Many types of completions are used in sand control operations. Generally, a completion assembly is positioned in a wellbore and a service tool is used in cooperation with the completion assembly to create a gravel pack in the annulus around the completion assembly. The gravel pack helps filter out sand and other particulates from a desired production fluid entering the wellbore.
The gravel pack is formed by flowing a gravel slurry downhole to the well zone to be treated. At the well zone, a carrier fluid is separated from the gravel slurry leaving gravel to form the gravel pack. The carrier fluid reenters the completion assembly through a screen and is returned upwardly through a washpipe section of the service tool. The return flow is directed upwardly through a central passage of the washpipe and then diverted outwardly to an annular flow path through a crossover port. Because of this construction, the length of the wash pipe is generally similar to the length of the well zone to be treated.
In general, the present invention provides a system and method for forming a gravel pack at one or more well zones along a wellbore. A completion assembly having a completion assembly central bore is positioned in a wellbore. A return is located radially outward of the completion assembly central bore and comprises a flow passage for returning a carrier fluid. Thus, the carrier fluid that is separated from gravel slurry during the gravel packing operation is returned along a flow path external to the completion assembly central bore at the well zone undergoing the gravel packing operation.
Certain embodiments of the invention will hereafter be described with reference to the accompanying drawings, wherein like reference numerals denote like elements, and:
In the following description, numerous details are set forth to provide an understanding of the present invention. However, it will be understood by those of ordinary skill in the art that the present invention may be practiced without these details and that numerous variations or modifications from the described embodiments may be possible.
The present invention generally relates to a well system that can be used for well treatment operations, such as sand control operations. The system and methodology provide a technique for forming a gravel pack at one or more well zones along a wellbore. A completion assembly is positioned in a wellbore and is constructed to provide return flow from the gravel packing operation external to a completion assembly central bore. As gravel is deposited in the desired well zone, the carrier fluid or return fluid is routed back to the surface through a return. However, the return is positioned so the flow of returning fluid is along a flow path that remains radially outward of the completion assembly central bore.
Referring generally to
In the embodiment illustrated, completion assembly 32 comprises a continuous internal passage referred to as a completion assembly central bore 45 defined within, for example, a tubular structure 46. Tubular structure 46 comprises screens 48 positioned at each well zone 40 to allow fluid flow therethrough. For example, screens 48 may allow the inward flow of returning carrier fluid that flows from the annulus surrounding the completion assembly 32 into the region between tubular structure 46 and service string 34 at the subject treatment zone. A packer 50, such as a GP packer, secures completion assembly 32 to wellbore casing 42. Additionally, a plurality of isolation packers 52 are positioned between completion assembly 32 and the surrounding casing 42 at predetermined locations to selectively isolate the well zones 40.
Service string 34 may be deployed downhole with completion assembly 32 on an appropriate conveyance 54, such as a tubing. The service string 34 may be attached to completion assembly 32 proximate the upper packer 50. Generally, service string 34 comprises an upper section 56 coupled to a service tool 58 through a crossover 60. Crossover 60 comprises one or more crossover exit ports 62 that are positioned adjacent corresponding circulating ports of completion assembly 32 to enable the flow of treatment fluid into the annulus surrounding completion assembly 32. In a gravel packing operation, a gravel slurry is pumped down into this annulus at a given well zone, and the carrier or return fluid portion of the slurry is returned up through service string 34. In the present design, this returning fluid does not enter the interior of the service tool washpipe.
During run-in, the service tool 58 may be maintained in a wash-down configuration that allows downward fluid flow through the service string and through an internal passage 64, as illustrated in
Referring generally to
As illustrated, gravel slurry is flowed downwardly through service string 34 until it is directed radially outward through crossover ports 62 and corresponding circulating ports 80 of completion assembly 32. The gravel slurry moves outward into the surrounding annulus where gravel is deposited and dehydrated in the desired well zone 40. The separated carrier fluid moves radially inward through the screen or screens 48 positioned in the well zone being treated and then is directed to flow path 76 of return 74. In the embodiment illustrated, the returning fluid is directed radially outward to the flow path 76 which is located at an offset position relative to completion assembly central bore 45 and service tool 58. This access to flow path 76 can be selectively controlled via valves 82. For example, the lowermost valve 82 is opened to permit outflow of returning fluid to flow path 76 in the well zone 40 being treated. Valves 82 can be simple on-off valves, such as sliding sleeve valves, or other suitable valves.
Isolation valves 84 also can be deployed along return 74, e.g. along shunt tubes 78, to enable sections of flow path 76 to be blocked. The valves 84 are used, for example, to shut off access to sections of the shunt tubes 78 that are not being treated. In the illustrated example, the lowermost isolation valve 84 is in a closed position to block any downward flow of return fluids relative to the well zone 40 being treated. A variety of valve types can be used to form isolation valves 84, e.g. ball valves, sliding sleeve valves, and other suitable valves that allow the selective blocking and opening of flow path 76 to isolate sections of the return.
Upon completion of a gravel pack 86 in the desired well zone 40, service string 34 is shifted to a reversing position, as illustrated in
Placement of the returning carrier fluid flow path 76 to the exterior of completion assembly central bore 45 relieves the need for screen isolation. Furthermore, because return flows are directed along the exterior flow path, there is no need to maintain washpipe return spacing that must correspond with well zone length. The various well zones being treated may be of dissimilar lengths, because the relationship of the washpipe to the well zone length is decoupled. Also, because return flows are not directed through the washpipe, there is no need for a corresponding crossover port. This lack of a corresponding crossover port greatly simplifies the design and operation of service tool 58. The well system 30 also offers the ability to wash-down when deploying the apparatus inside wellbore 36, as illustrated in
The well system 30 can be used for a variety of applications and in many types of environments. For example, well system 30 can be used with single zone wells or multiple zone wells. Accordingly, the following description is one application of well system 30. However, it should be understood that well system 30 can be used in a variety of other environments, other applications, in cased or open wellbores, and with other or alternate procedures.
By way of example, well system 30 can be used in a sequential multizone operation in a cased wellbore. In this example, a perforation assembly is initially run-in-hole and well zones 40 are perforated to form perforations 44. Completion assembly 32 is then run-in-hole along with service string 34. Generally, the service string 34 is connected to the completion assembly 32 at the upper packer 50. The completion assembly 32 is then moved to the desired location in wellbore 36.
Once the completion assembly 32 is placed on depth, ball 66 or other blanking device is dropped from the surface, and service string 34 becomes pressure competent. Pressure may then be applied to the service string 34 to set packer 50 which secures completion assembly 32 to wellbore casing 42. The isolation packers 52 may then be set. By way of example, isolation packers 52 may be set by adjusting service string 34 to a packer setting position and applying tubing pressure within the service string. Then, the service string 34 is placed in a circulating position with exit port 62 positioned adjacent circulating port 80 of completion assembly 32. Simultaneously, the valve 82 is shifted to open the return port at the lower end of the zone to be treated. The valve may be shifted to the open position by the movement of service string 34.
A gravel slurry is circulated into well zone 40 through the circulating port or ports 80, and gravel is placed in the well zone. The gravel is dehydrated from the bottom up such that clear return fluid passes through the outside diameter of the appropriate well screen 48. The returning carrier fluid flows into the annulus between the well screen and the service tool 58. From there, the carrier fluid is directed outwardly into return 74 and then directed upwardly until it exits into the wellbore annulus above stripper 72.
When screenout is achieved, service string 34 is moved to the reverse position, and the appropriate isolation valve 84 is closed (see, for example,
An alternate embodiment of well system 30 is illustrated in
In this embodiment, an additional valve 92 is located in the completion assembly at each well zone 40 and is used when the service string is positioned in the reversing configuration. Valve 92 may be an on-off valve, such as a sliding sleeve valve or other suitable valve. When the gravel pack is formed in the desired well zone 40, service string 34 is shifted to the reversing configuration, as illustrated in
Referring generally to
In the embodiment illustrated, a plurality of screen assemblies 48, e.g. two screens 48, are connected by a jumper tube 98 that allows carrier fluid to flow from the region between screen jacket 96 and base pipe 94 of one screen 48 to the region between screen jacket 96 and base pipe 94 of the next adjacent screen 48. Thus, return 74 can extend to the bottom of the lower screen 48 and still function to return carrier fluid entering any and all of the screen assemblies 48. It should be noted that return 74 can be routed to the bottom of the lowermost screen 48 internally or externally of one or more of the screen jackets 96.
In this embodiment, a valve 100, such as a sliding sleeve, is used to selectively open or block flow from return 74 into an annular region between service string 34 and completion assembly 32. When the service tool 58 is moved to a reversing configuration, as illustrated in
Referring generally to
Upon completion of the gravel packing operation, the service tool 58 is shifted to a reversing configuration, as illustrated in
When well system 30 is used in cased wellbore applications, a perforating assembly may be attached to the bottom of completion assembly 32. The casing 42 can then be perforated at the time completion assembly 32 is run downhole, and a separate perforating trip is eliminated. This approach also can minimize fluid losses because the well zones are treated directly after perforating which may avoid the need for loss control pills. However, well system 30 also can be used in open hole applications were no perforating operation is performed.
The embodiments described above provide examples of gravel packing well systems that maintain flow of returning carrier fluid radially outside of the completion assembly central bore in the desired well zone region. Depending on a given gravel packing operation, the configuration of the completion assembly and service string can be changed according to requirements of the job. Other components can be added, removed or interchanged to facilitate the treatment operation. For example, a variety of valves can be used, and a variety of return structures can be routed along various paths offset from the internal passage of the service tool. Additionally, the various embodiments described herein can be adapted for use in single zone or multizone applications in cased or open wellbores. The completion assembly central bore comprises a passage that may be formed in a variety of ways with a variety of configurations, orientations, and relative positions within the completion assembly.
Accordingly, although only a few embodiments of the present invention have been described in detail above, those of ordinary skill in the art will readily appreciate that many modifications are possible without materially departing from the teachings of this invention. Such modifications are intended to be included within the scope of this invention as defined in the claims.