1. Technical Field of the Invention
This invention pertains to the implementation of a procurement and accounts payable system or application. More particularly, it relates to a system and method for assessing, preparing, designing and developing, deploying, and supporting a general procurement and accounts payable system using electronic requisitions.
2. Background Art
A services company may be very good at implementing information technology (IT) solutions. However, as customer engagements increase, the ability of company to execute numerous engagements on time and within budget with quality becomes more difficult.
Today there exist many different software packages that perform project management and classes that teach methodologies for implementing solutions that involve information technology and services. However, there is no process that combines these activities along with an evaluation of a client's general procurement (GP) and accounts payable (AP) system, or application, into one package while providing detailed implementation instructions along with templates for completing the major deliverables required over the course of the project. Templates, may be used herein as an equivalent term for page, form, or document as used in connection with Lotus Notes. In Lotus Notes, a page is a database design element that displays information; a form, like a page, displays information and also can be used to collect information; and documents are the elements that store information in the database. A user is presented a form including fields for entering information. When the user fills out the information and saves it, the information is saved in the data base as a document. When a user opens the document, the document uses the form as a template to provide the structure for displaying the data or information. Fields store data of various types, including text, dialog list, rich text, and so forth.
Scalability of engagements is a known problem, the most common solution to which is to increase the number of persons involved. Experience has shown that this increase results in customer dissatisfaction due to inadequate gathering of requirements, poorly trained implementation teams, missed schedules, increased costs, and lower quality.
It is characteristic of general procurement and accounts payable systems that no two are identical, and may differ even within wholly owned subsidiaries of a single corporation.
Consequently, there is a need in the art for a system and method for evaluating a potential client system and for adapting a general procurement and accounts payable system to the requirements of each of many potential clients. Further, there is a need for a system and method for evaluating a potential client system and for adapting a general procurement and accounts payable system to the requirements of each of many potential clients which can be licensed to third party providers together with a system and method for monitoring and assuring the quality of services provided by those service providers.
There is a need in the art for an integrated system for assessing, preparing, designing and developing, deploying, and supporting a procurement and accounts payable system using electronic requisitions.
During project assessment, typically potential customers are contacted and evaluated by a marketing team that then recommends a product solution from their menu. There is no integration of Technical Team Leaders and Transition Management as key components of the installation. There is also limited to no flexibility to customize the product for the customer.
There is a large body of work on project planning in industry. While they are all more or less adequate, they do not provide the comprehensive integration of the client and supplier teams, Transition Management, and Quality required to accomplish a particular customer's goals.
Like project planning, project design and development processes are well known in industry. They usually consist of a project manager or team leader that manages the implementation of a project plan and interfaces with the client.
Deployment or implementation of a project is, again, a very standard operation. As the project plan steps are completed, they are usually held in queue until all necessary activities reach a point where the solution can be “turned on”.
All projects have close out functions that wrap up the end of the project. However, they do not provide for continuing support across the multitude of functions that have been used to provide the customer with a solution.
It is an objective of the invention to provide a system and method for evaluating a client's general procurement and accounts payable (GP/AP) system.
It is an object of the invention to provide an optimized solution for out-sourcing procurement of goods and services.
It is an object of the invention to provide a system and method for training service providers.
It is an object of the invention to provide a system and method for managing service providers to assure quality of service.
It is an object of the invention to provide a system and method for managing a project.
It is an object of the invention to provide an optimized general procurement and accounts payable system characterized by lower costs, a paperless process, and more comprehensive service with a shorter cycle time.
A system for providing ongoing support for a general procurement and accounts payable application includes a server; a storage device connected to the server; a plurality of team terminals; and a communication link interconnecting the server and terminals. The server is operable for (1) maintaining a database of templates on the storage device describing procedures for supporting the application and (2) serving the templates to team members operating the terminals for coordinating, recording, and tracking team activities executing the procedures with respect to supporting the application. These procedures include user education, survey and quality auditing tasks.
A method for providing ongoing support for a general procurement and accounts payable application of a customer of an enterprise includes maintaining a database of templates describing procedures for supporting an operational general procurement and accounts payable system; and operating a plurality of web-enabled user terminals to access via a server the database for coordinating tasks by a plurality of enterprise teams implementing the procedures. The procedures include user education, survey and quality auditing tasks.
In accordance with an aspect of the invention, there is provided a computer program product configured to be operable for providing ongoing support for a general procurement and accounts payable application of a customer of an enterprise.
Other features and advantages of this invention will become apparent from the following detailed description of the presently preferred embodiment of the invention, taken in conjunction with the accompanying drawings.
Referring to
Server 62 references and maintains playbook database 70. Database (also referred to as the playbook, or playbook database) 70 is provided for implementing procurement and accounts payable systems. This playbook 70 defines implementation steps and templates for creating the many required deliverables and project management functions. These functions include start and end dates, effort, duration, and so forth. This playbook also provides the steps and templates for training service providers 66 and serves as the repository for completed templates and as a source for auditing the performance of the service providers. As used herein, unless otherwise apparent from the context, system and applications are used to refer to hardware, software, procedures, instructional materials, and so forth, for implementing a general procurement and accounts payable process.
Also attached to intranet 60 are requisition and catalog (Req/Cat) servers 80. Server 80 functions as a front end server to accounting system server 82, and is connected to a file of vendor catalogs and contracts 72, to a client (customer) host system 74, and through a firewall to SAP servers 82. SAP server 82 is an accounting driver for the procurement and accounts payable (A/P) system of the customer. SAP servers 82 are connected to supplier systems 84, to a customer data warehouse 78, and to customer ledger and accounts payable systems 86, 88.
During the operational phase of a completed and functioning system, a customer (aka end user, or client) 98 enters requisitions via the intranet to server 80. Server 80 accesses client host system 74 for pricing, reports, etc., and vendor catalogs and contracts 72 to gather information needed by SAP servers 82 to generate purchase orders or requests for quotes (RFQs) to supplier 84, to update data warehouse 78, client ledger 86, and client accounts payable 88 systems. Warehouse 78 stores client data maintained by the supplier of the Req/Cat and general procurement system, which supplier may be the primary enterprise (a primary services organization, such as the IBM Corporation) with control of the design and implementation of the system, or a contractor of the enterprise qualified as a third party service provider.
In operation, during presales, assessment, preparation, development, deployment and support stages, team members 64, access database 70 via intranet 60 and server 62 to create a playbook including a detailed description of an accounts payable and Req/Cat system for a particular customer (aka client). This description is then used to personalize Req/Cat servers 80 and SAP servers 82 for the customer installation. During operation, a user 98 accesses Req/Cat server 80 via intranet 60 to enter a requisition or to query the status of previously entered requisition. When entering a requisition, Req/Cat responds to end user 98 with a form to complete. Req/Cat 80 accesses SAP server 82 through the firewall with the requisition or request for status. SAP server 82, responsive to a requisition, issues a purchase order or request for quote to supplier 84, and updates accounts payable 88 and ledger 86, as required through the normal procurement and accounting process implemented on behalf of the customer.
Referring to
Referring to
Further in accordance with the preferred embodiment of the invention, there is provided a web enabled delivery system.
Further in accordance with the preferred embodiment of the invention, there is provided a system and method for auditing service provider activities without being on site.
High level summary tasks implemented by playbook 70 database include business controls, information technology, SAP, communication, process, testing, configuration, project management, transition management, education and training, requisition and catalog (Req/Cat). Each of these summary tasks, as well as the drill-down (aka subsidiary) tasks implementing the details of each, may be accessed by team members 64 and service provider 66s within the playbook database 70.
Referring to
Referring to
Selection of create summary task 420 presents a first summary task template 440 that used to design and describe a high level summary task for one of the playbook operations. In a preferred embodiment of the invention, there are thirteen such high level summary tasks, including assessment, business controls, configuration, education, image, information technology (I/T), marketing, process, project management, requisition and catalog (req/cat), SAP, testing, and transition management. The summary and detail tasks within these high level summary tasks are further organized into five major processing segments: assessment 101, project preparation 102, project design and development 103, deployment 104, and ongoing support 105. A high level summary task provides a summary of the inputs to the task, and of the output (deliverables) after all detailed tasks are completed. There two levels, or templates for summary tasks: one for major operations, the second for major steps within each operation.
Activation of create a detail task 422 presents to the user a third template 520 which is used to summarize the detailed tasks for each major step of a summary task.
The first and second templates 440 are almost identical. They include the fields set forth in Tables 1 and 2. Third template 520 contents are summarized in Table 3.
Table 2 sets forth the template 440 fields which may vary between templates, including those for major operations and major steps within an operation.
Database 70 at server 62 includes all summary and detail tasks templates which have been completed in a set for a particular customer. An initial set of the tasks listed in Table 4 is provided for each customer, but during project implementation phases 101-105, these are configured or personalized to the customer.
While many summary and detailed tasks of Table 4 do not appear in the flow chart of
In each stage, the key to success is the integration through the use of the templates of the groups (
Table 4 is a chart of summary and detail tasks, pursuant to a particular embodiment of the invention, available for presentation in display area 426 of playbook summary view 400 upon selection of button 432. Selection by a user in display area 426 of a task designated with two or three alpha-numeric reference numerals P1, P11, P12, . . . , results in display of a template 440 personalized to the summary task, and selection of a task designated with four or more alpha-numeric reference numerals P111, P112, . . . , result in display of a template 520 personalized to the detail task. A user with appropriate authority may then view, correct, update, approve or otherwise modify the displayed task. The names of the detail tasks set forth broadly the functions or method steps performed in implementing the superior summary task. In Table 4, each summary task is identified in the first column by the stage 100-105 to which it pertains, in the second column by a task identifier P11, P12, . . . , and, for selected tasks, in the third column by the process step (150, . . . , 354 in
Referring to
After initial contact from marketing 118, the main thrust of Assessment Project 101 is to provide an integrated, cross-functional customer solution to the client. An assessment team is led by the Business Office 120, but requires input and participation from the project leaders of Architecture 122, Transformation Management 136, Business Process 112, EDI 114, and Application Development 116.
Assessment 101 begins with a complete review of the client's current general procurement and accounts payable processes. This includes debriefing the initial marketing team 118, instructing the project leaders 126, and accumulating all other relevant data available about the client's processes, tools, and organizational structures. The Assessment Team then defines an integrated customer solution that covers technical, educational, and Human Resource issues.
The delivery of the Workshop is intended to present an overview of the customer solution, initiate discussions on process analysis and strategic implementation, and confirmation of the solution fit. Specific goals of a workshop phase within assessment stage 101 include the following:
At the completion of the workshop phase, the assessment team 106 convenes to develop and cost the final customer solution and proposal. At this time, the members of assessment team 106 assemble, understand, and validate the collected data; review standard proposal options with assumptions and identify items that apply to this client; create a draft of the proposal including scope, risk, schedule, and resources; review the draft with team and other project members to obtain sizing and costing information for each area; compile costing information to add to the proposal; and perform QA review of the system integration, application development, managed operations (including service delivery center (SDC), application IT, and Process Operations) proposals, and of the overall proposal.
The resulting proposal is delivered or presented to the client. Final Assessment activities include follow up query responses and, should the proposal be declined, a loss analysis. This loss analysis feeds back into assessment process 101 to improve its overall effectiveness and efficiency.
Referring to Table 4, summary tasks pertaining to assessment stage 101 are listed, together with included detail tasks. For each task, a template 440 or 520 is maintained in data base 70, and accessed by team 108 members and others through summary view 400 to track progress (including viewing, updating, sharing, and approving) during this assessment stage 101.
Referring further to
A critical element of this stage is to ensure resources are assigned to transition management 136, both from the project implementation team 126 as well as from the client. During this stage the transition activities required for a smooth migration from the old client process and system to the new service offering are modeled. The result is a detailed transition management plan that is specifically designed for the client. Stage 102 tasks and deliverables include the following:
Integration of all critical Enterprise and client team members provides the glue to assure a smooth project. By completing the detailed tasks within project preparation stage 102, the recommended implementation standards, procedures and strategies for the project are shared with the technical and business functional members of the project team as well as with the customer. All team members have input in this process, and understand the basic procedures, once they have been agreed to. These procedures, documented in summary and detail task templates listed in Table 4, include the following:
Configuration Standards
CR/PTR Process
Testing Strategy
Production Support and Operations Strategy
SAP System Management Strategy
Req/Cat System Management Strategy
Network Computing Strategy
Vendor Conversion Strategy
Referring further to
During this stage 103, business controls 132 provides a comprehensive process that identifies key control points and establishes detailed procedures to assure a quality installation. The deliverables include documentation, separation of duties, sensitive programs, logical access control, logging (audit trail), change control for tables, change control for programs, system testing, input controls, processing controls, error handling controls, output controls, balancing and reconciliation, vital records and disaster recovery, records management, reports, local area network (LAN), and country specifics, as described below:
Req/Cat is a requisition and catalog product designed, developed, and maintained by Enterprise for use in systems such as those developed in this stage 103.
SAP is an financial and accounting package which an enterprise or company may license for its own use and for its customers. SAP configurators that customize package programs to fit the needs of the client are provided for use during design and development stage 103. All other installations of SAP are “off the shelf”, with the client changing its internal structures to fit SAP requirements.
Transition management is the most overlooked part of any implementation process. It is critical to address the corporate culture and personality at the earliest contact. Strategic and tactical plans may then be developed that guide the implementation through “Go Live” and for an agreed period thereafter. The purpose of transition management steps of the design and development stage 103 is to provide guidance to the development team members as they work with the client to institute policy changes that might be introduced as part of the implementation of the new process and system. Necessary changes to the legacy system are identified and a plan developed to announce and introduce changes in policy. Policy change includes key business rules that are part of the management system for purchasing and procurement. They may be associated with approval levels or procedural changes in the new system. The target is not the day to day operation but management decision and support systems that might be affected. The areas addressed include:
Measurements (old and new)
Management system
Approval levels
Supplier contacts and contracts
Reward systems
Incentive Plans
Security
Employee and user changes
All of these areas require strategic and tactical planning that includes the following steps:
Finally, integration of the above design and development stage 103 process steps along with the technical teams involved allow the delivery of a cross-functional solution under one unified and managed plan.
Referring again to
1. Quality (ASCA)
A business controls team provides dedicated resources throughout the life cycle of the project. During the project development stage 103, this team has planned and executed an ASCA self-assessment that has covered an extensive list of technical, business, financial, and client issues. In this deployment stage 104, its members are responsible for managing an independent audit that will cover the same areas. The independent auditors then issue an acceptance position that is required before the client can “Go Live” with the new system and process. Deployment stage 104 activities include:
During this deployment stage 104, project manager 126 has the task to validate and confirm that all checklists and status are acceptable prior to Go-live. This includes the readiness of all aspects of the project, and once satisfied, a review is conducted and the customer's formal sign-off for Go-live is obtained. Status transition management and client readiness assessment and confirmation activities include verification that:
A transition management team prepares for the deployment, or “Go Live” of the client solution. During this deployment stage 104 in the project, virtually all technical problems are resolved and systems configured. The client is now ready to deploy and the human factors must be aggressively managed to assure a smooth transition from the legacy systems to the improved client solution. Transition management activities within deployment stage 104 ensure that organization, measurements, management, support, and labor relations functions are developed, explained, reviewed, understood, in place or on schedule, as appropriate.
Integration of the cross-functional teams to accomplish the deployment of the customer solution is facilitated by use of the system and data base structure of the preferred embodiment of the invention.
Referring further to
During support stage 105, transition management 136 delivers an approved detailed questionnaire with quality questions in a logical format that allows end-users to express their opinion and provide information that meets the survey objective. Support stage 105 includes a plan for communicating the survey results to the participants and taking action in response to the survey results. This stage also incorporates a continuing education plan for training new employees as well as continually updating the material so that reflects the latest version of the application.
The survey in stage 105 is structured to determine the end users' perception of the new system, system ease of use, response time from both the system and CSC (Customer Service Center), and customer knowledge level of processes and product. Results of the survey are compiled and presented to the client and Enterprise Management Teams along with action plans, time tables, expected results for approval, and implementation. A Lessons Learned document is reviewed with the project team and appropriate adjustments made for future engagements.
Project Manager 126 provides a quality function task after “Go Live”. This task aims at checking the implementation of the EPS Offering to determine if anything needs special attention or focus. It is also the formal sign-off on the final delivery of the implementation by the customer. Its deliverables include:
The Req/Cat and SAP technical teams 128, 138 provide ongoing reviews and improvements to the client's process through the CR and PTR processes. These are formalized, documented processes with management controls to attain cost, schedule, and customer objectives.
As part of the new business process, support center 94 is established to provide long term assistance in any area of the application solution. This includes communication of feedback, real time application assistance, and special requests for problems concerning data.
It is the planned integration of these multi-functional teams that provides an innovative solution to the customer.
Referring to
While steps 230-244 represent a selection of key steps in stage 104, other summary and detail tasks designated in Table 4 as pertaining to stage 104 are typically included in the initial set of templates for this customer, and are also used as they are determined to be applicable. Some field entries are dynamic and changeable during the course of ongoing support stage 105. The templates are also editable for a particular project, and do not necessarily continue during use to conform to the original format.
In step 230, ongoing training, similar to that of step 214, is provided. Education material is supplied and maintained to the latest version of Req/Cat to the client. This is distributed using distance learning techniques.
In step 232, the data warehouse team accesses detail task template P633 in the course of developing additional reports. Task P633 is originally executed in stage 103, and is also applicable to on-going support stage 105. This task describes the steps necessary to complete in stage 103 the development required to support the Operational Reporting needs during on-going support stage 105. Template P633, Table 27, provides, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the data warehouse team.
In step 234, the Req/Cat team accesses detail task template P691, Table 28, in the course of providing ongoing Req/Cat support. After the Req/Cat system has Gone Live, the system is monitored any production problems that occurred solved. Template P691 provides, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the Req/Cat team through the task.
In step 236, the EDI team accesses detail task templates P694 (Table 29) and P697 (Table 30) in the course of supporting EDI transactions post go live. These tasks cover data management, help desk support procedures, report generation, and security. Templates P694 and P697 provide, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the EDI team through the steps of these tasks.
In step 238, service delivery center (SDC) ongoing support, help desk functions that are supplied to the client through time. This covers problem reporting, new requests for reports, education questions, and so forth.
In step 240, the transition management team accesses detail task template PD54, Table 31, in the course of insuring that the human resources aspects of the transition plan are in place and in progress. Specifically, this step deals with organizational impacts, changes in roles and responsibilities, labor relations, bonuses and incentives, meetings, feedback and comments. During this step, the auditors check to see the plan is being executed properly. Template PD54 provides, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the transition management team through the steps of this task during deployment and ongoing support stages 104 and 105.
In step 242, the transition management team accesses detail task template PD81 in the course of distributing and analyzing a survey questionnaire and preparing action plans for implementation by management. Template PD81 provides, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the transition management team through the steps of the task.
In step 244, the project office team accesses summary task P9C and its subsidiary tasks in the course of providing post implementation QA review. Template P9C provides, either directly or by way of links to other documents, instructions, flow charts, sample questionnaires, report models and checklists for guiding, coordinating and documenting the work of the project office team through the steps of the task.
It is an advantage of the invention that there is provided a system and method for evaluating a client's general procurement and accounts payable (GP/AP) system.
It is an advantage of the invention that there is provided an optimized solution for out-sourcing procurement of goods and services.
It is an advantage of the invention that there is provided a system and method for training service providers.
It is an advantage of the invention that there is provided a system and method for managing service providers to assure quality of service.
It is an advantage of the invention that there is provided a system and method for managing a project.
It is an advantage of the invention that there is provided an optimized general procurement and accounts payable system characterized by lower costs, a paperless process, and more comprehensive service with a shorter cycle time.
It will be appreciated that, although specific embodiments of the invention have been described herein for purposes of illustration, various modifications may be made without departing from the spirit and scope of the invention. In particular, it is within the scope of the invention to provide a computer program product or program element, or a program storage or memory device such as optical wire, tape or disc, or the like, for storing information readable by a machine, for controlling the operation of a computer according to the method of the invention and/or to structure its components in accordance with the system of the invention.
Further, each step of the method may be executed on any general computer, such as an IBM System 390, AS/400, PC or the like and pursuant to one or more, or a part of one or more, program elements, modules or objects generated from any programming language, such as C++, Java, Pl/1, Fortran or the like. And still further, each said step, or a file or object or the like implementing each said step, may be executed by special purpose hardware or a circuit module designed for that purpose.
Accordingly, the scope of protection of this invention is limited only by the following claims and their equivalents.
This application is a continuation of Ser. No. 11/496,698, filed 31 Jul. 2006, now U.S. Pat. No. 7,403,903 which is a divisional of U.S. patent application Ser. No. 10/727,443, filed 3 Dec. 2003, now U.S. Pat. No. 7,143,053 which is a divisional of U.S. patent application Ser. No. 09/444,256 filed 22 Nov. 1999, now U.S. Pat. No. 6,738,746 both by R. F. Barnard, et al. for System and Method for Ongoing Supporting a Procurement and Accounts Payable System. U.S. patent application Ser. No. 09/444,257, entitled “System and Method for Assessing a Procurement and Accounts Payable System”, Ser. No. 09/444,254, entitled “System and Method for Project Preparing a Procurement and Accounts Payable Process”, Ser. No. 09/444,255, entitled “System and Method for Project Designing and Developing a Procurement and Accounts Payable Process”, and Ser. No. 09/444,253, entitled “System and Method for Deploying a Procurement and Accounts Payable Process” filed concurrently herewith, are assigned to the same assignee hereof and contain subject matter related, in certain respect, to the subject matter of the present application. The above-identified patent applications are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
4862376 | Ferriter et al. | Aug 1989 | A |
4875162 | Ferriter et al. | Oct 1989 | A |
5189606 | Burns et al. | Feb 1993 | A |
5224034 | Katz et al. | Jun 1993 | A |
5233513 | Doyle | Aug 1993 | A |
5283745 | Tanaka | Feb 1994 | A |
5287267 | Jayaraman et al. | Feb 1994 | A |
5315509 | Natarajan | May 1994 | A |
5365425 | Torma et al. | Nov 1994 | A |
5381332 | Wood | Jan 1995 | A |
5450317 | Lu et al. | Sep 1995 | A |
5737727 | Lehmann et al. | Apr 1998 | A |
5745880 | Strothmann | Apr 1998 | A |
5793632 | Fad et al. | Aug 1998 | A |
5848394 | D'Arrigo et al. | Dec 1998 | A |
6381610 | Gundewar et al. | Apr 2002 | B1 |
7020621 | Feria et al. | Mar 2006 | B1 |
20020007298 | Jim et al. | Jan 2002 | A1 |
Number | Date | Country |
---|---|---|
0 895 171 | Feb 1999 | EP |
Number | Date | Country | |
---|---|---|---|
20080140499 A1 | Jun 2008 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 10727443 | Dec 2003 | US |
Child | 11496698 | US | |
Parent | 09444256 | Nov 1999 | US |
Child | 10727443 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 11496698 | Jul 2006 | US |
Child | 12012464 | US |