sloping roofs to allow as much natural light as possible to the areas below. Any run-off from the roof surfaces are collected and stored as gray water for irrigating plants on the vegetated roof and in-the-site landscape.
The application of the exterior walkways is preferably attached to the columns and/or beams 405, 410 immediately following the erection of the structural frame 400 and is determined by the overall building configuration and the need for structural framing adjacent to the face of the building. This preferred sequencing allows the exterior walkways to be utilized in attachment of the slabs to the structural frame as well as allowing easy access to the individual units. In
As further illustrated in
As shown in
Two Through Four Bedroom Units
The steps described in
A two bedroom unit of the present invention may be one and half times longer than a studio unit. Four bedroom units are typically twice the size of a standard studio unit. There are also standard plans for two and three bedroom corner units and efficiency units as shown in
The first step of constructing multiple bedroom units is delivering and staging of demising walls 500A-B as described in
The next step of constructing multiple bedroom units is placing end walls 510A-B for units as described in
Similar to the end walls 510 as shown in
The exterior side of the exterior wall receives exterior sheathing 803, a weather resistive barrier 802, furring channels 804, preferably metal or similar material, rigid insulation 805, associated flashing pieces 806, exterior fasteners 807 and an exterior cladding material 800. A section of exterior cladding 800, metal furring channels 804, rigid insulation 805, associated flashing pieces 806, and exterior fasteners 807 is temporarily left off the exterior wall at the slab edge 450 as a means of providing the connection of the exterior wall to the floor slab 450 as described below.
Similar to the end walls 510 as shown in
The next step of construction is placing the utility wall 520 as previously described in
As previously described in
The next step of constructing multiple bedroom units is installing the entry door 540A-B and its associated parts. Installation of the entry door 540A-B is described in
The next step of constructing multiple bedroom units is connecting utility components and installing fixtures. The sequence of the utility connections and placement of the plumbing fixtures are described in
The next step of constructing multiple bedroom units is inserting a shower pan 612A-B with an integral drain 613 into a recess 470 within the floor slab 450 as described in
The next step of constructing multiple bedroom units is installing interior partitions for separating rooms or configuring rooms with different layouts as described in
The final step of constructing outer structures such as the parapet wall, roof, and exterior or common walkways are the same as previously described in
It should be noted that relative terms are meant to help in the understanding of the structures and are not meant to limit the scope of the invention. Similarly, the term “head” is meant to be relative to the term “base,” and the term “top” is meant to be relative to the term “bottom.” It should also be noted that the term “right” is meant to be relative to the term “left,” and the term “horizontal” is meant to be relative to the term “vertical.” Furthermore, the present invention is described in terms of perpendicular and parallel in direction, the terms are not meant to be limiting. It should be further noted that although the present invention is described in terms of first and second walls, the terms are not meant to be limiting. It should be further noted that although the present invention is described using certain structures such as fasteners, however, any other types of means can be used to attach the walls.
The terms and expressions that have been employed in the foregoing specification are used as terms of description and not of limitation, and are not intended to exclude equivalents of the features shown and described. This application is intended to cover any adaptations or variations of the present invention. It will be appreciated by those of ordinary skill in the art that any arrangement that is calculated to achieve the same purpose may be substituted for the specific embodiment shown.
The present application is a divisional application of U.S. patent application Ser. No. 13/700,429, filed on Jun. 7, 2011, now U.S. Pat. No. 9,493,940, which is a U.S. National Stage filing under 35 U.S.C. § 371 of International Application No. PCT/US2011/001039, filed on Jun. 7, 2012, which is a continuation-in-part application under 35 U.S.C. § 120 of U.S. patent application Ser. No. 12/796,625, filed on Jun. 8, 2010, now U.S. Pat. No. 9,027,307, titled “Construction System And Method For Constructing Buildings Using Pre-manufactured Structures,” and is also a continuation-in-part application under 35 U.S.C. § 120 of U.S. patent application Ser. No. 12/796,603, filed on Jun. 8, 2010, U.S. Pat. No. 8,950,132, titled “Premanufactured Structures For Constructing Buildings.” The entirety of these applications are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
1168556 | Robinson et al. | Jan 1916 | A |
1876528 | Walters | Sep 1932 | A |
1883376 | Meier et al. | Oct 1932 | A |
2160161 | Marsh | May 1939 | A |
2419319 | Lankton | Apr 1947 | A |
2495862 | Osborn | Jan 1950 | A |
2562050 | Lankton | Jul 1951 | A |
2686420 | Youtz | Aug 1954 | A |
2722724 | Miller | Nov 1955 | A |
2758467 | Gilbert | Aug 1956 | A |
2871544 | Youtz | Feb 1959 | A |
2871997 | Simpson et al. | Feb 1959 | A |
3017723 | Von Heidenstam | Jan 1962 | A |
3052449 | Long et al. | Sep 1962 | A |
3053015 | Graham | Sep 1962 | A |
3053509 | Haupt et al. | Sep 1962 | A |
3065575 | Ray | Nov 1962 | A |
3079652 | Wahlfeld | Mar 1963 | A |
3184893 | Booth | May 1965 | A |
3221454 | Togni | Dec 1965 | A |
3235917 | Skubic | Feb 1966 | A |
3236014 | Edgar | Feb 1966 | A |
3245183 | Tessin | Apr 1966 | A |
3281172 | Kuehl | Oct 1966 | A |
3315424 | Smith | Apr 1967 | A |
3355853 | Wallace | Dec 1967 | A |
3388512 | Newman | Jun 1968 | A |
3392497 | Cushman | Jul 1968 | A |
3411252 | Boyle, Jr. | Nov 1968 | A |
3460302 | Cooper | Aug 1969 | A |
3490191 | Ekblom | Jan 1970 | A |
3579935 | Regan | May 1971 | A |
3590393 | Hollander | Jul 1971 | A |
3594965 | Saether | Jul 1971 | A |
3604174 | Nelson, Jr. | Sep 1971 | A |
3608258 | Spratt | Sep 1971 | A |
3614803 | Matthews | Oct 1971 | A |
3638380 | Perri | Feb 1972 | A |
3707165 | Stahl | Dec 1972 | A |
3713265 | Wysocki et al. | Jan 1973 | A |
3721056 | Toan | Mar 1973 | A |
3722169 | Boehmig | Mar 1973 | A |
3727753 | Starr | Apr 1973 | A |
3742666 | Antoniou | Jul 1973 | A |
3751864 | Berger et al. | Aug 1973 | A |
3755974 | Berman | Sep 1973 | A |
3762115 | McCaul, III | Oct 1973 | A |
3766574 | Smid, Jr. | Oct 1973 | A |
3821818 | Alosi | Jul 1974 | A |
3823520 | Ohta et al. | Jul 1974 | A |
3845601 | Kostecky | Nov 1974 | A |
3853452 | Delmonte | Dec 1974 | A |
3906686 | Dillon | Sep 1975 | A |
3921362 | Ortega | Nov 1975 | A |
3926486 | Sasnett | Dec 1975 | A |
3971605 | Sasnett | Jul 1976 | A |
3974618 | Cortina | Aug 1976 | A |
3990202 | Becker | Nov 1976 | A |
4038796 | Eckel | Aug 1977 | A |
4050215 | Fisher | Sep 1977 | A |
4059936 | Lukens | Nov 1977 | A |
4078345 | Piazzalunga | Mar 1978 | A |
4107886 | Ray | Aug 1978 | A |
4112173 | Roudebush | Sep 1978 | A |
4142255 | Togni | Mar 1979 | A |
4161087 | Levesque | Jul 1979 | A |
4171545 | Kann | Oct 1979 | A |
4176504 | Huggins | Dec 1979 | A |
4178343 | Rojo, Jr. | Dec 1979 | A |
4206162 | Vanderklaauw | Jun 1980 | A |
4214413 | Gonzalez Espinosa de los Monteros | Jul 1980 | A |
4221441 | Bain | Sep 1980 | A |
4226061 | Day, Jr. | Oct 1980 | A |
4251974 | Vanderklaauw | Feb 1981 | A |
4280307 | Griffin | Jul 1981 | A |
4314430 | Farrington | Feb 1982 | A |
4325205 | Salim | Apr 1982 | A |
4327529 | Bigelow, Jr. | May 1982 | A |
4341052 | Douglass, Jr. | Jul 1982 | A |
4361994 | Carver | Dec 1982 | A |
4389831 | Baumann | Jun 1983 | A |
4397127 | Mieyal | Aug 1983 | A |
4435927 | Umezu et al. | Mar 1984 | A |
4441286 | Skvaril | Apr 1984 | A |
4447987 | Lesosky | May 1984 | A |
4447996 | Maurer, Jr. | May 1984 | A |
4477934 | Salminen | Oct 1984 | A |
4507901 | Carroll | Apr 1985 | A |
4513545 | Hopkins, Jr. | Apr 1985 | A |
4528793 | Johnson | Jul 1985 | A |
4646495 | Chalik | Mar 1987 | A |
4648228 | Kiselewski | Mar 1987 | A |
4655011 | Borges | Apr 1987 | A |
4688750 | Teague et al. | Aug 1987 | A |
4712352 | Low | Dec 1987 | A |
4757663 | Kuhr | Jul 1988 | A |
4856244 | Clapp | Aug 1989 | A |
4862663 | Krieger | Sep 1989 | A |
4893435 | Shalit | Jan 1990 | A |
4918897 | Luedtke | Apr 1990 | A |
4919164 | Barenburg | Apr 1990 | A |
4974366 | Tizzoni | Dec 1990 | A |
4991368 | Amstutz | Feb 1991 | A |
5010690 | Geoffrey | Apr 1991 | A |
5036638 | Kurtz, Jr. | Aug 1991 | A |
5076310 | Barenburg | Dec 1991 | A |
5079890 | Kubik | Jan 1992 | A |
5127203 | Paquette | Jul 1992 | A |
5154029 | Sturgeon | Oct 1992 | A |
5185971 | Johnson, Jr. | Feb 1993 | A |
5205091 | Brown | Apr 1993 | A |
5212921 | Unruh | May 1993 | A |
5233810 | Jennings | Aug 1993 | A |
5307600 | Simon, Jr. | May 1994 | A |
5359820 | McKay | Nov 1994 | A |
5361556 | Menchetti | Nov 1994 | A |
5402612 | diGirolamo et al. | Apr 1995 | A |
5412913 | Daniels et al. | May 1995 | A |
5426894 | Headrick | Jun 1995 | A |
5459966 | Suarez | Oct 1995 | A |
5471804 | Winter, IV | Dec 1995 | A |
5493838 | Ross | Feb 1996 | A |
5509242 | Rechsteiner et al. | Apr 1996 | A |
5519971 | Ramirez | May 1996 | A |
5528877 | Franklin | Jun 1996 | A |
5584142 | Spiess | Dec 1996 | A |
5592796 | Landers | Jan 1997 | A |
5611173 | Headrick et al. | Mar 1997 | A |
5628158 | Porter | May 1997 | A |
5640824 | Johnson et al. | Jun 1997 | A |
5660017 | Houghton | Aug 1997 | A |
5678384 | Maze | Oct 1997 | A |
5697189 | Miller | Dec 1997 | A |
5699643 | Kinard | Dec 1997 | A |
5706607 | Frey | Jan 1998 | A |
5724773 | Hall | Mar 1998 | A |
5746034 | Luchetti et al. | May 1998 | A |
5755982 | Strickland | May 1998 | A |
5850686 | Mertes | Dec 1998 | A |
5867964 | Perrin | Feb 1999 | A |
5870867 | Mitchell | Feb 1999 | A |
5921041 | Egri, II | Jul 1999 | A |
5970680 | Powers | Oct 1999 | A |
5987841 | Campo | Nov 1999 | A |
5992109 | Jonker | Nov 1999 | A |
5997792 | Gordon | Dec 1999 | A |
6000194 | Nakamura | Dec 1999 | A |
6055787 | Gerhaher et al. | May 2000 | A |
6073401 | Iri et al. | Jun 2000 | A |
6073413 | Tongiatama | Jun 2000 | A |
6076319 | Hendershot | Jun 2000 | A |
6086350 | Del Monte | Jul 2000 | A |
6154774 | Furlong | Nov 2000 | A |
6170214 | Treister et al. | Jan 2001 | B1 |
6240704 | Porter | Jun 2001 | B1 |
6243993 | Swensson | Jun 2001 | B1 |
6244002 | Martin | Jun 2001 | B1 |
6244008 | Miller | Jun 2001 | B1 |
6260329 | Mills | Jul 2001 | B1 |
6289646 | Watanabe | Sep 2001 | B1 |
6301838 | Hall | Oct 2001 | B1 |
6308465 | Galloway et al. | Oct 2001 | B1 |
6308491 | Porter | Oct 2001 | B1 |
6340508 | Frommelt | Jan 2002 | B1 |
6371188 | Baczuk et al. | Apr 2002 | B1 |
6393774 | Fisher | May 2002 | B1 |
6430883 | Paz et al. | Aug 2002 | B1 |
6446396 | Marangoni et al. | Sep 2002 | B1 |
6481172 | Porter | Nov 2002 | B1 |
6484460 | VanHaitsma | Nov 2002 | B2 |
6625937 | Parker | Sep 2003 | B1 |
6651393 | Don | Nov 2003 | B2 |
6729094 | Spencer et al. | May 2004 | B1 |
6748709 | Sherman et al. | Jun 2004 | B1 |
6837013 | Foderberg et al. | Jan 2005 | B2 |
6922960 | Sataka | Aug 2005 | B2 |
7007343 | Weiland et al. | Mar 2006 | B2 |
7059017 | Rosko et al. | Jun 2006 | B1 |
7143555 | Miller | Dec 2006 | B2 |
RE39462 | Brady | Jan 2007 | E |
7389620 | McManus | Jun 2008 | B1 |
7395999 | Walpole | Jul 2008 | B2 |
7444793 | Raftery et al. | Nov 2008 | B2 |
7467469 | Wall | Dec 2008 | B2 |
7484329 | Levy | Feb 2009 | B2 |
7484339 | Fiehler | Feb 2009 | B2 |
7493729 | Semmes | Feb 2009 | B1 |
7574837 | Hagen, Jr. et al. | Aug 2009 | B2 |
7658045 | Elliott et al. | Feb 2010 | B2 |
7676998 | Lessard | Mar 2010 | B2 |
7694462 | O'Callaghan | Apr 2010 | B2 |
7721491 | Appel | May 2010 | B2 |
7748193 | Knigge et al. | Jul 2010 | B2 |
7908810 | Payne, Jr. et al. | Mar 2011 | B2 |
7921965 | Surace | Apr 2011 | B1 |
7966778 | Klein | Jun 2011 | B2 |
8051623 | Loyd | Nov 2011 | B2 |
8096084 | Studebaker et al. | Jan 2012 | B2 |
8109058 | Miller | Feb 2012 | B2 |
8166716 | Macdonald et al. | May 2012 | B2 |
8234827 | Schroeder, Sr. et al. | Aug 2012 | B1 |
8234833 | Miller | Aug 2012 | B2 |
8251175 | Englert et al. | Aug 2012 | B1 |
8276328 | Pepin | Oct 2012 | B2 |
8322086 | Weber | Dec 2012 | B2 |
8359808 | Stephens, Jr. | Jan 2013 | B2 |
8424251 | Tinianov | Apr 2013 | B2 |
8490349 | Lutzner et al. | Jul 2013 | B2 |
8505259 | Degtyarev | Aug 2013 | B1 |
8539732 | Leahy | Sep 2013 | B2 |
8555581 | Amend | Oct 2013 | B2 |
8555589 | Semmens et al. | Oct 2013 | B2 |
8621806 | Studebaker et al. | Jan 2014 | B2 |
8733046 | Naidoo | May 2014 | B2 |
8769891 | Kelly | Jul 2014 | B2 |
8833025 | Krause | Sep 2014 | B2 |
8950132 | Collins et al. | Feb 2015 | B2 |
8978324 | Collins et al. | Mar 2015 | B2 |
8997424 | Miller | Apr 2015 | B1 |
9027307 | Collins et al. | May 2015 | B2 |
9382709 | Collins et al. | Jul 2016 | B2 |
20020059763 | Wong | May 2002 | A1 |
20020170243 | Don et al. | Nov 2002 | A1 |
20030005653 | Sataka | Jan 2003 | A1 |
20030056445 | Cox | Mar 2003 | A1 |
20030084629 | Strickland et al. | May 2003 | A1 |
20030101680 | Lee | Jun 2003 | A1 |
20030140571 | Muha et al. | Jul 2003 | A1 |
20030167712 | Robertson | Sep 2003 | A1 |
20030200706 | Kahan et al. | Oct 2003 | A1 |
20030221381 | Ting | Dec 2003 | A1 |
20040065036 | Capozzo | Apr 2004 | A1 |
20040103596 | Don | Jun 2004 | A1 |
20050081484 | Yland | Apr 2005 | A1 |
20050108957 | Quesada | May 2005 | A1 |
20050188626 | Johnson | Sep 2005 | A1 |
20050188632 | Rosen | Sep 2005 | A1 |
20050198919 | Hester, Jr. | Sep 2005 | A1 |
20050204697 | Rue | Sep 2005 | A1 |
20050204699 | Rue | Sep 2005 | A1 |
20050210764 | Foucher et al. | Sep 2005 | A1 |
20050210798 | Burg et al. | Sep 2005 | A1 |
20050235571 | Ewing et al. | Oct 2005 | A1 |
20050235581 | Cohen | Oct 2005 | A1 |
20050247013 | Walpole | Nov 2005 | A1 |
20050262771 | Gorman | Dec 2005 | A1 |
20060021289 | Elmer | Feb 2006 | A1 |
20060070321 | Au | Apr 2006 | A1 |
20060096202 | Delzotto | May 2006 | A1 |
20060117689 | Onken et al. | Jun 2006 | A1 |
20060137293 | Klein | Jun 2006 | A1 |
20060143856 | Rosko et al. | Jul 2006 | A1 |
20060150521 | Henry et al. | Jul 2006 | A1 |
20060179764 | Ito | Aug 2006 | A1 |
20060248825 | Garringer | Nov 2006 | A1 |
20070000198 | Payne, Jr. et al. | Jan 2007 | A1 |
20070074464 | Eldridge | Apr 2007 | A1 |
20070107349 | Erker | May 2007 | A1 |
20070157539 | Knigge et al. | Jul 2007 | A1 |
20070163197 | Payne et al. | Jul 2007 | A1 |
20070209306 | Andrews et al. | Sep 2007 | A1 |
20070234657 | Speyer et al. | Oct 2007 | A1 |
20070283640 | Shivak et al. | Dec 2007 | A1 |
20070294954 | Barrett | Dec 2007 | A1 |
20080000177 | Siu | Jan 2008 | A1 |
20080057290 | Guevara et al. | Mar 2008 | A1 |
20080098676 | Hutchens | May 2008 | A1 |
20080104901 | Olvera | May 2008 | A1 |
20080168741 | Gilgan | Jul 2008 | A1 |
20080178542 | Williams | Jul 2008 | A1 |
20080202048 | Miller et al. | Aug 2008 | A1 |
20080222981 | De Gobbi | Sep 2008 | A1 |
20080229669 | Abdollahzadeh et al. | Sep 2008 | A1 |
20080282626 | Powers, Jr. | Nov 2008 | A1 |
20080289265 | Lessard | Nov 2008 | A1 |
20080295450 | Yogev | Dec 2008 | A1 |
20090031652 | Ortega Gatalan | Feb 2009 | A1 |
20090038764 | Pilz | Feb 2009 | A1 |
20090077916 | Scuderi et al. | Mar 2009 | A1 |
20090090074 | Klein | Apr 2009 | A1 |
20090100760 | Ewing | Apr 2009 | A1 |
20090100769 | Barrett | Apr 2009 | A1 |
20090107065 | LeBlang | Apr 2009 | A1 |
20090113820 | Deans | May 2009 | A1 |
20090134287 | Klosowski | May 2009 | A1 |
20090165399 | Campos Gines | Jul 2009 | A1 |
20090188192 | Studebaker et al. | Jul 2009 | A1 |
20090188193 | Studebaker et al. | Jul 2009 | A1 |
20090205277 | Gibson | Aug 2009 | A1 |
20090293395 | Porter | Dec 2009 | A1 |
20090313931 | Porter | Dec 2009 | A1 |
20100064590 | Jones et al. | Mar 2010 | A1 |
20100064601 | Napier | Mar 2010 | A1 |
20100146874 | Brown | Jun 2010 | A1 |
20100186313 | Stanford et al. | Jul 2010 | A1 |
20100212255 | Lesoine | Aug 2010 | A1 |
20100218443 | Studebaker et al. | Sep 2010 | A1 |
20100229472 | Malpas | Sep 2010 | A1 |
20100235206 | Miller et al. | Sep 2010 | A1 |
20100263308 | Olvera | Oct 2010 | A1 |
20100275544 | Studebaker et al. | Nov 2010 | A1 |
20100325971 | Leahy | Dec 2010 | A1 |
20100325989 | Leahy | Dec 2010 | A1 |
20110023381 | Weber | Feb 2011 | A1 |
20110041411 | Aragon | Feb 2011 | A1 |
20110056147 | Beaudet | Mar 2011 | A1 |
20110113709 | Pilz | May 2011 | A1 |
20110154766 | Kralic et al. | Jun 2011 | A1 |
20110162167 | Blais | Jul 2011 | A1 |
20110219720 | Strickland et al. | Sep 2011 | A1 |
20110247281 | Pilz et al. | Oct 2011 | A1 |
20110268916 | Pardue, Jr. | Nov 2011 | A1 |
20110296769 | Collins | Dec 2011 | A1 |
20110296778 | Collins et al. | Dec 2011 | A1 |
20110296789 | Collins et al. | Dec 2011 | A1 |
20110300386 | Pardue, Jr. | Dec 2011 | A1 |
20120151869 | Miller | Jun 2012 | A1 |
20120167505 | Krause | Jul 2012 | A1 |
20120186174 | LeBlang | Jul 2012 | A1 |
20120210658 | Logan | Aug 2012 | A1 |
20120297712 | Lutzner et al. | Nov 2012 | A1 |
20120317923 | Herdt et al. | Dec 2012 | A1 |
20130025222 | Mueller | Jan 2013 | A1 |
20130036688 | Gosain | Feb 2013 | A1 |
20130067832 | Collins et al. | Mar 2013 | A1 |
20130111840 | Bordener | May 2013 | A1 |
20130133277 | Lewis | May 2013 | A1 |
20140013678 | Deverini | Jan 2014 | A1 |
20140013695 | Wolynski et al. | Jan 2014 | A1 |
20140047780 | Quinn et al. | Feb 2014 | A1 |
20140059960 | Cole | Mar 2014 | A1 |
20140069035 | Collins et al. | Mar 2014 | A1 |
20140069040 | Gibson | Mar 2014 | A1 |
20140069050 | Bolin | Mar 2014 | A1 |
20140083046 | Yang | Mar 2014 | A1 |
20140090323 | Glancy | Apr 2014 | A1 |
20140130441 | Sugihara et al. | May 2014 | A1 |
20150096251 | McCandless et al. | Apr 2015 | A1 |
20150211227 | Collins et al. | Jul 2015 | A1 |
20160290030 | Collins et al. | Oct 2016 | A1 |
20170306624 | Graham et al. | Oct 2017 | A1 |
20180038103 | Neumayr | Feb 2018 | A1 |
Number | Date | Country |
---|---|---|
2005200682 | May 2005 | AU |
2012211472 | Feb 2014 | AU |
02137279 | Mar 2008 | CN |
102587693 | Jul 2012 | CN |
202299241 | Jul 2012 | CN |
102733511 | Oct 2012 | CN |
1045078 | Oct 2000 | EP |
1375804 | Jan 2004 | EP |
2128353 | Dec 2009 | EP |
2238872 | Oct 2010 | EP |
1739246 | Jan 2011 | EP |
2281964 | Feb 2011 | EP |
2988749 | Oct 2013 | FR |
898905 | Jun 1962 | GB |
S5215934 | Apr 1977 | JP |
S53000014 | Jan 1978 | JP |
S5484112 | Jun 1979 | JP |
S57158451 | Sep 1982 | JP |
H0310985 | Jan 1991 | JP |
H049373 | Mar 1992 | JP |
H0752887 | Dec 1995 | JP |
2576409 | Jan 1997 | JP |
10234493 | Sep 1998 | JP |
H10245918 | Sep 1998 | JP |
2000144997 | May 2000 | JP |
3137760 | Feb 2001 | JP |
2002364104 | Dec 2002 | JP |
2008073434 | Apr 2008 | JP |
2008110104 | May 2008 | JP |
20060066931 | Jun 2006 | KR |
9107557 | May 1991 | WO |
1997022770 | Jun 1997 | WO |
0058583 | Oct 2000 | WO |
0235029 | May 2002 | WO |
2007059003 | May 2007 | WO |
2010030060 | Mar 2010 | WO |
2010037938 | Apr 2010 | WO |
2016032537 | Mar 2016 | WO |
2016032538 | Mar 2016 | WO |
2016032539 | Mar 2016 | WO |
2016032540 | Mar 2016 | WO |
2016033429 | Mar 2016 | WO |
2016033525 | Mar 2016 | WO |
Entry |
---|
US 8,701,371, 04/2014, Collins et al. (withdrawn) |
Final Office Action dated Apr. 15, 2014, in U.S. Appl. No. 14/077,565, Arlan Collins, filed Jun. 8, 2010. |
Final Office Action dated Apr. 18, 2012, in U.S. Appl. No. 12/796,603, Arlan E. Collins, filed Jun. 8, 2010. |
Final Office Action dated Apr. 18, 2012, in U.S. Appl. No. 13/155,319, Arlan Collins, filed Jun. 7, 2011. |
Final Office Action dated May 9, 2013, in U.S. Appl. No. 13/155,319, Arlan Collins, filed Jun. 7, 2011. |
Final Office Action dated May 11, 2012, in U.S. Appl. No. 12/796,625, Arlan Collins., filed Jun. 8, 2010. |
Final Office Action dated May 6, 2014, in U.S. Appl. No. 12/796,603, Arlan E. Collins, filed Jun. 8, 2010. |
Final Office Action dated Oct. 28, 2014, in U.S. Appl. No. 13/700,429, Arlan K Collins, filed Nov. 27, 2012. |
International Search Report for PCT Application No. PCT/US2011/001039 dated Oct. 5, 2011. |
Non Final Office Action dated Dec. 27, 2013, in U.S. Appl. No. 14/077,565, Arlan Collins, filed Jun. 8, 2010. |
Non Final Office Action dated Jul. 18, 2013, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Non Final Office Action dated Nov. 8, 2012, U.S. Appl. No. 13/155,319, Arlan Collins, filed Jun. 7, 2011. |
Non Final Office Action dated Oct. 11 2011, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Non Final Office Action dated Oct. 19, 2011, in U.S. Appl. No. 13/155,319, Arlan Collins, filed Jun. 7, 2011. |
Non-Final Office Action dated Apr. 11, 2014, in U.S. Appl. No. 13/700,429, Arlan Collins, filed Nov. 27, 2012. |
Non-Final Office Action dated Jul. 18, 2013, in U.S. Appl. No. 12/796,603, Arlan E. Collins, filed Jun. 8, 2010. |
Non-Final Office Action dated Oct. 11, 2011, in U.S. Appl. No. 12/796,603, Arlan E. Collins, filed Jun. 8, 2010. |
Notice of Allowance Action dated Jun. 9, 2014, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Notice of Allowance Action dated Mar. 14, 2014, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Notice of Allowance Action dated May 6, 2014, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Notice of Allowance Action dated Nov. 15, 2013, in U.S. Appl. No. 12/796,625, Arlan Collins, filed Jun. 8, 2010. |
Notice of Allowance dated Jan. 7, 2015, in U.S. Appl. No. 12/796,625, Arlan K Collins, filed Jun. 8, 2010. |
Notice of Allowance dated Jul. 8, 2014, in U.S. Appl. No. 14/077,565, Arlan Collins, filed Jun. 8, 2010. |
Notice of Allowance dated Nov. 6, 2014, in U.S. Appl. No. 12/796,603, Arlan K Collins, filed Jun. 8, 2010. |
Notice of Allowance dated Nov. 13, 2014, in U.S. Appl. No. 14/077,565, Arlan K Collins, filed Nov. 12, 2013. |
Notice of Allowance dated Sep. 12, 2014, U.S. Appl. No. 12/796,625, Arlan K Collins, filed Jun. 8, 2010. |
Notice of Allowance dated Sep. 23, 2014, U.S. Appl. No. 12/796,603, Arlan K Collins, filed Jun. 8, 2010. |
“Beam to column connection”, TATA Steel, http://www.tatasteelconstruction.com/en/reference/teaching_resources/architectural_studio_reference/elements/connections/beam_to_column_connections, 2014. |
Canadian Office Action dated Jun. 9, 2016 received in CA App. No. 2,801,287. |
“Emerging Trends real estate”, accessed on Sep. 15, 2016 at https://web.archive.org/web/20140813084823/http://pwc.com.au/industry/real-estate/assets/Real-Estate-2012-Europe-Jan12.pdf, pp. 60 (2012). |
“Emerging Trends in Real Estate 2012 Executive Summary”, Urban Land Institute, Ch. 1, 2012, 3-13. |
“How to Soundproof a Ceiling—Soundproofing Ceilings”, http://www.soundproofingcompany.com/soundproofing-solutions/soundproof-a-ceiling/, Apr. 2, 2014, 1-7. |
“Insulspan Installation Guide”, Obtained at: http://www.insulspan.com/downloads/InstallationGuide.pdf on Feb. 2, 2016. |
“International Search Report and Written Opinion received for PCT US/2015/047383 dated Jan. 12, 2016”. |
“PCT International Search Report & Written Opinion dated Dec. 4, 2015, for Appln No. PCT/US15/47536”. |
“PCT Notification Concerning Availability of the Publication of the International Application”. |
“Structural Insulated Panel”, Wikipedia, http://www.en.wikipedia.org//wiki/Structural_insulated_panel, May 30, 2014. |
“Structural Insulated Panels”, SIP Solution, http://www.sipsolutions.com/content/structural-insulated-panels, Aug. 15, 2014. |
“US Apartment & Condominium Construction Forecast 2003-2017”, Statista, Inc. |
Azari, et al., “Modular Prefabricated Residential Construction—Constraints and Opportunities”, PNCCRE Technical Report #TR002, Aug. 2013, 90. |
Borzouie, Jamaledin et al., “Seismic Assesment and Reahbilitation of Diaphragms”, http://www.nosazimadares.ir/behsazi/15WCEE2012/URM/1/Roof.pdf, Dec. 31, 2011. |
Framecad, “FC EW 1—12mm Fibre Cement Sheet + 9mm MgO Board Wall Assembly”, 2013, 1. |
Giles, et al., “Innovations in the Development of Industrially Designed and Manufactured Modular Concepts for Low-Energy, Multi-Story, High Density, Prefabricated Affordable Housing”, Innovations in the Development of Industrially Designed and Manufactured Modular Concepts, Jun. 2006, 1-15. |
Gonchar, “Paradigm Shift—Multistory Modular”, Architectural Record, Oct. 2012, 144-148. |
Kerin et al., “National Apartment Market Report—2013”, Marcus & Millichap, 2013, 1-9. |
McIlwain: “Housing in America—The Next Decade”, Urban Land Institute, 2010, 1-28. |
McIlwain, “The Rental Boost From Green Design”, Urban Land, http://urbanland.uli.org/sustainability/the-rental-boost-from-green-design/, Jan. 4, 2012, 1-6. |
Riusillo, M. A. “Lift Slab Construction: its History, Methodology, Ecnomics, and Applications”, Abstract, International Concrete Reseacrh & Information Portal, Jun. 1, 1988, pp. 59-68, vol. 107, Special Publication. |
Shashaty, Andre, “Housing Demand”, Sustainable Communities, Apr. 2011, 14-18. |
Sichelman, “Severe Apartment Shortage Looms”, Urban Land, http://urbanland.uli.org/capital-markets/nahb-orlando-severe-apartment-shortage-looms/, Jan. 13, 2011, 1-2. |
Stiemer, S F., “Bolted Beam-Column Connections”, http://faculty.philau.edu/pastorec/Tensile/bolted_beam_column_connections.pdf, Nov. 11, 2007, 1-16. |
“Beam to column connection,” TATA Steel, accessed at https://web.archive.org/web/20140706075634/http://www.tatasteelconstruction.com/en/reference/teaching_resources/architectural_studio_reference/elements/connections/beam_to_column_connections, accessed on Mar. 1, 2017, pp. 3. |
“Emerging Trends in real estate,” Urban Land Institute, accessed at https://web.archive.org/web/20140813084823/http://pwc.com.au/industry/real-estate/assets/Real-Estate-2012-Europe-Jan12.pdf, pp. 60 (2012). |
“FC EW 1—12mm Fibre Cement Sheet+ 9mm MgO Board Wall Assembly”, FRAMECAD, pp. 2 (2013). |
“How to Soundproof a Ceiling—Soundproofing Ceilings,” accessed at https://web.archive.org/web/20140829130523/http://www.soundproofingcompany.com/soundproofing-solutions/soundproof-a-ceiling, accessed on Mar. 1, 2017, pp. 7. |
“Structural Insulated Panel;” Wikipedia, accessed at https://web.archive.org/web/20131207165431/http://en.wikipedia.org/wiki/Structural_insulated_panel, last modified on Nov. 20, 2013, pp. 3. |
“Structural Insulated Panels,” Whole Building Design Guide, accessed at https://web.archive.org/web/20140828133136/http://www.wbdg.org/resources/sips.php, accessed on Mar. 1, 2017, pp. 8. |
Azari, R., et al., “Modular Prefabricated Residential Construction—Constraints and Opportunities”, PNCCRE Technical Report #TR002, pp. 90 (Aug. 2013). |
Borzouie, J. and Mahdizadeh, A., “Seismic Assessment and Rehabilitation of Diaphragms—Technical report,” pp. 1-86 (2011). |
European Search Report for Patent Application No. 14891125.8, dated Jul. 8, 2016, pp. 4. |
Giles, H. and Lara, F., “Innovations in the Development of Industrially Designed and Manufactured Modular Concepts for Low-Energy, Multi-story, High-Density, Prefabricated Affordable Housing,” accessed at http://sitemaker.umich.edu/path-nsf giles/files/giles_and_lara_final.pdf, accessed on Jun. 16, 2015, pp. 1-15. |
Gonchar, J., “Paradigm Shift,” accessed at https://web.archive.org/web/20130326154444/http://continuingeducation.construction.com/article.php?L=5&C=943&P=2, Posted on Oct. 2012, pp. 2. |
Insulspan Installation Guide, Installation Guide, pp. 58 (Apr. 25, 2008). |
International Search Report and Written opinion for International Application No. PCT/US/2014/053613 dated Dec. 18, 2014, pp. 13. |
International Search Report and Written opinion for International Application No. PCT/US/2014/053614 dated Dec. 18, 2014, pp. 11. |
International Search Report and Written opinion for International Application No. PCT/US/2014/053615 dated Dec. 17, 2014, pp. 11. |
International Search Report and Written opinion for International Application No. PCT/US/2014/053616 dated Dec. 17, 2014, pp. 9. |
International Search Report and Written opinion for International Application No. PCT/US15/47536 dated Dec. 4, 2015, pp. 17. |
International Search Report and Written Opinion for International Application No. PCT/US2011/001039 dated Oct. 5, 2011, pp. 14. |
International Search Report and Written opinion for International Application No. PCT/US2015/047383 dated Jan. 12, 2016, pp. 14. |
Kerin, J. and Nadji , H., “National Apartment Report—2013”,pp. 1-62 (2013). |
McIlwain, J., “Housing in America—The Next Decade,” Urban Land Institute, pp. 36 (2010). |
McIlwain, J., “The Rental Boost From Green Design,” Urban Land, accessed at http://urbanland.uli.org/sustainability/the-rental-boost-from-green-design/, Jan. 4, 2012, pp. 7. |
Riusillo, M.A., “Lift Slab Construction: Its History, Methodology, Economics, and Applications,” International Concrete Abstracts Portal, Special Publication, vol. 107, pp. 59-68 (Jun. 1, 1988). |
Shashaty, A., “Housing Demand,” Sustainable Communities, pp. 3 (Mar./Apr. 2011). |
Sichelman, L., “NAHB/Orlando: Severe Apartment Shortage Looms,” accessed at http://urbanland.uli.org/capital-markets/nahb-orlando-severe-apartment-shortage-looms/, Urban Land, Jan. 13, 2011, pp. 2. |
Stiemer, S F., “Bolted Beam-Column Connections (Design and Cost Estimation),” Steel Design, pp. 1-16 (Nov. 11, 2007). |
Extended European Search Report for European Patent Application No. 14900469 dated Mar. 20, 2018, pp. 8. |
Number | Date | Country | |
---|---|---|---|
20170037613 A1 | Feb 2017 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 13700429 | US | |
Child | 15299163 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 12796603 | Jun 2010 | US |
Child | 13700429 | US | |
Parent | 12796625 | Jun 2010 | US |
Child | 12796603 | US |