Subterranean structures and methods for constructing subterranean structures

Information

  • Patent Grant
  • 6616380
  • Patent Number
    6,616,380
  • Date Filed
    Monday, October 7, 2002
    22 years ago
  • Date Issued
    Tuesday, September 9, 2003
    21 years ago
Abstract
One embodiment of the present invention provides for a subterranean structure, having a continuous ribbon slab having a plurality of flights fabricated from concrete. The ribbon slab defines periodic openings therein which generally align between adjacent flights. Another embodiment provides for a method of fabricating a subterranean structure. The method includes excavating soil to form a downward sloping ramp, and forming a concrete slab on the downward sloping ramp. The method further includes continuing to excavate soil to extend the downward sloping ramp to a location under the concrete slab, and continuing to form the concrete slab on the downward sloping ramp so that a subterranean structure is formed having an essentially continuous concrete slab with a first portion which is above and spaced-apart from a second portion.
Description




FIELD OF THE INVENTION




The invention claimed and disclosed herein pertains to methods and apparatus for constructing subterranean structures, as for example foundations for buildings, geo-retaining structures, storage containers, tunnels, and other such structures.




BACKGROUND OF THE INVENTION




There are a number of prior art methods for constructing subterranean walls and other subterranean structures. Prior-art soil-nailed walls achieve the same end of constructing a subterranean “wall”, but the method requires relatively long “nails” (deweydag rods or post tensioning tendons) to be anchored far into adjacent terrain and at relatively high cost. Such soil-nailed walls also require that one side of the “wall” be excavated to drill and insert the soil nails. Another method of forming subterranean walls in-situ is to excavate a deep trench while simultaneously filling the trench with a dense but flowable media (such as mud) to retain the soil on either side of the trench until such time as concrete placed in the trench is consolidated into the trench using a tremie and the concrete displaces the dense media. This method, called “slurry trenching”, is relatively costly and it is difficult to control construction quality since there is no access to the depths of the dense media. Typically, subterranean tanks or holding vessels are constructed by slurry trenching where ground conditions require it and then soil nailing as the excavation within this slurry trench wall system progresses. Afterwards a concrete and/or steel tank is constructed within the confines of this soil nailed and shotcreted tank cavity. (Shotcrete is a method of typically applying concrete to a generally vertical surface by projecting or “blasting” concrete onto the surface.) Subterranean tanks can also be constructed by over-excavating, then constructing a tank in the over-excavated area (as would be done above ground), and then compacting earth back around the tank. Both of these methods are relatively costly and require that excavation for the tank be done before or in conjunction with the construction of the wall. In no case with the current art can a tank or retained space be excavated for after-construction of the walls with the exception of the trench wall described above. Large retaining structures such as deep cuts for freeways and the like are typically performed using soil-nailing or with mechanical structured earth walls.




One major problem with the current art of soil nailing a large excavation is that the open face of the excavation (i.e., the exposed perimeter of the excavation below the current nailing and shotcrete level) makes it difficult to control the inflow of groundwater to the excavation before it can be sealed. Another significant disadvantage of soil nailing is that it is a costly method of stabilizing ground conditions or retained earth, especially when ground water in conjunction with non-cohesive soils requires that a slurry trench be used as a pre-stabilizer so that excavation and subsequent soil nailing can proceed. Soil nailing is also a relatively time consuming process since deep excavations often require soil nails in a closely-spaced pattern, which requires an extensive amount of drilling.




There is no prior art method for tying together or bracing caissons or cast-in-place or driven piles beneath the surface, as for example columns are analogously braced against buckling above ground with floor diaphragm beams and bracing members. Nor is there a current economic method of creating a mass or mono-caisson foundation with a plurality-of caissons or piles. Nor is there currently a method of constructing foundations while simultaneously constructing the intended structure(s) upon the foundation.




SUMMARY OF THE INVENTION




One embodiment of the present invention provides for a subterranean structure having a continuous ribbon slab having a plurality of flights fabricated from concrete. The ribbon slab defines periodic openings therein which generally align between adjacent flights.




Another embodiment of the present invention provides for a method of fabricating a subterranean structure. The method includes excavating soil to form a downward sloping ramp, and forming a concrete slab on the downward sloping ramp. The method further includes continuing to excavate soil to extend the downward sloping ramp to a location under the concrete slab, and continuing to form the concrete slab on the downward sloping ramp so that a subterranean structure is formed having an essentially continuous concrete slab with a first portion which is above, and spaced-apart from, a second portion of the slab.




A further embodiment of the invention provides for a structure having a building and a foundation which supports the building. The foundation includes a continuous ribbon slab having a plurality of flights fabricated from concrete.




Yet another embodiment of the invention provides for a method of supporting a secondary structure. This method includes forming a plurality of generally vertically aligned concrete slabs having an uppermost slab and a lowermost slab, and supporting the secondary structure on the uppermost slab. The secondary structure can also be supported indirectly on the uppermost slab by placing a tertiary structure, such as a concrete slab, between the secondary structure and the uppermost slab.




These and other aspects and embodiments of the present invention will now be described in detail with reference to the accompanying drawings, wherein:











DESCRIPTION OF THE DRAWINGS





FIG. 1

is a three dimensional diagram depicting a spiral slab, such as a concrete slab, which can be used in certain embodiments of the present invention.





FIG. 2

is a plan view depicting subterranean structures in accordance with embodiments of the present invention.





FIG. 3

is a side elevation sectional view of the subterranean structures depicted in FIG.


2


.





FIGS. 4 through 9

are partial, side elevation sectional views depicting variations of one of the subterranean structures depicted in

FIGS. 2 and 3

in accordance with embodiments of the present invention.





FIG. 10

is a side elevation sectional detail depicting a caisson and caisson liner of one of the subterranean structures depicted in

FIGS. 2 and 3

, in accordance with an embodiment of the present invention.





FIGS. 11 and 12

are plan sectional views depicting the caisson and caisson liner depicted in FIG.


10


.





FIG. 13

is a side elevation sectional view depicting another subterranean structure in accordance with an embodiment of the present invention.





FIG. 14

is a “fold-flat” partial side elevation sectional view depicting a method of constructing one of the subterranean structures of

FIG. 3

in accordance with an embodiment of the present invention.





FIGS. 15A through 15F

are sectional end views of the method depicted in

FIG. 14

, depicting various stages of constructing the subterranean structure.





FIGS. 16 and 17

are detail plan views depicting how a concrete slab constructed in accordance with a method of the present invention can be post-tensioned.





FIGS. 18 and 19

are “fold-flat” side elevation sectional views depicting other subterranean structures in accordance with embodiments of the present invention.





FIG. 20

is a side elevation sectional view depicting another subterranean structure in accordance with an embodiment of the present invention, wherein the structure is a vessel.











DETAILED DESCRIPTION OF THE INVENTION




The present invention relates generally to a method and apparatus for constructing ribbon slab, reinforced concrete, subterranean structures such as foundations, subterranean holding vessels, subterranean access and passageways, retaining structures, and earthen or structural columns. The method relates more specifically to the continuous (spiraling) or discrete (level-by-level) descending progression of tunneling and casting of vertically consecutive, typically parallel (i.e., aligned), ribbon slabs. These vertically consecutive or repeating slabs can be used to provide vertically periodic lateral rigidity to cast-in-place caissons, as well as to steel or concrete columns erected within the voids where cast-in-place caissons would ordinary be poured. Further, when bridged one to the other vertically with walls on one or both sides (or filled in-between), the slabs can be used to form hollow core or solid, thick-shell walls which can be used to retain earth and contain liquids by means of out-of-plane flexural and transverse shear rigidity, compressive or tensile hoop rigidity, or a combination thereof as is provided by thick-shell structural element theory. The method includes construction of vertically consecutive but non-spiraling ribbon slabs (level-by-level), compound slope or super elevation of ribbon slabs, complex aggregate shell geometries (spiraling larger or smaller which affects sectional profile geometry of the wall), and ascending progression of the structure in addition to a descending progression of the structure.




Exemplary uses for structures formed by selected methods of the present invention include, but are not limited to: (1) tied caisson foundations; (2) cylindrical, conical, or pyramidal mono-caissons (among other geometries); (3) seepage liners below earthen dams; (4) construct-and-uncover walls and retaining walls; (5) subterranean tanks, silos, and glory holes; (6) retained earth columns and earth confinement; (7) access or purposeful passageways such as spiral ladders or ramp systems for aquaculture (e.g. fish ladders), electromagnetic passageways such as for physics experimentation (such as a super-collider), livestock access, and hydraulic-based flow, drainage, and processing systems; and (8) large bore shafts, raises, and steep-walled pits, among other mining and heavy civil engineering type applications. Specific attributes of the methods and resultant structural properties make embodiments of the present invention suited to environmental mitigation such as construction of subterranean capture around buried or ground infiltrated hazardous waste. Methods and resulting structures of embodiments of the present invention also provide economical subterranean containment vessels for short and long-term storage of nuclear waste which allow complete monitoring access around the perimeter of the contained material (for example, a honeycomb structure provides complete access to the perimeter of the structure) and, in the case of the use of vertical curve capability of the invention, containment and monitoring below the contained material as well as around it.




The present invention allows braced-caisson or cast-in-place pile foundations to be economically built to great depths. Further, since a mass-caisson or mono-caisson foundation is inherently created with the method of this invention when spiraling slabs are produced, the slabs not only periodically laterally brace the caissons which are poured after the subterranean structure is constructed, but since the structure will typically be post-tensioned, it will compress and contain soil within the structure in a manner similar to sand being contained within a barrel, making the contained material essentially rigid and capable of carrying vertical loads to the strata below the contained earth. This allows the structure to act as a foundation resistant to the effects of liquefaction and the resultant deleterious amplitude modulation which can occur during an earthquake in liquefiable soils. As used herein, “soil” includes all earthen materials, including dirt, rock, aggregates, clays, and other material commonly encountered when excavating below the surface of the earth.




A further advantage of the present invention is that, by comparison to open-excavation construction of subterranean walls, in the present invention very little face is exposed to inflow of ground water during the construction process, thus significantly reducing the need to capture and treat recovered excavation water. In addition, excavation for tanks or retained-space uses can be performed after the subterranean retaining walls are constructed, thus allowing the excavation to progress more efficiently without being hindered by the inflow of groundwater. In one example, described below, it will be seen that the present invention also allows excavation to take place concurrently with the construction of the subterranean retaining wall. That is, the method of foundation construction in accordance with certain embodiments of the present invention is such that there is essentially always full bearing of the structure on the subjacent earth (with the exception of a small working void within the ground), as well as confinement of the contained earth within the foundation perimeter, thus making it possible to simultaneously construct a significant part of the structure supported by the foundation. As will be described below, the foundation wall can be made to have residual void-space so that access to all levels of the foundation for inspection purposes can be provided.




In a broad sense, certain embodiments of the present invention provide for a subterranean structure which includes a continuous ribbon slab having a plurality of flights fabricated from concrete. Turning to

FIG. 1

, a continuous ribbon slab


10


in accordance with an embodiment of the invention is depicted in an isometric diagram. It is understood that preferably most or all of the ribbon slab


10


is located in a subterranean location (i.e., “underground”, or below the surrounding grade). The ribbon slab


10


includes a plurality of generally concentric flights


12


,


14


,


16


and


18


, which are depicted here as having a common inside diameter “D” which is defined by an inner perimeter


22


of the flights. The area within the inside diameter of the flights


12


,


14


,


16


,


18


can remain filled with surrounding earth, or it can be excavated after (or as) the ribbon slab


10


is constructed. Likewise, the area outside of the ribbon slab


10


(i.e., the area outside of the outer perimeter line


20


) can remain as solid earth or it can be excavated after (or as) the ribbon slab


10


is constructed. The inside diameter “D” of the flights


12


,


14


,


16


,


18


can be constant or variable, as can the thickness “T” of the slab


10


, the width “W” of the slab, and the spacing “H” between the flights


12


,


14


,


16


,


18


. We will use the expression “slab interval” to mean the vertical distance “H” between immediately adjacent flights


12


,


14


,


16


,


18


of the continuous ribbon slab


10


. Preferably, the ribbon slab


10


is formed from concrete, which can be reinforced, post-tensioned concrete.




Preferably, the ribbon slab


10


is constructed in a top-down manner. That is, flight


12


is formed first, then flight


14


, and so on in a descending manner. Essentially, the method of placing the ribbon slab


10


can be considered as tunneling downward in a spiral, and laying concrete on the tunnel floor as the tunnel is formed. The tunnel is defined by height “H” and width “W”. Generally, the tunnel will be defined by walls along the outer perimeter


20


and inner perimeter


22


of the flights


12


,


14


,


16


,


18


. The walls can be defined by the natural surrounding rock or soil, by sheet piling, or by wall members which are placed during construction of the continuous ribbon slab


10


. The ribbon slab


10


is preferably constructed in a generally continuous manner (versus as integral flights), although this is not essential. Further, as the ribbon slab


10


is being constructed, the area between the flights


12


,


14


,


16


,


18


is preferably back-filled with earth or concrete to thereby allow a subjacent flight to support the flight above it. That is, for example, as flight


14


is being formed, the region (defined by height “H” and width “W”) between the bottom of flight


12


and the top of flight


14


is filled with material so that flight


14


supports flight


12


. Then, as flight


16


is being formed, the area between flight


14


and flight


16


is back-filled so that flight


16


supports flight


14


, and so on. There will, of course, be a relatively small work area between the two lowermost adjacent flights (as will be described later) that is not filled as work is being performed to advance the “tunnel” (and thus the slab


10


) into the earth. If calculations determine that the surrounding soils and the loads on the above flight (e.g., flight


12


) are such that the portion of the-above flight in the work area is not self-supporting, then that portion of the above flight can be temporarily supported on the immediate flight (e.g., flight


14


) by jacks or the like. Further, the above flight (e.g., flight


12


) can be supported in the work area by sheet piling which defines the walls of the tunnel, and which extends downward into the strata below the work area. It will occur that if the area “H” between the flight


12


,


14


,


16


,


18


is completely backfilled over the width “W” of the slab


10


as lower flights are constructed, and if the outer perimeter


20


of the flights, and the inner perimeter


22


of the flights, are closed (such as by adjacent rock, soil or sheet piling) then a means needs to be provided to allow excavated soil to be removed from the descending tunnel, and to allow worker access to the work area. In this instance, periodic, generally aligned openings (not shown in

FIG. 1

) can be formed in each of the flights, and a sleeve can connect the openings to thereby form raiseways or caissons in the evolving structure. (A “raiseway” is a passageway which can be used to pass materials out of, and into, the work area from the upper surface, or from an upper level of the evolving structure.)




While the ribbon slab


10


of

FIG. 1

is depicted as being circular in shape in plan view, this is not a requirement. The plan view of a subterranean structure in accordance with the present invention can also be a polygon, an ellipse, or any other convenient shape. Further, and as will be described more fully below, a subterranean structure in accordance with the present invention can include a plurality of interleaved continuous slabs. When we use the term “continuous slab” we mean that the slab has at least some physical continuity along the length of the slab. For example, where the slab is continuously poured from concrete, then the slab will be a continuous, integral slab of concrete. However, in many instances it will be more practical to pour sections of concrete and then join the sections together such as with reinforcing steel and/or (and more preferably), with post-tensioning cables.




While one or more continuous slabs can be used in many embodiments of the present invention, in other embodiments (described more fully below) the slabs do not need to be continuous, but only adjoined, such as by an access ramp or passageway (which can be temporary or permanent) allowing access from an upper slab to a lower slab. In this latter configuration the slabs are preferably generally concentric, and are also preferably generally aligned between adjacent slabs. However, the criteria of “generally aligned” should be considered as embracing adjacent slabs that are somewhat different in inside and/or outside dimensions (e.g., inside dimension “D” of FIG.


1


), as well slabs that are somewhat different in width (e.g., width “W” of FIG.


1


).




Turning now to

FIG. 2

, a plan view of a first embodiment of the present invention is depicted. Shown in

FIG. 2

is a first subterranean structure


100


which forms a foundation for a supported secondary structure


102


, which can be a building or the like. The supported structure


102


can be supported on the foundation


100


by a foundation cap


106


which rests on the foundation


100


. In one variation, the secondary structure can be indirectly supported on the foundation


100


by an intermediate slab. In yet another variation, the structure


100


can extend from below the surface to a distance above ground, in which case the “secondary structure” is essentially an extension of the foundation portion


100


. The surrounding soil or ground “S” can be isolated from the foundation


100


by a retaining wall


200


, thereby forming an intermediate zone


104


. The soil in the intermediate zone


104


can be left in place, or it can be excavated (removed) to form a voidspace, which can be used for example as a parking area for the supported secondary structure


102


. Further, a concrete cap or grade slab (not shown) can also be placed between the retaining wall


200


and the foundation


100


. Foundation


100


and retaining wall


200


can be formed in accordance with methods of the present invention. Since the foundation


100


and the retaining wall


200


are subsurface structures which are formed in place, and are preferably formed from reinforced concrete ribbon slabs, these structures can be properly identified as “cast-in-place reinforced subterranean structures”.




As depicted, retaining wall


200


is formed from a continuous ribbon slab


209


having multiple flights, of which only the uppermost flight


220


can be seen in FIG.


2


. The continuous ribbon slab


209


is defined by an outer perimeter


213


and an inner perimeter


215


. A plurality of openings


211


are formed in the flights (only flight


220


is depicted), the function of which will be more fully described below, except that the openings


211


can generally be described as defining construction access raiseways in the retaining wall structure


200


. Similarly, foundation


100


is formed from a continuous ribbon slab


109


having multiple flights, of which only the uppermost flight


120


can be seen (under cap


106


) in FIG.


2


. The continuous ribbon slab


109


is defined by an outer perimeter


113


and an inner perimeter


115


. A plurality of periodic openings


111


are formed in the flights (only flight


120


is depicted), which can generally be described as defining construction access raiseways in temporary use and caissons in permanent use in the foundation similar to openings


211


in retaining wall structure


200


.




Foundation


100


can be described variously a “tied caisson foundation”, “honeycomb wall foundation”, “hollow wall foundation”, or “solid wall foundation”, depending on details of construction of the foundation


100


. “Tied caisson” means the caissons (defined by openings


111


) are laterally braced intermittently at discrete ribbon slab (


109


) levels, or continuously in the case of having the tunnel voids (briefly described above, and more fully describe below) completely filled between caissons. “Honeycomb wall foundation” means that caisson liners (which are not shown in

FIG. 2

, but are described more fully below, and generally define the openings


111


) are not filled, the “honeycomb” nature being considered sheet piling, for example (placed around peripheries


113


and


115


along the vertical height of the foundation


100


, and described more fully below), or a wall that can be cast or shotcreted just inside of the sheet piling (i.e., in the “tunnel” defined between the flights) to continuously support the spiraling ribbon slab


109


all the way down to bearing strata or, depending on the profile, through friction support within the soil profile. “Solid wall foundation” means that the caisson liners (described below) are filled and the tunnel void spaces between adjacent caisson liners are also filled, or that no caisson liners are installed and the entirety of the void space in the tunnel between sheet piled walls is filled with concrete, shotcrete, or some type of engineered fill such as sand-cement slurry.




Likewise, retaining wall


200


can be variously described as a “chambered retaining wall”, “hollow retaining wall”, or “solid retaining wall” depending on details of construction of the retaining wall


200


. “Chambered retaining wall” means that the caisson liner part (described below, and used to define opening


211


) is filled with concrete to increase the strength of the retaining wall


200


. “Hollow retaining wall” means that either there is no shotcrete, concrete, or engineered fill within the tunnel void space created between the sheet piling (described below) and the spiral ribbon slab


209


, or there can be a wall cast against the sheet pile but that there is a tunnel void space defined between these walls and the spiral ribbon slab


209


. “Solid retaining wall” means the same as for the solid foundation wall described above with respect to foundation


100


. It will be appreciated that the ribbon slabs


109


,


209


used in the foundation


100


and retaining wall


200


provide significant resistance to out-of-plane bending and also provide transverse shear rigidity such that these type of walls can be used to retain soil to extreme depths and to brace caisson foundations even within liquefiable soils. In the latter case, the “mono-caisson approach” (depicted in

FIG. 2

) affords a foundation


100


which will resist the liquefaction of the captured soil S


1


′ (beneath cap


106


) during an earthquake because the captured soil is maintained in a state of triaxial compression within the limits of the spiral wall foundation


100


.




Turning now to

FIG. 3

, a side elevation sectional view of the foundation


100


and retaining wall structure


200


of

FIG. 2

is depicted. As can be seen, foundation cap


106


rests on foundation


100


and supports secondary structure


102


, which can be a building, for example. Foundation


100


is set below the ground level G, and rests on foundation ground G


2


and G


2


′, thus separating captured soil S


1


′ from outer free soil S


1


. Retaining wall


200


is supported by ground G


1


upon which ground slab GS can be formed, as from concrete or the like. Retaining wall


200


captures soil S′ and S″, and separates this captured soil from the free soil S. It will be appreciated that soil S


1


′ is captured inside of tied caisson foundation


100


and is analogous to sand in a steel barrel. This foundation


100


can be also called a “mono-caisson” foundation in that the spiral ribbon slab


109


, being typically post tensioned, confines the soil S


1


′ within its perimeter and in so doing causes the foundation


100


to act like both a continuous support wall bearing on strata G


2


but also a singular foundation bearing also on strata G


2


′. Transfer of load to strata G


2


′ occurs as the soil S


1


′ is tri-axially strained. This strain occurs for two reasons: (1) settlement of the caisson wall foundation


100


and foundation cap


106


, and (2) tensioning of the tendons (described below) within the spiral slab


109


. Although the structure


102


is depicted as being supported on the foundation cap


106


somewhat inward of the inner periphery


115


of foundation


100


(see also FIG.


2


), the structure


102


can also be supported directly over the area of the foundation


100


between the outer periphery


113


and the inner periphery


115


. In this latter configuration the structure


102


can inhibit access to the openings


111


. If the structure


102


does inhibit access to the openings


111


, then either the foundation


100


will need to be constructed prior to constructing the structure


102


, or means will need to be provided (such as side access to openings


111


) to allow construction of the foundation


100


to proceed notwithstanding the positioning of the structure


102


directly over the foundation


100


.




The structures


100


and


200


are essentially subterranean “walls”. “Subterranean” as used herein essentially means that the structures


100


,


200


are constructed within soil or below grade and will typically have soil remaining on one or both sides of the continuous walls which define the structures after construction is accomplished and any adjacent excavation is accomplished. For example, retaining wall


200


is accomplished by constructing it in a descending spiral fashion through soil that it divides into soil regions S and S′ (and including S″). In a like manner, foundation


100


divides the regions S


1


and S


1


′. It will be appreciated that there are cases where a free-standing wall or retaining wall can be more economically constructed in accordance with a subterranean method of construction of the present invention, but it can be uncovered for all or part of its height on both sides of the wall. It will also be appreciated that construction of both the retaining wall


200


and foundation


100


can proceed simultaneously by first excavating soil S″, and leaving soil S′ so that retaining wall


200


can be accomplished in this subterranean fashion. After construction of the retaining wall is complete, soil S′ can be excavated and grade slab “GS” can be poured. It will also be appreciated that after accomplishing the first full spiral or flight


120


of the ribbon slab


109


of foundation


100


, foundation cap


106


can be poured and casting of structure


102


can proceed simultaneous with the construction of foundation


100


provided there is no deleterious settlement of the foundation


100


, cap


106


, or secondary structure


102


, and so far as the foundation


100


and its cap


106


are structurally adequate at all phases of construction to carry the loads imposed by the growing structure


102


.




As indicated, retaining wall


200


includes a continuous ribbon slab


209


which is circular in plan view and which “spirals” into soil S in the manner depicted in FIG.


1


. Preferably, the ribbon slab


209


is fabricated from concrete. As depicted, ribbon slab


209


forms seven concentric, generally vertically aligned flights


220


through


226


. Each of the flights


220


-


226


are closed with the immediately above and subjacent flight (where applicable) at the outer perimeter


213


by a first wall member. In the example depicted in

FIG. 3

, the first or outer wall member is outer sheet piling


230


. Likewise, each of the flights


220


-


226


are closed with the immediately above and subjacent flight (where applicable) at the inner perimeter


215


by a second or inner wall member, which in the example depicted is inner sheet piling


232


. For clarity, flights


220


-


226


are not indicated by hidden lines as they continue around behind structure


102


, but they would appear similar to the hidden lines shown for flights


120


-


129


for foundation


100


, as described below.




The spiral flights


220


-


226


and the wall members


230


and


232


define a continuous tunnel


455


which “spirals” downward from flight


220


to flight


226


. Each of the flights


220


-


226


can have one or more openings (not specifically called out) defined therein, which generally align with similar openings in immediately-above or subjacent flights (as appropriate) to thereby connect the adjacent levels of the tunnel


455


. Caisson liners


240


(described more fully below with respect to caisson liners


140


of foundation


100


) can be placed within the openings in the flights


220


-


226


to thereby form a plurality of caissons


211


in the retaining wall


200


. The function of these caissons


211


will be described more fully below, but they can generally be used to provide access to lower flights


221


-


226


of the spiral slab


209


.




In a manner similar to retaining wall


200


, foundation


100


includes a continuous ribbon slab


109


which is circular in plan view and which “spirals” into soil S


1


in the manner depicted in FIG.


1


. Preferably, the ribbon slab


109


is fabricated from concrete. As depicted, ribbon slab


109


forms ten concentric, generally vertically aligned flights


120


through


129


. Each of the flights


120


-


129


is closed with the immediately above and subjacent flight (where applicable) at the outer perimeter


113


by a first wall member. In the example depicted in

FIG. 3

, the first or outer wall member is outer sheet piling


130


. Likewise, each of the flights


120


-


129


is closed with the immediately above and subjacent flight (where applicable) at the inner perimeter


115


by a second or inner wall member, which in the example depicted is inner sheet piling


132


.




The spiral flights


120


-


129


and the wall members


130


and


132


of the foundation


100


define a continuous tunnel


456


which “spirals” downward from flight


120


to flight


129


. Each of the flights


120


-


129


can have one or more openings (not specifically called out) defined therein, which generally align with similar openings in immediately-above or subjacent flights (as appropriate) to thereby connect the adjacent levels of the tunnel


456


. Caisson liners


140


(described more fully below) can be placed within the openings in the flights


120


-


129


to thereby form a plurality of caissons


111


in the foundation


100


. The function of these caissons


111


will be described more fully below, but they can generally be used to provide access to lower flights


121


-


129


of the spiral slab


109


.




The method of construction of foundation


100


will be described more fully below, along with details of specific design components for the foundation


100


.




Turning now to

FIGS. 4 through 9

, a number of variations of a subterranean structure in accordance with embodiments of the present invention are depicted. The views in

FIGS. 4-9

generally correspond to the left side of the foundation


100


depicted in FIG.


3


. That is,

FIGS. 4-9

depict partial side sectional views through a circular (in plan view) subterranean structure similar to structure


100


of FIG.


3


. Each structure


300


,


320


,


340


,


360


,


380


and


390


in

FIGS. 4-9

includes a spiral slab (respectively,


301


,


321


,


341


,


361


,


381


and


391


) which forms ten generally concentric flights (which are numbered in the figures as will be described more fully below). All of the flights in each structure


300


,


320


,


340


,


360


,


380




390


, except for the lower-most flight, have generally aligned openings defined therein, similar to flights


120


-


128


of FIG.


3


. Each structure in

FIGS. 4-9

is depicted as having a foundation cap


306


which is supported by the structure, and a secondary structure


102


(such as identical structure


102


of

FIGS. 2 and 3

) is supported on the foundation cap


306


. The variations in

FIGS. 4-9

depict how various construction parameters can be varied in constructing subterranean structures in accordance with embodiments of the present invention.




With respect to

FIG. 4

, a structure


300


includes a spiral ribbon slab


301


having flights f


1


through f


10


. The outer perimeters of the flights f


1


-f


10


are joined together by outer sheet piling


302


, while the inner perimeters of the flights are joined together by inner sheet piling


304


. A caisson liner


308


passes through the openings in each flight f


18


f


9


to thereby form a caisson


303


(similar to caisson


111


of FIG.


3


). As can be seen, the width of each flight f


2


-f


10


is slightly wider than the width of the immediately-above flight. This can be accomplished by continuously increasing the width of the ribbon slab


301


as the slab descends from flight f


1


to flight f


10


. Alternately, the width of the ribbon slab


301


can be periodically incremented as the slab descends. It will be noted that the width dimension is increased only at the outer perimeter of the slab


301


adjacent to sheet piling


302


. There are several reasons for increasing the structural section (i.e., width of the slab) with depth while keeping the internal radius (i.e., the inner perimeter adjacent to sheet piling


304


) constant. These include: (1) earthen pressures within the captured soil inside the large mono-caisson structure


300


increases with depth, and therefore post tension strands in the slab


301


(described more fully below) can require more concrete to handle the larger pre-stress loads; (2) localized out-of-plane load on the foundation


300


can require a high sectional modulus to withstand the effects of partial liquefaction of the soil surrounding the mono-caisson (i.e., the area outside of the outer perimeter of the foundation


300


, defined by sheet piling


302


); and (3) if the structure


300


is a retaining wall around a tank within the inner perimeter area (defined by sheet piling


304


), it will more practically be of a constant internal radius.




In

FIG. 5

an alternate way of achieving more structural section with depth (similar to the objective of the design of structure


300


of FIG.


4


), is depicted, but the objective is achieved without changing the internal or external radii of the structure. In

FIG. 5

, a structure


320


includes a spiral ribbon slab


321


having flights f


1




a


through f


10




a


. The outer perimeters of the flights f


1




a


-f


10




a


are joined together by outer sheet piling


322


, while the inner perimeters of the flights are joined together by inner sheet piling


324


. A caisson liner


328


passes through the openings in each flight f


1




a


-f


9




a


to thereby form a caisson


323


(similar to caisson


111


of FIG.


3


). As can be seen, the thickness (equivalent to thickness “T” of spiral slab


10


of

FIG. 1

) of each flight f


2




a


-f


10




a


is slightly wider than the thickness of the immediately-above flight. This can be accomplished by continuously increasing the thickness of the ribbon slab


321


as the slab descends from flight f


1




a


to flight f


10




a


. Alternately, the thickness of the ribbon slab


321


can be periodically incremented as the slab descends. A further means of increasing effective out-of-plane rigidity is to decrease the interval between slab flights as the spiral descends, i.e., varying the dimension “H” as given in

FIG. 1

, holding the slab thickness “T” constant or in conjunction with varying slab thickness “T” of FIG.


1


.




Turning to

FIG. 6

, a structure


340


includes a spiral ribbon slab


341


having flights fib through f


10




b


. The outer perimeters of the flights f


1




b


-f


10




b


are joined together by outer sheet piling


342


, while the inner perimeters of the flights are joined together by inner sheet piling


344


. A caisson liner


348


passes through the openings in each flight f


1




b


-f


9




b


to thereby form a caisson


343


. As can be seen, the width of each flight f


2




b


-f


10




b


is slightly wider than the immediately-above flight, similar to flights f


2


-f


10


of FIG.


4


. However, in

FIG. 6

the width of the flights f


2




b


-f


10




b


is increased around both sides of the centerline of the caisson liner


348


. That is, the width dimension of the ribbon slab


341


is increased at the outer perimeter of the slab


341


(adjacent to sheet piling


342


), as well as at the inner perimeter of the slab


341


(adjacent to sheet piling


344


). The main purpose for the configuration depicted in

FIG. 6

is to increase substantially the end bearing potential of the mono-caisson foundation


340


. In this case, “flaring” the ribbon slab


341


continuously about the centerline of the caisson


343


affords a larger bearing area of slab


341


under the ends of each of the caissons


343


which make up this mono-caisson foundation


340


.




It will be appreciated that the profile of the foundation


100


depicted in

FIG. 3

, as well as the profiles of structures


300


,


320


and


340


depicted in

FIGS. 4-6

, imply that the ribbon slabs which make up these structures can be varied in a wide variety of ways to achieve virtually any wall profile required for the particular application, including the ability to produce curvilinear profiles as well as constant slope profiles.




Turning now to

FIG. 7

, a structure


360


includes a spiral ribbon slab


361


having flights f


1




c


through f


10




c


. The outer perimeters of the flights f


1




c


-f


10




c


are joined together by outer sheet piling


362


, while the inner perimeters of the flights are joined together by inner sheet piling


364


. The structure


360


of

FIG. 7

is similar to the structure


100


of

FIG. 3

, except that in the structure


360


the caisson liners


366


do not extend continuously from flight f


1




c


to f


10




c


(whereas in

FIG. 3

the caisson liner


140


does extend continuously from flight


120


to flight


129


). In the structure


360


of

FIG. 7

the ribbon slab


361


relies essentially only on the sheet piling


362


,


364


for vertical support until such time as the tunnel void space


363


is back-filled in part or in full such that the back-fill supports the ribbon slab


361


.




Turning to

FIG. 8

, a structure


380


includes a spiral ribbon slab


381


having flights f


1




d


through f


10




d


. The outer perimeters of the flights f


1




d


-f


10




d


are joined together by outer sheet piling


382


, while the inner perimeters of the flights are joined together by inner sheet piling


384


. The structure


380


of

FIG. 8

is similar to the structure


360


of

FIG. 7

in that the caisson liners


386


of the structure


380


do not extend continuously from flight f


1




d


to f


10




d


, thus leaving tunnel voids


383


. However, whereas the structure


360


of

FIG. 7

relies essentially only on the sheet piling


362


,


364


to temporarily support the ribbon slab


361


, the structure


380


of

FIG. 8

additionally relies on wall members


387


and


388


to support the ribbon slab


381


. Wall member


387


is attached to the inner sheet piling


384


and faces the inner perimeter of the flights f


1




d


-f


10




d


, while wall member


388


is attached to the outer sheet piling


382


and faces the outer perimeter of the flights. While typically the tunnel area


383


of structure would be backfilled, this is not a necessity, and the wall members


387


,


388


can be the primary support for the ribbon slab


381


(along with sheet piling


382


,


384


). The sidewalls


387


,


388


are preferably reinforced cast-in-place concrete or shotcrete. The wall members


387


,


388


can also be post-tensioned, in which case tensioning buttresses can be cast periodically (e.g., every 90 degrees if the subterranean wall is radial) inward into the chamber


383


. The wall members


387


,


388


can also be precast concrete panels which are bolted, grouted or welded via inserts to the concrete slab


381


.




Turning to

FIG. 9

, a structure


390


includes a spiral ribbon slab


391


having flights f


1




e


through f


10




e


. The outer perimeters of the flights f


1




e


-f


10




e


are joined together by outer sheet piling


392


, while the inner perimeters of the flights are joined together by wall member


397


(i.e., there is no sheet piling at the inner perimeter of the flights f


1




e


-f


10




e


. Otherwise, the structure


390


of

FIG. 9

is similar to the structure


380


of

FIG. 8

in that the caisson liners


396


of the structure


390


do not extend continuously from flight f


1




e


to f


10




e


, thus leaving tunnel voids


393


. Structure


390


further includes an outer wall member


398


which is attached to the outer sheet piling


392


, and faces the inner periphery of the ribbon slab


391


(i.e., wall


398


faces wall


397


). As evidenced by

FIG. 9

, it will be appreciated that the use of sheet piling (e.g., sheet piling


382


and


384


of

FIG. 8

) is not a requirement of the methods and apparatus of the present invention, since ground conditions can be such that sheet piling is not required to maintain the excavation for the ribbon slab


391


(FIG.


9


), especially within competent fills or rock. However, there does need to be an adequate means of supporting the evolving ribbon slab


391


so that it remains structurally sound and the structure


390


as a whole does not undergo undo settlement during construction. This is particularly important where the secondary structure


102


which will be supported on the foundation


390


is being simultaneously constructed with the foundation


390


. It will also be appreciated that sheet piling is typically a temporary means of earth and/or ribbon slab support within what can be called the “active zone” where the excavation for the subterranean wall is progressing, but the casting of slab


391


and secondary support walls


397


,


398


of void space


393


fill to support the ribbon slab


391


lags behind the excavation face by a certain finite distance, all of which will be described more fully below. Secondary support walls


397


,


398


are preferably reinforced cast-in-place concrete or shotcrete. The wall members


397


,


398


can also be post-tensioned, in which case tensioning buttresses can be cast periodically (e.g., every 90 degrees if the subterranean wall is radial) inward into the chamber


393


. The wall members


397


,


398


can also be precast concrete or steel panels which are bolted, grouted or welded via inserts to the concrete slab


391


.




Another reason to not use sheet piling is that the profile (defined by wall members


397


and


398


) of the structure


390


of

FIG. 9

can represent the simultaneous construction of a subterranean wall and the excavation of the interior soil (e.g., soil S


1


′ of

FIG. 3

) so that a tank can be constructed within the confines of the subterranean wall


390


. In this method of construction, outer sheet piling


392


is used to contain the soil outside of the subterranean structure


390


and to reduce the inflow of groundwater into the area within the structure, but no inner sheet piling on the inside face (by wall


397


) is required because the excavation is accomplished with an “open side” type approach wherein the ribbon slab


391


on the inside is temporarily supported with screw-jacks within the “active zone” until such time as support wall


397


has caught up to the jacks and they are moved forward and downward (recall that the slab is continuously descending) following the excavation of the face of the spiraling tunnel. In this way, embedment for a water tight steel membrane or moisture barrier (for example, as used in LNG tanks) can be embedded in the inside edge of the ribbon slab


391


as well as within the support wall


397


,


398


being cast between spiral intervals of ribbon slab.




Turning briefly to

FIG. 13

, a side elevation sectional view (similar to the view of

FIG. 3

) depicts a subterranean structure


410


which supports a secondary structure


102


. Secondary structure


102


can be a building, for example. The foundation


410


includes a continuous ribbon slab


409


which is made up of flights


411


through


420


, and is preferably fabricated from cast, reinforced concrete. Caisson liners


403


are placed in periodic openings in the flights


411420


to form caissons


401


. It will be noted that in

FIG. 13

the secondary structure


102


is placed directly on top of the caissons


401


, rather than being offset as in

FIG. 3. A

foundation cap


423


can provide additional support for the secondary structure


102


, but is not essential for all applications to support of structure


102


. The outer perimeters


421


of flights


411


-


420


are joined to one another by outer sheet piling


405


, while the inner perimeters


422


of flights


411


-


420


are joined to one another by inner sheet piling


407


. The ribbon slab


409


is defined by an outside diameter “d


1


”, and an inside diameter “d


2


”. As can be seen, the outside diameter d


1


of each subjacent flight is larger than the outside diameter of an immediately-above flight. For example, the outside diameter of flight


415


is larger than the diameter of the immediately-above flight


414


. This configuration helps the structure


410


to achieve many of the structural benefits accorded by structures


300


and


340


depicted in

FIGS. 4 and 6

.

FIG. 13

also depicts a structure


400


which includes a building


102


, and a foundation


410


which supports the building


102


.




While

FIGS. 4-6

and


13


all depict means of increasing effective out-of-plane rigidity of the respective structures


300


,


320


,


340


and


400


as a function of the depth of the structure below grade, in some applications it can be useful to decrease the effective out-of-plane rigidity of the structure as a function of depth, or to maintain a constant out-of-plane rigidity of the structure (such as structures


100


and


200


of FIG.


3


). Other times it can be useful to vary the out-of-plane rigidity of the structure as a function of depth. For example, in a mining application where the structure passes through broken rock and then hard rock, in this instance the out-of-plane rigidity of the structure can be increased through the broken rock and then decreased into the hard rock, and then gradually increased again with depth. Further, the width (“W”,

FIG. 1

) of the slab, and/or the thickness “T” of the slab, as well as the slab interval “H”, can be varied as a function of depth for tied caisson foundations where the lateral rigidity can be reduced through more competent soils, and then increased again at the bottom of the foundation where a large end bearing component of the caissons can be achieved with a spreading and thickening of the ribbon slab. By “competent soils” we mean soils that are more structurally sound than adjacent soils, in that the “competent soils” are less likely to shift under loads, and in particular lateral loads, than the adjacent less-competent soils.




Moreover, the width, thickness, inside diameter and/or slab interval of the continuous slab can be varied depending on the application of the structure, and not just as a function of surrounding soil types. For example, if the structure is to be used to form a subterranean isolation barrier for contaminated soil, and the area of the contamination decreases as a function of depth, then the inside diameter of the slab (and other dimensions of the slab) can be decreased with depth.




Turning now to

FIG. 10

, a side elevation sectional detail from

FIG. 3

is shown.

FIG. 10

depicts details of the caisson liner


140


. The view depicted in

FIG. 10

shows the second and third flights


121


and


122


of the ribbon slab


109


, the outer sheet piling


130


at the outer periphery


113


of the ribbon slab, and the inner sheet piling


132


at the inner periphery


115


of the ribbon slab. As can be seen, each flight


121


,


122


of the ribbon slab


109


defines an opening therein (not numbered), and the openings are generally aligned. A two-part cylindrical caisson liner


140


is received within the openings defined in the flights


121


,


122


, to thereby define a caisson


111


which passes through the tunnel areas


456


defined between the sheet piling


130


,


132


and adjacent flights


121


,


122


. When in place, the caisson liner


140


, along with sheet piling


130


,


132


and flights


121


,


122


, define a void area


454


external to the caisson


111


. As will be described further below, this void area


454


can be filled with a fill material (such as concrete, shotcrete, rock, dirt, sand, etc.) as the ribbon slab


109


is being constructed to support adjacent flights of the slab


109


. During construction, the caisson liners


140


can provide access from lower flights to upper flights, and to the top of the structure itself (see for example FIG.


3


). Following construction, the caissons


111


can also be filled with a fill material, or they can be left open. One instance in which the caissons can be left open is so that the foundation


100


can be periodically inspected.




The two parts of the caisson liner


140


include a first part


146


which is received within the opening defined in the flights


121


,


122


. This first part


146


corresponds to the partial caisson liners


366


,


386


and


396


of respective

FIGS. 7

,


8


and


9


. During construction, the ribbon slab


109


can be cast about the liner first part


146


merely by placing the liner part on the ground in front of the evolving slab


109


, and then pouring the next portion of the slab around the liner part. Turning briefly to

FIG. 11

, a plan sectional view through the flight


121


and the caisson liner first part


146


is depicted. The liner first part


146


can itself be a two-part component, having first and second halves


146




a


and


146




b


, which can be connected together by bolts or pins


147


. In this way the liner first part


146


can be passed down through the caisson liner


140


as it evolves downward with construction of the ribbon slab


109


. Turning back to

FIG. 10

, the caisson liner


140


includes a liner second part


142


which overlaps an upper and lower edge of the adjacent liner first parts


146


to thereby allow the caisson


111


to span between adjacent flights


121


,


122


of the ribbon slab


109


. The liner second part


142


can be attached to the liner first part


146


by screws


145


, bolts, pins or welding. Turning briefly to

FIG. 12

, a plan sectional view through the caisson liner second part


142


between flights


121


and


122


is depicted. The liner second part


142


can be a two-part component, having first and second halves


142




a


and


142




b


, which can be connected together by bolts or pins


149


. In this way the liner second part


142


can be easily installed around the ends of the liner first part


146


, as depicted in FIG.


10


. It will be appreciated that liner parts


142


and


146


can also be made from more than two parts, for example they can each be in three parts rather than in halves.




We will now describe a method of constructing a subterranean structure in accordance with one embodiment of the present invention. Generally, this method includes excavating soil to form a downward sloping ramp, and then forming a concrete slab on the downward sloping ramp. Soil is continued to be excavated to extend the downward sloping ramp to a location under the concrete slab. For example, the ramp can be circular in plan view (see

FIG. 2

, for example) to allow the extending ramp to pass under the previously-formed portion of the evolving concrete slab. The concrete slab is continued to be formed on the downward sloping ramp so that a subterranean structure is formed having an essentially continuous concrete slab. The continuous concrete slab will have a first portion (such as flight


120


of

FIG. 3

) which is above and spaced-apart from a second portion (such as flight


121


of FIG.


3


). Preferably, the second portion of the concrete slab is generally in alignment with the first portion.

FIGS. 5-9

and


13


all depict structures where the flights can be considered generally in alignment, notwithstanding that some of the flights widen as they descend. The method can further include joining the first and second portions of the slab at their inner and/or outer peripheries with wall members, as shown for example in

FIG. 8

where first wall member


387


joins flights f


1




d


-f


10




d


at the inner peripheries of the flights, and second wall member


388


flights f


1




d


-f


10




d


at the outer peripheries of the flights.




Turning now to

FIG. 14

, a side elevation sectional view depicts a method of forming a subterranean structure in accordance with an embodiment of the present invention. The view depicted in

FIG. 14

is a “fold-flat” partial section taken from FIG.


2


. By “fold-flat” we mean that the view has been adjusted to remove the effects of curvature which would be present in a true sectional view as taken from FIG.


2


.

FIG. 14

depicts a portion of the foundation


100


(of

FIGS. 2 and 3

) beneath the foundation cap


106


. As indicated, the view portrays flights


120


and


121


of the continuous spiral slab


109


as having already been formed, and the third flight


122


as being only partially formed, and in the process of continuing to be formed. The third flight


122


is supported on the surface


468


of the ground or soil S


1


at this point in the forming process. A tunnel


456


is formed by the partially formed slab


122


, the ground S


1


, the immediately-above flight


121


, and the sides defined by sheet piling


458


. Openings


464


in the foundation cap, and caisson liners


140


which pass through aligned openings in the flights


120


and


121


(in the manner depicted in FIG.


10


), allow access from the surface “A” to the tunnel area


456


. The caisson liners


140


define caissons


111


. The area between the work-face


452


(where soil S


1


′ is being excavated by excavator


450


) and the fill-face


457


(where fill material is being placed in the tunnel


456


) define the “active-zone” (or “work-zone”). Flight


121


can be sufficiently strong to be self-supporting in the active zone, but it can also be temporarily supported in the active zone by jacks, shoring, sheet piling, timbers, or other known means common to mining practices. Although not particularly evident in

FIG. 14

, the excavation at the work-face


452


advances the tunnel


456


not only inward (i.e., rightward as viewed in FIG.


14


), but also slightly downward so that a continually downward spiral slab


109


is formed (as in FIG.


1


). Excavated soil is placed in one or more buckets


455


which can then be raised to the surface “A” by a crane or a winch or the like. Although the excavation is depicted as being performed by an overshot excavator


450


, other means of excavating can be used, depending on the nature of soil S


1


′, the available space in the tunnel


456


, local availability of equipment and labor, and other factors. For example, the excavation can be performed using water-jetting to erode the work-face


452


, and the soil-water slurry can then be recovered by a pump and pumped to the surface “A” via hoses or pipes which are located in the caissons


111


. The excavator


450


can also be a slewable excavator, an overshot excavator, or a tunnel boring apparatus such as are commonly used in the mining industry, and particularly for underground coal mining.




As is depicted in

FIG. 14

, as the tunnel


456


is being advanced into soil S


1


′, sheet piling


458


is driven into soil S


1


down to a location slightly below the area where the next flight will be formed (indicated by phantom lines as


123


′). Similarly, the sheet piling


458


in the work-zone will have been put in place as flight


121


was formed, thus providing for a relatively solid wall in the work-zone to thus reduce cave-ins and groundwater intrusion into the work zone. As can be seen, the surface


468


on which the excavator


450


is supported is slightly above the bottom of the sheet piling


458


in the area where the work face


452


is being excavated. The reason for driving the sheet piling


458


below the level where the next-to-be installed flight will be located is to provide that as the excavation progresses, the bottom of the sheet piling stays in a competent footing with soil S


1


and is not undermined. This distance below the next-to-be installed flight which the sheet piling


458


is installed is preferably about one-third or greater of the spiral interval “I”.




As the excavation progresses, the buckets


455


(and/or slurry pipes, not shown) are moved to the next succeeding caisson chambers


111


to facilitate the construction activities within the advancing “active zone”. Immediately behind the excavating activity at the workface


452


the sheet piling


458


for the next level


123


′ is being installed. Preferably, spliced sheets are used for the sheet piling


458


since the ceiling height “I” does not allow a single length sheet to reach the required depth as just described. Also, it is preferable to use a machine to perform installation of the sheet piling


458


(versus using hand pile-driving equipment) since there is better geometric control with a machine (i.e., the advancing spiral path of the flights of the slab


109


can be better controlled). Immediately behind the sheet piling activity is where spools


462


for post tensioning ducts and/or tendons


460


are located (as described more fully below).





FIG. 14

shows section lines for

FIGS. 15A through 15F

, which depict the various activities within the active zone (other than the excavation which occurs at the workface


452


).

FIGS. 15A-15F

all show the same common following items: a portion of the foundation cap


106


, the soil S


1


outside of the foundation


100


(FIG.


3


), the soil S


1


′ inside the foundation


100


(FIG.


3


), the caisson liner


140


, the caisson


111


defined by the caisson liner, the first flight


120


and second flight


121


of the spiral slab


109


(FIG.


3


), outer sheet piling


130


, inner sheet piling


132


, and fill material


134


placed between the inner and outer sheet piling. It should be noted that only those features which appear in the plane of the section in

FIGS. 15A-15F

are depicted in the figures to facilitate understanding of the process being depicted.




Turning now to

FIG. 15A

, the excavation bucket


455


is located in the tunnel area


456


, and work in the active zone takes place on the slab grade


468


(i.e., the ground surface grade on which the future slab


122


will be installed).

FIG. 15B

depicts the area where sheet piling


458


is being installed down to the next level where flight


123


will be installed (indicated by dashed lines


123


′). The sheet piling


458


facilitates in aligning the outer and inner perimeters


113


and


115


(respectively) where the next flight


123


′ will be located, in the same manner that sheet piling


130


and


132


generally vertically aligns flight


121


with flight


120


. In

FIG. 15C

the sheet piling


458


for the level flight


123


′ has been fully installed, and post-tensioning cables or ducts


460


are in place. At this time, a caisson liner first part (


146


,

FIG. 10

) can be placed on the grade slab


468


between the post-tensioning cables


460


so that when the slab is poured the caisson liner first part will be cast into the slab, thereby forming a hole or opening in the slab.

FIG. 15D

depicts the next level of the caisson liner


140


as being completely installed. As described previously, liner first part


146


can be supported on the grade slab


468


, and caisson liner second part


142


can be installed around the previous liner first part in slab


121


, and the liner first part


146


which is resting on the grade slab


468


. The manner in which the liner second part


142


can be installed was previously described with respect to FIG.


12


. In

FIG. 15E

the next portion of spiral slab flight


122


has been poured or cast on grade slab


468


, and has been formed around the post-tensioning tendons


460


and the caisson liner first part


146


. Finally, in

FIG. 15F

the remaining tunnel area (


454


,

FIG. 15E

) at the sides of the caisson liner


140


, and the area behind the caisson liner (not visible in

FIG. 15F

) is filled with a fill material


134


. As the excavation at the workface


452


of

FIG. 14

advances, the process depicted in

FIGS. 15A-15F

is repeated. This is done until the whole ribbon slab (


109


,

FIG. 3

) has been formed.




It will be appreciated that other variations described herein can also be included with the method depicted in

FIGS. 15A-15F

. For example, wall members (e.g.,


387


,


388


,

FIG. 8

) can be installed in lieu of, or in addition to, sheet piling


458


and/or fill material


134


. Further, after the ribbon slab


109


(

FIG. 3

) has been fully formed, the caissons


111


can be filled with a fill material. In embodiments where the structure


100


is a foundation, a typical fill material for the caissons


111


is reinforced concrete. In other embodiments the slab


109


does not need to be continuously downward sloping, but can be incrementally stepped-down (as described more fully below). In yet another embodiment a plurality of interleaved slabs can be simultaneously formed (as also described more fully below). Thus, it is appropriate to describe the evolving structure as having a “first portion” and a “second portion” of a “slab”, in which the first portion and the second portion are generally vertically aligned. For example, in

FIG. 15A

flight


120


can be considered the “first portion” and flight


121


can be considered the “second portion”.




Returning briefly to

FIG. 3

, it will be appreciated that the subterranean structure


100


is a foundation having soil S


1


′ on the inside of the structure


100


(thus making the structure a “mono-caisson” to support the building structure


102


), and being surrounded by soil S


1


on the outside of the structure. In another embodiment of the present invention, in a structure similar to the structure


100


of

FIG. 3

, the soil around the outside of the structure (equivalent to soil S


1


of

FIG. 3

) can be excavated to produce an earthen column constrained by the structure


100


. In yet another embodiment, in a structure similar to the structure


100


of

FIG. 3

, the soil inside of the structure (equivalent to soil S


1


′ of

FIG. 3

) can be excavated to produce a storage area, such as a tank, vessel or bin. In this latter embodiment a roof or a top can be placed over the open inner area to complete the storage container, as will be described more fully below. In a further embodiment, in a structure similar to the structure


100


of

FIG. 3

, both the soil outside the structure (equivalent to soil S


1


of FIG.


3


), as well as the soil inside of the structure (equivalent to soil S


1


′ of FIG.


3


), can be excavated after (or as) the structure is formed to leave a remaining free standing structure, such as a self supporting wall.





FIG. 16

is a plan view depicting how post-tensioning tendons


460


can be anchored in exemplary flight


122


(see

FIGS. 15D and 15E

) of an evolving continuous concrete slab of the present invention.

FIGS. 16

shows a short portion of the slab flight


122


, including the outer sheet piling


130


, the inner sheet piling


132


, and caisson liners


140


which define the periodic caissons


111


. In this example the tendon anchors


470


are set in the liner first part (similar to liner first part


146


of FIG.


11


). This is advantageous since it allows the anchors


470


to be provided as adjustable tensioning sites, and the tendons


460


can thus be tensioned by entering the caissons


111


. This allows tension in the tendons


460


to be adjusted several times at all flights of the continuous slab as the entire slab is being formed. A less preferred embodiment for anchoring the post-tensioning tendons is depicted in

FIG. 17

, which is similar to

FIG. 16

in that it is a plan view depicting a section of flight


122


, including sheet piling


130


and


132


, caisson liners


140


, and caissons


111


. In

FIG. 17

the anchors


470


are set in block-outs


472


(i.e., open areas) in flight


122


. As can be seen in

FIG. 15A

, when fill material


134


is provided around the caisson liners


140


, then post-tensioning anchors set in the flights themselves (as in

FIG. 17

) are generally not later accessible once the next-lower flight (in

FIG. 15A

, flight


121


) is fully formed. It will be appreciated that

FIGS. 16 and 17

only depict initiating anchors for post-tensioning tendons, and that similar terminating post-tensioning anchors can similarly be provided, which essentially mirror the initiating anchors along a line perpendicular to the centerline of the flight


122


.




Turning now to

FIG. 18

a simplified side elevation, sectional diagram depicts a subterranean structure


500


in accordance with another embodiment of the present invention. The structure


500


includes a foundation cap


506


and three interleaved continuous ribbon slabs


510


,


520


and


530


, which are preferably fabricated from concrete.

FIG. 18

is similar to

FIG. 3

except that in

FIG. 18

the slabs are fully visible, and no caissons or sheet pilings are depicted. Further, the view of

FIG. 18

is a “fold-flat” section of the entire subterranean structure


500


, depicting all 360 degrees of the circular structure (i.e., circular when viewed in a plan view). As described before, the structure


500


can be other shapes in plan view as well (such as rectangular, oval, elliptical, square, polygonal, etc.). Slab


510


includes consecutive, descending flights


512


through


516


, slab


520


includes consecutive, descending flights


522


through


526


, and slab


530


includes consecutive, descending flights


532


through


536


. As can be seen, slabs


510


and


520


define a first continuous tunnel


501


, slabs


520


and


530


define a second continuous tunnel


502


, and slabs


530


and


510


define a third continuous tunnel


503


. Generally, the slabs


510


,


520


and


530


of

FIG. 18

are set on a greater pitch (i.e., slope) than for example slab


109


of FIG.


3


. The arrangement of interleaved slabs


510


,


520


and


530


allow construction to be performed on all three slabs simultaneously. Caissons (not shown) can be formed in each of the slabs so that construction can be performed in a manner to that depicted in FIG.


14


and

FIGS. 15A-15F

. While

FIG. 18

depicts a structure


500


having three interleaved slabs


510


,


520


and


530


, it will be appreciated that a similar structure can be formed using only two interleaved slabs, or using more than three interleaved slabs.





FIG. 19

is a side elevation view depicting a structure


600


in accordance with yet another embodiment of the present invention. Structure


600


includes a foundation cap


606


and three, interleaved slabs


610


,


620


and


630


. The view shown in

FIG. 19

is similar to the view shown in

FIG. 18

, in that all of the slabs are fully shown and other details (sheet piling, caisson liners, caissons, etc.) have been eliminated from the view for the sake of simplicity and facilitating understanding of the salient details. Further, the view of

FIG. 19

is a “fold-flat” section of the entire subterranean structure


600


, depicting all 360 degrees of the circular structure (i.e., circular when viewed in a plan view). As described before, the structure


600


can be other shapes in plan view as well (such as rectangular, oval, elliptical, square, polygonal, etc.). Unlike structure


500


of

FIG. 18

where the three slabs


510


,


520


and


530


are all continually downward sloping slabs, the slabs


610


,


620


and


630


of the structure


600


of

FIG. 19

are generally horizontal, with periodic downward transition points


650


every 120 degrees. Slab


610


includes consecutive, descending sections


611


through


619


, slab


620


includes consecutive, descending sections


621


through


629


, and slab


630


includes consecutive, descending sections


631


through


639


. It will be noted that we have used the expression “sections” rather than “flights”, since certain of the sections within a given slab


610


,


620


,


630


do not overlap. For example, section


611


does not overlap sections


612


or


613


, but it does overlap section


614


. The slabs


610


,


620


and


630


are spaced-apart so that they define three descending subterranean tunnels. For example, the sections of slabs


610


and


620


which overlap one another form tunnel


601


, the sections of slabs


620


and


630


which overlap one another form tunnel


602


, and the sections of slabs


630


and


610


which overlap one another form tunnel


603


. Preferably, after the slabs


610


,


620


and


630


have been constructed (or as they are being constructed), the tunnels


601


,


602


and


603


are being backfilled with a fill material so that the levels are supported by one another and generally by the soil on which the structure


600


is being constructed. While

FIG. 19

depicts a structure


600


having three interleaved slabs


610


,


620


and


630


, it will be appreciated that a similar structure can be formed using only two interleaved slabs, or using more than three interleaved slabs. Accordingly, the structure of

FIG. 19

can be described as a structure having a plurality of adjoined (by joint ramps


650


), spaced-apart concrete slabs (e.g., slabs


611


through


619


) positioned in a subterranean excavation, (the excavation being performed as the slabs are being formed), and the concrete slabs (e.g., slabs


611


-


619


) are preferably generally vertically aligned to thereby define a descending subterranean tunnel (e.g., tunnel


601


). In this instance, the slabs


611


-


619


are generally aligned from side-to-side, but because of the periodic stepping-down at ramp joints


650


every 120 degrees, they are not aligned horizontally. However, if the ramping-down occurs only every 360 degrees, then the sections will be generally aligned horizontally as well. More preferably, the tunnel (e.g., tunnel


601


) is at least partially filled with a fill material. Alternately, or in addition to fill material, wall elements (such as wall elements


387


and


388


of

FIG. 8

) can be formed in the tunnel.




Turning now to

FIG. 20

, a side sectional view of another subterranean structure


700


in accordance with a further embodiment of the present invention is depicted. The structure


700


is a vessel generally having a top


702


, a bottom


722


, and a continuous closed wall


710


connecting the top and the bottom. The wall


710


includes a continuous ribbon slab


709


having a plurality of flights


731


through


743


fabricated from concrete and being defined by an inner perimeter


715


and an outer perimeter


713


. The vessel


700


further includes wall panels


724


attached to the inner perimeter


715


of the ribbon slab


709


between the top


702


and the bottom


722


.




The embodiment depicted in

FIG. 20

makes use of the fact that the tank wall


710


and the roof


702


can be constructed simultaneously and that a watertight wall and structural wall can be constructed at the same time. A method for constructing the vessel


700


can be performed as follows. A tank lid


718


, such as from nickel steel or the like, can be site fabricated on prepared ground surface G


1


′. The roof


702


(which can be fabricated from steel or the like) can then be constructed over the lid


718


, and tension rods


720


can be attached between the lid


718


and the roof


702


. A concrete portion


703


of the roof


702


roof can be cast having bearing flanges


714


to support the roof


702


on the soil G


1


. A foundation cap similar to cap


102


of

FIG. 3

can also be provided to support the roof


702


. Since the wall


710


can be fabricated simultaneously with fabrication of the roof


702


, if the walls


710


are sufficiently developed when the roof


702


is placed, then the bearing flanges


714


can be eliminated. Preferably, simultaneously as the roof


702


is being constructed, the subterranean wall


710


can be constructed in accordance with methods described above with respect to

FIGS. 3

,


14


and


15


A-


15


F. Excavation of the contained soils S


1


′ can be begun as soon as the lid


718


is sufficiently supported. Note that the wall


710


does not necessarily have to be complete when excavation of the soils S


1


′ begins. Excavation of soils S


1


′ continues until grade G


2


′is established. The excavated material S


1


′ can be removed with a hoist and bucket system, a high lift conveyor system, or using a hydraulic solids transport method with slurry pumps, or some combination of the these methods. Ballast weight


706


, which can be concrete and/or a magnetite-cement mixture, can then be placed on the grade G


2


′. A moisture barrier liner


704


, such as of carbon steel, can then be placed over the ballast


706


. Thereafter leveling courses and bottom insulation


708


can be placed over the moisture barrier


704


along the bottom of the forming vessel


700


, followed by the tank bottom


722


, which can be fabricated from nickel steel plate or the like. Similarly, a moisture barrier


746


can be placed adjacent to the inner perimeter


715


of the wall


710


, side insulation


712


can be placed over the side wall moisture barrier


746


, and interior tank walls


724


, which can be fabricated from nickel-steel, placed over the side insulation


712


. Insulation (not shown) can be placed over the lid


718


in the area beneath the top


703


. In one variation of the above method, the inner wall


724


can be constructed by hanging it from rods


716


around the perimeter of the roof


702


and constructing the inner tank wall


724


as the inside of the tank


700


is excavated from soil S


1


′.




While the structures


100


,


200


,


300


,


320


,


340


,


360


,


380


,


390


,


410


,


500


,


600


and


700


have all be described herein as “subterranean structures”, it will be appreciated that the entire structure does not need to be located below the surrounding grade to be within the scope of the embodiments of the present invention. So long as at least two flights of a continuous concrete slab, which forms a part of the structure, are located below the surrounding grade, then the structure can be considered a “subterranean structure”.




Furthermore, while embodiments of the present invention have described forming a subterranean structure to support a secondary structure (e.g., subterranean structure


100


of

FIG. 3

supports secondary structure


102


), it will be appreciated that similar methods and structures can be provided above grade to support a secondary structure. In this later embodiment the method of forming the support structure proceeds from the bottom up, rather than from the top down (as described with respect to FIGS.


14


and


15


A-


15


F). In one example of this embodiment a spiral slab is constructed beginning with a first flight on a grade (or slightly below grade). Thereafter, a second flight is formed over the first flight, and the second flight is supported on a fill material placed over the first flight. Subsequent flights can be added by placing a fill material on the immediately subjacent flight, and then forming the next flight. Rather than using sheet piling (such as piling


130


and


132


of FIG.


3


), a retaining wall can be formed between the flights to constrain the fill material being placed between the flights. In fact, the just-described above-grade structure can be incorporated similar to foundation


100


of

FIG. 3

, for example, so that an overall structure, having an above-grade section and a below-grade section, both constructed in accordance with embodiments of the present invention, can be constructed.




Another embodiment of the present invention provides for a method of subterranean mining. This method can be similar to the method depicted in FIGS.


14


and


15


A-


15


F. In this embodiment, the soil excavated as the continuous slab proceeds downward into the earth can be processed to remove commercially valuable materials (such as metals, coal, etc.). With reference to

FIG. 1

, a subterranean structure in accordance with certain embodiments of the present invention includes a continuous concrete slab


10


which has a width “W” which is typically significantly smaller than the diameter “D” across the flights


12


,


14


,


16


,


18


and


20


. However, when methods of the present invention are used for subterranean mining, then typically the ratio of the width of the flight to the diameter of the flight will be much larger to increase soil extraction (and therefore mineral recovery), and reduce unclaimed soils. Further, using methods of the present invention for mining purposes allows tailings to be used for fill material between flights.




In yet another embodiment of the present invention methods and structures in accordance with other embodiments of the present invention can be used for open pit mining. In this embodiment a structure similar to retaining wall


200


of

FIGS. 2 and 3

can be constructed (but without foundation


100


and secondary structure


102


) to define the open pit and provide geo-stability of the walls defined by the forming pit. In one example, the retaining wall structure can be formed as the pit, defined within the retaining wall, is excavated to remove useful ores and other subsurface materials. Although retaining wall


200


of

FIG. 3

is depicted as having an essentially vertical wall, in the case where a retaining wall constructed in accordance with embodiments of the resent invention is used to define an open pit mine, the wall can also taper inward as the depth of the wall increases. The use embodiments of the present invention for open pit mining can result in a single structure being used to define the open pit mine, such as a structure which is circular in plan view (similar to retaining wall


200


of FIG.


2


), which results in a single, continuous wall (as viewed in the plan view). Alternately, a plurality of structures in accordance with embodiments of the present invention can be used to produce a plurality of walls which thus define the open pit mine.




Continuous concrete spiral slabs having generally vertically aligned flights or levels are well known structures. One common example is to use a continuous concrete spiral slab to provide access to various levels of a parking garage. While such prior art structures are commonly located above ground, they have also been used below ground for access purposes. Such prior art structures are used to support a localized load on the slab itself, as for example the load imposed by a vehicle using the slab to access a level of a parking garage. Such prior art continuous slabs have not been used to support a secondary structure. Accordingly, prior art continuous slabs are designed and constructed for localized loads. That is, prior art continuous slabs are not designed or configured to support a generalized load placed over the uppermost flight or level of such a structure. One significant feature of certain structures in accordance with the present invention is providing a fill material, and/or supporting wall elements, between levels or flights of an essentially continuous concrete slab (wherein the levels or flights are generally vertically aligned) to provide support between the levels or flights themselves. Furthermore, prior art continuous slabs have not been used to form a mono-caisson (such as structure


100


of

FIG. 3

) to contain soil (such as soil S


1


′ of FIG.


3


), or to define the wall of a storage vessel (such as vessel


700


of FIG.


20


).




While examples described herein have been depicted as using a single subterranean structure (such as foundation


100


of

FIG. 3

) to support a single secondary structure (e.g., secondary structure


102


of FIG.


3


), it will be appreciated that multiple subterranean structures in accordance with embodiments of the present invention can be used to support a single secondary structure. For example, two or more foundation structures similar to structure


100


of

FIG. 3

can be used to support a single secondary structure. In this example, a monolithic foundation cap (similar to foundation cap


106


of

FIG. 3

) can be used to support the secondary structure on the multiple subterranean foundation structures. Further, a single subterranean structure (such as structure


100


of

FIG. 3

) can be used to support multiple secondary structures. In this latter example a single foundation cap placed over the single subterranean structure can support the multiple secondary structures on the single subterranean foundation structure. While the secondary structure (


102


,

FIGS. 2-9

) has been described as being a building, it can also be a movable piece of equipment, or any other structure or device which can be supported on a foundation.




Thus far we have described examples of a subterranean structure which have a closed form in plan view, and which define an inner volumetric area (e.g., spiral slab


10


of

FIG. 1

defines an inner volumetric area of diameter “D” having a height between the uppermost flight


12


and the lowermost flight


20


). By “closed form” we mean that, in a plan view, if one begins at a first point and follows a continuous forward-progressing line along the form, one will eventually arrive again at the first point. However, the present invention also provides for a subterranean structure which can be in an open form. By “open form” we mean that, in a plan view, if one begins at a first point and follows a continuous forward-progressing line along the form, one will not again arrive at the first point. In simple terms, a “closed form” does not have endpoints, whereas an “open form” has two or more endpoints. Examples of a “close form” include a circle, an ellipse, an oval, and a polygon. An example of an “open form” is a line (straight or curvilinear). Accordingly, the present invention provides for forming a subterranean open-form structure (such as a retaining wall) using methods disclosed herein, which includes a continuously downward-progressing concrete slab. For example, if the structure is a retaining wall having endpoints “A” and “B”, then the structure includes multiple levels or flights having switch-backs located essentially at the endpoints (as viewed in a plan view).




While the above invention has been described in language more or less specific as to structural and methodical features, it is to be understood, however, that the invention is not limited to the specific features shown and described, since the means herein disclosed comprise preferred forms of putting the invention into effect. The invention is, therefore, claimed in any of its forms or modifications within the proper scope of the appended claims appropriately interpreted in accordance with the doctrine of equivalents.



Claims
  • 1. A subterranean vessel, comprising:a top and a bottom; and a continuous closed wall connecting the top and the bottom, the wall comprising: a continuous ribbon slab having a plurality of flights fabricated from concrete and being defined by an inner perimeter; and wall panels attached to the inner perimeter of the ribbon slab between the top and the bottom.
  • 2. A subterranean structure, comprising:a continuous ribbon slab having a plurality of flights fabricated from concrete, the ribbon slab defining periodic openings therein which generally align between adjacent flights, and wherein the flights are separated by a slab interval, the structure further comprising a fill material located in the slab interval.
  • 3. A subterranean structure, comprising:a continuous ribbon slab having a plurality of flights fabricated from concrete, the ribbon slab defining periodic openings therein which generally align between adjacent flights, and wherein the periodic openings which are generally aligned between adjacent flights define a caisson; and the structure further comprising a plurality of caisson liners, each caisson liner being located within an associated caisson.
  • 4. The subterranean structure of claim 3-4, and wherein the caisson liners are filled with a fill material.
  • 5. A subterranean structure, comprising:a continuous ribbon slab having a plurality of flights fabricated from concrete, the ribbon slab defining periodic openings therein which generally align between adjacent flights, and wherein the flights are defined by an outer perimeter and an inner perimeter; and the structure further comprising outer sheet piling located at the outer perimeter of the flights and between adjacent flights.
  • 6. The subterranean structure of claim 5, and further comprising inner sheet piling located at the inner perimeter of the flights and between adjacent flights.
  • 7. The subterranean structure of claim 5, and further comprising a concrete wall attached to the outer sheet piling and facing the inner perimeter of the flights.
  • 8. The subterranean structure of claim 7, and further comprising outer inner sheet piling located at the inner perimeter of the flights and between adjacent flights.
  • 9. The subterranean structure of claim 8, and further comprising a concrete wall attached to the inner sheet piling and facing the inner perimeter of the flights.
  • 10. The subterranean structure of claim 7, and further comprising a concrete wall attached to the continuous ribbon slab at the inner perimeter of the flights.
CROSS REFERENCE TO RELATED APPLICATIONS

This application claims priority to U.S. Provisional Patent Application serial No. 60/385,325, filed Jun. 3, 2002, and entitled “Methods and Apparatus for Constructing Subterranean Structures”.

US Referenced Citations (2)
Number Name Date Kind
3307361 Waterman Mar 1967 A
5775043 Muroi Jul 1998 A
Foreign Referenced Citations (1)
Number Date Country
04049324 Feb 1992 JP
Provisional Applications (1)
Number Date Country
60/385325 Jun 2002 US