Abstract
The present invention is carried out to supply a small sized and lightweight steel pipe bending apparatus so as to bring to construction sites, so as to keep thinning a thickness of the pipe at lower level and so as to obtain the pipe with a desired bending radius. The following apparatus realizes above-mentioned objectives of the present invention. A pipe bending apparatus comprises; a heating means to heat a steel pipe circularly around an center axis of the pipe, a cooling means to cool the heated portion of the pipe circularly around the center axis of the pipe, a tensile force applying means to apply the tensile force on points of application which are located in the opposite directions from the circular heated portion, a variable controlling means to control the tensile force variably, a transfer means to transfer the heated portion and the steel pipe relatively to the heating means and the cooling means in the direction of the axis of the steel pipe and a controlling means to control a velocity of the transfer.
Description




BACKGROUND OF THE INVENTION




1. Field of the Invention




The present invention relates to an apparatus and a method of steel pipe bending.




2. Brief Description of the Related Art





FIG. 10

shows a conventional steel bending apparatus. A bending procedure according to this apparatus is carried out as follows:




(1) As shown in

FIG. 10

a steel pipe


51


to be bent is placed between support rollers


52


and rear end of the pipe facing a pusher


54


is held by a tail-stock


53


. The front end of the pipe is held by an arm clamp


57


attached to a pivotal arm


56


which revolve the front end of the steel pipe


51


around a pivot


55


.




(2) Power is supplied to a heating coil


60


via a heating unit


62


. Then as shown in

FIG. 11

, the steel pipe


51


is pushed through a pair of guide rollers


58


and


59


disposed right and left sides of the pipe by the pusher


54


in the direction of an axis of the steel pipe, is transferred toward heating coil


60


and is passed through the coil


60


. In this way, the pushed steel pipe


51


is successively heated with induced current from the heating coil


60


. Since the coil has a circular shape, the periphery of the steel pipe


51


is heated circularly around the axis of the pipe. As shown in

FIG. 12

, since the front side of the heated portion of the pipe is cooled successively by water


62


spouted from a plurality of holes h formed circularly on a circular channel


60




a


of the coil


60


so as to obtain cooled circular portion c of the steel pipe


51


, only portion t having a width W, of the steel pipe


51


, virtually remains in a heated state. The locally heated potion t successively transfers toward the rear end of the pipe as the steel pipe


51


transfers forward. The temperature of the locally heated portion t is kept over a crystallization temperature of the pipe. In the case of a carbon steel pipe, for example, the heated zone having width W in the direction of the steel pipe axis is kept between 760° C. to 900° C. The front end of the steel pipe


51


is transferred forward by a successive pushing force from the pusher


54


, but since it is fixed by the arm clamp


57


attached to the pivotal arm


56


, the steel pipe is forced to bend successively at the locally heated portion t.




However, there are the following problems in the conventional steel pipe bending apparatus.




(1) Since enough rigidity is necessary to cope with a bending moment of the steel pipe and with an applied restraining force to the steel pipe via the pivotal arm, a massive and huge pipe bending apparatus is required. Therefore, because of the inferior portability of the apparatus, a large lot of pipes have to be bent at bending plants situated far from construction sites. Which is inevitably accompanied with the following drawbacks.




{circle around (1)} At first, straight pipes are transported to a pipe bending plant and bent pipes are transported to construction sites by trucks or ships. However, bent pipes occupy more voluminous space, namely, higher transportation costs are inevitable.




{circle around (2)} It is difficult to adjust pipe bending schedules flexibly according to modified schedules or designs or additional orders which often occur at sites such as plants and pipelines construction sites etc.




(2) According to the conventional method, since a compression force is imposed in the direction of the axis of the steel pipe due to the restraining force to the steel pipe moving forward via the pivotal arm, thinning a thickness of the pipe is prevented to a certain extent, but which is not satisfactory yet. In order to compensate such thinning thickness of the pipe, a one gage thicker pipe compared with a straight pipe to be connected with the bent pipe, is employed as the pipe for bending.




SUMMARY OF THE INVENTION




The present invention is carried out in view of the above-mentioned technical background to provide a steel pipe bending apparatus and a method having an excellent portability, having a good performance to minimize the thinning the thickness of the pipe during the bending procedure and having a flexible control on the bending radius.




The present invention provides the following pipe bending apparatuses.




(1) An apparatus of steel pipe bending comprises; a heating means to heat the steel pipe circularly around a center axis of the pipe, a cooling means to cool the heated portion of the pipe circularly around the center axis of the pipe, a tensile force applying means to apply the tensile force on points of application which are located in the opposite directions from the circularly heated portion, a variable controlling means to control the tensile force variably, a transfer means to transfer relatively the steel pipe and the heating means and the cooling means in a direction of the axis of the steel pipe and a controlling means to control the relative transfer velocity (Hereinafter referred as “the first apparatus”).




(2) An apparatus of steel pipe bending comprises; a heating means to heat the steel pipe circularly around an center axis of the pipe, a cooling means to cool the heated portion of the pipe circularly around the center axis of the pipe, a tensile force applying means to apply the tensile force on points of application which are located in the opposite directions from the circularly heated portion, a variable controlling means to control the tensile force variably, a transfer means to transfer relatively the steel pipe and the heating means and the cooling means in a direction of the axis of the steel pipe, a controlling means to control the relative transfer velocity and a scale to measure bent values stepwise according to a predetermined bending schedule (Hereinafter referred as “the second apparatus”).




The present invention provides the following pipe bending methods.




(1) A method of steel pipe bending comprises; forming a locally heated circular portion around a center axis of the steel pipe, relatively transferring the locally heated portion and the steel pipe in a direction of the center axis of the steel pipe and controlling the relative transfer velocity of the heated portion and the steel pipe during a bending procedure by applying a tensile force between two points of application which are located in the opposite directions from the heated portion along an eccentric axis of the steel pipe (Herein after referred as “the first method”).




(2) A method of steel pipe bending comprises; forming a locally heated circular portion around a center axis of the steel pipe, relatively transferring the locally heated portion and the steel pipe in a direction of the center axis of the steel pipe, measuring actual bent values stepwise during a successive bending procedure according to a bending schedule where bent values are predetermined stepwise and controlling the relative transfer velocity of the heated portion and the steel pipe during the bending procedure by applying a tensile force between two points of application which are located in the opposite directions from the heated portion along an eccentric axis of the steel pipe according to a difference between the predetermined bent value and the actual bent value (Hereinafter referred as “the second method”).











BRIEF DESCRIPTION OF DRAWINGS





FIG. 1

is a plan view with a partial cutout of a pipe bending apparatus in the embodiment 1.





FIG. 2

shows a pipe bending movement of the pipe bending apparatus in the embodiment 1.





FIG. 3

is a plan view with a partial cutout of a pipe bending apparatus in the embodiment 2.





FIG. 4

shows a pipe bending movement of the pipe bending apparatus in the embodiment 2.





FIG. 5

is a plan view of an essential part of the pipe bending apparatus in the embodiment 2.





FIG. 6

is a plan view with a partial cutout of a pipe bending apparatus in the embodiment 3.





FIG. 7

is a plan view with a partial cutout of other pipe bending apparatus in the embodiment 3.





FIG. 8

is a plan view with a partial cutout of a pipe bending apparatus in the embodiment 4.





FIG. 9

shows a pipe bending movement of the pipe bending apparatus in the embodiment 4.





FIG. 10

is a plan view with a partial cutout of a conventional pipe bending apparatus.





FIG. 11

shows a pipe bending movement of the conventional pipe bending apparatus.





FIG. 12

shows an enlarged cross-sectional view of the heating coil in FIG.


10


and shows a temperature distribution curve in the vicinity of a heated portion along the axis of the steel pipe.











DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS




Hereinafter the detailed examples according to the present invention are described with reference to embodiments.




Embodiment 1




FIG.


1


and

FIG. 2

show an embodiment of the first apparatus.

FIG. 1

is a plan view with a partial cutout of a pipe bending apparatus in the embodiment 1 and

FIG. 2

shows a pipe bending movement of the pipe bending apparatus. An embodiment of the first method is realized by employing the pipe bending apparatus according to this embodiment.




In these figures a numeric character


1


represents a steel pipe, to front and rear ends of which a front cramping plate


2


and a rear cramping plate


3


are applied respectively. An alphabetic character T represents a tensile force application unit that applies a tensile force between the plate


2


and the plate


3


. The unit T is constituted of a chain


4


and a hydraulic jack


5


which supplies the tensile force to the chain. A front end of the chain


4


is fixed to the front cramping plate


2


and the hydraulic jack


5


is fixed to the rear cramping plate


3


.




The fixed front end of the chain


4


to the front cramping plate


2


and the fixed end of the hydraulic jack


5


to the rear cramping plate are aligned in an eccentric axis line on a plane which extends along an axis line of the steel pipe


1


. The both fixed ends are application points of the tensile force applied to the chain


4


by the hydraulic jack


5


.




An adjustable wheel unit


6


which supports the weight of the steel pipe and moves a horizontal floor without restrictions is attached to the front cramping plate


2


. A steel pipe transfer unit


7


in which the rear cramping plate


3


is built, transfers along rails


9


laid on supports


8


in the direction of the axis of the steel pipe


1


. A numeric character


10


represents a heating coil to heat a periphery of the steel pipe


1


and a numeric character


11


represents a heating unit. Via a coil holder


12


, the heating coil


10


is supported by a frame of the heating unit


11


which is fixed to a support


13


. The detailed structure and functions of the heating coil are similar to the conventional one shown in FIG.


12


.




A transfer velocity of the steel pipe transfer unit


7


is adjustable by a velocity regulator


14


for the steel pipe transfer with referring to a measured value from a velocity indicator


15


for the steel pipe transfer. The tensile force supplied from the hydraulic jack


5


to drag the chain is adjustable by a tensile force regulator


16


with referring to a measured value from a tensile force indicator


17


.




The tensile force supplied from the hydraulic jack is adjustable by adjusting a drag velocity of the chain, since the tensile force and the drag velocity of the chain correlate with each other.




In this embodiment, the drag velocity of the chain derived from the hydraulic jack


5


is adjusted by a drag velocity regulator


18


with referring to a measured value from a tensile velocity indicator


19


.




A ratio of the drag velocity of the chain


4


to a relative velocity of the locally heated portion t (See

FIG. 12

) and the steel pipe


1


is adjusted by a velocity ratio regulator


20


and its measured value is displayed on a velocity ratio indicator


21


. Heated temperature of the steel pipe


1


by the heating coil


10


and temperature of cooing water


62


are controlled by controlling means (which are not shown in figures).




Herein after a steel pipe bending procedure is described according to the apparatus with the above-mentioned constitution.




The steel pipe


1


is transferred forward by driving the steel pipe transfer unit


7


and when the hydraulic jack


5


applies the tensile force to the chain


4


, the steel pipe


1


is bent continuously at the locally heated portion t (see

FIG. 12

) which transfers backward successively receiving a compression force in the direction of the eccentric axis of the steel pipe, since the both fixed ends are aligned on the eccentric axis.




If the drag velocity of the chain


4


is increased (i.e. the tensile force is increased), a bent radius of the steel pipe can be decreased due to an increasing bent amount per unit time. On the other hand if the drag velocity of the chain


4


is decreased (i.e. the tensile force is decreased), the bent radius of the pipe can be increased due to a decreasing bent amount per unit time. If the transfer velocity of the steel pipe transfer unit


7


is decreased the bent radius of the pipe can be decreased due to the same reasons mentioned above.




Consequently, if a ratio V


1


/V


2


, where V


1


is the drag velocity of the chain


4


and V


2


is the transfer velocity of the steel pipe transfer unit


7


, is increased, the bent radius is decreased, and vice versa.




As described in the embodiment 1, when a bending procedure of the steel pipe is executed by applying the tensile force to the two points of application aligned on the eccentric axis of the steel pipe


1


, the bent radius of the steel pipe


1


can be controlled for example according to a bending curve depicted on a floor, since the above-mentioned tensile velocity (i.e. tensile force) and the relative velocity of the above-mentioned locally heated portion and the pipe can be controlled.




In the embodiment 1, during the bending procedure, thinning the thickness of the pipe is suppressed, since the steel pipe is compressed in the longitudinal direction by applying the tensile force between the two points of the application along the eccentric axis of the steel pipe.




In addition, in the embodiment 1, since the steel pipe can be bent by employing the tensile force application unit, it is possible to render the pipe bending apparatus smaller and lighter. It is not necessary to prepare a massive and heavy apparatus to cope with a huge bending moment as seen in the conventional pushers (to apply pressing force) and pivotal arms. Therefore the present invention enables the pipe bending apparatus to be portable and to be set up on construction sites more easily.




Embodiment 2




FIG.


3


and

FIG. 4

show an embodiment of the second apparatus. An embodiment of the second method is realized by the steel pipe bending apparatus in the embodiment 2.




The steel pipe bending apparatus in the embodiment 2 employs the same apparatus in the embodiment 1 except having an additional measuring instrument S (hereinafter referred as “scale”) which revolves according to the bending procedure of the steel pipe


1


and measures expanded value of an arm of the scale S in accordance with a revolved angle θ so as to determine bent value (hereinafter referred as “actual bent value”) of the steel pipe


1


, having an indicator


23


to display bent value, having a measuring instrument


24


to determine revolved angle of the scale S and having an indicator


25


to display revolved angle of the scale S.




Except instruments and indicators relevant to the scale S, the pipe bending apparatus has the same configuration as the embodiment 1. Since in FIG.


3


and

FIG. 4

, the same numeric or alphabetic characters are used to represent the same members or units as in

FIG. 1

, a detailed explanation of the apparatus is omitted.




The above-mentioned scale S is constituted of a cylinder


22




a


and a rod


22




b


built in the cylinder


22




a


so as to ensure expandable movement. One of the ends of the rod


22




b


is attached to a circular metal fitting


26


fixed to the front end of the steel pipe via a shaft B so as to revolve relatively to the fitting


26


, while one of the ends of the cylinder


22




a


is attached to the frame of the heating unit


11


via a shaft A so as to revolve relatively to the frame.




The scale S revolves around the shaft A in accordance with the bending procedure of the steel pipe


1


by keeping its length constantly or variably, and the shaft B plays an outermost revolving point of the scale S.




An alphabetic character C


1


represents a center line in the diameter direction of the heating coil


10


perpendicular to an axis line C


2


of the steel pipe on a parallel plane to the floor. The revolving center A is aligned on the extended line of C


1


. In

FIG. 3

a cross point D where the axis line C


2


and the center line C


1


meet is a bending initiation point of the steel pipe


1


.




As shown in

FIG. 3

before bending, the scale S is arranged at a position with revolved angle α (hereinafter referred as “initial position”) from the center line C


1


and at this stage the revolving point B is situated ahead of the above-mentioned cross point D on the axis line C


2


. In this embodiment the angle α is set 20 degrees.




The above-mentioned actual bent value is expressed as an extended value of the scale S at a revolved angle θ of the scale when the length of the scale S at the initial position is set zero.




The extended value is displayed on the indicator


23


. The revolved angle θ of the scale S is determined by the measuring instrument


24


and the determined value θ is displayed on the indicator


25


.




By employing the steel bending apparatus with above-described constitution in the embodiment 2, a 90 degree bending procedure where the shaft A is set as the revolution point of the scale S and a bending radius R is set as a distance between the cross point D and the revolution point of the scale S (i.e. shaft A), is executed as follows.




(1) A bending schedule table as shown in Table 1 where the length of the scale S is exhibited in relation to the revolved angle θ of the scale S is prepared beforehand. The length of the scale S at the angle θ (1 to 90 degrees) in the Table 1 means the scheduled value expressed in mm when the value is set zero at the initial position.















TABLE 1











Revolved




Scheduled bent







angle (θ)




value (mm)
































0












0












0












0












0












0







.




.







.




.







90°




0















(2) In the same way as in the embodiment 1, the steel pipe


1


is successively bent by driving the steel pipe transfer unit


7


so as to transfer the steel pipe forward and applying the tensile force to the chain


4


from the hydraulic jack


5


with referring to the Table 1. As shown in in

FIG. 4

the steel pipe


1


is continuously bent at the heating portion t which successively transfers backward reecieving applied compression force in the direction of the eccentric axis line of the pipe.




(3) During the bending procedure, if the actual bent values displayed on the indicator


23


are, for example, values in Table 2, the above-mentioned tensile velocity V


1


from the hydraulic jack


5


and the transfer velocity V


2


of the steel pipe transfer unit


7


are controlled as that the actual bent values attain the same values as scheduled ones.














TABLE 2









Revolved




Scheduled bent




Actual bent






angle (θ)




value (mm)




value (mm)






























0




0











0




+1











0




−1











0




+1











0




−1











0




+1






.




.




.






.




.




.






90°




0




0














Since the actual bent value, for example, +1 means that the actual bending amount is less than the scheduled one, the adjustment is made by increasing the above-mentioned tensile velocity V


1


, decreasing the transfer velocity V


2


or increasing the ratio (V


1


/V


2


). When the actual bent value shows −1, the opposite controlling measure is taken.




In the bending procedure depicted in FIG.


3


and

FIG. 4

, the center of the bending radius R is set at the revolving center A of the scale S. However, the bending radius of the steel pipe


1


can be increased by setting the center of the radius at E situated on the center line C


1


of the heating coil


5


apart from the revolving center A of the scale S so as to obtain the bent pipe with a larger radius R


1


as shown in FIG.


5


.




In order to obtain the bent steel pipe


1


with radius R


1


, the scheduled bent values are prepared, for example, as shown in Table 3. Scheduled bent values are exhibited in the table, when a distance between the revolving center A and the bent initiating point D is set 200 mm and bent radius R


1


is set 500 mm. The scheduled bent values are increased as revolved angles θ are gradually incereased up to 90 degrees.















TABLE 3











Revolved




Scheduled bent







angle (θ)




value (mm)
































0







10°




+9.8







20°




+24.4







30°




+44.3







40°




+70.5







50°




+103.9







60°




+145.0







70°




+193.7







80°




+249.2







90°




+309.1















Though not shown in figures, the center of the bending radius of the steel pipe


1


can be set on the extended center line C


1


at the same of the heating coil apart from the revolving center A. If the bending radius is gradually increased or decreased at the bending initiation point and ending point, fluctuation of the thickness of the bent pipe in the vicinity of these points can be made more moderate. In this case the bending procedure is executed in the same way as described above.




Embodiment 3





FIG. 6

illustrates other embodiment of the second apparatus. The embodiment of the second method is realized by the steel pipe bending apparatus in the embodiment 3.




In the above-mentioned the steel pipe bending apparatus in the embodiment 2 is constituted so as that the heating coil


10


is fixed and the steel pipe


1


is transferred. In the embodiment 3, on the other hand, the steel pipe bending apparatus is constituted so as that the steel pipe


1


is fixed and the heating coil is transferred along the steel pipe.




Namely, the bending apparatus is constituted such that the rear cramping plate


3


is fixed to a support


27


and the heating coil


10


is transferred by a coil transfer unit


28


along the steel pipe


1


. A transfer velocity of the coil transfer unit


28


is controlled by a velocity regulator


29


of the unit referring displayed value on an indicator


30


of the transfer velocity. Other configuration is virtually the same as the embodiment 2. Also the bending procedure is carried out in the same way as in the embodiment 2.




The above-mentioned coil transfer unit


28


transfers along the steel pipe


1


, but the coil can be transferred by rollers fixed to the coil heating unit


11


such as a coil transfer unit


31


which transfers on a rail


33


fixed to a support


32


as shown in FIG.


7


. In this case the transfer velocity of the coil transfer unit


31


controlled by a velocity regulator


34


with referring to a measured value displayed on a velocity indicator


35


of the coil transfer velocity. In this case the bending procedure is also executed in the same way as the embodiment 2.




Embodiment 4




FIG.


8


and

FIG. 9

illustrate other embodiment of the second apparatus. The embodiment of the second method is realized by the steel pipe bending apparatus in the embodiment 4.




The pipe bending apparatus in the embodiment 4 employs an extendable scale S


1


in place of the scale S in FIG.


3


. The other configuration is the same as the embodiment 2 as shown in FIG.


3


.




One of the ends of a rod


36


constituting the scale S


1


is movably attached to the circular fitting


26


via a shaft F so as to revolve around the shaft, while one of the ends of a cylinder


37


is attached to a rail


39


mounted on a support


38


via a slider


40


so as to slide along the rail.




The rail


39


is fixed to the support


38


parallel to the axis C


2


of the steel pipe


1


the scale S


1


is attached to the rail


39


parallel to the center line C


1


of the heating coil.




The rail


39


in this embodiment is not constituted as a guide rail for scale S


1


during the bending procedure as shown in

FIG. 9

, but also as a measuring instrument to determine a transferred distance of the scale S


1


.




An actual bent value in the embodiment 4 is expressed as an extended value of scale S


1


according to a transferred distance L of the scale S


1


along the rail


39


when the length of the scale S


1


before the bending procedure is set zero as shown in FIG.


8


.




The extended value of the scale S


1


is displayed on an indicator


41


. The transferred distance L of the scale S


1


, determined by the measuring instrument (rail)


39


, is displayed on an indicator


42


to display the transferred distance.




By employing the steel bending apparatus with the above-mentioned constitution where a bending radius R


2


is set as a distance between a center point A on the extended center line C


1


and the initiation point D of the bending on the steel pipe


1


, a 90 degree bending of the steel pipe


1


is executed as follows.




(1) A bending schedule table as shown in Table 4 where a length of the scale S


1


is given in relation to a transferred distance L of the scale S


1


is prepared beforehand. In this Table scheduled bent values are exhibited when the bending radius is set 500 mm. The length of the scale S


1


in relation to the transferred distance L means the scheduled bending value expressed in mm of the steel pipe


1


when the length of the scale S


1


is set zero before the bending.















TABLE 4











Transferred




Scheduled







distance L




bent value







(mm)




(mm)



























0




0







33.6




15.7







64.0




37.0







90.2




63.7







111.5




93.6







127.2




127.2







136.8




163.0







140.0




200.0







136.8




237.0







127.2




272.8















(2) The steel pipe


1


is successively bent by driving the steel pipe transfer unit


7


so as to transfer the steel pipe forward and applying the tensile force to the chain


4


from the hydraulic jack


5


with referring to the table, in the same way as the embodiment


1


. The steel pipe


1


is continuously bent at the heating portion t that successively transfers backward receiving compression force in the direction of the eccentric axis line of the pipe.




(3) During the bending procedure, if the actual bent values displayed on the indicator


41


are, for example, values in Table 5, the above-mentioned tensile velocity V


1


of the hydraulic jack


5


and the transfer velocity V


2


of the steel pipe transfer unit


7


are controlled so as that the actual bent values attain the same values as scheduled ones.

















TABLE 5











Transferred




Scheduled









Distance L




Bent value




Actual bent




Difference







(mm)




(mm)




Value (mm)




(mm)





























0




0




0




0







33.6




15.7




17




+1.3







64.0




37.0




35




−2.0







90.2




63.2




65




+1.8







111.5




93.6




95




+1.4







127.2




127.2




125




−2.2







136.8




163.0




164




+1.0







140.0




200.0




198




−2.0







136.8




237.0




239




+2.0







127.2




272.8




273




+0.2















For example, if the difference is +1.3, namely, it means the actual bent amount is less than the scheduled one, either a measure to increase the tensile velocity V


1


, a measure to decrease the transfer velocity V


2


or a measure to increase the ratio (V


1


/V


2


) is employed. If the difference is −2.0, namely it means the actual bent is more than the scheduled one, the opposite controlling measure is taken.




The bending schedules in the embodiments 2 to 4 mentioned above can be stored in recording media as computer programs so as to execute computer controlled bending procedures.




As explained, above-mentioned constitutions according to the present invention attain, the following effects.




(1) The bending procedure of the steel pipes can be executed on construction sites in accordance with a progress of the construction, since the present invention realizes a small sized, lightweight and portable steel pipe bending apparatus.




(2) Thinning thickness of the steel pipe during the bending procedure can be kept to a lower extent, since the compression force is applied in the longitudinal direction of the steel pipe by the tensile force applying means.




(3) Bending accuracy of the steel pipe can be improved, since the bending amount of the steel pipe is controlled successively and stepwise.



Claims
  • 1. An apparatus of steel pipe bending comprises; a heating means to heat said steel pipe circularly around a center axis of said pipe, a cooling means to cool said heated portion of said steel pipe circularly around said center axis of said pipe, a tensile force applying means to apply said tensile force on points of application which are located in the opposite directions from said circularly heated portion, a variable controlling means to control said tensile force variably, a transfer means to transfer relatively said steel pipe and said heating means and said cooling means in a direction of said axis of said steel pipe a controlling means to control said relative transfer velocity and a scale to measure bent values stepwise.
  • 2. An apparatus of steel pipe bending comprises; a heating means to heat said steel pipe circularly around a center axis of the pipe, a cooling means to cool said heated portion of said pipe circularly around said center axis of said pipe, a tensile force applying means to apply said tensile force on points of application which are located in the opposite directions from said circularly heated portion, a variable controlling means to control said tensile force variably, a transfer means to transfer relatively said steel pipe and said heating means and said cooling means in a direction of said axis of said steel pipe, a controlling means to control said relative transfer velocity and a scale to measure bent values stepwise according to a predetermined bending schedule so as to control said relative transfer velocity.
  • 3. A method of steel pipe bending comprises; forming a locally heated circular portion around a center axis of said steel pipe, relatively transferring said locally heated portion and said steel pipe in a direction of said center axis of said steel pipe and controlling said relative transfer velocity of said heated portion and said steel pipe during said bending procedure by applying a tensile force between two points of application which are located in the opposite directions from said heated portion along an eccentric axis of said steel pipe based on the measured bent value.
  • 4. A method of steel pipe bending comprises; forming a locally heated circular portion around a center axis of said steel pipe, relatively transferring said locally heated portion and said steel pipe in a direction of said center axis of said steel pipe, measuring actual bent values stepwise during a successive bending procedure according to a bending schedule where stepwise bent values are predetermined stepwise and controlling said relative transfer velocity of said heated portion and said steel pipe during said bending procedure by applying a tensile force between two points of application which are located in the opposite directions from said heated portion along an eccentric axis of said steel pipe according to a difference between said predetermined bent value and said actual bent value so as to control said tensile force.
Priority Claims (1)
Number Date Country Kind
12-051208 Feb 2000 JP
US Referenced Citations (5)
Number Name Date Kind
RE. 30639 Hofstede et al. Jun 1981
4122697 Hanyo et al. Oct 1978
4195506 Kawanami et al. Apr 1980
4412442 Kawanami et al. Nov 1983
4596128 Ringersma et al. Jun 1986
Foreign Referenced Citations (2)
Number Date Country
P8-294729A Nov 1996 JP
P12-15350A Jan 2000 JP