The invention concerns in general the technical field of elevator systems. Especially the invention concerns elevator systems operating in a construction time use mode.
Typically, an elevator system comprises systems and/or devices for providing and collecting usage data of the elevator system during a normal operation of the elevator system. The normal operation in this context means operation of the elevator system in a finished, i.e. completed, building. In other words, in the normal operation the elevator system serves end-users of the finished building. The usage data may be important for an operator of the elevator system and/or an operator of the building, e.g. a facility manager of the building.
A construction time use (CTU) of the elevator systems is constantly increasing. Thus, there may also be need for providing and collecting usage data of the elevator system during the construction time use of the elevator system.
The following presents a simplified summary in order to provide basic understanding of some aspects of various invention embodiments. The summary is not an extensive overview of the invention. It is neither intended to identify key or critical elements of the invention nor to delineate the scope of the invention. The following summary merely presents some concepts of the invention in a simplified form as a prelude to a more detailed description of exemplifying embodiments of the invention.
An objective of the invention is to present a method, a computing unit, and an elevator system for managing usage data of an elevator system operating in a construction time use (CTU) mode. Another objective of the invention is that the method, the computing unit, and the elevator system for managing usage data of an elevator system operating in a construction time use (CTU) mode enable providing usage data of an elevator system operating in a construction time use (CTU) mode.
The objectives of the invention are reached by a method, a computing unit, and an elevator system as defined by the respective independent claims.
According to a first aspect, a method for managing usage data of an elevator system operating in a construction time use (CTU) mode is provided, wherein the method comprises: operating the elevator system in the CTU mode, obtaining statistical usage data of the elevator system, comparing the obtained statistical usage data to reference data, detecting that the obtained statistical usage data deviates at least partly from the reference data, and generating at least one control signal comprising an indication of the detected deviation to at least one operator system in response to the detection of the deviation.
The reference data may be predefined, dynamically adjusted, or defined based on previously obtained statistical usage data.
The step of detecting the deviation may comprise detecting that the obtained statistical usage data deviates from the reference data at least by a predefined difference value.
The statistical usage data may comprise at least one of: a number of departures of at least one elevator car during a predefined period of time, a number of departures of at least one elevator car from each departure floors during a predefined period of time, a number of arrivals of at least one elevator car to each destination floors during a predefined period of time, a weight of a load of at least one elevator car at the departure of said elevator car, and/or a response time of an elevator call.
The at least one control signal may further comprise at least one recommended action that depends on the obtained statistical usage data.
The statistical usage data of the elevator system may be obtained from an elevator control unit of the elevator system and/or a separate unit.
The at least one operator system may comprise an operator system of the elevator system, an operator system of a construction site comprising the elevator system, and/or an operator system of a building.
According to a second aspect, a computing unit for managing usage data of an elevator system is provided, wherein the elevator system is configured to operate in a construction time use (CTU) mode, wherein the computing unit comprises: a processing unit, and a memory unit storing at least one portion of computer program code, wherein the processing unit being configured to cause the computing unit at least to perform: obtain statistical usage data of the elevator system, compare the obtained statistical usage data to a reference data, detect that the obtained statistical usage data deviates from the reference data, and generate at least one control signal comprising an indication of the detected deviation to at least one operator system in response to the detection of the deviation.
The reference data may be predefined, dynamically adjusted, or defined based on previously obtained statistical usage data.
The detection of the deviation may comprise detecting that the obtained statistical usage data deviates from the reference data at least by a predefined difference value.
The statistical usage data may comprise at least one of: a number of departures of at least one elevator car during a predefined period of time, a number of departures of at least one elevator car from each departure floors during a predefined period of time, a number of arrivals of at least one elevator car to each destination floors during a predefined period of time, a weight of a load of at least one elevator car at the departure of said elevator car, and/or a response time of an elevator call.
The at least one control signal may further comprise at least one recommended action that depends on the obtained statistical usage data.
The statistical usage data of the elevator system may be obtained from an elevator control unit of the elevator system and/or a separate unit.
The at least one operator system may comprise an operator system of the elevator system, an operator system of a construction site comprising the elevator system, and/or an operator system of a building.
According to a third aspect, an elevator system for managing usage data of the elevator system is provided, wherein the elevator system is configured to operate in a construction time use (CTU) mode, wherein the elevator system comprises: at least one operator system, and a computing unit described above, wherein the computing unit and the at least one operator system are communicatively coupled with each other.
Various exemplifying and non-limiting embodiments of the invention both as to constructions and to methods of operation, together with additional objects and advantages thereof, will be best understood from the following description of specific exemplifying and non-limiting embodiments when read in connection with the accompanying drawings.
The verbs “to comprise” and “to include” are used in this document as open limitations that neither exclude nor require the existence of unrecited features. The features recited in dependent claims are mutually freely combinable unless otherwise explicitly stated. Furthermore, it is to be understood that the use of “a” or “an”, i.e. a singular form, throughout this document does not exclude a plurality.
The embodiments of the invention are illustrated by way of example, and not by way of limitation, in the figures of the accompanying drawings.
The elevator system 100 according to the invention locates in a building, which is under construction. In other words, the elevator system 100 according to the invention is configured to operate in a construction time use (CTU) mode. The elevator system 100 may be configured to operate in the CTU mode during the construction of the building. In the CTU mode the elevator system 100 may be configured to transport and/or serve people, e.g. construction workers, and/or material, e.g. construction material, during the construction. After completion of the construction project of the building, the elevator system 100 may be converted into a final permanent elevator system of the building and configured to operate in a normal operation mode. The normal operation of an elevator system is used in this patent application to mean operation of the elevator system in a finished, i.e. completed, building to serve end-users of the finished building.
At a step 220, the computing unit 112 obtains statistical usage data of the elevator system 100. The statistical usage data may be obtained from the elevator control unit 106 and/or from a separate unit 302. If the computing unit 112 is the elevator control unit 106, the elevator control unit 106 may itself provide the statistical usage data of the elevator system 106 and/or obtain the statistical usage data from the separate unit 302.
At a step 230, the computing unit 112 compares the obtained statistical usage data to reference data. The reference data may be predefined, dynamically adjusted, or defined based on previously obtained statistical usage data. The reference data may be a single reference value or a range of reference values. Alternatively or in addition, the reference data may be dependent on the obtained statistical usage data. In other words, the obtained statistical usage data of the elevator system 100 is compared to respective reference data. For example the obtained number of departures of the at least one elevator car 102 during the predefined period of time may be compared to a reference value or a reference range of values representing number of departures of the at least one elevator car 102 during the predefined period of time.
At a step 240, the computing unit 112 detects that the obtained statistical usage data deviates from the reference data at least partly. Depending on the obtained statistical usage data the deviation may be exceeding the reference data, meeting the reference data, or being less than the reference data. The term “meet” in the context of the reference data is used in this patent application to mean that a predefined condition is fulfilled. For example, the predefined condition may be that the reference data is reached and/or exceed. The step of detecting the deviation may comprise detecting that the obtained statistical usage data deviates from the reference data at least by a predefined difference value. The predefined difference value may for example be dependent on the obtained statistical usage data.
At a step 250, the computing unit 112 generates at least one control signal to the at least one operator system 114 in response to the detection of the deviation at the step 240. The at least one control signal may comprise an indication of the detected deviation. The at least one control signal may further comprise at least one recommended action that depends on the obtained statistical usage data. The at least one recommended action may be e.g. a maintenance action, at least one instruction to one or more users of the elevator system, and/or load related action.
According to an a non-limiting example case, wherein the statistical usage data comprises the number of departures of the at least one elevator car 102 during the predefined period of time, e.g. the number of departures per 1 hour, and the computing unit 112 detects that the obtained number of departures of the at least one elevator car 102 exceeds the respective reference data, e.g. reference number of departures per 1 hour. In response to the detection of the deviation the computing unit 112 may generate the at least one control signal to the at least one operator system 114, wherein the at least one control signal may comprise at least one maintenance action, e.g. a need for maintenance of the at least one elevator car 102.
According to another non-limiting example case, wherein the statistical usage data comprises the number of departures of the at least one elevator car 102 from each departure floor during the predefined period of time, e.g. the number of departures per 1 week, and the computing unit 112 detects that the obtained number of departures of the at least one elevator car 102 from at least one departure floor exceeds the respective reference data, e.g. reference number of departures per 1 week. In response to the detection of the deviation the computing unit 112 may generate the at least one control signal to the at least one operator system 114, wherein the at least one control signal may comprise at least one maintenance action, e.g. a need for maintenance at said at least one departure floor and/or condition inspection at said at least one departure floor.
According to another non-limiting example case, wherein the statistical usage data comprises the number of arrivals of the at least one elevator car 102 from each destination floor during the predefined period of time, e.g. the number of arrivals per 1 week, and the computing unit 112 detects that the obtained number of arrivals of the at least one elevator car 102 from at least one destination floor exceeds the respective reference data, e.g. reference number of arrivals per 1 week. In response to the detection of the deviation the computing unit 112 may generate the at least one control signal to the at least one operator system 114, wherein the at least one control signal may comprise at least one maintenance action, e.g. a need for maintenance at said at least one destination floor and/or condition inspection at said at least one destination floor.
According to another non-limiting example case, wherein the statistical usage data comprises weight of the load of the at least one elevator car 102 at the departure of the at least one elevator car 102, and the computing unit 112 detects that the obtained weight of the load in the at least one elevator car 102 at the departure of the at least one elevator car 102 is less than the respective reference data, e.g. a reference weight. In response to the detection of the deviation the computing unit 112 may generate the at least one control signal to the at least one operator system 114, e.g. to the operator of the construction site, wherein the at least one control signal may comprise at least one load related action, e.g. a notification of missing material and/or need of more material. For example, if the load comprises material, e.g. construction material, to be transported to a specific destination floor and the computing unit 112 detects that the weight of the load is less than the reference weight, e.g. expected weight of the material to be transported, it indicates that at least some material may be missing and more material may be needed.
According to another non-limiting example case, wherein the statistical usage data comprises the response time of an elevator call, and the computing unit 112 detects that the obtained response time exceeds the respective reference data, e.g. a reference response time. In response to the detection of the deviation the computing unit 112 may generate the at least one control signal to the at least one operator system 114, e.g. to the operator of the construction site, wherein the at least one control signal may comprise at least one instruction to one or more users of the elevator system, e.g. construction workers. The at least one instruction may comprise e.g. instructions to adapt a schedule and/or a route of the one or more users.
The specific examples provided in the description given above should not be construed as limiting the applicability and/or the interpretation of the appended claims. Lists and groups of examples provided in the description given above are not exhaustive unless otherwise explicitly stated.
Number | Date | Country | |
---|---|---|---|
Parent | PCT/FI2020/050565 | Sep 2020 | US |
Child | 18105403 | US |