The present invention is directed toward applications of on-grid communications for optimizing electrical distribution, and specifically for real-time identification and location of non-technical losses occurring in a service transformer area network.
Electrical Distribution Substations contain one or more Substation Transformers, which step down the voltage from high transmission line levels (typically 130 kV to 700 kV) to the medium voltage levels (typically from 4 kV to about 35 kV) at which power is distributed to consumers within a distribution service area. At the edge of the Distribution Grid are a number of Service Transformers, which transform the medium voltage of the distribution grid to the low voltages (in the US, typically 120, 208, 240, 277, or 480) required for commercial, industrial, and residential consumers. Other voltages in addition to some of these can be used elsewhere in the world. Each Service Transformer powers one or more metered loads. A load can be a dwelling, a commercial or industrial building, an element of municipal infrastructure such as a series of street lamps, or agricultural apparatus such as irrigation systems.
Other than the wires connecting a consumer load and the associated meter to a service transformer, the service transformer is the outermost element of the distribution grid before the power is actually delivered to a consumer. A meter is typically attached at the point where the power from the service transformer is delivered to the consumer. Service transformers can be three-phase, dual-phase, or single phase, as can meters. Herein the collection of electrical apparatus inclusive from a service transformer to the collection of at least two communicating electrical meters is referred to as a Transformer Area. Network (TAN). A TAN can have a radial topology, such as is common in the US, or it can have a linear or “bus” topology, as is more common in Europe and elsewhere in the world.
Traditionally, reading meters was one of the largest operational costs incurred by electrical utilities. Original electric meters were analog devices with an optical read-out that had to be manually examined monthly to drive the utility billing process. Beginning in the 1970s, mechanisms for digitizing meter data and automating its collection began to be deployed. These mechanisms evolved from walk-by or drive-by systems where the meter would broadcast its current reading using a short-range radio signal, which was received by a device carried by the meter reader. These early systems were known as Automated Meter Reading systems or AMRs. Later, a variety of purpose-built data collection networks, commonly employing a combination of short-range RF repeaters in a mesh configuration with collection points equipped with broadband backhaul means for transporting aggregated readings began to be deployed.
These networks were capable of two-way communication between the “metering head-end” at a utility service center and the meters at the edge of this data collection network, which is generally called an Advanced Metering infrastructure or AMI. AMIs can collect and store readings frequently, typically as often as every 15 minutes, and can report them nearly that often. They can read any meter on demand provided that this feature is used sparingly, and can connect or disconnect any meter on demand as well. AMI meters can pass signals to consumer devices for the purpose of energy conservation, demand management, and variable-rate billing. Because the AMI network is separate from the power distribution grid except for the intersection at the meters, AMI meters are neither aware of nor sensitive to changes in the grid topology or certain conditions on the grid. Nonetheless, the introduction of AMI is generally considered to be the beginning of the distribution Smart Grid. Additionally, because of the mesh architecture typically used in the AMIs in the United States, the available bandwidth for an individual electrical meter to send its own data is quite limited.
The total billable kilowatt-hours produced by a typical electrical distribution grid anywhere in the world is substantially less than the actual power distributed, as measured at a distribution substation, over the billing period. The loss of power can be classified into two groups. Technical losses result from the overall impedance of the distribution infrastructure, from power-factor mismatch between what the population of loads requires and what the grid produces at each load point, and from the fact that utilities oversupply voltage to ensure that power sags will not occur during unpredictable peak loads. Utilities can work to minimize these technical losses, but some technical losses are unavoidable.
Non-technical losses of actual power-hours (as opposed to revenue) result from power theft by consumers who avoid or subvert the metering process by tampering with meters or by tapping power lines above the metered load points. Non-technical revenue losses also include non-payment of bills by customers, and accounting errors by utilities. However, these types of revenue losses are addressed by Meter Data Management systems integrated with the Advanced Metering Infrastructure. These automated systems have the capability to prevent clerical errors, to immediately cut off service to non-paying customers, and to require customers with poor payment histories to be on a pay-in-advance billing plan. Because AMIs provide little or no information about the grid-schematic relationship of one electrical meter to another and the relationship between the electrical meter and the service transformer supplying it with power, AMIs are of little value in pinpointing the source of power theft. Some Smart Meters can detect and report tampering. On the other hand, the absence of meter readers from neighborhoods reduces the chance that illegal taps will be seen and reported.
The social and financial costs of power theft are highly variable, in the developing world, these costs are quite high: sometimes exceeding 50% of power delivered from substations. In India, for example, the major private utilities (Reliance and Tata) report non-technical losses around 10%, but the state-owned utilities have losses exceeding 30% in most cases, according to the India's Maharashtra Electricity Regulation Commission (MERC).
In the developed world, losses from theft represent a relatively small percentage of the total generation cost. In the United States, losses from theft have traditionally been estimated at one to three percent of revenue, though this figure increases during difficult economic times.
Power theft represents a safety and quality-of-service issue as well as an economic issue. Jury-rigging power taps is dangerous and often results in injury and even death. Additionally, the jury-rigged taps represent a fire hazard. Most significantly, the resultant unpredictable loading of the distribution grid can cause transformer fires and explosions that can result not only in dangerous situations but in major power outages.
Prior art methods for detecting power theft can be divided into three categories. One category involves comparing voltage and current at a meter with voltage and current at a point of origin for delivery, such as the service distribution transformer for a neighborhood. The technical losses due to the resistance of the low voltage line between the point of origin and each meter are presumed to be less than a predetermined amount, so that any difference in power loss above the predetermined amount can be presumed to be due either to theft or to line defects. United States Patent Application Publication No. 2012/0265355, titled System and Method for Single and Multizonal Optimization of Utility Services Delivery and Utilization (incorporated herein by reference) describes a system of this sort, wherein intelligent software agents at the service transformer collect measurements both at the transformer and from other instruments located at or incorporated in the electric meters. Theft detection is cited as one of the applications of this system. However, systems involving placing agents and instruments at the transformer are less desirable than would be a system that did not require any devices at the transformer, because transformers are far less physically accessible than meter sockets, and modifying them by adding instrumentation inside the transformer housing or on the high-voltage side of the transformer can be costly and even dangerous.
A second category involves measuring current and voltage outside the meter of a metered load, and inside the premises of the metered load. If more power is being used on the premises than is being delivered via the meter, then either power is being locally generated on the premises, or the meter is being bypassed. Methods of this sort are problematic for utilities because a service utility typically does not have access to data from inside the metered load. The consumer would have to agree to the placement of devices inside the premises.
A third category involves detecting the instantaneous changes in power usage or minor outages caused by tampering with the distribution lines in order to install an unmetered tap. This category of mechanism falls short because tampering can be masked by larger events such as a legitimate outage or interruption in service, and because it would create many false positives.
The present invention is an apparatus and methods for real-time or near-real-time detecting and reporting of power theft in such a way that the tamper point may be determined to have occurred on the low-voltage side of a specific service transformer. In cases of meter tampering the specific meter or meters involved may be identified. The present invention does not require instrumentation of the transformer at the service delivery point (service transformer). All instruments and the intelligent agents which perform and collect the measurements and process the collected data to find evidence of power theft are located where instruments and intelligence would reside anyway: at the electrical meter. This is beneficial in that the meter socket is typically easily accessible, and because a smart meter already contains memory and processors for hosting software agents, already has the capability of making many of the measurements used by the methods of the present invention, and because most smart meters are designed to accommodate an additional circuit board where the native instruments, communication capabilities, and/or memory and processing capabilities are insufficient to support the methods described herein.
U.S. patent application Ser. No. 13/871,944, titled A System and Method for inferring Schematic and Topological Properties of an Electrical Distribution Grid, incorporated herein by reference, describes augmenting Smart Meters with long-range (Edge-to-Substation) on-grid transmitters, and also short-range (low voltage, local to the service transformer) on grid transceivers. A Smart Meter having both short-range and long-range on-grid transmission capability is called a Remote Hub. A Smart Meter having only short-range on-grid capability is called a Subordinate Remote. The term Remotes is used to refer collectively to both Subordinate Remotes and Remote Hubs. A service transformer having a Remote Hub and zero or more Subordinate Remotes is defined as a Transformer Area Network, or TAN. Further, that application discloses a method for determining the feeder and phase supplying a Remote Hub with power based on characteristics of a long-range message transmitted from the Remote Hub.
U.S. patent application Ser. No. 13/888,102, titled Methods for Discovering, Partitioning, Organizing, and Administering Communication Devices in a Transformer Area Network, also incorporated herein by reference, teaches a method of ensuring that all Remote Hubs and Subordinate Remotes in a TAN are, in fact, supplied with power by the same service transformer, and, in the case of a multi-phase transformer, determining which Remotes are on the same phase as a Remote Hub and which Remotes are on a different phase. Additionally, U.S. patent application Ser. No. 13/911,849, titled A System and Method for Inferring Schematic Relationships between Load Points and Service Transformers and incorporated herein by reference, describes a method for identifying the specific service transformer and its geospatial coordinates which supply a given meter socket, and incorporating the association and coordinates into a map of the distribution grid. The utility already knows at least the street address, if not the precise geospatial coordinates, of every meter. Using the information obtained from the systems and methods in the above-referenced applications, the physical and schematic origin of a report from a Remote Hub, and the physical and schematic extent of the Transformer Area Network the Remote Hub represents, may be very precisely defined. These inventions teach a Transformer Area Network Architecture which is master-slave in nature, wherein one Remote, typically the Remote Hub, contains most of the intelligence, and polls simpler agents on the Subordinate Remotes both to organize the TAN, and to implement applications on the TAN. The system and methods of the present invention are primarily described in terms of such a TAN organization. However, a master-slave network organization is only one of the possible network organizations suitable for hosting the present invention. For example, a peer-to-peer transformer area network is also suitable. A wider peer-to-peer network, such as an AMI mesh network, might also be suitable given that a) the nodes in the network have sufficient information to partition themselves logically by transformer area and b) that there is sufficient bandwidth for sharing the measurements taken by the measurement agents of the present invention, as described herein below.
The present invention provides a method for a Remote Hub in communication with at least one Subordinate Remote, each Remote operable to measure and store voltage at the meter and current passing from the meter to the metered load, to identify indications that power theft is occurring in the TAN, without placing apparatus either at the service transformer of the TAN or inside the premises of the loads powered by the TAN. For this purpose, the TAN comprises at least two nodes, such as one Remote Hub and one or more Subordinate Remotes, on each phase of the TAN. Further, every load (metered service point) on the TAN has a Remote (or another type of communicating meter) if complete theft protection is to be achieved. The method can be employed with some meters not having a Remote, but some thefts may go undetected in that case, depending on the topology of the TAN and the location of the unauthorized tap with respect to the communicating meters. Methods for inferring the existence and location of illegal taps that do not require taking measurements at the service transformer of the TAN are taught. Avoiding the need to take measurements at the service transformer is desirable because the cost of only adding instrumentation at the meters is significantly lower than the cost of adding instrumentation at both the meter and the transformer, as is the cost of maintaining the network when all instruments and intelligence reside at the meter only. Avoiding the need to place apparatus inside the premises of the metered service point is desirable because the consent of the consumer is required to place apparatus inside the premises, and because maintenance of equipment inside the premises is typically outside the charter of the utility.
The accompanying drawings, which are incorporated in and form a part of the specification, illustrate the embodiments of the present invention and, together with the description, serve to explain the principles of the invention. In the drawings:
Refer to
Refer now to
In one embodiment of the invention, a measurement agent resides on each of Remotes 402, 404, and 403. Each agent periodically measures the delivered voltage V and flowing current I at its service point. A monitoring agent which may reside on Remote Hub 403 periodically collects the time-stamped current and voltage measurements from Subordinate Remotes 402 and 404 and from its own measurement agent. The period of the monitoring agent is not required to be the same as the period of the measurement agents, but the time at which the measurements are taken is synchronized to the closest tolerance possible given the capabilities of the TAN. Both periods are very small with respect to the time scale of events in a typical AMI network, wherein, for example, meter readings may be transmitted only every fifteen minutes or even less frequently. The monitoring agent executes a software algorithm that compares current and voltage measurements taken at the different meters at the same time and uses them to infer when an unmetered flow of current is occurring between the transformer and one or more of the metered service points.
In
Consider now the components in the rectangle 605 representing Node 1. Node 1 comprises the apparatus delivering power from service transformer 607 to meter 627. Interesting measurable quantities are marked on the diagram. Impedance 616 represents the legitimate metered load of the premise of Node 1, which may vary over time according to what appliances and devices are in use on the premise. Point 626 is not an actual piece of equipment, but represents an arbitrary place on the power line from transformer 607 to meter 627 where an illegal tap might be installed. Impedance 612, which is normally extremely large when no theft is occurring, represents a potential unauthorized, unmetered load. Impedances 609 and 613 represent the normal impedance of the power line from transformer 607 to meter 627. Voltage 611 represents the voltage at hypothetical tap point 626. None of these quantities are known to or measureable by the software agents residing at meter 627. Current 614 and voltage 615 are measured periodically by the measurement agent residing at meter 627 and shared on the TAN by the communication equipment at meter 627. Regardless of the network architecture of the TAN, the sharing is always conducted in such a way that the identity of the meter from which the measurements originate and the time the measurements were taken is known to any receiver of the messages in which the measurements are transmitted. Note that element 622 of
Similarly, consider the components in the rectangle 610 representing Node N. This is the apparatus delivering power from service transformer 607 to meter 629. Impedance 625 represents the legitimate metered load of the premise of Node N, which may vary over time according to what appliances and devices are in use on the premise. Point 628 is not an actual feature of the TAN, but represents an arbitrary place on the power line from transformer 607 to meter 629 where an illegal tap might be installed. Impedance 623, which is normally extremely large when no theft is occurring, represents a possible unauthorized, unmetered load. Impedances 618 and 620 represent the normal impedance of the power line from transformer 607 to meter 629. Voltage 619 represents the voltage at hypothetical tap point 628. None of these quantities are known to or measureable by the software agents residing at meter 629. Current 621 and voltage 624 are measured periodically by the measurement agent residing at meter 629 and shared on the TAN by the communication equipment at meter 629.
For the purposes of the algorithm of the monitoring agent, it does not matter whether meter 629, meter 627, or the meter of another Node between 1 and N has the Remote Hub and which meters have Subordinate Remotes. Indeed, as is noted herein above, another type of TAN communication entirely may be employed, as long as it provides sufficient bandwidth for all the meters of the TAN to share their measurements within a sufficiently small period. The TAN may host at least one monitoring agent somewhere on the TAN and a measuring agent at each communicating meter. With some network architectures, it may be more effective to host a monitoring agent in every node. Alternatively, the work of the monitoring agent may be distributed among multiple communicating meters. If the monitoring agent does not reside on a meter having the capability to send a wide-area message such as an Edge-to-Substation message, then the monitoring agent must transmit a command to a wide-area enabled device to transmit the anomaly report.
Suppose that an unauthorized load represented by impedance 612 is now attached at point 626. Voltage 611 will drop because more current (the current drawn by the unauthorized load at 612) is flowing through impedance 609. This will also cause a drop in voltage 615. However, the current 614 flowing through impedance 613 does not drop correspondingly. A measurement agent at meter 627, able to measure only current 614 and voltage 615, will not be able to infer whether the drop in voltage 615 is due simply to a drop in voltage 606, or whether it is caused by a theft represented by a drop in voltage 611 and a decrease in impedance 612 (which ought to always be very large). However, consider the observations made by a measurement agent at meter 629. For simplicity, assume that impedance 623 in Node N (610) is properly large—no power is being stolen in Node N. A measurement agent at meter 629 will observe a drop in voltage 624 due to the drop in voltage 606. A monitoring agent can use the measured currents 614 and 621 at the meters 627 and 629 respectively (and others, if there are more communicating nodes in the TAN) to estimate the proper voltage drop due to each metered load. Once the effects of the metered loads (616, 624) have been removed, the adjusted magnitudes of the voltages measured at each meter can be compared. Even though there will be small differences in the line impedance between the transformer 607 and each meter, these are expected to be negligible. (In this example, compare impedances 609+613 to meter 627 with impedances 618+620 to meter 629.) If one meter, in this example 627, sees a greater adjusted voltage drop than the other meters, within a tolerance representing normal differences in the line impedance, then it is to be expected that an unmetered load exists between that meter and transformer 607.
Further, this method of comparing current and voltage from each available “viewpoint” detects theft in the TAN even if there are multiple theft points. Even if there were an unmetered load attached between every meter and the transformer, unless the impedances 612, 623, etc. due to unauthorized loads were identical at all times, then the theft points could still be inferred by a monitoring agent with access to the current and voltage measurements of each measurement agent, because the voltage drops at some measurement points would not be proportional to the current at the same point.
When the monitoring agent residing at the Remote Hub of the TAN detects a probable theft, then the Remote Hub may send an Edge-to-Substation message to alert the utility about the anomaly. Edge-to-Substation messages, as described in U.S. patent application Ser. No. 13/871,944 referenced above, travel from a Remote Hub to an electrical distribution substation supplying power to the substation transformer, here, transformer 607. From the substation, the message is transferred by a conventional network to a data center provided by the utility or an energy management services provider. A theft alert may also be propagated via another available network connected to the Remote Hub or other communicating meter, such as an AMI network. Such a message may include at least a unique identifier of the service transformer or a meter at which the anomalous current-voltage relationship was detected which may be used to match the origin of the message with the data in a grid map database.
The method described herein above with minor computational adjustments can be equally applied to a transformer area which has a bus topology such as is shown in
In order to apply this method in a TAN with a bus topology, it is necessary for the order of the nodes in the TAN with respect to the transformer to be known to the monitoring agent (at least). This can be inferred by the monitoring agent. The ordering of the series will correspond to the measured voltage at each metered point, with the lowest voltage being schematically furthest from the transformer. Referring again to
U.S. patent application Ser. Nos. 13/871,944, 13/888,102, and 13/911,849, all referenced above, teach methods for recording an accurate grid map of an electrical distribution network. The grid mapping method taught by these inventions includes the feeder and phase of each substation operable to power each metered load supplied by the network and a correct and current partitioning of the meters of the network into Transformer Area Networks. In order to perform theft detection, the grid map of a TAN with a bus topology may be augmented with the series order of the meters of the TAN, and this order can be kept up-to-date as meters and loads are added and removed from the TAN. For theft detection, this information may only need to be maintained by a monitoring agent in each TAN, and indeed it may be recomputed periodically by each monitoring agent. However, it may be beneficial to record this additional information in a centralized grid map database, said centralized grid map database being taught by Ser. No. 13/871,944. To do this, the Edge-to-Substation message sent when a new node is discovered in the TAN may include the schematic order of the meter on the power line bus from the transformer. Similarly, if the order of nodes were observed to change, for example after a power outage or extension of the TAN due to construction, then the new ordering might be reported in an Edge-to-Substation message to be recorded in a grid map database.
Another method of power theft is sometimes used that does not involve creating an illegal tap. This method involves creating misdirection by switching meters with a neighbor prior to making an increase in consumption. A communicating meter of any kind can already be enabled to report being disconnected from the meter socket if it is plugged into a meter socket again (whether the same socket or a different one) while power is available. However, an enterprising power thief can wait for a natural power outage in which to swap meters with another premise, or can vandalize the network to create an outage in which to effect the swap. An intelligent meter, however, that participates in a Transformer Area Network with real-time grid mapping as is described herein and in the referenced related inventions, can detect an illegal move in a variety of ways:
This leaves only one case—swapping two meters not enabled to receive a geospatial location signal, between two premises on the same phase of the same radial TAN—which is not easily detected. This case may be undesirable from the viewpoint of the thief because of the proximity of the premises: better to tamper with a meter socket several blocks away than with that of the next-door neighbor.
To manage the detection process, an agent such as the monitoring agent on at least one communicating meter (such as a Remote Hub) on each TAN may report each of the detected anomalous conditions using an Edge-to-Substation message or another available wide-area network capable of forwarding the message to a software program residing in a data center with access to the consolidated grid map. The software program also receives reports of planned grid changes from other applications used to manage the grid. An example of such reports could be the work orders used to dispatch field engineers to make required changes and repairs to the distribution grid. The software program avoids reporting false theft indications by matching the anomaly reports from the communicating meters against the work orders or similar reports. Anomalies which are explained by the work orders are not reported as potential indicators of theft. The anomalies which cannot be matched with a work order create alerts that a potential theft may be occurring, regardless of whether the anomaly is a change in the grid map or a voltage anomaly reported by a monitoring agent. The theft alert may contain the account numbers and addresses of the affected premises, the identity and geospatial coordinates of the affected transformers and meters, and any other relevant information that may be used to locate the theft, whether the theft is perpetrated by means of moving meters or by means of creating an unauthorized, unmetered tap
The foregoing description of the invention has been presented for purposes of illustration and description and is not intended to be exhaustive or to limit the invention to the precise forms disclosed. Many modifications and variations are possible in light, the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical application to thereby enable others skilled in the art to best utilize the invention in various embodiments and with various modifications as are suited to the particular use contemplated. It is intended that the scope of the invention be defined by the claims appended hereto.
This application claims the benefit of U.S. provisional patent application No. 61/834,567, filed Jun. 13, 2013, the disclosure of which is incorporated herein by reference in its entirety.
Number | Name | Date | Kind |
---|---|---|---|
4200770 | Hellman et al. | Apr 1980 | A |
4371867 | Gander | Feb 1983 | A |
4668934 | Shuey | May 1987 | A |
4918422 | Mak | Apr 1990 | A |
5463624 | Hogg et al. | Oct 1995 | A |
5812557 | Stewart et al. | Sep 1998 | A |
6212560 | Fairchild | Apr 2001 | B1 |
6366062 | Beretich et al. | Apr 2002 | B2 |
6373399 | Johnson et al. | Apr 2002 | B1 |
6650249 | Meyer et al. | Nov 2003 | B2 |
6690655 | Miner et al. | Feb 2004 | B1 |
6788702 | Garcia-Luna-Aceves et al. | Sep 2004 | B1 |
6961641 | Forth et al. | Nov 2005 | B1 |
7069117 | Wilson et al. | Jun 2006 | B2 |
7076378 | Huebner | Jul 2006 | B1 |
7188003 | Ransom et al. | Mar 2007 | B2 |
7194528 | Davidow | Mar 2007 | B1 |
7236765 | Bonicatto et al. | Jun 2007 | B2 |
7280931 | Kim et al. | Oct 2007 | B1 |
7369579 | Logvinov et al. | May 2008 | B2 |
7571028 | Lapinsky et al. | Aug 2009 | B2 |
7598844 | Corcoran et al. | Oct 2009 | B2 |
7701330 | Iwamura | Apr 2010 | B2 |
7808128 | Weber, Jr. et al. | Oct 2010 | B1 |
7870600 | Huotori et al. | Jan 2011 | B2 |
7873077 | Downey et al. | Jan 2011 | B2 |
7948255 | Shim et al. | May 2011 | B2 |
8013570 | Baxter et al. | Sep 2011 | B2 |
8207726 | Vaswani | Jun 2012 | B2 |
8639922 | Phatak | Jan 2014 | B2 |
8639992 | Haufe et al. | Jan 2014 | B2 |
8711995 | Glende | Apr 2014 | B2 |
8737555 | Haug et al. | May 2014 | B2 |
8818742 | Ansari | Aug 2014 | B2 |
8872667 | Bhageria et al. | Oct 2014 | B2 |
9287933 | Yu | Mar 2016 | B2 |
9647994 | Bernheim et al. | May 2017 | B2 |
9654287 | Zhao et al. | May 2017 | B2 |
20010018561 | Tanida | Aug 2001 | A1 |
20010037378 | Hirayama | Nov 2001 | A1 |
20020069299 | Rosener | Jun 2002 | A1 |
20020089927 | Fischer et al. | Jul 2002 | A1 |
20030098671 | Hochgraf | May 2003 | A1 |
20040062267 | Minami et al. | Apr 2004 | A1 |
20040110044 | McArthur et al. | Jun 2004 | A1 |
20040218688 | Santhoff et al. | Nov 2004 | A1 |
20040226621 | Phillips et al. | Nov 2004 | A1 |
20040227621 | Cope et al. | Nov 2004 | A1 |
20050005150 | Ballard | Jan 2005 | A1 |
20050017848 | Flen et al. | Jan 2005 | A1 |
20050043860 | Petite | Feb 2005 | A1 |
20050063422 | Lazar et al. | Mar 2005 | A1 |
20050144437 | Ransom et al. | Jun 2005 | A1 |
20050207079 | Tiller et al. | Sep 2005 | A1 |
20060071757 | Burghard et al. | Apr 2006 | A1 |
20060091877 | Robinson et al. | May 2006 | A1 |
20060152344 | Mowery et al. | Jul 2006 | A1 |
20060291575 | Berkman et al. | Dec 2006 | A1 |
20070076650 | Manjeshwar et al. | Apr 2007 | A1 |
20070100506 | Teichmann | May 2007 | A1 |
20070101438 | Govindarajan | May 2007 | A1 |
20070114987 | Kagan | May 2007 | A1 |
20070162550 | Rosenberg | Jul 2007 | A1 |
20070208521 | Petite et al. | Sep 2007 | A1 |
20070211401 | Mak | Sep 2007 | A1 |
20070237181 | Cho et al. | Oct 2007 | A1 |
20070271383 | Kim et al. | Nov 2007 | A1 |
20070297425 | Chirco et al. | Dec 2007 | A1 |
20080040479 | Bridge et al. | Feb 2008 | A1 |
20080109387 | Deaver et al. | May 2008 | A1 |
20080209481 | Barrett | Aug 2008 | A1 |
20080273521 | Shao | Nov 2008 | A1 |
20080312851 | Kagan et al. | Dec 2008 | A1 |
20090027061 | Curt et al. | Jan 2009 | A1 |
20090088907 | Lewis et al. | Apr 2009 | A1 |
20090096416 | Tonegawa et al. | Apr 2009 | A1 |
20090125351 | Davis, Jr. et al. | May 2009 | A1 |
20090134699 | Choi et al. | May 2009 | A1 |
20090210197 | Cleary | Aug 2009 | A1 |
20090219932 | Kobayashi | Sep 2009 | A1 |
20090240504 | Pang et al. | Sep 2009 | A1 |
20090256686 | Abbot et al. | Oct 2009 | A1 |
20090304101 | LoPorto et al. | Dec 2009 | A1 |
20100005273 | Lee et al. | Jan 2010 | A1 |
20100007219 | de Buda et al. | Jan 2010 | A1 |
20100007336 | de Buda | Jan 2010 | A1 |
20100010857 | Fadell | Jan 2010 | A1 |
20100054349 | Spencer | Mar 2010 | A1 |
20100134089 | Uram | Jun 2010 | A1 |
20100141392 | Jo et al. | Jun 2010 | A1 |
20100188260 | Cornwall et al. | Jul 2010 | A1 |
20100217549 | Galvin et al. | Aug 2010 | A1 |
20100217550 | Crabtree et al. | Aug 2010 | A1 |
20100262313 | Chambers et al. | Oct 2010 | A1 |
20100262393 | Sharma et al. | Oct 2010 | A1 |
20100286840 | Powell et al. | Nov 2010 | A1 |
20100296560 | Sadan et al. | Nov 2010 | A1 |
20100306533 | Phatak | Dec 2010 | A1 |
20110035073 | Ozog | Feb 2011 | A1 |
20110040803 | Pasquero et al. | Feb 2011 | A1 |
20110043340 | Kim et al. | Feb 2011 | A1 |
20110103429 | Tanaka et al. | May 2011 | A1 |
20110109320 | Curt et al. | May 2011 | A1 |
20110121654 | Recker et al. | May 2011 | A1 |
20110122798 | Hughes et al. | May 2011 | A1 |
20110130991 | Koste et al. | Jun 2011 | A1 |
20110130992 | Kolwalkar et al. | Jun 2011 | A1 |
20110133655 | Recker et al. | Jun 2011 | A1 |
20110140911 | Pant et al. | Jun 2011 | A1 |
20110196546 | Muller et al. | Aug 2011 | A1 |
20110216747 | Shao et al. | Sep 2011 | A1 |
20110224935 | Hampel et al. | Sep 2011 | A1 |
20110267202 | Efthymiou | Nov 2011 | A1 |
20110282508 | Goutard et al. | Nov 2011 | A1 |
20110285382 | Kolwalkar et al. | Nov 2011 | A1 |
20120036250 | Vaswani | Feb 2012 | A1 |
20120041696 | Sanderford et al. | Feb 2012 | A1 |
20120052870 | Habicher | Mar 2012 | A1 |
20120062210 | Veillette | Mar 2012 | A1 |
20120062390 | Solomon | Mar 2012 | A1 |
20120068784 | Varadarajan et al. | Mar 2012 | A1 |
20120075099 | Brown | Mar 2012 | A1 |
20120137126 | Matsuoka et al. | May 2012 | A1 |
20120139554 | Parsons | Jun 2012 | A1 |
20120155557 | Bush et al. | Jun 2012 | A1 |
20120158329 | Hurri et al. | Jun 2012 | A1 |
20120185838 | Schwartzman et al. | Jul 2012 | A1 |
20120195355 | El-Essawy et al. | Aug 2012 | A1 |
20120201145 | Ree | Aug 2012 | A1 |
20120201155 | Du et al. | Aug 2012 | A1 |
20120232915 | Bromberger | Sep 2012 | A1 |
20120242499 | Ree et al. | Sep 2012 | A1 |
20120250864 | Nishibayashi et al. | Oct 2012 | A1 |
20120265355 | Bernheim et al. | Oct 2012 | A1 |
20120266209 | Gooding et al. | Oct 2012 | A1 |
20120275526 | Hughes et al. | Nov 2012 | A1 |
20120310424 | Taft et al. | Dec 2012 | A1 |
20120310558 | Taft et al. | Dec 2012 | A1 |
20120313620 | Swarztrauber et al. | Dec 2012 | A1 |
20120314782 | Boivin et al. | Dec 2012 | A1 |
20120314868 | Bernheim et al. | Dec 2012 | A1 |
20120316696 | Boardman et al. | Dec 2012 | A1 |
20120323388 | Littrell et al. | Dec 2012 | A1 |
20130013232 | Parwal et al. | Jan 2013 | A1 |
20130031201 | Kagan et al. | Jan 2013 | A1 |
20130034086 | Martin et al. | Feb 2013 | A1 |
20130067253 | Tsuda | Mar 2013 | A1 |
20130121157 | Logvinov et al. | May 2013 | A1 |
20130132555 | Wang et al. | May 2013 | A1 |
20130151177 | Hughes | Jun 2013 | A1 |
20130193767 | Carralero et al. | Aug 2013 | A1 |
20130194975 | Vedantham et al. | Aug 2013 | A1 |
20130204450 | Kagan et al. | Aug 2013 | A1 |
20130257452 | DeLeo et al. | Oct 2013 | A1 |
20140035372 | Normoyle et al. | Feb 2014 | A1 |
20140062719 | Rowitch et al. | Mar 2014 | A1 |
20140105313 | Kim et al. | Apr 2014 | A1 |
20140118163 | Li et al. | May 2014 | A1 |
20140125125 | Wyatt | May 2014 | A1 |
20140140358 | Kim et al. | May 2014 | A1 |
20140172723 | Borisov et al. | Jun 2014 | A1 |
20140191568 | Partovi | Jul 2014 | A1 |
20140233620 | Bernheim et al. | Aug 2014 | A1 |
20140233662 | Hansell et al. | Aug 2014 | A1 |
20140236365 | Martin et al. | Aug 2014 | A1 |
20140236366 | Livadaras et al. | Aug 2014 | A1 |
20140236506 | Nikovski | Aug 2014 | A1 |
20140300210 | Abi-Ackel | Oct 2014 | A1 |
20140359595 | Sehgal et al. | Dec 2014 | A1 |
20140361907 | Bernheim et al. | Dec 2014 | A1 |
20150010093 | Hansell et al. | Jan 2015 | A1 |
20150316620 | Luan | Nov 2015 | A1 |
20160112378 | Bemheim et al. | Apr 2016 | A1 |
20160124421 | Hansell et al. | May 2016 | A1 |
20160127242 | Bernheim et al. | May 2016 | A1 |
20160164287 | Bernheim | Jun 2016 | A1 |
20160204991 | Martin et al. | Jul 2016 | A1 |
20160285511 | Hansell et al. | Sep 2016 | A1 |
20160302238 | Martin et al. | Oct 2016 | A1 |
20170344047 | Cioraca et al. | Nov 2017 | A1 |
Number | Date | Country |
---|---|---|
101770007 | Jul 2010 | CN |
0395495 | Oct 1990 | EP |
0 629 098 | Dec 2001 | EP |
1 901 145 | Mar 2008 | EP |
2330430 | Jun 2011 | EP |
2 566 125 | Mar 2013 | EP |
H09501766 | Feb 1997 | JP |
2003-339120 | Nov 2003 | JP |
2003-259696 | Dec 2003 | JP |
2004015840 | Jan 2004 | JP |
2004147063 | May 2004 | JP |
2005252671 | Sep 2005 | JP |
2006262570 | Sep 2006 | JP |
2007-185083 | Jul 2007 | JP |
2008-508781 | Mar 2008 | JP |
2008-098812 | Apr 2008 | JP |
2008-124859 | May 2008 | JP |
2010156694 | Jul 2010 | JP |
2010161923 | Jul 2010 | JP |
2010533843 | Oct 2010 | JP |
2010268121 | Nov 2010 | JP |
2011525787 | Sep 2011 | JP |
2012227928 | Nov 2012 | JP |
2013-005718 | Jan 2013 | JP |
2013106255 | May 2013 | JP |
9501030 | Jan 1995 | WO |
9806187 | Feb 1998 | WO |
2009067250 | May 2009 | WO |
2010027421 | Mar 2010 | WO |
WO2010141859 | Dec 2010 | WO |
2013006273 | Jan 2013 | WO |
2013013162 | Jan 2013 | WO |
2014006662 | Jan 2014 | WO |
2014096911 | Jun 2014 | WO |
Entry |
---|
International Search Report for PCT/US2014/016538, dated Jun. 16, 2014, 3 pages. |
International Preliminary Report on Patentability for PCT/US2014/016538, dated Sep. 3, 2015, 10 pages. |
International Search Report for PCT/US2014/016540, dated Jun. 17, 2014, 3 pages. |
International Preliminary Report on Patentability for PCT/US2014/016540, dated Sep. 3, 2015, 9 pages. |
International Search Report for PCT/US2014/016535, dated Jun. 3, 2014, 2 pages. |
International Preliminary Report on Patentability for PCT/US2014/016535, dated Sep. 3, 2015, 8 pages. |
International Search Report and Written Opinion for PCT/US2014/041396, dated Oct. 29, 2014, 12 pages. |
International Search Report and Written Opinion for PCT/US2014/042393, dated Oct. 20, 2014, 15 pages. |
International Search Report for PCT/US2009/046644, dated Mar. 2, 2010, 7 pages. |
International Preliminary Report on Patentability for PCT/US2009/046644, dated Dec. 6, 2010, 10 pages. |
International Search Report for PCT/US2012/033789, dated Sep. 6, 2012, 4 pages. |
International Search Report for PCT/US2012/041971, dated Dec. 7, 2012, 5 pages. |
International Search Report for PCT/US2012/049524, dated Jan. 3, 2013, 3 pages. |
Non-Final Office Action for U.S. Appl. No. 13/566,481, dated Aug. 7, 2015, 27 pages. |
Non-Final Office Action for U.S. Appl. No. 13/493,983, dated Feb. 5, 2014, 11 pages. |
Final Office Action for U.S. Appl. No. 13/493,983, dated Oct. 31, 2014, 12 pages. |
Non-Final Office Action for U.S. Appl. No. 13/448,005, dated Sep. 11, 2014, 20 pages. |
Non-Final Office Action for U.S. Appl. No. 13/448,005, dated Apr. 15, 2015, 22 pages. |
Non-Final Office Action for U.S. Appl. No. 12/480,493, dated Jul. 16, 2012, 24 pages. |
Notice of Allowance and Examiner-Initiated Interview Summary for U.S. Appl. No. 12/480,493, dated Jun. 20, 2013, 13 pages. |
Non-Final Office Action for U.S. Appl. No. 13/896,029, dated Sep. 18, 2015, 16 pages. |
Non-Final Office Action for U.S. Appl. No. 13/871,944, dated Oct. 16, 2015, 13 pages. |
Non-Final Office Action for U.S. Patent Application No. 13/888,102, dated Jul. 9, 2015, 18 pages. |
Search Report for Japanese Patent Application No. 2011-512749, search date Aug. 14, 2013, 29 pages pages. |
Office Action for Japanese Patent Application No. 2011-512749, drafting date Sep. 4, 2013, 7 pages. |
Cuthbert Nyack, “Covolution and Autocorrelation,” http://cnyack.homestead.com/files/aconv/convau1.htm, Web. (Jun. 7, 2009). |
Dermot Collins et al., “Transmission on Power Line Cables,” Telektronikk 2/3, (1999). |
Chong Hock K. Goh, “A Current Study of Automatic meter Reading Solutions via Power Line Comunications,” http://wpweb2k.gsia.cmu.edu/ceic/publications.htm. ((Published 2003 or later as evidenced by the bibliography)). |
K.B. Ha, “Power Line Communication Technology,” Presentation at Hong Kong Institute of Engineers Seminar on Last Mile Technology, (Jun. 20, 2003). |
Olaf G. Hooijen, “A Channel Model for the Residential Power Circuit Used as a Digital Communications Medium,” IEEE Transactions on Electromagnetic Compatibility, 40(4): pp. 331-336, (Nov. 1998). |
Luis F. Montoya, “Power Line Communications Performance Overview of the Physical Layer of Available Protocols,” Thesis of Research, University of Florida, Gainesville, Florida, pp. 1-15 (publication date unknown). |
J.E. Newbury, “Efficient Communication Services Using the Low Voltage Distribution Line,” Proceedings of 2002 PES Winter Meeting, pp. 579-591, (2002). |
Niovi Pavlidou, et al., “Power Line Communications: State of the Art and Future Trends,” IEEE Communications Magazine, 41(4): pp. 34-40, (Apr. 2003). |
Gerald Schickhuber and Oliver McCarthy, “Control Using Power Lines—A European View,” Computing & Control Engineering Journal, 8(4): pp. 180-184, (Aug. 1997). |
Petrus A. Hanse Van Rensburg and Hendrik C. Ferreira, “Design of a Bidirectional Impedence-Adapting Transformer Coupling Circuit for Low-Voltage Power-Line Communications,” IEEE Transactions on Power Delivery, 20(1); pp. 64-70 (Jan. 2005). |
Universal Powerline Bus Communication Technology Overview, http://pulseworx.com/downloads/upb/UpbOverview.pdf (Jan. 8, 2002). |
X-10 (U.S.A.) Inc., X-10.RTM. Powerhouse (TM) Technical Note, “The X-10 Powerhouse Power Line Interface Model #PL513 and Two-Way Power Line Interface Model #TW523”, 12 pages, Revision 2.4, Dave Rye, (1991). |
Moreno-Munoz A., et al., “Integrating Power Quality to Automated Meter Reading”, IEEE Industrial Electronics Magazine, IEEE, US, vol. 2, No. 2, pp. 10-18 (Jun. 17, 2008). |
Moonsuk Choi, et al., “Design of Integrated Meter Reading System based on Power-Line Communication”, Power Line Communications and Its Applications, IEEE, International Symposium, pp. 280-284 (Apr. 2, 2008). |
Paola Bresesti, et al., “SDNO: Smart Distribution Network Operation Project”, Power Engineering Society General Meeting, IEEE, pp. 1-4 (Jun. 1, 2007). |
EnergyIdeas Clearinghouse PTR #6. Product and Technology Review. MicroPlanet® Voltage Regulators for residential and small commercial applications. http://www.energyideas.org/documents/factsheets/PTR/Microplanet.pdf pp. 1-5 (Jun. 4, 2008). |
Fierce Energy Daily. “Dominion Conservation Voltage Reduction software reduces energy use by 2.8%.” http://www.fierceenergy.com/story/dominion-conservation-voltage-reduction-soflware-reduces-energy-use-28/2011-09-27, pp. 1-3. (Sep. 17, 2011). |
RenewGRID. “CVR has Potential Beyond Pushing Efficiencies on Feeders.” Bates, Michael. http://www.renew-grid.com/e107 plugins/contenl/contenl.php?contenl.8215, pp. 1-2 (Mar. 25, 2012). |
Angelo Baggini “Handbook of Power Quality” (Jun. 2008). |
Sherman et al, “Location Authentication through Power Line Communication: Design, Protocol, and Analysis of a New Out of Band Strategy”, 2010, Cyber Defense Lab, Department of CSEE, University of Maryland, Baltimore County, IEEE, p. 279-284 (2010). |
International Search Report in Application No. PCT/US2014/042003, dated Oct. 20, 2014. |
M. Dilek “Integrated Design of Electrical Design Distribution Systems: Phase Balancing and Phase prediction Case Studies”, http://scholar.lib.vt.edu/theses/available/etd-11132001-222401/unrestricted/mdilekETD/pdf (2001). |
“TWACS low Frequency Power Line Communication Signals Problematic to Public Health”, pp. 1-20, http://www.eiwellspring.org/smartmeter/TWACS.htm (May 3, 2013). |
G3-PLC alliance, “The G3 PLC Alliance Unveils its Interoperability Process.” Paris, The G3 PLC Alliance, http://www.g3-plc.com/, p. 1 (Oct. 2012). |
Prime Alliance Official Web Site http://www.prime-alliance.org (). |
McGhee et al., —“Smart High Voltage Substation based on IEC 61850 Process Bus and IEEE 1588 Time Synchronization” 2010 First IEEE International Conference on Smart Grid Communications, published/presented on Oct. 4-6, 2010. (Oct. 4, 2010). |
Pallares-Lopez et al., “Embedding synchronism in SmartGrid with IEEE1588-based for Intelligent Electronics” 2010 First IEEE International Conference on Smart Grid Communications, published/presented Oct. 4-6, 2010 (Oct. 4, 2010). |
International Preliminary Report on Patentability for PCT/US2014/041396, dated Dec. 17, 2015, 8 pages. |
International Preliminary Report on Patentability for PCT/US2014/042300, dated Dec. 23, 2015, 9 pages. |
International Preliminary Report on Patentability for PCT/US2014/042393, dated Dec. 23, 2015, 11 pages. |
Office Action for Canadian Patent Application No. 2,727,034, dated Nov. 26, 2015, 4 pages. |
Decision of Final Rejection for Japanese Patent Application No. 2014-119504, dated Nov. 10, 2015, 5 pages. |
Translation of Decision to Grant for Japanese Patent Application No. 2014-119505, dated Dec. 15, 2015, 3 pages. |
Office Action for Cuban Patent Application No. 2015-0088, dated Oct. 30, 2015, 3 pages. |
Final Office Action for U.S. Appl. No. 13/888,102, dated Dec. 24, 2015, 18 pages. |
Non-Final Office Action for U.S. Appl. No. 13/911,849, dated Nov. 24, 2015, 15 pages. |
Sendin, Alberto, et al., “Enhanced Operation of Electricity Distribution Grids Through Smart Metering PLC Network Monitoring, Analysis and Grid Conditioning,” Energies, vol. 6, Issue 1, Jan. 21, 2013, www.mdpi.com/journal/energies, pp. 539-556. |
Wetula, Andrzej, “A Hilbert Transform Based Algorithm for Detection of a Complex Envelope of a Power Grid Signals—an Implementation,” Journal of Electrical Power Quality and Utilisation, vol. 14, Issue 2, 2008, EPQU Journal, pp. 13-18. |
Partial Supplementary European Search Report for European Patent Application No. 14754343.3, dated Feb. 8, 2016, 5 pages. |
International Search Report and Written Opinion for International Patent Application No. PCT/US2015/058423, dated Jan. 19, 2016, 12 pages. |
International Search Report and Written Opinion for International Patent Application No. PCT/US2015/058492, dated Feb. 26, 2016, 18 pages. |
International Search Report and Written Opinion for International Patent Application No. PCT/US2015/063752, dated Mar. 24, 2016, 16 pages. |
Notice of Allowance and Examiner Initiated Interview Summary for U.S. Appl. No. 13/911,849, dated Apr. 5, 2016, 10 pages. |
Non-Final Office Action for U.S. Appl. No. 14/720,780, dated Feb. 26, 2016, 7 pages. |
Notice of Allowance for U.S. Appl. No. 13/566,481, dated Feb. 26, 2016, 7 pages. |
Colson, C.M., “Algorithms for Distributed Decision-Making for Multi-agent Microgrid Power Management,” IEEE Power and Energy Society General Meeting, Jul. 24-29, 2011, San Diego, California, IEEE, pp. 1-8. |
Final Office Action for U.S. Appl. No. 13/896,029, dated Jun. 22, 2016, 22 pages. |
Final Office Action for U.S. Appl. No. 13/871,944, dated Jun. 21, 2016, 22 pages. |
Corrected Notice of Allowance for U.S. Appl. No. 13/911,849, dated May 31, 2016, 4 pages. |
Final Office Action for U.S. Appl. No. 13/448,005, dated Jun. 6, 2016, 11 pages. |
Extended European Search Report for European Patent Application No. 14754343.3, dated May 24, 2016, 12 pages. |
Examination Report for European Patent Application No. 09759619.1, dated May 13, 2016, 7 pages. |
Partial Supplementary European Search Report for European Patent Application No. 14754339.1, dated Oct. 4, 2016, 6 pages. |
Partial Supplementary European Search Report for European Patent Application No. 14754714.5, dated Oct. 5, 2016, 6 pages. |
Non-Final Office Action for U.S. Appl. No. 13/896,029, dated Nov. 10, 2016, 18 pages. |
Notice of Allowance for U.S. Appl. No. 13/871,944, dated Oct. 4, 2016, 9 pages. |
Non-Final Office Action for U.S. Appl. No. 14/304,648, dated Sep. 7, 2016, 4 pages. |
Final Office Action for U.S. Appl. No. 14/720,780, dated Sep. 1, 2016, 9 pages. |
Notice of Allowance for U.S. Appl. No. 14/720,780, dated Nov. 4, 2016, 5 pages. |
Extended European Search Report for European Patent Application No. 14754339.1, dated Jan. 16, 2017, 10 pages. |
Office Action No. 13556 for Colombian Patent Application No. 15-222367, dated Nov. 28, 2016, 13 pages. |
Examination Report No. 1 for Australian Patent Application No. 2014219244, dated Dec. 21, 2016, 4 pages. |
Extended European Search Report for European Patent Application No. 14754714.5, dated Jan. 16, 2017, 10 pages. |
Extended European Search Report for European Patent Application No. 14808081.5, dated Jan. 30, 2017, 7 pages. |
Extended European Search Report for European Patent Application No. 14810273.4, dated Feb. 1, 2017, 12 pages. |
Extended European Search Report for European Patent Application No. 14811042.2, dated Jan. 2, 2017, 7 pages. |
Examination Report No. 1 for Australian Patent Application No. 2014219246, dated Dec. 22, 2016, 3 pages. |
Yan, Ping et al., “Study of Linear Models in Steady State Load Flow Analysis of Power Systems,” IEEE Power Engineering Society Winter Meeting, vol. 1, Jan. 27-31, 2002, New York, NY, IEEE, pp. 666-671. |
First Office Action for Chilean Patent Application No. 2325-2015, dated Jan. 26, 2017, 13 pages. |
First Office Action for Chilean Patent Application No. 2323-2015, dated Jan. 26, 2017, 15 pages. |
Office Action No. 11851, Colombian Patent Application No. 15-222367, dated Mar. 17, 2017, 19 pages. |
First Office Action for Chilean Patent Application No. 2322-2015, dated Jan. 26, 2017, 15 pages. |
Translated Summary of Office Action No. 4963 for Columbian Patent Application No. 15-222371, dated Apr. 5, 2017, 3 pages. |
First Office Action for Chinese Patent Application No. 201480032631.X, dated Feb. 27, 2017, 5 pages. |
First Office Action for Chinese Patent Application No. 201480034010.5, dated Feb. 17, 2017, 7 pages. |
International Preliminary Report on Patentability for International Patent Application No. PCT/US2015/058423, dated May 11, 2017, 8 pages. |
International Preliminary Report on Patentability for International Patent Application No. PCT/US2015/058492, dated May 11, 2017, 10 pages. |
Non-Final Office Action for U.S. Appl. No. 15/177,930, dated Mar. 3, 2017, 6 pages. |
Final Office Action for U.S. Appl. No. 14/304,648, dated Mar. 9, 2017, 7 pages. |
Final Office Action for U.S. Appl. No. 14/304,648, dated May 19, 2017, 7 pages. |
Advisory Action for U.S. Appl. No. 14/304,648, dated May 24, 2017, 3 pages. |
Non-Final Office Action for U.S. Appl. No. 14/928,783, dated May 8, 2017, 16 pages. |
Non-Final Office Action for U.S. Appl. No. 15/184,642, dated Mar. 9, 2017, 5 pages. |
Examination Report No. 1 for Australian Patent Application No. 2014219247, dated Apr. 26, 2017, 4 pages. |
Second Office Action for Chilean Patent Application No. 2323-2015, dated May 17, 2017, 14 pages. |
Second Office Action for Chilean Patent Application No. 2322-2015, dated May 17, 2017, 13 pages. |
First Office Action for Chinese Patent Application No. 201480009549.5, dated May 31, 2017, 9 pages. |
Examination Report No. 1 for Australian Patent Application No. 2014277951, dated Jun. 8, 2017, 4 pages. |
Office Action Summary for Columbian Patent Application No. 7058, dated Jun. 16, 2017, 2 pages. |
International Preliminary Report on Patentability for International Patent Application No. PCT/US2015/063752, dated Jun. 15, 2017, 12 pages. |
First Office Action for Chinese Patent Application No. 201480009551.2, dated Jun. 19, 2017, 9 pages. |
Extended European Search Report for European Patent Application No. 17173049.2, dated Aug. 11, 2017, 8 pages. |
Examination report No. 1 for Australian Patent Application No. 2014277983, dated Jun. 16, 2017, 4 pages. |
Non-Final Office Action for U.S. Appl. No. 13/871,944, dated Jun. 15, 2017, 14 pages. |
Non-Final Office Action for U.S. Appl. No. 13/896,029, dated Jul. 20, 2017, 17 pages. |
Advisory Action for U.S. Appl. No. 14/304,648, dated Aug. 17, 2017, 3 pages. |
Notice of Allowance for U.S. Appl. No. 15/184,642, dated Jul. 13, 2017, 8 pages. |
Notice of Allowance for U.S. Appl. No. 15/184,642, dated Jul. 27, 2017, 4 pages. |
Notice of Allowance for U.S. Appl. No. 14/929,087, dated Aug. 15, 2017, 9 pages. |
Non-Final Office Action for U.S. Appl. No. 15/177,930, dated Nov. 1, 2017, 14 pages. |
Notice of Allowance for U.S. Appl. No. 14/928,783, dated Nov. 6, 2017, 9 pages. |
Office Action for Colombian Patent Application No. 15222371, dated Oct. 15, 2017, 9 pages. |
First Office Action for Chinese Patent Application No. 201480034011.X, dated Oct. 30, 2017, 16 pages. |
Notice of Acceptance for Australian Patent Application No. 2014219246, dated Dec. 5, 2017, 3 pages. |
Office Action for Mexican Patent Application No. MX/a/2015/017231, dated Oct. 20, 2017, 13 pages. |
Second Office Action for Chinese Patent Application No. 201480032631.X, dated Sep. 4, 2017, 5 pages. |
Second Office Action for Chinese Patent Application No. 201480034010.5, dated Aug. 2, 2017, 5 pages. |
Final Office Action for U.S. Appl. No. 13/896,029, dated Jan. 24, 2018, 22 pages. |
Notice of Allowance for U.S. Appl. No. 13/871,944, dated Feb. 23, 2018, 18 pages. |
Corrected Notice of Allowance for U.S. Appl. No. 14/928,783, dated Jan. 23, 2018, 6 pages. |
Corrected Notice of Allowance for U.S. Appl. No. 14/928,783, dated Feb. 15, 2018, 6 pages. |
Notice of Allowance for U.S. Appl. No. 15/852,496, dated Mar. 8, 2018, 9 pages. |
Non-Final Office Action for U.S. Appl. No. 14/958,385, dated Jan. 12, 2018, 33 pages. |
International Telecommunications Union, “ITU-T G.9960, Series G: Transmission Systems and Media, Digital Systems and Networks,” Dec. 1, 2011, 160 pages. |
International Telecommunications Union, “Updated draft text for ITU-T G.9961, Series G: Transmission Systems and Media, Digital Systems and Networks—Amendment 1 Corrigendum 1,” ITU-T: Telecommunication Standardization Sector, Study Group 15, Amendment approved Sep. 21, 2012, 82 pages. |
International Telecommunications Union, “ITU-T G.9961, Series G: Transmission Systems and Media, Digital Systems and Networks,” Apr. 1, 2014, 306 pages. |
First Office Action for Chinese Patent Application No. 201480009550.8, dated Jan. 26, 2018, 4 pages. |
Decision to Grant a Patent for Japanese Patent Application No. 2015-558888, dated Jan. 30, 2018, 4 pages. |
Notice of Reasons for Rejection for Japanese Patent Application No. 2015-558889, dated Jan. 23, 2018, 7 pages. |
Extended European Search Report for European Patent Application No. 17203296.3, dated Feb. 15, 2018, 8 pages. |
Second Office Action for Chinese Patent Application No. 201480009549.5, dated Jan. 23, 2018, 4 pages. |
Notice of Reasons for Rejection for Japanese Patent Application No. 2015-558887, dated Jan. 23, 2018, 7 pages. |
Notice of Reasons for Rejection for Japanese Patent Application No. 2016-518052, dated Feb. 20, 2018, 8 pages. |
Third Office Action for Chinese Patent Application No. 201480034010.5, dated Jan. 17, 2018, 4 pages. |
Notice of Reasons for Rejection for Japanese Patent Application No. 2016-519694, dated Feb. 27, 2018, 11 pages. |
First Examination Report for Indian Patent Application No. 13/CHENP/2011, dated Jan. 11, 2018, 6 pages. |
Office Action for Canadian Patent Application No. 2,870,452, dated Dec. 28, 2017, 4 pages. |
Office Action for Canadian Patent Application No. 2,874,132, dated Jan. 25, 2018, 3 pages. |
Extended European Search Report for European Patent Application No. 15853935.3, dated Feb. 15, 2018, 10 pages. |
Extended European Search Report for European Patent Application No. 15855864.3, dated Feb. 21, 2018, 9 pages. |
Extended European Search Report for European Patent Application No. 18152637.7, dated Apr. 26, 2018, 8 pages. |
Notice of Acceptance for Australian Patent Application No. 2014219247, dated Apr. 11, 2018, 3 pages. |
Second Examination Report for Australian Patent Application No. 2014277983, dated Mar. 15, 2018, 4 pages. |
Second Official Action for Mexican Patent Application No. MX/a/2015/017231, dated Feb. 28, 2018, 5 pages. |
Notice of Acceptance for Australian Patent Application No. 2014277951, dated Mar. 28, 2018, 3 pages. |
Extended European Search Report for European Patent Application No. 15865305.5, dated May 3, 2018, 8 pages. |
Non-Final Office Action for U.S. Appl. No. 15/257,191, dated Apr. 4, 2018, 10 pages. |
Non-Final Office Action for U.S. Appl. No. 15/450,153, dated Apr. 19, 2018, 10 pages. |
Interview Summary for U.S. Appl. No. 14/958,385, dated Apr. 6, 2018, 3 pages. |
Number | Date | Country | |
---|---|---|---|
20140368189 A1 | Dec 2014 | US |
Number | Date | Country | |
---|---|---|---|
61834567 | Jun 2013 | US |