This is a U.S. national stage of application No. PCT/FR03/00723, filed on 6 Mar. 2003.
Priority is claimed on that application and on the following application:
Country: France, Application No. 02/03637, Filed 22 Mar. 2002.
The PCT International application was published in the French language.
The present invention relates to a structure for the transport, commissioning and decommissioning of a deck of an offshore fixed oil production platform. Moreover, it relates to a method for the transport, commissioning and decommissioning of a deck of a fixed oil platform.
A known approach to oil production is to install above an oil field a fixed oil platform with a deck carrying production equipment and accommodation premises, in particular. A column anchored to the seabed supports the deck.
To date, there are two major methods for the transport, commissioning and decommissioning of a fixed oil platform deck.
The first method involves using barge-mounted lifting cranes for transfering the oil platform deck from the transport vessel to a superstructure comprising a supporting column. Although this method has been the most widely used to date, it has limitations.
The first limitation is effectively the capacity of the lifting cranes, which may require the deck to be fabricated in several units, thereby significantly increasing the fabrication cost of the oil platform deck and the cost of commissioning and decommissioning said deck.
The second limitation lies in the fact that this method imposes the need for a relatively long favorable time window to be able to perform this operation at sea under satisfactory conditions.
Without incurring a considerable increase in cost, this method is difficult to implement in areas in which time windows are relatively short, for example in the North Sea.
The second method involves commissioning the oil platform deck in a single unit by causing it to float over the supporting column. The deck is then positioned on this supporting column either by a ballasting/deballasting system or by a mechanical system.
In the case of a ballasting system, the oil platform deck is supported either by a floating support comprising, for example, a barge or pontoons or a U-shaped floating support, or by using a structure associated with this floating support.
In cases in which the superstructure can be ballasted or deballasted, deballasting of the floating support and ballasting of the superstructure is a known approach used to decommission an oil platform deck. The decommissioning operation can be performed relatively quickly because the superstructure offers a large ballasting capacity. In cases in which the superstructure is anchored to the seabed, only the deballasting capacity of the floating support can be used. The operation progresses slowly because this capacity is limited.
Systems using ballasting or deballasting have drawbacks due mainly to the fact that they require a complex structure in terms of chambers or pumps and very accurate control of chamber filling and emptying to maintain floating support stability during the operation. Operation speed depends on the ballasting and deballasting capacity of these floating support chambers, which is generally rather low inasmuch as the operation speed is often limited, especially when the superstructure is anchored to the seabed. Furthermore, maritime conditions must be favorable in order to perform such an operation in satisfactory conditions.
An alternative to the ballasting/deballasting system is to use a mechanical system to raise or lower the oil platform deck. These systems enable an oil platform deck commissioning or decommissioning operation to be performed faster than the abovementioned systems.
For this purpose, a known approach involves a system including two barges that support the oil platform deck using two swiveling structures. Furthermore, a cable and winch system is used to ensure system stability and control the raising and lowering of the oil platform deck.
Barge clearance is controlled by actuating these winches, thereby allowing the deck to be raised or lowered. However, the stability of this type of mechanical system is very insecure and it is frequently incompatible in relation to open sea use.
Another mechanical system comprises a rack and pinion system for raising or lowering the oil platform deck.
In general, mechanical systems used to date for commissioning and decommissioning an oil platform deck are faster than ballasting or deballasting systems, but they are dependent on maritime conditions, which makes them difficult to use in areas in which favorable time windows are relatively short.
The object of the invention is to overcome these drawbacks by proposing a structure for the transport, commissioning or decommissioning of a fixed oil platform deck that has been designed to facilitate different operations, whilst achieving a significant saving of time, avoiding any risk of polluting the environment and increasing the safety of personnel in charge of performing the various operations.
For this purpose, the subject of the invention is a structure for the transport, commissioning and decommissioning of a deck of an offshore fixed oil production platform, characterized in that it comprises:
Depending on the specific implementation methods:
A further subject of the invention is a method for decommissioning and transporting a fixed oil platform deck from a production site to a deck disassembly quay, characterized in that it comprises the following stages:
A further object of the invention is a method for transporting from a quay to a production site and commissioning a fixed oil platform deck, characterized in that it comprises the following stages:
floating the structure until it is near to the production site,
The invention will be better understood on reading the following description, provided only as an example and made in reference to the appended drawings, in which:
A fixed oil platform designated generally by reference 1 and including a deck 2, featuring customary production equipment and accommodation premises, is diagrammatically represented in
A structure designated by general reference 10 and represented in
General structural dimensions and proportions between the various units making up this structure 10 have not necessarily been respected in
In general, the structure 10 includes a U-shaped floating hull 11 fitted with lifting legs 12 for this hull 11, adapted so as to rest upon the seabed. The hull 11 features two lateral sections 11a and a link section 11b connecting the two lateral sections 11a.
In the construction example represented in
In an alternative embodiment, the hull 11 may be fitted with three lifting legs 12 arranged in a triangle, one leg 12 being located on each lateral section 11a and one leg 12 being located on the link section 11b.
The bottom end of each leg 12 terminates with a shoe 13 designed to bear on the seabed 4.
In this construction method, each leg 12 has a triangular section as represented in
Each leg 12 is made up of three chords 14 interlinked by a lattice of steel beams 15.
Each leg 12 is associated with mechanical displacement means designated by general reference 20 (
The mechanical displacement means 20 for each leg 12 are located inside a supporting framework 16, also called a “jack-house” by specialists, which itself is supported by the hull 11.
As represented in
The structure 10 also features a shuttle designated by general reference 30, which can be displaced along the legs 12 by the hull 11 and is intended to be applied to the bottom face of deck 2 of oil platform 1, as will be seen later.
The shuttle 30 is made up of independent units 31, whose number corresponds to the number of legs 12 of the structure 10, as represented in
In an alternative embodiment, the shuttle 30 may also comprise a single unit in the form of a frame supported by lifting legs 12 using mechanical displacement means 20.
In reference to
The unit 31 includes a vertical branch 32 for positioning the unit on a lateral face of the supporting framework 16 of the hull 11 and a horizontal branch 33 for supporting the deck 2 during transport. The vertical branch 32 features guidance means along the corresponding leg 12 and means of locking onto the leg 12.
Two opposing flanges 34 located in the top section of the vertical branch 32 and extending parallel to the horizontal branch 33 of the unit 31 form guidance means. Each flange 34 determines, in conjunction with said vertical branch 32, a housing 35 for one plate 21 on the corresponding leg 12. Each unit 31 is thereby guided along the corresponding leg 12 by plates 21.
As represented by
Furthermore, each unit 31 of the shuttle 30 is fitted with devices ensuring lateral stabilization of the deck 2 in its supported position. These devices are formed by at least one hydraulic or pneumatic horizontal displacement cylinder 38 located, for example, in the vertical branch 32 of said unit 31.
As represented, in particular in
Finally, the top face of the horizontal branch 33 of each unit 31 features elastic bearing devices 41 for the deck 2 of the oil platform 1. These elastic devices 41 comprise, for example, elastomer blocks or inflatable cushions or any other suitable system.
As represented in
Finally, the open part of hull 11 features a door 43 formed by, for example, two gates 44 which can be moved from an open position for positioning the structure 10 beneath the deck 2 to a closed position during transfer of said deck 2 by the structure 10.
Transport of the deck 2 by the structure 10 between the production site and a port quay is performed in the following way.
First and foremost, as represented by
Geared motor units 26 are then actuated to rotationally drive the pinions 27, which engage with sets of teeth 22 on plates 21 in each lifting leg 12 to bring the shoes 13 into contact with the seabed 4.
As soon as the shoes 13 contact the seabed 4, the hull 11 moves upward along the lifting legs 12 under the effect of the rotational driving of the pinions 27, which engage with sets of teeth 22 on plates 21 in each lifting leg 12. By moving upward, the hull 11 lifts the shuttle 30 to apply elastic devices 41 of each unit 31 against the bottom face of the deck 2. Driving of the pinions 27 is stopped and the counterlocking racks 36 are actuated by the cylinders 37 to make these counterlocking racks 36 engage with the adjacent teeth 22 to lock each unit 31 of the shuttle 30 onto the lifting legs 12, as represented in
The supporting column 3 is then separated from the deck 2, for example by cutting its connecting rods, and the combination comprising hull 11, shuttle 30 and deck 2 is lifted to separate the deck 2 from the supporting column 3, which remains in a vertical position, as represented in
After these different operations, the hull 11 is lowered into floatation by reverse driving of the pinions 27, which engage with sets of teeth 22 (
The lifting legs 12 are then relowered to bring the shoes 13 to bear on the seabed 4 and the hull 11 is raised by rotational driving of the pinions 27 to bring the hull 11 into contact with the units 31 of the shuttle 30 (
During displacements of the shuttle 30 units 31 with respect to the hull 11, these units 31 are guided by flanges 34 on the vertical branch 32 and by the slideways 39 and 40.
During transport, lateral stabilization of the deck 2 is ensured by the cylinders 38 on each unit 31 of the shuttle 30, which are in contact with the lateral faces of the deck 2.
The hull 11 supporting the deck 2 is floated (
The deck 2 is transported by the structure 10 from the port quay to the production site by performing reverse operations which are mentioned in brief hereinbelow.
Firstly, the transport structure 10 is floated near to the quay and the lifting legs 12 are applied to the seabed to stabilize the hull 11. The link between the hull 11 surface and the quay is ensured by the linkspan 6 and the deck 2 is transferred from the quay onto the shuttle 30 units 31 by making it slide on the rails 42.
The deck 2 is then laterally stabilized on the units 31 of the shuttle 30 using cylinders 38 on each unit 31, the linkspan 6 is removed and the lifting legs 12 are raised.
The structure 10 supporting the deck 2 is floated near to the production site and the lifting legs 12 are applied to the seabed such that the deck 2 is lifted using the hull 11 and the shuttle 30.
The units 31 of the shuttle 30 are locked onto lifting legs 12 by means of counterlocking racks 36, which are actuated by the cylinders 37 such that these counterlocking racks 36 engage with adjacent teeth 22, thereby locking each unit 31 of the shuttle 30 onto the lifting legs 12.
The hull 11 is brought into floatation and the legs 12 of the structure 11 are raised. The deck 2 is positioned above the supporting column 3 of the oil platform 1 and the lifting legs 12 of the structure 10 are again applied to the seabed. The hull 11 is lifted to bring it into contact with the units 31 of the shuttle 30 and these units 31 are unlocked, then the hull 11, the shuttle 30 and the deck 2 are lowered to place this deck 2 on the supporting column 3.
The deck 2 is fixed to the supporting column 3, the hull 11 and the shuttle 30 are lowered to bring said hull 11 into floatation, then the lifting legs 12 are raised.
The structure 10 is then removed from the production site.
The structure according to the invention has the advantage of being able to transport directly the whole oil platform deck from the production site to a fixed site, where its disassembly can be undertaken safely and without risk of polluting the marine environment or vice versa, from a fixed site to a production site, where the deck is mounted on its supporting column.
Furthermore, the different transfer and transport stages can be performed without any ballasting operation, thereby achieving considerable time saving, which is significant in regions in which atmospheric conditions change very quickly.
Finally, operations involving the transfer of the deck from the transport structure to the quay and vice versa are facilitated because the transport structure hull is level with this quay.
Number | Date | Country | Kind |
---|---|---|---|
02 03637 | Mar 2002 | FR | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/FR03/00723 | 3/6/2003 | WO | 00 | 9/21/2004 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO03/080425 | 10/2/2003 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
3830071 | LeTourneau | Aug 1974 | A |
3967457 | Lovie | Jul 1976 | A |
4382718 | Inoue et al. | May 1983 | A |
4431343 | Uchiyama et al. | Feb 1984 | A |
4456404 | Evans | Jun 1984 | A |
4813814 | Shibuta et al. | Mar 1989 | A |
5224798 | Thomas | Jul 1993 | A |
5855455 | Williford et al. | Jan 1999 | A |
6840713 | Schia et al. | Jan 2005 | B1 |
20080131209 | Thomas | Jun 2008 | A1 |
Number | Date | Country |
---|---|---|
57-9911 | Jan 1982 | JP |
58-160427 | Sep 1983 | JP |
62017218 | Jan 1987 | JP |
63-44010 | Feb 1988 | JP |
Number | Date | Country | |
---|---|---|---|
20050158125 A1 | Jul 2005 | US |