Embodiments pertain to a standby power system, and more particularly to a standby power system that predicts a need to supply power to a load based on data received from a sensor and acts to minimize start time of a generator.
Electric generators are typically used to provide electrical power. One common use of electric generators is as a standby power source. A standby power source typically provides power to a load when a primary power source is unable to power the load.
One common type of electric generator includes an internal combustion engine. The internal combustion engine drives an electrical alternator that produces alternating electricity.
Existing standby generator systems utilize an automatic transfer switch (ATS) to monitor the primary power source. The ATS determines that the primary power source is unavailable to provide power to the load, and provides a signal to the standby power source that it should start. Once the standby power source receives this signal, it will initiate a start sequence for the standby power source.
One of the drawbacks with such existing standby power systems is that there is typically a delay between the primary power source becoming unavailable and the standby power source becoming available. One factor causing the delay is that there is typically a gap in time to determine that the primary source is unavailable. This delay is utilized to avoid unnecessary starting of the standby power source when there is a momentary interruption in power provided by the primary power source.
Another factor causing the delay is that the starting sequence of engine driven generators takes valuable time. This delay can be especially problematic in standby power systems where the standby power source requires pre-start preparation. This pre-start preparation causes an increase in start time of the standby power source thereby extending the time that is load is without power.
The following description and the drawings sufficiently illustrate specific embodiments to enable those skilled in the art to practice them. Other embodiments may incorporate structural, logical, electrical, process, and other changes. Portions and features of some embodiments may be included in, or substituted for, those of other embodiments. Embodiments set forth in the claims encompass all available equivalents of those claims.
The standby power system 10 further includes a generator 14 that is also adapted to supply power to the load 13 through switch 17. As an example, the generator 14 may include an internal combustion engine that drives an alternator.
The standby power system 10 further includes a generator controller 15 that operates the generator 14 and exchanges data with the sensor 11. The generator controller 15 predicts a need to supply power to the load 13 based on data received from the sensor 11. The generator controller 15 then acts to minimize the time to availability of the generator 14 based on the prediction. The actions may include performing, pre-starting functions to minimize the start time of the generator 14.
Minimizing the start time of the generator 14 based on the prediction may reduce the amount of time during which the load 13 is not receiving power from either the primary source 12 or the generator 14. Decreasing the amount of time in which the load 13 is not supplied with power may allow for (i) the use of smaller uninterruptible power supplies; and/or (ii) reduced facility down time due to lack of power.
In some embodiments, the generator controller 15 may operate an oil pump (not shown) to lubricate mechanical components (not shown in the internal combustion engine in order to minimize start time of the generator 14 once the primary power source 12 is unable to provide power to the load 13. Operating the oil pump to lubricate the mechanical components may (i) allow quicker starting of the internal combustion engine; (ii) decrease wear on bearing surface thereby increasing the operating life of the internal combustion engine; and/or (iii) provide oil pressure to oil-actuated speed governors or fuel injection systems before generator 14 starting.
Embodiments are also contemplated where the generator controller 15 activates heating elements (not shown) that enhance combustion in the internal combustion engine in order to minimize start time of the generator 14 once it is determined that the generator 14 should be started. Heating elements may be used to (i) heat intake air that is used for combustion or (ii) preheat the combustion chamber. Heating intake air that is used for combustion may permit prompt compression-ignition of an air-fuel mix under cold conditions thereby permitting quicker starting under cold conditions.
In some embodiments, the generator controller 15 may operate air inlet louvers on an enclosure (not shown) for the generator 14 to permit the flow of combustion and cooling air to the generator 14 in order to minimize start time of the generator 14 once it is determined that the generator 14 should be started. Opening the air inlet louvers based on a predicted toss of power from the primary power source 12 may permit quicker starting of the generator 14 because the louvers may not be able to open while the generator 14 is cranking. The louvers may not be able to open while the generator 14 is cranking because (i) the louvers obtain power from generator cranking battery; and/or (ii) the air required by the generator 14 while cranking creates a pressure head that may prohibit the louvers from opening.
Embodiments are also contemplated where the generator controller 15 operates other starting aids. As an example, some type of fluid (e.g., ether, alternative fuels or some other fuel additive) may be injected for combustion to permit quicker starting of the internal combustion engine that is part of the generator 14. As another example, fuel preparation equipment (e.g., a fuel heater, pump or a fuel cooler) may be activated to improve starting of a combustion engine.
It should be noted that the standby power system 10 may further include a server 16 that allows exchanging information with the generator controller 15 and other devices on a network (e.g., the Internet I). At least one of the server devices 16 and the generator controller 15 may predict a need to supply power to the load 13 based on data received from the sensor 11.
The standby power system 30 further includes a notification system 31 that predicts a need for the generator 34 to supply standby power to the load 33. In some embodiments, the notification system 31 may monitor characteristics of power that is supplied by a primary power source 32. As an example, the notification system 31 may be used to sense abnormalities in the power that is supplied by the primary power source 32 to the load 33.
The standby power system 30 further includes a generator controller 35 that operates the generator 34 and exchanges data with the notification system 31 via a network (e.g., the Internet I). The generator controller 35 predicts a need to supply power to the load 33 based on data received from the notification system 31 relating to power that is supplied by the primary power source 32. The generator controller 35 then acts to minimize a start time of the generator 34 based on the prediction.
Minimizing the start time of the generator 34 based on the prediction may reduce the amount of time during which the load 33 is not receiving power from either the primary source 32 or the generator 34. Decreasing the amount of time in which the load 33 is not supplied with power may allow for (i) the use of smaller uninterruptible power supplies; and/or (ii) reduced facility down time due to lack of power.
Similarly, as discussed above with regard to generator controller 15, the generator controller 35 may (i) operate an oil pump (not shown) to lubricate mechanical components (not shown) in the internal combustion engine in order to minimize start time of the generator 34 once the primary power source 32 is unable to provide power to the load 33; (ii) activate heating elements (not shown) that enhance combustion in the internal combustion engine in order to minimize start time of the generator 34 once the primary power source 32 is unable to provide power to the load 33; and/or (iii) operate air inlet louvers on an enclosure (not shown) for the generator 34 to permit the flow of combustion and cooling air to the generator 34 in order to minimize start time of the generator 34 once the primary power source 32 is unable to provide power to the load 33.
It should be noted that the standby power system 30 may further include a server 36 that exchanges information with the generator controller 35 via a network (e.g., the Internet I). At least one of the server 36 and the generator controller 35 may predict a need to supply power to the load 33 based on data received from the notification system 31 or other information available to the server 36.
The standby power system 50 further includes a controller 55 that monitors power that is provided to a load 53 by a primary power source 52. The controller 55 starts the generator 54 when the controller 55 anticipates a need for the generator 54 to supply power to the load 53.
In the example embodiment that is illustrated in
In some embodiments, the controller 55 may monitor characteristics of power that is supplied by a primary power source 52. As an example, the controller 55 may be used to sense abnormalities in the power that is supplied by the primary power source 52 to the load 53.
Minimizing the time to availability of the generator 54 based on the prediction may reduce the amount of time during which the load 53 is not receiving power from either the primary source 52 or the generator 54. Decreasing the amount of time in which the load 53 is not supplied with power may allow for (i) the use of smaller uninterruptible power supplies; and/or (ii) reduced facility down time due to lack of power.
Similarly as discussed above with regard to generator controllers 15, 35, the controller 55 may (i) operate an oil pump (not shown to lubricate mechanical components (not shown) in the internal combustion engine in order to minimize start time of the generator 54 once the primary power source 52 is unable to provide power to the load 53; (ii) activate heating elements (not shown) that enhance combustion in the internal combustion engine in order to minimize start time of the generator 54 once the primary power source 52 is unable to provide power to the load 53; and/or (iii) operate air inlet louvers on an enclosure (not shown) for the generator 54 to permit the flow of combustion and cooling air to the generator 54 in order to minimize start time of the generator 54 once the primary power source 52 is unable to provide power to the load 53.
It should be noted that the standby power system 50 may further include a server 56 that exchanges information with the generator controller 55 via a network (e.g., the Internet I). At least one of the server 56 and the controller 55 may predict a need to supply power to the load 53 based on data collected by the controller relating to power supplied by the primary power source 52 (or other information available to the server 56).
The example standby power systems 10, 30, 50 described herein may serve to perform pre-start preparation for the standby power source. This pre-start preparation for the standby power source may permit quicker starting for the standby power source thereby minimizing the time that the load is in an undesirable unpowered state.
The Abstract is provided to comply with 37 C.F.R. Section 172(b) requiring an abstract that will allow the reader to ascertain the nature and gist of the technical disclosure. It is submitted with the understanding that it will not be used to limit or interpret the scope or meaning of the claims. The following claims are hereby incorporated into the detailed description, with each claim standing on its own as a separate embodiment.
Number | Name | Date | Kind |
---|---|---|---|
2546410 | Schwendner et al. | Mar 1951 | A |
2832896 | Stineman et al. | Apr 1958 | A |
3300647 | Gogia et al. | Jan 1967 | A |
3489914 | Taylor | Jan 1970 | A |
4233555 | Roche | Nov 1980 | A |
4302683 | Burton | Nov 1981 | A |
4384213 | Bogel | May 1983 | A |
4405892 | Staerzl | Sep 1983 | A |
4469071 | Bassi et al. | Sep 1984 | A |
4625123 | Gillett et al. | Nov 1986 | A |
4899706 | Sasaki | Feb 1990 | A |
5252905 | Wills et al. | Oct 1993 | A |
5256959 | Nagano et al. | Oct 1993 | A |
5332927 | Paul et al. | Jul 1994 | A |
5625276 | Scott et al. | Apr 1997 | A |
5635768 | Birch et al. | Jun 1997 | A |
5694027 | Satake et al. | Dec 1997 | A |
5703410 | Maekawa | Dec 1997 | A |
5730098 | Sasaki et al. | Mar 1998 | A |
5886890 | Ishida et al. | Mar 1999 | A |
6191500 | Toy | Feb 2001 | B1 |
6313544 | Mongia et al. | Nov 2001 | B1 |
6605878 | Arce | Aug 2003 | B1 |
6657416 | Kern et al. | Dec 2003 | B2 |
6844706 | Pinkerton, III et al. | Jan 2005 | B2 |
6894403 | Shinogi | May 2005 | B2 |
6923168 | Bryde | Aug 2005 | B2 |
7180210 | Jorgenson et al. | Feb 2007 | B1 |
8049348 | Czajkowski | Nov 2011 | B2 |
20030014200 | Jonker et al. | Jan 2003 | A1 |
20040059542 | Apostolides | Mar 2004 | A1 |
20040164618 | Bryde | Aug 2004 | A1 |
20050184589 | Fujita | Aug 2005 | A1 |
20060244327 | Kundel | Nov 2006 | A1 |
20070262661 | Ai | Nov 2007 | A1 |
20090164806 | Dishman et al. | Jun 2009 | A1 |
20100102637 | Dozier et al. | Apr 2010 | A1 |
20100207454 | Jagota et al. | Aug 2010 | A1 |
20100269776 | Mizuno | Oct 2010 | A1 |
20110149624 | Yamanaka | Jun 2011 | A1 |
20110272952 | Richardson et al. | Nov 2011 | A1 |
20110291411 | Folken | Dec 2011 | A1 |
20120007431 | Jang et al. | Jan 2012 | A1 |
20120242451 | Tanaka et al. | Sep 2012 | A1 |
20140028102 | Frampton | Jan 2014 | A1 |
20140210256 | Raats et al. | Jul 2014 | A1 |
20150115745 | Wang et al. | Apr 2015 | A1 |
Number | Date | Country |
---|---|---|
201781325 | Mar 2011 | CN |
1006641 | Jun 2000 | EP |
WO-2012154451 | Nov 2012 | WO |
Entry |
---|
European Application No. 13003307.9, Extended European Search Report dated Sep. 26, 2013, 8 pgs. |
European Application No. 13003307.9, Response filed Jul. 2, 2014 to European Sesrch Report dated Sep. 26, 2013, 17 pgs. |
European Application No. 13003380.6, European Search Report dated Feb. 17, 2014, 9 pgs. |
European Application No. 13003380.6, Response filed Sep. 17, 2014 to European Search Report dated Feb. 17, 2014, 18 pgs. |
U.S. Appl. No. 13/559,643, Non Final Office Action mailed May 7, 2015, 13 pgs. |
Chinese Application Serial No. 201310271829.0, Office Action mailed Feb. 27, 2015, (w/ English Translation), 19 pgs. |
“Chinese Application Serial No. 201310261793.8, Office Action mailed Mar. 23, 2015”, (w/ English Summary), 11 pgs. |
“European Application Serial No. 15155923, Extended European Search Report mailed Aug. 7, 2015”, 6 pgs. |
Number | Date | Country | |
---|---|---|---|
20140002032 A1 | Jan 2014 | US |