1. Technical Field
The present disclosure relates to a static testing and calibrating method for PID (proportion-integration-differentiation) link of control system of wind turbine.
2. Description of the Related Art
With the rapid development of wind farm industry, the installed wind power capacity in the power network operation has reached 100 million kilowatts. The wind power output often brings a certain impact to the operation stability of the power grid.
In order to meet the challenge and solve the problem of security and stability, the power grid needs advanced technology and management measures. These are inseparable from the simulation study of wind turbines and the wind farm power system. Thus mathematical modes and accurate parameters of the wind turbine and wind farm need to be researched. However, it is not convenient and low in accuracy to test the parameters at present.
What is needed, therefore, is a static testing and calibrating method for PID link of control system of wind turbine that can overcome the above-described shortcomings.
Many aspects of the embodiments can be better understood with reference to the following drawings. The components in the drawings are not necessarily drawn to scale, the emphasis instead being placed upon clearly illustrating the principles of the embodiments. Moreover, in the drawings, like reference numerals designate corresponding parts throughout the several views.
The disclosure is illustrated by way of example and not by way of limitation in the figures of the accompanying drawings in which like references indicate similar elements. It should be noted that references to “an” or “one” embodiment in this disclosure are not necessarily to the same embodiment, and such references mean at least one.
In order to analyze the impact of wind power on the dynamic characteristics of the power system, a dynamic mathematical model of the wind farm and the wind turbine need to be established.
Wind turbine is a complex system that contains multi-disciplinary working principle. The working principle of the wind turbine blade is based on the aerodynamics. The working principle of the transmission system is related to mechanical theory. The electromechanical energy conversion and the wind power control systems are widely involved in control theory and electrical works. Therefore, a test validation is very necessary and useful after the completion of the dynamic modeling of wind turbines.
A static testing and calibrating method for PID link of control system of wind turbine is applied to the modeling and commissioning of the wind turbine control system. The method is applied to test the PID link of the pitch angel control model, the torque control model, and the reactive power control model in the wind turbine control system (master PLC). The static testing and calibrating method for PID link of control system of wind turbine belongs to the static test range.
The method is based on time-domain test method and frequency-domain test method. In the time-domain test method, the parameters of the system model is obtained by inputting certain values into the control system, and analyzing the model structure of the control system based on the time domain representation of outputs. The method is a direct way but more accurate, and can provide all the information of the time-domain response of the system. Because the time-domain analysis analyze the system directly in the time-domain, thus the time-domain analysis is intuitive and accurate. The outputs of the system can be obtained through the differential equation or transfer function.
In the frequency-domain test method, the frequency-domain analysis takes frequency as independent variable, the signal value of each frequency component (power value or energy value) as the dependent variable. The spectrum analyzer can analyze the signal, and nonlinear distortion coefficient of linear system. The harmonic components of the signal can be determined, and the spectrum occupancy of signal ban be recognized. The frequency-domain test method adopts multi-frequency signal as the test signals, and utilize white noise signal as the test signals.
Referring to
In step al, the PID control link test comprises:
In step a11, a torque control link of fans controls the active power of the wind turbine. Referring to
The relative parameters and variables are listed:
In step a12, a reactive power control link of fans controls the reactive power of the wind turbine. Referring to
The reactive power control PID test focuses on the closed-loop control link after the open-loop control logic generates the reactive power instruction. The input of the reactive power control link is reactive power deviation (measured reactive power-reactive power reference value). The master control link is PI controller. The PI output passes through a first limiting link of a maximum reactive current Iqmax and a minimum reactive current Iqmin, and a second limiting link of a maximum reactive current variety dIg/dtmax and a minimum reactive current variety dIq/dtmin. The final output is a given reactive current Iq. The final output is transferred to the main frequency converter (not shown) to carry out reactive control.
The relative parameters and variables are listed:
In step a13, a pitch angle control link of fans controls the pitch angle of the wind turbine. Referring to
The input of the rotation speed channel control link is rotation speed deviation (measured angular velocity of engine-angular velocity reference value of generator). The master control link is proportional and integral PI controller.
The input of the active power channel control link is active power deviation (active power instruction-maximum active power Pmax can be issued at this time). The master control link is proportional and integral PI controller. Furthermore, the value of Pmax can be calculated based on various conditions such as wind speed. Due to rapidity of control, the Pmax is adopted instead of the actual active power P because the variety of actual active control is slower than that of the Pmax.
A pitch speed instruction is generated by summing the output of the PI control of rotation speed channel control link and the active power channel control link. A pitch angle instruction is generated after the pitch speed instruction passing through a first limiting link of a maximum pitch angle βmax and a minimum pitch angle βmax, and a second limiting link of a maximum pitch angle variety dβ/dtmax and a minimum pitch angle variety dIq/dtmin. The pitch angle instruction is transferred to a pitch actuator system to achieve the control of the pitch variety.
The parameters and variables are listed:
In step a2, the PID regulator response characteristics test comprises:
In step (a21), the time domain test comprises:
In step a211, while measuring the proportional magnification, the differential and integral link quit. While measuring the integral coefficient, the proportional and differential link quit. While measuring the differential link, the proportional and integral link quit.
In step a22, the frequency domain test comprises:
In step a221, while measuring the proportional magnification, the differential and integral link quit. While measuring the integral coefficient, the proportional and differential link quit. While measuring the differential link, the proportional and integral link quit.
The step a3 comprises:
In step a31, in the torque control PID test, the software and hardware of the master PLC can be modified before carry out the test, thus it is convenient for applying disturbance to the measuring link and sampling and recording waveform of the input of PID (PID IN) and the output of PID (PID OUT). Table 1 is listed:
In one embodiment, a typical parameters computational design is shown below:
In step a32, in the reactive power control PID test, the software and hardware of the master PLC can be modified before carry out the test, thus it is convenient for applying disturbance to the measuring link and sampling and recording waveform of the input of PID (PID IN) and the output of PID (PID OUT). Table 2 is listed:
In one embodiment, a typical parameters computational design is shown below:
In step a33, in the pitch angle control PID test, the software and hardware of the master PLC can be modified before carry out the test, thus it is convenient for applying disturbance to the measuring link and sampling and recording waveform of the input of PID (PID IN) and the output of PID (PID OUT). Table 3 is listed:
In one embodiment, atypical parameters computational design is shown below:
The static testing and calibrating method for PID link of control system of wind turbine has following advantages. The method is based on time-domain theory and frequency-domain theory. The key parameters can be obtained through the static testing and calibrating method for PID link of control system of wind turbine, and the correctness of the wind turbine model. The inconvenient and low in accuracy can be overcome. The static testing and calibrating method for PID link of control system of wind turbine is convenient for testing and high in accuracy.
Depending on the embodiment, certain of the steps of methods described may be removed, others may be added, and that order of steps may be altered. It is also to be understood that the description and the claims drawn to a method may include some indication in reference to certain steps. However, the indication used is only to be viewed for identification purposes and not as a suggestion as to an order for the steps.
It is to be understood that the above-described embodiments are intended to illustrate rather than limit the disclosure. Variations may be made to the embodiments without departing from the spirit of the disclosure as claimed. It is understood that any element of any one embodiment is considered to be disclosed to be incorporated with any other embodiment. The above-described embodiments illustrate the scope of the disclosure but do not restrict the scope of the disclosure.