Excavators used for digging slurry walls range in size from approximately 190,000 to 240,000 or more pounds. These Excavators are equipped with custom sticks and/or booms, to extend the digging depths from 50 feet to 90 feet or more.
When used to excavate slurry walls, the trenching excavator starts at the ground surface and digs to the required depths per engineer requirements. The operating cost of the machine is the same when digging at shallow depths and at the maximum depths. But typically, there is no way around using a larger, more expensive excavator (e.g., costing $50,000 to $80,000 or more per month) to dig both the shallow and deeper depths, even though a less expensive machine could handle the shallower depths. That is, the contractor often has to start the job with a machine capable of digging to the maximum required depths on the plans/design because it is not cost effective to have the larger excavator move out of the way to allow a smaller machine to dig first. In addition, the larger machine would just sit dormant while the smaller machine digs and vice versa. Therefore, this would simply increase the overall cost, for little if any increase in production efficiency (i.e., having just increased the cost for very little increase in production, if any).
However, larger excavators are difficult to operate with an open, continuous trench in slurry wall construction. Large excavators are cumbersome, and still risk collapsing the trench when straddling the trench trying to reset the mats on a new set. The larger machines cannot straddle the trench for very long to allow use of two machines working on the same heading. The excavators weigh too much and the distance between the tracks are too narrow (the trench might collapse).
Mats can be used, but the footprint is still small, and still risk collapsing the trench. In addition, moving mats take a long time, as sections of the mat need to be moved one at a time, while still having to support the excavator with other sections of the mats, which can be very time consuming. Thus, typically the only time contractors use mats are when they are working on unstable/soft soil.
There are two types of support equipment that are commonly used while digging a slurry wall, which are used for the backfill operations. First, an excavator (e.g., Komatsu PC 350 or the like); and second, a dozer (e.g., Komatsu D65, or Cat D6-8 dozer, or the like). There are also multiple pumps, pipe, de-sanding machines, fork lifts, storage units, etc., that are utilized for digging slurry walls. When production is very slow due to extreme depths, the support equipment can sit dormant a considerable amount of time. That is, the support equipment cannot backfill until the trenching excavator is far enough ahead of the toe of the backfill slope. Everything is at a standstill or at a very slow pace, waiting for the larger excavator to finish a set.
There has not been a way to utilize two excavators on the same heading in an open trench slurry wall 2. That is, a large excavator 1 had to dig from the surface 3 at varying depths 4a as shown in
Contractors still have to maintain all of the support equipment and personnel, but they are utilized based on the production rate of the trenching excavator. If the job has very tight time constraints, the contractor has to mobilize two of every type of equipment and dig two separate headings.
By way of illustration, a contractor may have a very stringent time constraint where a project has to be completed by the end of the year; before the cold weather arrived. It is difficult to dig slurry walls in freezing temperatures, because of the high percentage of moisture in the spoils and backfill. Part of the wall depths are in the range of 40 to 60 feet. A PC 800 Komatsu or the like can be utilized, with a custom boom and stick. But maximum digging depths are about 60 feet. The other approximately 40% of the wall depths are up to about 70 feet or more. A PC 1250 Komatsu or the like can be used, with a custom boom and stick with maximum digging depth of about 90 feet.
In this illustration, the contractor may mobilize two slurry wall crews, with two of everything. For example, the contractor may mobilize two small excavators and two dozers for backfilling at the two slurry wall headings. This requires two crews to man both operations, which also entails housing and meal allowances. This also requires two pumps to supply slurry to the different slurry wall headings, along with hundreds/thousands of feet of slurry pipe, two de-sanders, valves, and a host of smaller equipment/supplies. This is a big expense to incur at the start and end of a project, including the mobilization and de-mobilization of equipment, which approximately doubles the cost.
In addition, larger excavators 1 cannot straddle a trench 5 for very long to allow use of two excavators 1 working on the same heading. The excavators 1 weigh too much and the distance between the tracks are too narrow. Large excavators 1 are cumbersome, and risk collapsing the trench 5 when straddling the trench, as illustrated in
A stabilizing system for excavators including an extended center frame, mat(s), and/or trench support(s) is disclosed herein. In an example, the extended center frame includes a frame component for mounting between opposing tracks of the excavator and a base portion of the excavator. The frame component extends beyond the base portion of the excavator on both sides to move the opposing tracks apart from one another relative to the opposing tracks being mounted to the base portion.
A lift may be provided to raise and lower the mat below the excavator so that the mat stays with the excavator when the excavator moves.
Both the extended center frame and the mat(s) relieve pressure on the ground due to weight of the excavator.
The trench support relieves any remaining pressure toward the open trench, and reduces or eliminates the sidewalls from caving in. By implementing the trench support, it might not be necessary to widen the tracks of the excavator as far, thus further reducing time-related costs. In addition, the trench support may also enhance safety of the trenching operations.
Before continuing, it is noted that as used herein, the terms “includes” and “including” mean, but is not limited to, “includes” or “including” and “includes at least” or “including at least.” The term “based on” means “based on” and “based at least in part on.”
The trenching arm 8 of the excavator 1 can be operated (e.g., by an operator in the cab 7) to dig a trench 10 in the ground 12. As the trench 10 is dug deeper into the ground, pressure from the weight of the excavator 1 is applied both in a downward direction and toward the trench 10, as indicated by arrows 14. This pressure may cause the trench to collapse, thus destabilizing the ground that the excavator is sitting on. Depending on the extent of this destabilizing of the ground, the excavator may fall over, e.g., as illustrated in
In an example, the frame component 102 of the center frame 100 is bolted (or otherwise attached, e.g., at 7a-d) onto the base portion 6 of the excavator 1. For example, the frame component 102 may be bolted onto the base portion 6 where the opposing tracks 9a and 9b are attached, so that no modification to the excavator 1 is necessary. The frame component 102 may also be bolted onto the track frame of the opposing tracks 9a and 9b, again using existing bolt holes and requiring no modification to the excavator 1 itself. This may be particularly advantageous, for example, where the excavator is rented and cannot be modified by drilling new holes. This also maintains the structural integrity of the original equipment.
For purposes of illustration, the extended center frame 100 can be bolted onto standard excavators (e.g., 190,000-240,000 pound or higher; or smaller machines that have bolted on tracks). This configuration widens the overall footprint of the excavator 1, and reduces the overall ground pressure. There is no need to make permanent modifications to the excavator 1, thus allowing the extended center frame 100 to be installed on a rented machine.
The frame component 102 widens a footprint 104 of the excavator 1. In an example, the frame component 102 provides a width 104 or “footprint” of about 16 to 28 feet (although any suitable footprint may be achieved based on the size of the frame component 102). By way of illustration, compare the footprint 104′ of the excavator 1 shown in
In an example, the extended center frame 100 may also include one or more stabilizer 108a and 108b. The stabilizer(s) 108a and 108b may be extended from the excavator 1 to further reduce ground pressure, e.g., as indicated by relieving some of the pressure 14′ at the stabilizers 108a and 108b, as illustrated by arrows 110.
It is noted that the stabilizers 108a and 108b may be any desired width, as indicated in the drawings by the dashed lines. In addition, more than one stabilizer may be provided on each side, e.g., as shown in
As shown in
In an example, the extended center frame 100, the mat 120, and the trench support 122 may be implemented in addition to, or instead of the other components of the stabilizing system. For example, the extended center frame 100 may be implemented by itself, or in combination with the mat 120 and/or the trench support 122. Likewise, the mat 120 may be implemented by itself, or in combination with the extended center frame 100 and/or the trench support 122. And the trench support 122 may be implemented by itself and/or in combination with the extended center frame 100 and/or the mat 120.
The mat 120 may be provided on the ground over the trench 10 that has already been dug, so that the excavator 1 can be moved onto the mat 120. The mat 120 may be implemented to spread pressure from the weight of the excavator 1 more evenly across the ground and reduce ground pressure. The stabilizer(s) 108 may be lowered onto the mat to further spread ground pressure from the excavator 1.
In an example, the mats 120 can be implemented on large excavators to redistribute the ground pressure. With the ability to straddle the trench, when the excavator 1 starts a new set, the mats 120 can be pulled into place. As such, lifting sections one at a time (because they were not able to straddle an open trench safety) is not necessary, saving time and money. In an example, the mats 120 can be about 4 to 6 inches thick
In an example, the mat 120 is attached to at least one of the opposing tracks 9a and 9b of the excavator 1. The mat 120 may further be attached to the trench support 122 by at least one pin 124a-d, as illustrated in
The trench support 122 may be implemented in addition to, or instead of the mat 120. In an example, the trench support 122 is connected to the mat 120. As such, the trench support 122 stays substantially beneath the excavator 1, where it is needed. In addition, this configuration enables the trench support 122 to move with the mat 120 so that the trench support 122 does not need to be moved separately from the mat 120.
In an example, the trench support 122 forms a plurality of voids 126. These voids may be formed by the structure of the trench support 122. The voids and the structure provide structural integrity. In addition, the voids provide openings, e.g., for a slurry to pass through without having to remove the trench support 122.
The trench support 122 may be substantially the same width as a bucket 125 (
The stabilizing system 101 enables a larger excavator 1 to operate while straddling an open trench and concentrate on the deeper depths. At the same time a smaller excavator 1′ (e.g., operating at a fraction of the cost) can dig the shallower depths, thereby increasing production.
The stabilizing system 101 implemented for the larger excavator, while also enabling the smaller trenching excavator to work simultaneously, utilizes all equipment to its full potential and reduces project costs. For example, finishing a project faster results in cost savings related to hourly employees and all equipment for the job (e.g., excavators, dozers, pumps, pipes, office trailers de-sanding machines, inspectors, etc.).
By way of illustration, production can be increased (e.g., by 100% or more) without increasing the cost, other than the cost of the first pass excavator. The percent in increased production, translates to almost the same percentage cut in overall cost (the only constant, is the cost of bentonite, mixing the slurry, and the design).
In addition, the stabilizing system 101 may be implemented by both size excavators 1 and 1′. This reduces the acquisition cost for a contractor that has both sizes of excavators in their fleet. That is, a single extended track frame can be implemented that fits both excavators 1 and 1′. For example, an extended center frame 100 for a Komatsu PC 800 or the like will fit other PC 800's.
It is noted that the examples shown and described are provided for purposes of illustration and are not intended to be limiting. Still other examples are also contemplated.
This application claims the priority benefit of U.S. Provisional Patent Application No. 62/313,280 filed Mar. 25, 2016 titled “Extended Center Frame For Excavators” of Ruben D. Hernandez, hereby incorporated by reference as though fully set forth herein.
Number | Name | Date | Kind |
---|---|---|---|
2914127 | Ricouard | Nov 1959 | A |
3037571 | Zelle | Jun 1962 | A |
4018458 | Shumaker | Apr 1977 | A |
4548528 | Bell | Oct 1985 | A |
5598896 | Haest | Feb 1997 | A |
10087595 | Williamson | Oct 2018 | B2 |
Number | Date | Country | |
---|---|---|---|
20170275850 A1 | Sep 2017 | US |
Number | Date | Country | |
---|---|---|---|
62313280 | Mar 2016 | US |