The invention relates to a system for laying underground cables or underground lines in the ground near the surface, the cables or lines being laid in a borehole along a laying route between a starting point and a target point, having a drilling apparatus with an advancement head for creating the borehole, and with drill piping and/or a casing, and to a method for laying underground cables or underground lines in the ground near the surface, the cables or lines being laid in a borehole along a laying route between a starting point and a target point, in the case of which an advancement head is moved along the laying route by a drilling apparatus transmitting a feed motion or a feed motion and a rotation via drill piping.
For constructing a power-supply system, for example for creating a 380 kV line, it is necessary not just to create power lines, but also to lay these lines in the ground.
In the case of underground cables being laid near the surface, use is made of open-trench excavation. This gives rise, in some cases, to considerable environmental interference along the route and is associated with not insignificant outlay for the excavation of trenches and the refilling of the same. In order to create a 380-kV-cable route, it is necessary to create, for example, two trench profiles each with a width of 5.5 m and a depth of 2.15 m. The operation of separating the individual layers of soil has proven to involve particular outlay, as it renders a number of separate heaps necessary. This is needed so that, when the trench is subsequently refilled, the soil quality is restored to the original state. Furthermore, during construction work, a surface area of approximately 40 m has to be kept clear for construction purposes, whereas, following completion of the construction work, a cable-protection strip of approximately 23 m has to be kept accessible. These very high-outlay interventions during construction, and resulting effects following completion of the work involved with open-trench laying, make it necessary to develop an appropriate underground laying method.
In order also to keep the interference with nature during construction and the construction costs to a low level it is necessary to achieve long lengths between supports for trenchless laying. Lengths of up to 1500 m are the target here. A problem with laying near the surface is that the line has a small overburden (for example merely 2 to 6 m). The diameter of the lines to be laid here is less than 800 mm, in some cases even less than 300 mm.
There are already trenchless drilling methods available from pipeline construction (microtunneling and HDD drilling). However, it is not possible for these methods to cover the necessary parameters.
There are therefore drilling methods in existence which make it possible to lay the desired diameter range, but these methods, for technical reasons, are limited to significantly shorter route lengths. These methods include, for example, microtunnel drilling up to 300 mm. For a length of up to more than 1.5 km, it would also currently be necessary to make use of microtunnel drilling with a diameter of approximately 1000 mm. However, the amount of space required by the construction-site equipment and also the costs increase significantly as the diameter increases. It is therefore not possible to use microtunnel drilling.
The Horizontal Directional Drilling (HDD) method would be a conceivable laying method to use in order to meet the requirements relating to diameter and route length. This method is already used specifically for passing beneath rivers or roads. In this method, first of all a pilot hole is created from the starting point in the direction of the target point using a rotating drilling head and drill piping. The positional accuracy is ensured here by a measuring system fitted behind the drilling head. The material removed is brought to the surface by a bentonite suspension. The bentonite suspension is pumped through the drill piping directly to the nozzles fitted on the drilling head. The suspension mixes with the loosened soil and flows back to the starting point through the annular space between the drill piping and soil. For good delivery of loosened soil, however, high mud pressures are necessary. However, in order to prevent mud from exiting in an undesirable manner at the surface, as large as possible laying depths and therefore overburdens for example of more than 30 m are necessary here in the case of the HDD method. With certain types of soil laying depths of less than 10 m can result in mud exiting in an undesirable manner in the case of the conventional HDD method.
It is an object of the invention to provide a system and a method which are intended for laying underground cables or underground lines in the ground near the surface and by means of which the above described disadvantages can be overcome and it is possible for underground cables or underground lines to be laid near the surface with lengths between supports of up to 1500 m.
As far as the system is concerned, the object according to the invention is achieved by a first solution according to the invention, in that the diameter of the advancement head is larger than the diameter of the casing or of the drill piping, and this results in an annular space between the borehole wall and casing or drill piping, in that the annular space is provided with a lubrication, and in that the advancement head is a drilling-head system made up of a drilling tool and drilling-tool drive for loosening the soil.
The essential advantage of the system is that, in comparison with the known laying methods, the amount of surface area required by the construction-site equipment is relatively small. Interference with the landscape is necessary only at certain points: at the starting point and target point. The limited capability of transporting the cable in one piece makes it necessary to construct a coupling or junction-box assembly at the starting point and target point, and this further reduces the amount of intervention or interference. Furthermore, there is no need for the environment to suffer from any structural interference along the route, and this makes it possible for underground cables to be laid in a particularly environmentally compatible manner. For example, the use of heavy machinery between the starting point and target point is dispensed with. There is no alteration to soil layers precisely in respect of agricultural use, and therefore, following completion of the work, planting and growth can continue unaltered. In contrast to overhead-line construction, underground laying does not result in the appearance of the landscape being adversely affected. At the same time, the small overburden means that lines requiring servicing are quick to reach.
As far as the system is concerned, the object according to the invention is achieved by a further solution according to the invention, in that the diameter of the advancement head is larger than the diameter of the casing or of the drill piping, and this results in an annular space between the borehole wall and casing or drill piping, in that the annular space is provided with a lubrication, and in that the advancement head is a displacement drilling head. The aforementioned advantages also apply here.
A further solution of the invention provides for the displacement drilling head to be a hammer drill or a soil-displacement screw. It is also advantageous for the displacement drilling head (15, 16, 41) to have a drilling-tool drive (22). Displacement-action introduction reliably avoids drilling mud being blown out at the surface and the associated harm to the environment.
A further solution of the invention provides for the drilling-tool drive to be an electric motor or a mud motor. This reliably and straightforwardly provides for a drilling head to be driven without rotation of the drill piping. Furthermore, the mud motor can be operated particularly straightforwardly and reliably when the drive fluid is provided in a closed system or in a quasi-closed system. A quasi-closed system is one in which a small quantity of fluid is discharged in a controlled manner in order to provide lubrication. As an alternative, it is also possible to have a drive with drill piping.
A further solution of the invention provides for the drilling apparatus to be a drilling apparatus of an HDD drilling system or to be a feed unit. The drilling apparatus here is a comparatively small one which is easy to manouver or move and therefore does not involve any significant load during movement between the individual drilling sites.
A further solution of the invention provides for a mud circuit which can drive and/or steering the the advancement head. A further solution of the invention provides for a steering element for horizontal or vertical steering. A further solution of the invention provides for a mud circuit, which can convey away from the borehole the soil loosened by the drilling-head system wherein preferably a jet pump is provided for transporting the soil away. A further solution of the invention provides for the drill piping to be of double-walled design and to be a constituent part of a drilling-fluid circuit, or the interior of the drill piping and the annular space between the casing and drill piping to be constituent parts of a drilling-fluid circuit.
A further solution of the invention provides for at least one discharging point for discharging drilling fluid in the form of lubrication. A further solution of the invention provides for the lubrication to be a stationary lubrication.
A further solution of the invention provides, in a second drilling run, for a reamer-drilling head to be capable of being connected to the drill piping and/or casing.
A further solution of the invention provides for the reamer-drilling head to be a hammer drill for displacing the soil, a soil-displacement screw, preferably with a drilling-tool drive for displacing the soil, or a drilling-head system made up of a drilling tool and drilling-tool drive for loosening the soil.
A further solution of the invention provides for a protective pipe to be capable of being introduced into the borehole, preferably during or before the operation of removing the drill piping and/or casing from the borehole, the underground cables or underground lines being introduced into said protective pipe.
A further solution of the invention provides for the protective pipe to be capable of being produced on site from a hose, made of flat material, preferably made of plastics material, or from pipe sections, preferably made of plastics material.
In respect of the method, the object according to the invention is achieved in that the soil is displaced or loosened and removed by the advancement head, and this results in an annular space between a borehole wall and the casing, the drill piping and/or a protective pipe and in that a lubrication is provided in the annular space.
A further solution of the invention provides for a drilling apparatus to transmit a feed motion to the drilling head via a casing.
A further solution of the invention provides, in the case of the soil being displaced, for the advancement head used to be a displacement drilling head, preferably a hammer drill or a soil-displacement screw, particularly preferably with a drilling-tool drive.
A further solution of the invention provides, in the case of the soil being loosened and removed, for the advancement head used to be a drilling-head system made up of a drilling tool and drilling-tool drive.
A further solution of the invention provides for a mud circuit for a mud medium, preferably bentonite, which drives and/or steers the advancement head and/or conveys away from the borehole the loosened soil, wherein the operations of feeding and discharging the mud medium in the mud circuit take place preferably via double-walled drill piping or via the interior of the drill piping and the annular space between the casing and drill piping.
The method according to the invention and the system according to the invention will be explained in more detail in the following text with reference to a preferred exemplary embodiment in conjunction with a drawing, in which:
At a starting point 100, an HDD drilling apparatus 10 is installed (
The advancement head 12 illustrated and used in
The advancement head 12 provided in
Once the advancement head 12 has penetrated the surface at the target point 110 it is removed. The drill piping 11 is then connected, at the target point, to a protective pipe 20, for example made of plastics material, and is drawn in via the drilling apparatus 10 as the drill piping 11 and/or the casing 14 are/is being drawn back. The connection in
As an alternative, it is also possible for the casing 14 to be pushed out of the borehole 102 by the protective pipe 20, for example made of polymer concrete or of a pressure-resistant plastics material, such as for example GRP, by the protective pipe 20 being introduced into the borehole 102. There is no need here for the casings 14 to be connected to one another in a tensile-resistant manner.
It is possible, as shown in
As an alternative, the starting point 100 and target point 110 may also be provided in the form of a starting trench and target trench (not illustrated).
The middle part of
The middle part of
The operation of laying the cables directly in the soil is shown in
If protective pipework 31 is introduced, the underground cables then being introduced into said pipework, the latter can be constructed in various ways.
As an alternative, the protective pipework 31 can be produced on site from flat material. Appropriate equipment (not illustrated) is necessary for this purpose.
A further variant for on-site production of the protective pipework from flat material is shown in
As an alternative to this,
Number | Date | Country | Kind |
---|---|---|---|
10 2015 108 576.3 | May 2015 | DE | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/EP2016/000877 | 5/27/2016 | WO | 00 |