1. Field of the Invention
The present invention relates to a storage battery control system and a storage battery control method.
2. Description of the Related Art
Systems that couple multiple storage batteries to a power grid have been proposed in recent years. Although not related to a storage battery coupled to a power grid, a technology for supplying power to a common load using batteries of different types is known (Japanese Patent Application Laid-open No. 2010-246211). A technology for making effective use of electric power by feeding the surplus power of a secondary battery to a selected load, and, in addition, enhancing the soundness of the secondary battery is also known (Japanese Patent Application Laid-open No. H10-322924). In addition, although not related to a storage battery coupled to a power grid, a technology for mounting a storage battery having high output density and a storage battery having high energy density in an electric vehicle, and supplying power from either one of the storage batteries is known (Japanese Patent Application Laid-open No. H9-298806).
In order to stably and efficiently operate a power grid using multiple storage batteries coupled to the power grid, it is necessary to systematically control each storage battery based on a power supply-demand prediction. However, in Japanese Patent Application Laid-open No. 2010-246211 and Japanese Patent Application Laid-open No. H9-298806, the technologies do not individually control multiple storage batteries coupled to the power grid, and do not systematically control the charging and discharging of the storage batteries. Japanese Patent Application Laid-open No. H10-322924 is technology for maintaining the soundness of a certain specified secondary battery, and does not control the charging and discharging of multiple storage batteries to achieve stable and efficient operation of the power grid.
Consequently, an object of the present invention is to provide a storage battery control system and a storage battery control method, which make it possible to stably and efficiently operate a power grid by effectively utilizing multiple storage batteries installed in the power grid.
A storage battery control system related to the present invention for solving the above problems is a storage battery control system for controlling the operation of a storage battery coupled to a power grid, and comprises multiple storage batteries disposed in the power grid, and a storage battery control apparatus, which is for controlling the charging and discharging of the multiple storage batteries and is communicably coupled to both the multiple storage batteries and an energy management system, wherein the storage battery control apparatus acquires storage battery information comprising a charging-discharging performance and a remaining capacity from each storage battery, acquires power supply-demand prediction information showing a prediction of power supply and demand in a prescribed range from the energy management system, which manages the power supply and demand in the prescribed range, decides an individual charging-discharging rate for each storage battery based on the storage battery information and the power supply-demand prediction information, and sends the decided individual charging-discharging rate to each storage battery, and each storage battery operates on the basis of the individual charging-discharging rate received from the storage battery control apparatus.
The charging-discharging performance may comprise a charging performance, which shows charging rate per unit of time, a discharging performance, which shows discharging rate per unit of time, and a full charge capacity.
The energy management system, based on a power consumption of a customer, who exists within a prescribed range, can predict power demand within the prescribed range during a prescribed time period, which is configured longer than the unit of time, and based on the predicted power demand, can calculate a total charging-discharging rate needed for the storage batteries as a whole, include the calculated total charging-discharging rate in the power supply-demand prediction information, and send this information to the storage battery control apparatus.
The energy management system can also calculate load prediction information showing a trend of a change in the power demand based on the predicted power demand, include the calculated load prediction information in the power supply-demand prediction information, and send this information to the storage battery control apparatus.
The storage battery control apparatus, based on the load prediction information received from the energy management system, can determine a mode to be either a balanced mode in which the power demand and the power supply are balanced, a discharging performance priority mode in which the power demand is greater than the power supply, or a charging performance priority mode in which the power supply is greater than the power demand, and based on the determined mode, can also select a control pattern for deciding the individual charging-discharging rate for each storage battery.
The storage battery control apparatus, in the case of the balanced mode, selects a balanced control pattern for deciding the individual charging-discharging rate that allows the remaining capacity of each storage battery to approach half of the full charge capacity of the relevant storage battery, in the case of the discharging performance priority mode, selects a discharge control pattern for deciding the individual charging-discharging rate that allows charging from a low-discharging-performance storage battery of the respective storage batteries to a high-discharging-performance storage battery of the respective storage batteries, and in the case of the charging performance priority mode, selects a charge control pattern for deciding the individual charging-discharging rate that allows charging from a high-charging-performance storage battery of the respective storage batteries to a low-charging-performance storage battery of the respective storage batteries.
The storage battery control apparatus, in a case where there exist multiple control pattern candidates, may select any one of the candidates as the control pattern based on a prescribed selection criterion.
At least a portion of the configuration of the present invention should be able to be realized as either a computer program or a hardware circuit. The computer program, for example, can be delivered via a communication medium such as the Internet, or a recording medium such as a hard disk or a flash memory device.
An embodiment of the present invention will be explained by referring to the drawings. The battery control system of the embodiment, as described hereinbelow, comprises an energy management system 30 for providing power grid supply-demand prediction information, multiple charge-discharge controllable storage batteries 120, which are coupled to the power grid, and a storage battery control apparatus 110 for controlling the charging and discharging of a storage battery. There may be cases in which a storage battery is abbreviated as either “VT” or “battery” in the drawings, or is omitted from the drawings.
The storage battery control apparatus receives supply-demand prediction information from the energy management system, and, in addition, receives storage battery information from each storage battery. The storage battery control apparatus instructs each storage battery to perform charging and discharging based on a control pattern corresponding to a power demand prediction.
In accordance with this, the embodiment systematically charges and discharges each storage battery by matching the charging-discharging performance of each storage battery with the power supply-demand prediction. That is, the remaining capacity in each storage battery is adjusted in accordance with the power supply-demand prediction.
Therefore, in a case where a lot of discharging is required, the energy stored in the storage battery can be rapidly supplied to the power grid. In contrast, in a case where a lot of charging is required, the surplus power from the power grid can be rapidly stored in the storage battery. In a case where the power supply and demand are in balance, the power supply-demand balance can be maintained as much as possible by adjusting the SOC (State Of Charge) of the storage battery to near 50% beforehand.
Thus, according to the embodiment, since storage batteries can be effectively utilized by systematically adjusting the remaining capacity in each storage battery, it is possible to operate a power grid stably and efficiently. The embodiment will be explained in detail hereinbelow.
Example 1 will be explained by referring to
Multiple customers (20(1) and 20(2) and multiple storage batteries 120(1), 120(2), 120(3) and 120(4) are coupled to the low voltage-side power grid (distribution line) 41 emanating from the pole transformer 40. When no particular distinction is made, the storage batteries 120(1) through 120(4) may be called storage battery 120.
The customers 20(1) and 20(2), for example, are an ordinary private residence, a multi-unit housing complex, a commercial facility, a hospital, and so forth. When no particular distinction needs to be made, the customers 20(1) and 20(2) may be called customer 20. The customer 20, for example, has various types of electrical loads that consume power, such as an electrical lighting system, an air conditioning system, a hot-water heater, and a passenger conveyance system. In addition, for example, the customer 20 can also be equipped with a power generation apparatus, such as a solar power generation system and a wind turbine power generation system.
The power consumption (and power output) of the customer 20 is measured at prescribed periods using a power measurement part 21. The power measurement part 21 sends measured power consumption information to the energy management system 30 via a communication network CN1. The communication network CN1, for example, is configured using either one or multiple of a wireless communication network, a communication network, which uses power lines, the Internet, and a local area network (LAN).
The energy management system 30 is for managing power supply and demand in a prescribed range. The energy management system 30 is configured as a computer comprising a microprocessor and a memory. A load prediction part 31 and a requested charging-discharging rate decision part 32 are both realized by the microprocessor executing a prescribed computer program stored in the memory.
The load prediction part 31 creates load prediction information showing a prediction of the load (power demand) in the future based on a history of the power consumption of the customer 20. Although various load prediction methods are conceivable, for example, it is possible to predict the power consumption of a corresponding time based on an average value of power consumptions measured at the same times on the same days in the past. In addition, power consumption can also be predicted by referring to power consumption historical data, and past meteorological data and weather forecasts.
The load prediction information of this example comprises information for determining whether “the load tends to increase”, “the load tends to decrease”, or “the load tends to maintain current state”. The load prediction information, for example, may comprise symbols or alphanumerics, which directly denote a variation trend such as “−”, “+”, or “0”. The load prediction information, for example, may comprise both a load variation trend and variation quantity, such as “−20%”, “+15%”, and “±0”.
The load is the power demand in a prescribed range (the total value of the power consumption of the respective customers 20). As described below, in a case where the load tends to increase, the remaining capacity of the storage battery 120 is adjusted beforehand in preparation for an increase in load. In a case where the load tends to decrease, the remaining capacity of the storage battery 120 is adjusted beforehand in preparation for a decrease in load. In a case where the load tends to maintain the current state, the remaining capacity of the storage battery 120 is adjusted beforehand to maintain this balance as much as possible.
The storage battery requested charging-discharging rate decision part (the requested charging-discharging rate decision part in the drawing) 32 is a function for deciding either the charging rate or the discharging rate requested for the multiple storage batteries 120 as a whole. This part will be called the requested charging-discharging rate decision part 32 hereinafter.
The requested charging-discharging rate decision part 32 decides the requested charging-discharging rate for all the storage batteries 120 based on the load prediction information created by the load prediction part 31 and the power consumption of the respective customers 20 measured by the power measurement part 21. The decided requested charging-discharging rate is sent to the storage battery control apparatus 110 via the communication network CN1.
As explained above, the requested charging-discharging rate is the value requested for the multiple storage batteries 120 as a whole, and is equivalent to a “total charging-discharging rate”. That is, the requested charging-discharging rate is either the charging rate or the discharging rate requested for one virtual storage battery, which comprises multiple storage batteries 120.
An example of a method for deciding the requested charging-discharging rate will be explained. For example, a target value for the power demand (load) on the pole transformer 40 is configured, and the difference between the target value and the total value of the power consumption of the respective customers 20 is used as either the charging rate or the discharging rate for the storage batteries 120 as a whole.
That is, in a case where the total demand of the pole transformer 40 low voltage-side grid (distribution lines) 41 is larger than the target value (target load), power is supplied to the low voltage-side grid 41 from any one or multiple of the storage batteries 120. Alternatively, in a case where the total demand on the low voltage-side grid is smaller than the target value, the surplus power of the low voltage-side grid 41 is stored in any one or multiple of the storage batteries 120.
The configuration of the storage battery control system 10 will be explained. The storage battery control system 10 comprises multiple storage batteries 120(1) through 120(4), which are coupled to the low voltage-side grid 41, and a storage battery control apparatus (VT control apparatus in the drawing) 110, which is coupled to these storage batteries 120(1) through 120(4) via a communication network CN2.
Four storage batteries 120(1) through 120(4) are shown in the drawing, but the configuration may be such that two, three, five or more storage batteries are disposed in the storage battery control system 10. In this example, a case in which the storage batteries 120(1) through 120(4) are storage batteries having respectively different electrical characteristics will be explained. However, this example can also apply to a case in which the electrical characteristics of the storage batteries 120(1) through 120(4) are the same.
In this example, the electrical characteristics of the storage batteries 120(1) through 120(4) are different, but the basic configuration is shared in common. Accordingly, the storage batteries 120(1) through 120(4) will be called storage battery 120. Each storage battery 120, for example, comprises a communication part 121, a storage battery main unit 122, and a charge-discharge control part 123.
The communication part (I/F in the drawing) 121 is a circuit for communicating with the storage battery control apparatus 110 via the communication network CN2. The communication network CN2 is for communications between the storage batteries 120 and the storage battery control apparatus 110, and, for example, can be configured using either any one or multiple of a wireless communication network, a power line communications (PLC), and the Internet. The communication part 121 receives a charge-discharge control signal, which will be explained further below, from the storage battery control apparatus 110 via the communication network CN2. The communication part 121 delivers the received charge-discharge control signal to the charge-discharge control part 123. In addition, the communication part 121 can also send the remaining capacity and the like, which will be explained further below, to the storage battery control apparatus 110 via the communication network CN2.
The storage battery main unit 122 is configured by coupling together multiple cells comprising electrodes and an electrolyte. The storage battery main unit 122, for example, can comprise a lithium ion storage battery, a lead storage battery, a nickel hydride storage battery, and a sodium-sulfur storage battery. In addition, the storage battery 120 may comprise a capacitor such as an electric double-layer capacitor, in addition to the storage battery main unit 122.
The charge-discharge control part 123 is a control circuit for controlling charging to the storage battery main unit 122 and discharging from the storage battery main unit 122. The charge-discharge control part 123, for example, can comprise an inverter circuit and a microcomputer circuit.
At charging time, the charge-discharge control part 123 charges the storage battery main unit 122 by converting alternating current power from the power grid 41 to direct current power. At discharging time, the charge-discharge control part 123 converts the direct current power of the storage battery main unit 122 to alternating current power and supplies the alternating current power to the power grid 41.
The charge-discharge control part 123 either charges or discharges the storage battery main unit 122 in accordance with a charge-discharge control signal received from the storage battery control apparatus 110. The charge-discharge control part 123 manages the remaining capacity of the storage battery main unit 122 (current remaining capacity). The charge-discharge control part 123 can send the remaining capacity to the storage battery control apparatus 110 on either a regular or irregular basis.
The configuration of the storage battery control apparatus 110 will be explained. The storage battery control apparatus 110 individually controls the charging and discharging of each storage battery 120 based on a power supply-demand state of the power grid. The storage battery control apparatus 110 can be configured as a computer apparatus comprising a microprocessor and a memory. The storage battery control apparatus 110 may be integrated with the energy management system 30.
The storage battery control apparatus 110, for example, may be installed in a charging station or the like. The charging station comprises multiple storage batteries 120, and is a facility for supplying power to a prescribed region and for storing surplus power created by a prescribed region.
The storage battery control apparatus 110 microprocessor realizes the following functions 111 through 116 by executing a prescribed computer program stored in the memory.
A remaining capacity receiving part 112 receives the remaining capacity sent from each storage battery 120. The received remaining capacity is stored in a storage battery management database (VT management DB in the drawing) 113.
The remaining capacity receiving part 112 can receive the remaining capacity from each storage battery 120 with respect to a prescribed period, and can update the storage battery management DB 113. Or, the configuration may be such that, in a case where the latest remaining capacity is needed, the remaining capacity receiving part 112 requests that the remaining capacity be sent from the storage battery control apparatus 110 to each storage battery 120.
A load prediction receiving part 115 receives load prediction information sent from the load prediction part 31 of the energy management system 30.
A storage battery control rate receiving part 116 receives the requested charging-discharging rate information sent from the requested charging-discharging rate decision part 32 of the energy management system 30. The requested charging-discharging rate information comprises information on either the charging rate or the discharging rate requested for all of the storage batteries 120, which are the control targets of the storage battery control apparatus 110, and information on a future load prediction.
The storage battery management database 113 stores information, which shows the remaining capacity of each storage battery 120, and information, which shows the charging-discharging performance of each storage battery 120.
A charging-discharging rate operation part 114 calculates the individual charging-discharging rate of each storage battery 120. The charging-discharging rate operation part 114 calculates the individual charging-discharging rate of each storage battery 120 based on the remaining capacity information of each storage battery 120, the charging-discharging performance information of each storage battery 120, and the requested charging-discharging rate information and load prediction information sent from the energy management system 30. An individual charging-discharging rate, which is the operation result thereof, is delivered to a control information sending part 111. The individual charging-discharging rate can be called the charge-discharge control capacity since it is a control capacity for controlling the charging and discharging of each storage battery 120.
The control information sending part 111 converts the charging-discharging rate (charge-discharge control capacity) created for each storage battery 120 to a charge-discharge control signal, and sends this signal to each storage battery 120.
Remaining capacity information T10 and charging-discharging performance information T20, which are stored in the storage battery management database 113, will be explained here be referring to
The battery ID C100 is information for identifying the respective storage batteries 120. It is preferable that each storage battery 120 in the storage battery control system 10 be able to be uniquely identified. The remaining capacity C101 is information showing the amount of electrical energy stored in a storage battery 120. The SOC C102 is information showing the charge ratio of the storage battery 120. The SOC can be determined using a value obtained by dividing the remaining capacity by the full charge capacity (SOC (remaining capacity/full charge capacity)×100%).
For example, a look at the storage battery 120(1) shown as “VT 1” in the drawing clearly shows that the remaining capacity is 5 kWh and the SOC is 50%. A look at the storage battery 120(2) shown as “VT 2” in the drawing clearly shows that the remaining capacity is 8 kWh and the SOC is 50%. A look at the storage battery 120(3) shown as “VT 3” in the drawing clearly shows that the remaining capacity is 9 kWh and the SOC is 50%. A look at the storage battery 120(4) shown as “VT 4” in the drawing clearly shows that the remaining capacity is 5 kWh and the SOC is 50%.
An example of the charging-discharging performance information T20 is shown in
The full charge capacity C201 is information showing the maximum value of the battery capacity. The charging performance C202 is information showing the amount of electrical energy (kWh) capable of being charged per unit of time. The discharging performance C203 is information showing the amount of electrical energy (kWh) capable of being discharged per unit of time.
A look at the storage battery 120(1) clearly shows that the full charge capacity thereof is 10 kWh, the charging performance is 5 kWh, and the discharging performance is 5 kWh. Similarly, a look at the storage battery 120(2) therebelow clearly shows that the full charge capacity is 16 kWh, the charging performance is 4 kWh, and the discharging performance is 4 kWh. A looking at the storage battery 120(3) clearly shows that the full charge capacity is 18 kWh, the charging performance is 3 kWh, and the discharging performance is 3 kWh. A look at the storage battery 120(4) clearly shows that the full charge capacity is 10 kWh, the charging performance is 1 kWh, and the discharging performance is 1 kWh.
A control information calculation process for creating a charge-discharge control signal will be explained by referring to the flowcharts of
The charging-discharging rate operation part 114 first acquires the requested charging-discharging rate information from the energy management system 30 (S10). The requested charging-discharging rate information comprises the amount of electrical energy, which must be either charged to or discharged from all the storage batteries 120 managed by the storage battery control apparatus 110, and the load prediction information.
The charging-discharging rate operation part 114 acquires the storage battery information of each storage battery 120 from the storage battery management DB 113. The storage battery information comprises the remaining capacity information T10 and the charging-discharging performance information T20 (S11). That is, the storage battery information comprises the full charge capacity, the discharging performance, the charging performance, and the remaining capacity of each storage battery 120.
The charging-discharging rate operation part 114 respectively calculates the charging capability and the discharging capability, which correspond to an elapsed time from the current time, based on the remaining capacity, and discharging performance and charging performance of each storage battery 120 (S12). The charging capability corresponding to an elapsed time is information showing how the charging capability (charging performance) will change over the course of time from the current time. Similarly, the discharging capability corresponding to an elapsed time is information showing how the discharging capability (discharging performance) will change over the course of time from the current time.
The charging capability corresponding to an elapsed time is shown in
The charging-discharging rate operation part 114 respectively calculates the total value of the charging capability per time period and the discharging capability per time period by adding the charging capability and the discharging capability of each storage battery 120 to each control cycle.
The charging capability per time period and the discharging capability per time period are for calculating how much charging and discharging are possible when the charging-discharging performance of the storage battery 120 is displayed to the utmost at the current remaining capacity for each control cycle time period.
A storage battery 120 comprising the charging-discharging performance shown in
The charging capability per period of time of the storage battery 120(1) changes as shown in
Similarly, look at the storage battery 120(2) therebelow. The remaining capacity of the storage battery 120(2) is 8 kWh, 4 kWh of energy is charged in the first one hour period, and 4 kWh of energy is charged in the next one hour period. The result is that the remaining capacity of the storage battery 120(2) reaches 16 kWh, which is the full charge capacity. Therefore, in the third one hour period and beyond, it becomes impossible to charge the storage battery 120(2).
Look at the storage battery 120(3). The remaining capacity of the storage battery 120(3) is 9 kWh, and, in accordance with its charging performance, 3 kWh of energy is charged in the first one hour period. In the second and third one hour periods, 3 kWh of energy each are charged to the storage battery 120(3). The result is that the remaining capacity of the storage battery 120(3) reaches 18 kWh, which is the full charge capacity. Therefore, in the fourth one hour period and beyond, it becomes impossible to charge the storage battery 120(3).
Look at the storage battery 120(4). The remaining capacity of the storage battery 120(4) is 5 kWh, and, in accordance with its charging performance, 1 kWh of energy is charged in the first one hour period. In the second, third, fourth, and fifth one hour periods, 1 kWh of energy each is charged to the storage battery 120(4). The result is that the remaining capacity of the storage battery 120(4) reaches 10 kWh, which is the full charge capacity. Therefore, in the sixth one hour period and beyond, it becomes impossible to charge the storage battery 120(4).
When the charging rate of each of the respective units of time (control cycles) are totaled, the first one hour period is 13 kWh, the second one hour period is 8 kWh, the third one hour period is 4 kWh, the fourth one hour period is 1 kWh, and the fifth one hour period is 1 kWh. The total value of the charging rate in the sixth one hour period and beyond is 0 kWh.
The change in discharging capability per unit of time will be explained by referring to
Look at the storage battery 120(1). The remaining capacity of the storage battery 120(1) is 5 kWh, and the discharging capability is 5 kWh. Since 5 kWh of energy is discharged in the first one hour period, the remaining capacity of the storage battery 120(1) becomes 0 kWh. Therefore, the storage battery 120(1) is unable to discharge in the second one hour period and beyond.
Look at the storage battery 120(2). The remaining capacity of the storage battery 120(2) is 8 kWh, and the discharging capability is 4 kWh. The storage battery 120(2) discharges 4 kWh of energy in the first one hour period, and discharges 4 kWh of energy in the subsequent second one hour period. At this point in time, the remaining capacity of the storage battery 120(2) becomes 0 kWh. Therefore, the storage battery 120(2) is unable to discharge in the third one hour period and beyond.
Look at the storage battery 120(3). The remaining capacity of the storage battery 120(3) is 9 kWh, and the discharging capability is 3 kWh. The storage battery 120(3) discharges 3 kWh of energy in the first one hour period, and discharges 3 kWh of energy each in the second and third one hour periods. At the point in time when the third one hour period ends, the remaining capacity of the storage battery 120(3) is 0 kWh. Therefore, the storage battery 120(3) is unable to discharge in the fourth one hour period and beyond.
Look at the storage battery 120(4). The remaining capacity of the storage battery 120(4) is 5 kWh, and the discharging capability is 1 kWh. The storage battery 120(4) discharges 1 kWh of energy each in the first through the fifth one hour periods. At the point in time when the fifth one hour period ends, the remaining capacity of the storage battery 120(4) is 0 kWh. Therefore, the storage battery 120(4) is unable to discharge in the sixth one hour period and beyond.
When the discharging rate of each of the respective units of time (control cycles) are totaled, the first one hour period is 13 kWh, the second one hour period is 8 kWh, the third one hour period is 4 kWh, the fourth one hour period is 1 kWh, and the fifth one hour period is 1 kWh. The total value of the charging rate in the sixth one hour period and beyond is 0 kWh.
The topmost region of the graph is a first storage battery display region showing the changes over time in charging and discharging related to the storage battery 120(1). The next region is a second storage battery display region showing the changes over time in charging and discharging related to the storage battery 120(2). The next region after that is a third storage battery display region showing the changes over time in charging and discharging related to the storage battery 120(3). The next region after that is a fourth storage battery display region showing the changes over time in charging and discharging related to the storage battery 120(4).
Return to the flowchart of
Although various allocation methods are conceivable, for example, the requested charging-discharging rate is allocated in order from the storage battery having the lowest charging-discharging performance. Generally speaking, a storage battery has a technical feature whereby deterioration occurs as charging and discharging are performed repeatedly. In addition, a higher performance storage battery is generally expensive, and a lower performance storage battery is generally inexpensive.
In this example, as shown in the table T20 of
Therefore, the operating costs of the storage battery control system 10 can be lowered by using the lowest performance storage battery 120 as much as possible to meet the requirements from the energy management system 30. Consequently, in this example, a case in which the requested charging-discharging rate is small, for example, is dealt with using the least expensive low-performance storage batteries 120(3) and 120(4), and a case in which the requested charging-discharging rate is large, is dealt with using the expensive high-performance storage batteries 120(1) and 120(2). In accordance with this, the high-performance storage batteries 120(1) and 120(2) are used as infrequently as possible, delaying deterioration.
Therefore, the allocation order of priority becomes the storage battery 120(4), the storage battery 120(3), the storage battery 120(2), and the storage battery 120(1), in that order. The lowest performance storage battery 120(4) is used on a priority basis, and the likelihood of using the highest performance storage battery 120(1) is reduced.
To make this easier to understand, in the example shown in a table T10 of
In this case, first, the charging-discharging rate operation part 114 selects the storage battery 120(4), which has the highest order of priority, from among the four storage batteries 120(1) through 120(4), and allocates 1 kWh, which is the energy capable of being discharged over the next one hour, as the storage battery 120(4) discharging rate.
As a result of this, the unallocated discharging rate (the discharging rate required by the energy management system 30) becomes 4 kWh. Consequently, the charging-discharging rate operation part 114 selects the next highest priority storage battery 120(3), and allocates 3 kWh, which is the energy capable of being discharged over the next one hour period, as the storage battery 120(3) discharging rate.
As a result of this, the unallocated discharging rate becomes 1 kWh. Consequently, the charging-discharging rate operation part 114 selects the next highest priority storage battery 120(2). The storage battery 120(2) is able to discharge 4 kWh of energy over the next one hour period. However, since the unallocated discharging rate is 1 kWh, 1 kWh is allocated to the discharging rate of the storage battery 120(2).
As a result of this, the unallocated discharging rate becomes 0, and as such, the lowest priority storage battery 120(1) is not used. Thus, the control plan (control pattern) for determining how much of a charging-discharging rate is allocated to each storage battery 120 is decided individually like this (S13).
The high-performance storage battery 120(1) does not change since discharging has not been instructed. Since a discharge of 1 kWh was allocated to the next highest performance storage battery 120(2), although the future discharging capability of the storage battery 120(2) is 4 kWh over the one hour period from the current time, this discharging capability becomes 3 kWh for the next one hour period. Alternatively, the charging capability of the storage battery 120(2) is 4 kWh for the one hour period from the current time, is 4 kWh for the subsequent one hour period, and becomes 1 kWh for the next one hour period after that.
Since a discharge of 3 kWh was allocated to the storage battery 120(3), the future discharging capability of the storage battery 120(3) makes it possible for the storage battery 120(3) to discharge 3 kWh each hour over a two hour period from the current time. Alternatively, the charging capability of the storage battery 120(3) makes it possible for the storage battery 120(3) to charge 3 kWh per hour over a four hour period from the current time.
Since a discharge of 1 kWh was allocated to the storage battery 120(4), the storage battery 120(4) is able to discharge 1 kWh per hour over a four hour period from the current time. The charging capability of the storage battery 120(4) makes it possible for the storage battery 120(4) to charge 1 kWh per hour over a six hour period from the current time.
Return to the flowchart of
In a case where the contents of the load prediction information is “load tends to maintain current state”, the charging-discharging rate operation part 114 selects the storage battery control mode, which places priority on balancing the charging-discharging performance of the storage battery 120 (S15). In this example, this control mode is called the balanced mode.
In a case where the contents of the load prediction information is “load tends to increase”, the charging-discharging rate operation part 114 selects the storage battery control mode, which places priority on the discharging performance of the storage battery 120 (S16). In this example, this control mode is called the discharging performance priority mode.
In a case where the contents of the load prediction information is “load tends to decrease”, the charging-discharging rate operation part 114 selects the storage battery control mode, which places priority on the charging performance of the storage battery 120 (S17). In this example, this control mode is called the charging performance priority mode.
The charging-discharging rate operation part 114 creates a plan (control pattern) for controlling the charging and discharging of each storage battery 120 in accordance with the selected control mode.
As shown in
Another example T10(2) of the remaining capacity information is shown at the top of
Upon carrying out the same computations therebelow, the SOC of the storage battery 120(2) is 100%, the SOC of the storage battery 120(3) is roughly 33%, and the SOC of the storage battery 120(4) is 80%.
The storage battery 120(1) is not charged at all, and as such, does not lose its discharging capability. However, because the remaining capacity of the storage battery 120(1) is 0 kWh, the storage battery 120(1) is able to accumulate surplus energy generated by the power grid 41 until this energy reaches 10 kWh, which is the full charge capacity.
The storage battery 120(2) is fully charged, and as such, cannot be charged any more, but is able to discharge until it has used up 16 kWh of energy, which is the full charge capacity. The explanations for the storage batteries 120(3) and 120(4) will be omitted.
Return to
In the case of the remaining capacity information T10(2) shown at the top of
As a balanced mode evaluation index, the sum of an absolute value of the charging-discharging rate required for the SOC of each storage battery 120 to become 50% is called “required charging-discharging rate” here. The required charging-discharging rate in the above-cited example is 19 kWh (=5+8+3+3).
Next, the charging-discharging rate operation part 114 computes the amount of energy capable of being charged and discharged in a one hour period from the current time from among the charging-discharging rates required for realizing a SOC of 50% (S151).
In the example of the remaining capacity information T10(2) of
Similarly, the storage battery 120(2) must discharge 8 kWh to realize the SOC of 50%. Since the storage battery 120(2) is able to discharge 4 kWh in one hour, the required discharging rate is 4 kWh.
Similarly, the storage battery 120(3) must be charged 3 kWh to realize the SOC of 50%. Since the storage battery 120(3) can be charged 3 kWh in one hour, the required charging rate is 3 kWh.
In the case of the storage battery 120(4), a discharge of 3 kWh is required for realizing the SOC of 50%. Since the storage battery 120(4) is able to discharge 1 kWh in one hour, the required discharging rate is 1 kWh.
The charging and discharging already allocated in Step S13 makes it necessary to implement the allocation of this Step S151. For example, in a case where a 5 kWh charge has been allocated to the storage battery 120(1) in Step S13, the charging-discharging capability of the storage battery 120(1) has already been exhausted, and as such, the amount of energy capable of being charged and discharged is 0 (Step S151).
That is, Step S13 of
Thus, in this example, the charging and discharging of each storage battery 120 is individually controlled in accordance with the power supply-demand situation (S13), and the remaining capacity of each storage battery 120 is adjusted beforehand in accordance with a load trend prediction (S151). Therefore, as long as the load fluctuation trend prediction is not way off the mark, each storage battery 120 can be used rapidly and efficiently.
Return to the flowchart of
That is, the charging-discharging rate operation part 114 combines the charging rate per hour required for realizing the SOC of 50% in a certain storage battery 120 with the discharging rate per hour required for realizing the SOC of 50% in another storage battery 120.
Matching also allocates energy in order from the storage battery having the lowest charging-discharging performance for the same reason as described using Step S13.
A matching process in a case where the requested charging-discharging rate is 0, and the load prediction information is “load tends to maintain current state” will be explained on the premise of the remaining capacity information T10(2) shown in
The charging-discharging rate operation part 114 allocates 1 kWh of the 3 kWh charging rate of the storage battery 120(3) to the 1 kWh discharging rate of the storage battery 120(4). The charging-discharging rate operation part 114 allocates 2 kWh of the 4 kWh discharging rate of the storage battery 120(2) to the remaining 2 kWh charging rate of the storage battery 120(3). The charging-discharging rate operation part 114 allocates 2 kWh of the 5 kWh charging rate of the storage battery 120(1) to the remaining 2 kWh discharging rate of the storage battery 120(2). The 3 kWh charging rate remaining in the storage battery 120(1) constitutes energy, which could not be matched.
As a result of the above-described matching process, the control rate of the respective storage batteries 120 becomes a 2 kWh charge for the storage battery 120(1), a 4 kWh discharge for the storage battery 120(2), a 3 kWh charge for the storage battery 120(3), and a 1 kWh discharge for the storage battery 120(4).
Remaining capacity information T10(3) after the matching process is shown at the bottom of
The required charging-discharging rates in the remaining capacity information T10(3) will be considered. Because the remaining capacity of the storage battery 120(1) is 2 kWh (=0+2) and the full charge capacity is 10 kWh, the charging rate required to realize a SOC of 50% is 3 kWh.
Because the remaining capacity of the storage battery 120(2) is 12 kWh (=16−4) and the full charge capacity is 16 kWh, the discharging rate required to realize a SOC of 50% is 4 kWh.
Because the remaining capacity of the storage battery 120(3) is 9 kWh (=6+3) and the full charge capacity is 18 kWh, the energy required to realize a SOC of 50% is 0.
Because the remaining capacity of the storage battery 120(4) is 7 kWh (=8−1) and the full charge capacity is 10 kWh, the discharging rate required to realize a SOC of 50% is 2 kWh.
When the charging-discharging rate operation part 114 computes the “required charging-discharging rate” described hereinabove, the result is 3+4+0+2=9, which is an improvement over the case of the remaining capacity information T10(2) shown in the top part of
The discharging performance priority mode (S16) will be explained by returning to the flowchart of
Thus, the charging-discharging rate operation part 114 compares the discharging performance of the respective storage batteries 120 acquired in Step S11 of
The charging-discharging rate operation part 114 computes the charging-discharging capability for each storage battery 120 for each unit of time that elapses (Step S161).
The charging-discharging rate operation part 114 performs a charging-discharging rate matching process to realize a discharging performance priority state. The charging-discharging rate matching process for discharging performance priority is for distributing the remaining capacity of each storage battery 120 beforehand to enable the highest possible discharging performance to continue for the respective storage batteries 120 as a whole.
In this example, multiple storage batteries 120(1) through 120(4) are likened to a single virtual storage battery. Then, the storage battery control apparatus 110, in a case where the discharging performance priority mode is to be executed, individually controls the remaining capacity of each storage battery 120 comprising the virtual storage battery to make the discharging performance of the virtual storage battery as large as possible.
In the case shown in the charging-discharging performance information T20 of
In the case of the remaining capacity information T10(2) shown in the top part of
The discharging capability of the storage battery 120(4) for the second hour is 1 kWh, the discharging capability of the storage battery 120(3) for the second hour is 3 kWh, and the discharging capability of the storage battery 120(2) for the second hour is 4 kWh. Therefore, 5 kWh, which is the total of the 1 kWh discharging rate from the low discharging performance storage battery 120(4), the 3 kWh discharging rate from storage battery 120(3), and the 1 kWh discharging rate from storage battery 120(2), is charged to the storage battery 120(1).
The 1 kWh-worth of discharging capability from the storage battery 120(4) is lost in accordance with the 1 kWh from the storage battery 120(4) being charged to the storage battery 120(1) as shown in the black-border parts in
Similarly, the 3 kWh-worth of discharging capability from the storage battery 120(3) is lost in accordance with the 3 kWh from the storage battery 120(3) being charged to the storage battery 120(1). Alternatively, the storage battery 120(3) obtains 3 kWh-worth of charging capability as shown by the arrow.
Similarly, the 1 kWh-worth of discharging capability from the storage battery 120(2) is lost in accordance with the 1 kWh from the storage battery 120(2) being charged to the storage battery 120(1). Alternatively, the storage battery 120(2) obtains 1 kWh-worth of charging capability as shown by the arrow.
As a result, a total of 5 kWh of energy is charged to the storage battery 120(1) in a one-hour period from the current time. Therefore, instead of losing 5 kWh-worth of charging capability as shown in the black-border part, the storage battery 120(1) obtains 5 kWh-worth of discharging capability as shown by the arrow.
The charging performance priority mode (S17) will be explained by returning to
Thus, the charging-discharging rate operation part 114 compares the charging performance of the respective storage batteries 120 acquired in Step S11 of
The charging-discharging rate operation part 114 computes the charging-discharging capability for each storage battery 120 for each unit of time that elapses (Step S171).
The charging-discharging rate operation part 114 performs a charging-discharging rate matching process to realize a charging performance priority state (S172).
The charging-discharging rate matching process for charging performance priority is for distributing the remaining capacity of each storage battery 120 so that the highest possible charging performance will continue.
In the case of the charging-discharging performance information T20 of
In the case of the remaining capacity information T10(2) shown at the top of
According to
The charging capability of the storage battery 120(4) for the second hour is 1 kWh, the charging capability of the storage battery 120(3) for the second hour is 3 kWh, and the discharging capability of the storage battery 120(1) for the second hour is 5 kWh. Therefore, 1 kWh is charged to the storage battery 120(4), which has the lowest charging performance, and 3 kWh is charged to the storage battery 120(3), which has the next lowest charging performance, by discharging of 4 kWh of energy from the storage battery 120(2).
Return to
The charging-discharging rate operation part 114, after notifying the control part 123 of each storage battery 120 of the control rate, waits for a prescribed control cycle (S19), and returns once again to Step S10.
This example, being configured as described hereinabove, achieves the following effects. In this example, the storage battery control apparatus 110 can handle multiple storage batteries 120 just like a single virtual storage battery. Then, this example controls the remaining capacity of each storage battery 120 so as to be able to deal with a power supply-demand prediction. Therefore, in this example, it is possible to systematically adjust the remaining capacity of each storage battery 120 and to make effective use of each storage battery 120, thereby making it possible to operate the power grid stably and efficiently.
This example predicts which of the balanced mode, the discharging performance priority mode, or the charging performance priority mode is the relevant control mode, and adjusts the remaining capacity of each storage battery 120 beforehand in accordance with the predicted control mode. Therefore, it is possible to quickly deal with fluctuations in power demand.
In this example, since the storage batteries 120 are used in ascending order of charging-discharging performance, it is possible to curb the deterioration of an expensive storage battery, enabling system operating costs to be reduced.
Example 2 will be explained by referring to
The storage batteries 120(1) through 120(3) are used as normal storage batteries. The storage battery 120(SP) is used as a spare storage battery, and is not used at normal times. In
In a case where any of the normal storage batteries 120(1) through 120(3) stops functioning due to maintenance or the like, the spare storage battery 120(SP) is used in place of the storage battery targeted for maintenance.
Being configured like this, this example also achieves the same effects as Example 1. In addition, this example comprises a spare storage battery 120(SP). Therefore, it is possible to use multiple storage batteries efficiently and to stabilize control of the power grid 41 even in a case where normal storage batteries 120(1) through 120(3) have stopped functioning as a result of maintenance or the like.
Instead of providing a spare storage battery 120(SP), for example, the electricity bill can be raised temporarily during maintenance. This will make it possible to reduce the power consumption of the customers 20 while the storage battery 120 is undergoing maintenance.
Example 3 will be explained by referring to
The manufacturing equipment 20A(1) and 20A(2) correspond to the customers 20 of Example 1. Each piece of manufacturing equipment 20A(1) and 20A(2) comprises a power measurement part 21. The factory energy management system 30A corresponds to the energy management system 30 of Example 1. Although omitted from the drawing, the factory energy management system 30A comprises a load prediction part 31 and a requested charging-discharging rate decision part 32.
The storage battery control system 10A comprises multiple electric vehicles 120A(1) through 120A(4), and a storage battery control apparatus 110A. Each electric vehicle 120A is coupled to the factory power grid 41 via an electric plug 42. Each electric vehicle 120A corresponds to a storage battery 120 of Example 1, and comprises a communication part 121, a storage battery main unit 122, and a control part 123.
A worker travels to the factory 50 by riding in either an electric vehicle 120A he owns himself, or an electric vehicle 120A lent out by the company. Multiple electric plugs 42 are installed in the factory 50 parking lot. Each electric vehicle 120A is electrically coupled to the factory 50 power grid 41 via an electric plug 42.
Thereafter, the storage battery of the electric vehicle 120A is controlled and the power grid 41 stabilized in accordance with the power demands inside the factory 50 the same as described in Example 1. This example may be combined with a stationary-type storage battery.
Being configured like this, this example also achieves the same effects as Example 1. In addition, in this example, it is possible to make effective use a storage battery of an electric vehicle 120A. The example of a factory 50 was used in the explanation, but the venue is not limited to a factory, and, for example, the present invention can be applied to an office building, a multi-unit housing complex, a hospital, municipal offices, and so forth.
Example 4 will be explained by referring to
It is possible for there to exist multiple control patterns for adjusting the remaining capacity in accordance with the balanced mode, the discharging performance priority mode, and the charging performance priority mode. In Example 1, the use of storage batteries 120 in ascending order from that with the lowest charging-discharging performance is given as one selection criterion.
In contrast to this, the focus in this example is on responsiveness. In this example, as shown in the graph of
The storage battery control apparatus 110, when deciding on a charging-discharging control pattern for each of the respective storage batteries 120 for adapting to the balanced mode, the discharging performance priority mode, or the charging performance priority mode, selects a control pattern having the lowest total evaluation score from among multiple candidates. Therefore, this example also achieves the same effects as Example 1. In addition, in this example, it is possible to enhance the response performance of the storage batteries 120 as a whole, and to rapidly deal with sudden fluctuations in power supply and demand.
Example 5 will be explained by referring to
It is supposed here that the storage battery 120(1) is higher performance than the storage battery 120(2), and that the storage battery 120(3) is higher performance than the storage battery 120(4). The superiority or inferiority of the performance of the storage battery 120(1) and the storage battery 120(3), and the superiority or inferiority of the performance of the storage battery 120(2) and the storage battery 120(4) do not particularly matter.
The storage battery control apparatus 110B utilizes the charging and the discharging of the storage batteries 120(1) and 120(2) of the first storage battery group to meet the power demands of the customer 20(1). Similarly, the storage battery control apparatus 110B utilizes the charging and the discharging of the storage batteries 120(3) and 120(4) of the second storage battery group to meet the power demands of the customer 20(2).
That is, in this example, the configurations shown as selection range 1 and selection range 2 respectively comprise virtual storage batteries. Each virtual storage battery is associated with a prescribed customer 20, who is a short distance away in terms of the electric power supply.
The storage battery control apparatus 110B, when deciding from among the above-mentioned multiple control patterns, selects a control pattern having the smallest total value of the distance over which power is supplied to the customer. This makes it possible to stabilize the power supply and demand of the power grid 41 more efficiently because it enables the transmission distance to be shortened and voltage drops to be reduced.
The present invention is not limited to the examples described hereinabove. A person having ordinary skill in the art will be able to make various additions and changes without departing from the scope of the present invention. For example, the configuration may be such that the control pattern is selected on the basis of the cost of the storage battery.
The present invention, for example, can also be expressed as a computer program invention as follows.
A computer program for controlling, using a computer, the operation of a storage battery coupled to a power grid, the computer program causing the computer to:
acquire storage battery information comprising a charging-discharging performance and a remaining capacity from multiple storage batteries coupled to the power grid;
acquire power supply-demand prediction information showing a prediction of power supply and demand in a prescribed range from an energy management system for managing the power supply and demand in the prescribed range;
decide an individual charging-discharging rate for each of the above-mentioned storage batteries based on the above-mentioned storage battery information and the above-mentioned power supply-demand prediction information; and
send the decided individual charging-discharging rate to each storage battery, and operate the above-mentioned each storage battery based on the above-mentioned individual charging-discharging rate received from a storage battery control apparatus.
Number | Date | Country | Kind |
---|---|---|---|
2011-246554 | Nov 2011 | JP | national |