System and method for positioning a pile cap underneath an existing elevated bridge assembly

Information

  • Patent Grant
  • 6701564
  • Patent Number
    6,701,564
  • Date Filed
    Friday, May 24, 2002
    22 years ago
  • Date Issued
    Tuesday, March 9, 2004
    20 years ago
  • Inventors
  • Examiners
    • Will; Thomas B.
    • Pechhold; Alexandra K.
    Agents
    • Howrey Simon Arnold & White LLP
Abstract
A system and method for inserting pre-cast concrete pile caps under wooden railroad bridges without removing essential load bearing rails, cross-ties, and stringers is disclosed. The system and method minimizes the time that the track is closed to normal rail traffic. The system and method uses recycled oil well drill pipes that are cast into pile caps so that female-threaded ends are flushed with an upper surface of the pile caps. Lifting rods have male threaded ends that are used with a multi-point lifting device that allows the pile cap to be slipped under the existing bridge in a number of small incremental steps utilizing the spaces between wooden bridge stringers.
Description




FIELD OF THE INVENTION




This invention relates generally to railroad bridges and more particularly to a system and method for positioning a pile cap underneath an existing elevated bridge assembly to upgrade the bridge assembly to support a rail assembly.




BACKGROUND OF THE INVENTION




Many existing wooden railroad bridges were built 70 or 80 years ago and are now in the process of being repaired because of deterioration or upgraded to handle the freight loads and speeds of modern trains. Most of the existing wooden railroad bridges are supported by wooden piles topped by wooden pile caps. The repair and upgrade of the bridges includes installing new steel beam piles and topping the new piles with pre-cast, concrete pile caps. Ultimately, the old, wooden piles and caps are removed, and new pre-cast, concrete spans, which are supported by the new caps and piles, are used to support the rail assembly.




A typical concrete pile cap is 17 feet long by three feet wide by three feet deep, and weighs 30,000 pounds. Currently, concrete pile caps are cast with lifting loops at each end so that the pile cap may be lowered straight down from the rail assembly onto the steel piles. This, however, requires that at least portions of all the stingers be removed and that both rails be cut and removed from the rail assembly. Train traffic is interrupted since the rail assembly is separated, and traffic cannot resume until the pile cap is placed on the steel piles and the rail assembly is restored.




It is preferred that upgrading the exiting wooden bridges is done with a minimum interruption of the train traffic. Windows of opportunity for performing the construction are seldom longer than six hours and frequently are as short as forty-five minutes. Current systems and methods in the art do not allow for minimum interruption.




The present invention is directed to overcoming, or at least reducing the effects of, one or more of the problems set forth above.




SUMMARY OF THE INVENTION




A system and method for positioning a pile cap underneath an existing bridge assembly is disclosed. A portion of the rail assembly is removed to define an access area. At least three new piles are installed through the access area. The piles include a center pile and two opposing outer piles. Each pile has a proximal end and a distal end. The distal ends of each pile are driven into a support surface so that each pile generally extends from the support surface to the existing elevated rail assembly. The proximal ends of each pile are removed to define a gap between the piles and the existing elevated rail assembly. A new pile cap is then inserted into the gap. To insert the pile cap, a lifting device and a crane are used. The lifting device is used to incrementally insert the pile cap into the gap. The pile cap is supported on the piles and is used to support a new span for supporting the rail assembly.




The foregoing summary is not intended to summarize each potential embodiment, or every aspect of the invention disclosed herein.











BRIEF DESCRIPTION OF THE DRAWINGS




The foregoing summary, a preferred embodiment, and other aspects of the present invention will be best understood with reference to a detailed description of specific embodiments of the invention, which follows, when read in conjunction with the accompanying drawings, in which:





FIG. 1

illustrates a perspective view of an existing bridge assembly having wooden piles and wooden pile caps;





FIG. 2A

illustrates the bridge assembly being partially upgraded according to the present invention;





FIG. 2B

illustrates a side view of the partially upgraded bridge assembly of

FIG. 2A

;





FIG. 3

illustrates a perspective view of the existing bridge assembly of

FIG. 1

with a portion of the wooden ballast retainers and cross-ties removed according to the present invention;





FIG. 4

illustrates the bridge assembly with ballast boards removed according to the present invention;





FIG. 5

illustrates the bridge assembly with outboard non-load-bearing stringers removed according to the present invention.





FIG. 6

illustrates a new, center pile positioned through the assembly according to the present invention;





FIG. 7

illustrates the center pile, a first outer pile, and a second outer pile positioned through the assembly according to the present invention;





FIG. 8

illustrates a front view of proximal ends removed from the new piles to define a gap according to the present invention;





FIG. 9

illustrates a crane and a freight car positioned over the prepared portion of the assembly according to the present invention;





FIG. 10

illustrates a support bar being connected to a new pile cap according to the present invention;





FIG. 11

illustrates the crane lifting the pile cap out of the freight car according to the present invention;





FIG. 12

illustrates the crane lowering the pile cap adjacent the assembly according to the present invention;





FIG. 13

illustrates the crane rotating the pile cap to be perpendicular to the assembly according to the present invention;





FIGS. 14A-B

illustrate the crane utilizing a first pair of lifting rods to position the pile cap to rest on two, new piles according to the present invention;





FIGS. 15A-B

illustrate the crane positioning the pile cap further into the rail assembly utilizing a second pair of lifting rods with one of the lifting rods being located between the rails;





FIGS. 16A-B

illustrate the crane positioning the pile cap further into the rail assembly utilizing a third pair of lifting rods with one of the lifting rods being located between the rails;





FIG. 17

illustrates the crane positioning the pile cap further into the rail assembly utilizing a fourth pair of lifting rods with one of the lifting rods being located between the rails;





FIGS. 18A-B

illustrate the crane positioning the pile cap into a final position utilizing a fifth pair of lifting rods located outside of both rails;





FIG. 19

illustrates the crane placing the support bar into the freight car according to the present invention;





FIG. 20

illustrates an embodiment of a support bar in cross-section having lifting rods according to the present invention;





FIG. 21

illustrates an embodiment of a lifting rod according to the present invention;





FIG. 22A

illustrates a perspective view of an embodiment of a pile cap according to the present invention;





FIG. 22B

is a cross sectional view of

FIG. 22A

taken from line A—A; and





FIG. 23

illustrates a rope used to raise and lower a lifting rod according to the present invention.











While the invention is susceptible to various modifications and alternative forms, specific embodiments have been shown by way of example in the drawings and will be described in detail herein. However, it should be understood that the invention is not intended to be limited to the particular forms disclosed. Rather, the invention is to cover all modifications, equivalents, and alternatives falling within the scope of the invention as defined by the appended claims.




DETAILED DESCRIPTION OF THE INVENTION





FIG. 1

illustrates a portion of an existing bridge assembly


100


typically used to span a low elevational area, such as a valley, canyon, riverbed, or creek bed. The bridge assembly


100


includes an elevated rail assembly


102


supported by wooden pile caps


106


on wooden piles


104


. The wooden piles


104


extend into a support surface or ground surface


108


.




The rail assembly


102


includes first and second, parallel rails


114


and


16


used by railroad cars and engines. The rails


114


and


116


are supported on a plurality of cross-ties


118


along the length of the rails


114


and


116


. The cross-ties


118


are supported on crushed stone ballast (not shown) and a plurality of ballast boards


122


, which also extend along the length of rails


114


and


116


. The ballast boards


122


are fastened together by a plurality of side ballast retainers


120


located at each end of the ballast boards


122


.




The ballast boards


122


are supported on a plurality of outboard non-load-bearing stringers


124


and a plurality of load-bearing stringers


126




a


-


126




e


. The non-load-bearing stingers


124


are located underneath and at the ends of the ballast boards


122


. The plurality of load-bearing stringers


126




a


-


126




e


is supported on the wooden pile caps


106


. The stingers on bridge assemblies can have a number of configurations. In one configuration, for example, the load-bearing stringers


126




a


-


126




e


extend between adjacent, wooden caps


106


and are spaced approximately 18 inches apart in relation to each other with


126




a


being an inboard stringer and


126




e


being an outboard stringer.




Referring to

FIGS. 2A-B

, the existing, wooden bridge assembly


100


is illustrated partially upgraded according to the present invention.

FIG. 2A

illustrates a perspective view of the bridge assembly


100


showing only selected components, and

FIG. 2B

illustrates a side view of the bridge assembly


100


of FIG.


2


A. Upgrading the existing, wooden bridge assembly


100


to handle the freight loads and speeds of modern trains involves replacing the existing wooden piles


104


with new piles


110


, which are preferably made of steel, and replacing the existing wooden pile caps


106


with new pile caps


112


, preferably made of pre-cast concrete. In addition, upgrading the wooden bridge assembly


100


involves replacing the exiting stingers


124


and


126


and ballast boards


122


with new spans


50


, which are preferably pre-cast and made of concrete.




It is to be understood that

FIGS. 2A-B

do not necessarily represent how the bridge assembly


100


would appear during the process of upgrading the assembly according to the present invention. Rather, the partially upgraded bridge assembly


100


is presented to contrast the existing wooden structures (piles


104


, caps


106


, ballast boards, stingers


126


, etc.) with the new structures (piles


110


, caps


112


, and spans


50


) that are used to replace them.




Two sections


101




a


and


101




b


of the assembly


100


are shown for illustrative purposes. The first section


101




a


shows the exiting assembly


100


in an incomplete form. In the first section


101




a


, the rails


114


and


116


are shown supported on existing cross-ties


118


, as best described above. For clarity, neither the crushed ballast nor the plurality of ballast boards is shown. For illustrative purposes, a part of the first section


101




a


is shown without the cross-ties, crushed ballast, and ballast boards so that the plurality of stringers


126


can be seen supported on the existing wooden caps


106


and piles


104


.




In accordance with upgrading the bridge assembly


100


, a new, concrete pile cap


112




a


is shown positioned underneath the stingers


126


between existing wooden pile caps


106




b


and


106




c


. This new, concrete pile cap


112




a


is supported on a plurality of new piles


110




a


. Preferably, the new piles


110




a


are steel H beams having a width of approximately 14 inches. The new piles


110




a


extend from the support surface


108


to the pile cap


112




a


. In the process of upgrading the bridge assembly


100


described in detail below, distal ends of the piles


110




a


are stabilized with the support surface or driven into the ground


108


. Opposite, proximal ends of the piles


110




a


are eventually cut off to make room for the new pile cap


112




a


to be positioned below the exiting stingers


126


.




To elucidate the system and method described in more detail below, the second section


101




b


of the assembly illustrates the desired result of the present invention. For illustrative purposes, the second section


101




b


is shown in an incomplete form. New piles and caps, such as piles


110




b-c


and caps


112




b-c


, are installed between every other wooden cap


106


and piles


104


. In contrast to the conventional wooden piles


104


and caps


106


that are positioned every 15-feet along the assembly


100


, the new piles


110




b-c


and caps


110




b-c


are positioned approximately every 30-feet along the assembly


100


. After installing the new piles


110




b-c


and caps


112




b-c


under the existing stingers, the old, wooden components are removed. In particular, the old caps are removed, and the old, piles are removed or truncated, such as piles


105


. Ultimately, the newly installed caps


112




b-c


and piles


110




b-c


support pre-cast, concrete spans


50




a


and


50




b


. The concrete spans


50




a-b


hold the ballast (not shown), cross-ties


118


, and rails


114


and


116


of the rail assembly


102


and replace the old stingers and ballast boards.




The new pile caps


112


are approximately 34-inches in height, while the old wooden pile caps


106


are about 14-inches. As best shown in the side view of

FIG. 2B

, the top surface of the new pile caps


112


are set about three or four feet lower than the old wooden pile caps


106


. This allows for the approximately three feet depth of the pre-cast, concrete bridge spans


50


that will eventually be positioned on the new pile caps


112


, such as the span


50




b


supported on caps


112




b


and


112




c


and piles


110




b


and


110




c


in the second section


101




b


. In addition, the position of the concrete piles


112


can include about another foot in depth to accommodate for ballast (not shown). The 30-inch deep span


50




b


replaces the 17-inch wood stingers


126


and the 3-inch wooden ballast boards (not shown).




With the benefit of the overview of the system and method according to the present invention described above, particular steps for positioning new piles and caps underneath an existing elevated bridge assembly to upgrade the assembly will now be discussed in more detail with reference to

FIGS. 3-24

. Referring to

FIGS. 3 through 5

, initial steps for creating an access area


128


in the assembly


100


according to the present invention are discussed and illustrated. Creation of the access area


128


allows new piles (not shown) to be installed through the rail assembly


102


and allows new pile caps (not shown) to be positioned on top of the new piles. In

FIGS. 3-5

and in

FIGS. 6-19

described below, the exiting wooden piles used to support the wooden caps


106


are not shown for simplicity.





FIG. 3

illustrates a first step in creating the access area. A plurality of cross-ties


118


is removed from underneath the rails


114


and


116


. Side ballast retainers


120


adjacent the removed cross-ties are also removed from the both sides of the rail assembly


102


. Although not shown, a three-foot section of crushed stone ballast is removed from the rail assembly


102


as well.




As illustrated in

FIG. 4

, ballast boards


122


are removed from underneath the rails


114


and


116


where the cross-ties


118


were previously removed. At this point, the stringers


126




a


-


126




e


are exposed to view from the top of the rail assembly


102


. As illustrated in

FIG. 5

, outboard, non-load-bearing stringers


124


are removed on both sides of the rail assembly


102


. At this point, only the stringers


126




a


-


126




e


span across the access area


128


. A center stringer may also be removed if necessary.




As illustrated in

FIG. 6

, a center pile


130


is positioned between the rails


114


and


116


, between a central pair of stringers


126


, and through the access area


128


. Alternatively, depending on the spacing of the stringers


126


, a portion of one of the stringer may be cut away to make room for the center pile


130


. A distal end


130




d


of the pile


130


is then stabilized to a support surface


108


. For example, the distal end


130




d


is driven into the ground


108


“to refusal” so that the center pile


130


extends generally from the ground


108


to the existing elevated rail assembly


102


. Alternatively, the distal end


130




d


can be stabilized to another support or structure by methods known in the art. In the present embodiment, the pile


130


is preferably a steel H beam having a width of approximately 14 inches, but it will be appreciated that other support members or structures known in the art can be used.




As illustrated in

FIG. 7

, a first outer pile


132


and an opposing second outer pile


134


are then positioned through the access area


128


. Distal ends


132




d


and


134




d


of each of the outer piles are driven into the ground


108


. Each of the outer piles


132


and


134


generally extend from the ground surface


108


to the existing elevated rail assembly


102


. Preferably, the two outer piles


132


and


134


extend from the ground surface


108


at convergent angles relative to the center pile


130


.




Proximal ends


130




p


,


132




p


, and


134




p


of each pile are horizontally cut off to define a generally uniform gap


136


between piles


130


,


132


,


134


and the rail assembly


102


, as illustrated in FIG.


8


. The ends


130




p


,


132




p


, and


134




p


are cut with level tops to a precise height for welding to steel plates on the bottom of a new, pre-cast concrete pile cap (not shown). The proximal ends are cut immediately after the piles are driven into the ground surface


108


so that rail assembly


102


can continue to be used for rail traffic. In the present embodiment, the steel piles


130


,


132


, and


134


can be cut using a gas/oxygen flame at exactly the height where the cut end will be welded to the new caps. As noted above, it is understood that other members or structures can be used for the new piles. Thus, the step of horizontally cutting proximal ends of the piles may be unnecessary when the piles are not driven into the ground as described above, but are stabilized by other methods or structures.




At this point, the ballast, a substantial majority of cross-ties


118


, and the rails


114


and


116


are still in place, and there are no obstacles to normal train traffic. The cross-ties that were removed to allow for driving the new piles can be replaced, and other cross-ties


118


approximately 30-feet away can be removed for driving the next set of piles.




Once the piles


110


are ready, a new, pile cap


112


of pre-cast concrete can be delivered by railroad car on the existing rail assembly


102


, as illustrated in

FIG. 9. A

locomotive crane


138


is moved approximately over the access area


128


. Coupled to the crane


138


is a freight car


144


housing the new pile cap


112


. The crane


138


and freight car


144


are stopped in a position where the coupling (not shown) between the car


144


and crane


138


does not block the access area


128


from the top. The hand brake is set on the freight car


144


, and the coupling is opened.




As shown in

FIG. 10

, the crane


138


is moved away from the car


144


to clear the coupling from the access area


128


. The crane


138


has a boom


142


and a retractable cable


146


. To lift and move the new pile cap


112


, a lifting device is used. The lifting device includes an intermediate member or support bar


148


and a plurality of interconnecting members or lifting rods


150


-


160


. Relevant details of the lifting device are provided below with reference to

FIGS. 20

,


21


, and


23


.




The cable


146


is connected to a center rod


152


, which extends from the support bar


148


along with a first end lifting rod


150


. The first end lifting rod


150


and the center lifting rod


152


define a first pair of lifting rods, which are both releasably connected to lifting points on the concrete pile cap


112


. Relevant details of the pile cap


112


are provided below with reference to

FIGS. 22A-B

.




The lifting rods


150


,


152


each have an extended position and a retracted position on the support bar


148


. In

FIG. 10

, the first end-lifting rod


150


and the center-lifting rod


152


are shown in the extended position releasably connected to lifting points on the pile cap


112


. A second end lifting rod


154


, a first mid-portion lifting rod


156


, a second mid-portion lifting rod


158


, and a third mid-portion lifting rod


160


are shown in the retracted position on the support bar


148


.




As will be further described below, each lifting rod corresponds to a lifting point or threaded hole in the pile cap


112


being approximately determined by the spacing of the stingers


126


. The lifting rods each weigh approximately 90-lbs. and must be raised approximately eight feet when retracted on the support bar


148


. To aid in the lifting of the rods, a double-sheave block is suspended from the crane arm to support two, one-inch diameter ropes. The ropes have eye splices at one end, which are slipped over the tops of the two active lifting rods. In a preferred embodiment shown in

FIG. 23

, a rope


137


is threaded through a sheave


139


. The rope


137


has an eye splice


141


at the working end. It is slipped over the top of one of the lifting rods, for example


150


. A pin


164


is placed through the top end of the lifting rod


150


so that the rope


137


may be used to raise and lower the lifting rod


150


.




As shown in

FIG. 11

, the crane


138


lifts the pile cap


112


out of the freight car


144


. The weight of the pile cap


112


is transferred through the center-lifting rod


152


, while the first end lifting rod


150


helps to stabilize the pile cap


112


. The pile cap


112


is lifted high enough to clear the side of the freight car


144


and is swung to the side of the rail assembly


102


. The crane


138


preferably rotates approximately 20 degrees or less. The pile cap


112


is positioned parallel to the rails to decrease the required rotation of the crane and the resulting moment arm thereon.




As shown in

FIG. 12

, the crane


138


lowers the pile cap


112


adjacent the access area


128


to approximately a few inches, such as three inches, above the pile cap's intended final elevation. The crane


138


is then moved away from the access area


128


backward until the crane's lifting arc is directly over the center pile


130


. The pile cap


112


is then rotated by a rope (not shown) attached to the first end lifting rod


150


until the pile cap


112


is generally perpendicular to the rail assembly


102


, as shown in FIG.


13


.




In this preferred embodiment, the locomotive crane


138


is used to lift and move the new concrete pile cap


112


. It understood that attention must be made to the maximum moment arm on the crane


138


, which can tend to overturn the crane as it holds the approximately 30,000-lb. pile cap


112


adjacent the rail assembly


102


. While lowering the cap


112


adjacent the access area


128


, the new cap


112


is preferably slightly rotated to clear the existing wooden pile cap


106


at one end and to clear the edge of the bridge assembly at the other end. In this way, the maximum overturning moment arm can be limited to approximately 100-inches measured from the center of the rails


114


and


116


to the lifting cable


146


.




If such a locomotive train is not used to move the pile cap adjacent the access area


128


, then particular attention must be further paid to the maximum overturning moment arm. For example, in another embodiment, a crane can be carried in a freight car delivering the new pile caps. With a crane in a freight car, the limiting point of the overturning moment arm is a side bearing on top of a truck bolster of the freight car, which is only about 20 inches from an axial centerline of the rails


114


and


116


. This imposes a severe limit on the load and or/moment arm that can be handled without danger of overturning the crane and freight car. Accordingly, if other cranes, mechanisms, or methods are used in the art to lift and move the concrete pile caps, particular attention must be paid to the overturning moment. It will be appreciated by one of ordinary skill in the art, however, that a number of cranes, methods, and mechanisms are known in the art for providing an increased maximum moment arm to resist overturning.




As shown in

FIGS. 14A-B

, the crane


138


positions one end of the pile cap


112


partially into the access area


128


and gap


136


from the side of the rail assembly until the center lifting rod


152


is adjacent to or in contact with the outboard stringer


126




a


. At this position, an additional lifting point on the pile cap


112


that is approximately 60 inches from the center is visible through the access area


128


. As shown in

FIG. 14B

, the cable of the crane


146


can include a hook or other connector


147


connected to one end of the center lifting rod


152


.




As shown in

FIGS. 15A-B

, the crane


138


lowers the pile cap


112


onto at least two piles, such as the center pile


130


and the first outer pile


132


. The weight of the pile cap


112


is thereby taken off the lifting rods. The first mid-portion lifting rod


156


is extended from the support bar


148


and is releasably connected to the lifting position of the pile cap


112


visible through the access area


128


. The center lifting rod


152


is disconnected from the pile cap


112


and is retracted up into the support bar


148


, as best shown in the end view of FIG.


15


B. Thus, at least two lifting rods are preferably connected to the pile cap


112


when alternating the interconnection of the rods with the pile cap. The center lifting rod


152


and the first mid-portion lifting rod


156


define a second pair of lifting rods extending from the support bar


148


. The first end lifting rod


150


stabilizes the pile cap


112


, while the center lifting rod


152


is retracted from support bar


148


and the first mid-portion lifting pipe


156


is releasably connected to the pile cap


112


.




The crane


138


then lifts the pile cap


112


off the center pile


130


and the first outer pile


132


. The crane


138


further positions the pile cap


112


into gap


136


by moving the center of the pile cap


112


approximately 18-inches closer to the center of the rail assembly


102


. At this position, an additional lifting point on the pile cap


112


that is approximately 42 inches from the center is visible through the access area


128


. The pile cap


112


is then lowered to rest on at least two of the piles, such as center pile


130


and first outer pile


132


.




The second mid-portion lifting rod


158


is extended from the support bar


148


and is releasably connected to the pile cap


112


, as best shown in the end view of FIG.


16


B. The first mid-portion lifting rod


156


is then disconnected from the pile cap


112


and retracted from the support bar


148


. The second mid-portion lifting rod


158


and the first end lifting rod


150


define a third pair of lifting rods extending from the support bar


148


. The crane


138


then lifts the pile cap


112


off the center pile


130


and the first outer pile


132


.




The crane


138


further positions the pile cap into the gap


136


an additional 18 inches toward the center until the second mid-portion lifting rod


158


is adjacent to or in contact with stringer


126




c


. At this point, an additional lifting point on the pile cap


24


inches from the center of the cap is visible through the access area


128


. The pile cap


112


is then lowered to rest upon two piles, such as center pile


130


and first outer pile


132


.




As illustrated in

FIG. 17

, the third mid-portion lifting rod


160


is extended from the support bar


148


and is releasably connected to the pile cap


112


. The second mid-portion lifting rod


158


is disconnected from the pile cap


112


and retracted from the support bar


148


. The third mid-portion lifting rod


160


and the first end-lifting rod


150


define a fourth pair of lifting rods.




The crane


138


then lifts the pile cap


112


off the center pile


130


and outer pile


132


. The crane


138


further positions the pile cap


112


into the gap


136


an additional 18-inches until the third mid-portion lifting rod


160


is adjacent to or in contact with the next stringer


126




d


. At this point, an outboard lifting point in the pile cap


112


is visible beyond the outboard stringer


126




e


. The pile cap is then lowered to rest upon piles


130


,


132


, and


134


.




As illustrated in

FIGS. 18A-B

, the second end lifting rod


154


is then extended from the support bar


148


and is releasably connected to the pile cap


112


. The second end-lifting rod


154


and the first end-lifting rod


150


define a fifth pair of lifting rods. Then, the third mid-portion lifting rod


160


is disconnected from the pile cap


112


and retracted from the support bar


148


. The crane


138


then lifts the pile cap


112


off piles


130


,


132


, and


134


. The crane


138


further positions the pile cap


112


into the gap


136


so that the pile cap


112


is centered directly under the rail assembly


102


. The pile cap


112


is then lowered onto piles


130


,


132


, and


134


so that the weight of the pile cap


112


is taken off the fifth pair of lifting rods


150


and


154


.




The pile cap


112


includes three steel plates (not shown) that are cast and anchored into a bottom surface of the pile cap


112


. These steel plates correspond to the spacing of the piles


130


,


132


, and


134


. The pile cap


112


is welded at the juncture of the steel plates and the piles


130


,


132


, and


134


. The first end lifting rod


150


and the second end lifting rod


154


are then disconnected from the pile cap


112


and retracted from the support bar


148


. The crane


138


then lifts the support bar


148


and the lifting rods back into the freight car


144


, as illustrated in FIG.


19


.




With the new cap


112


and piles


130


,


132


, and


134


installed, the above system and method according to the present invention can be repeated at further locations along the bridge assembly. As discussed above, new caps and piles are positioned between every other wooden cap and piles or about every 30-feet along the bridge assembly. Once the new caps and piles are installed below the exiting bridge assembly, the old, wooden caps, piles, and ballast can be removed.




In practice of the present invention, it is understood that all the steps discussed above need to be preformed at one location at one time on the bridge assembly


100


. Instead, it is preferred that at least some of the steps be performed along the length of the assembly


100


before further steps are performed. For example, creating the access area, driving the new piles, cutting the new piles, and positioning the new caps on the piles can be performed at one location and then further locations along the assembly before the wooden caps and piles are replaced with new, concrete spans. As evidenced herein, the system and method according to the present invention advantageously maintains a substantial portion of the load-bearing components of the rail and bridge assembly and allows the exiting rails and bridge assembly to be used while performing the steps in this manner.





FIG. 20

illustrates an embodiment of a lifting device according the present invention. The lifting device includes an intermediate member or support bar


148


and a plurality of interconnecting members or lifting rods


150


-


160


. The support bar


148


is illustrated in cross-section to show an internal hollow defined therein. The support bar


148


defines a plurality of first or top apertures


161




a


from a top of the bar to the internal hollow. The support bar


148


defines a plurality of equally located, second or bottom apertures


161




b


from a bottom of the bar to the internal hollow. The bottom apertures


161




b


have a greater dimension than the top apertures


161




a.






The lifting rods


150


-


160


are disposed in the plurality of apertures


161




a-b


in the support bar


148


. The apertures


161




a-b


are approximately spaced to cooperate with the spacing of the stringers of the rail assembly and with the spacing of the lifting points on the new pile cap. For example, the first mid-portion lifting rod


156


is preferably spaced approximately 60 inches from the center-lifting rod


152


. Also, the second mid-portion lifting rod


158


is preferably spaced approximately 42 inches from the center lifting rod


152


, and the third mid-portion lifting rod


160


is preferably spaced approximately 24 inches from the center lifting rod


152


. This spacing accommodates the typical spacing of stringers in a rail assembly, although it is understood that other arrangements of spacing may also be applicable to the present invention. In an alternative embodiment, three additional lifting rods (not shown) can be located between the center lifting rod


152


and the first end lifting rod


150


. The spacing of the three, additional lifting rods can be similar to the first, second, and third mid-portion lifting rods from the center.




The first end lifting rod


150


and the second end lifting rod


154


are shown in the extended position in relation to the support bar


148


. The center lifting rod


152


, the first mid-portion lifting rod


156


, the second mid-portion lifting rod


158


, and the third mid-portion lifting rod


160


are all shown in the retracted position. Removable pins


164


are used to hold the rods in the retracted position. Preferably, all of the lifting rods can be retracted so that a threaded end can be housed in the internal hollow of the support bar, which protects the threads from damage when not in use.




The center-lifting rod


152


is movably disposed in central apertures of the support bar


148


between extended and retracted positions. The center-lifting rod


152


has a lower end capable of releasably connecting to the cap at one of the lifting points when in the extended position (not shown). The lower end is also capable of engaging the inner hollow of the support bar


148


adjacent the upper aperture


161




a


when in the retracted position as shown in FIG.


20


. The center-lifting rod


152


also has an upper end capable of connecting to the cable. In one embodiment, the center-lifting rod


152


includes a swivel and shackle


162


so that the cable of the crane can be attached to the center-lifting rod


152


. The upper end is also capable of engaging the outer surface of the support bar


148


adjacent the upper aperture


161




a


when in the extended position (not shown).




The plurality of other lifting rods


150


,


154


,


156


,


158


, and


160


are also movably disposed in the apertures


161




a-b


of the support beam between extended and retracted positions. These rods have a lower end capable of releasably connecting to the cap at one of the lifting points when in the extended position. These rods also have an upper end capable of engaging outside surface of the support beam adjacent the upper aperture


161




a


when in the extended position, such as rods


150


and


154


are shown in FIG.


20


.





FIG. 21

illustrates an embodiment of a lifting rod according to the present invention. Shown by way of example is a first end lifting rod


150


with an upper collar


166


at an upper end of the lifting rod and a large diameter area


168


at a lower end of the lifting rod. The upper collar


166


, which may be welded to the rod, is a stop to keep the lifting rod


150


from sliding out of the support bar when the pile cap is being lifted. Adjacent to the large diameter area


168


is a male member or tapered threaded section


170


for releasably connecting to the cap. The lifting rod


150


further includes an aperture


172


for a pin, such as the pin


164


in

FIG. 20

, to hold the rod


150


in the retracted position in the support bar. The lifting rod also includes another aperture


173


receiving the pin to retract and extend the rod in the support bar. The male member


170


on the rod


150


can be threaded to a lifting point on the pile cap by a hydraulic motor on the crane under the remote operation of the operator.





FIGS. 22A-B

illustrate an embodiment of a pile cap


112


according to the present invention. The pile cap


112


includes a plurality of lifting points or threaded holes


174


,


176


,


178


,


180


,


182


, and


184


used for the lifting rods. The lifting points are positioned along a longitudinal axis of the pile cap


112


. In particular, the pile cap


112


includes a first outboard-threaded hole


174


and a center threaded hole


176


at the center of the pile cap


112


. Opposite the outboard-threaded hole


174


is a second outboard-threaded hole


178


. Spaced apart between the center threaded hole


176


and the outboard-threaded hole


178


is a first threaded hole


180


, a second threaded hole


182


, and a third threaded hole


184


. The threaded holes on the pile cap


112


are spaced to match the spacing of the lifting rods spaced across the support bar


148


.




The releasable connection between the threaded holes and the lifting rods is made by mating the threads of the lifting rods with the appropriate threaded hole of the pile cap


112


. The load bearing surface


186


is adapted to support new pre-cast concrete bridge spans, which in turn support the existing elevated rail assembly. The pile cap


112


can further include three additional threaded holes located between the center-threaded hole


176


and the inboard-threaded hole


174


so that the pile cap


112


is symmetrical about the center.




Past attempts of providing the lifting points or threaded holes in the pile cap


112


involved welding threaded steel nuts to reinforcing steel that was then cast in the material of the cap. It has been found that the heavy load of the pile cap striped the threads of the welded nuts. Thus, as best shown in

FIG. 22B

, the threaded holes


174


,


176


,


178


,


180


,


182


, and


184


according to the present invention are preferably formed from cut lengths of oil well drilling pipe


190


. The pipes


190


are attached to reinforcing steel


188


and then cast into the concrete when the cap


112


is formed. The oil well drilling pipe


190


is internally threaded and is flush with the load bearing surface


186


of the cap


112


. The flush ends of the pipe


190


will not interfere with the new, pre-cast concrete spans to be supported on the load bearing surface


186


.




The threaded holes


174


,


176


,


178


,


180


,


182


, and


184


are tapered to provide automatic alignment with the threaded section of the lifting rods, such as section


170


in FIG.


21


. The threads are very coarse so that only a few turns of the lifting rod is required to make the releasable connection. As is known in the art, the threads of the oil well drilling pipe


190


are designed to support thousands of feet of interconnected drill pipe, which can impose loads of 100,000-lbs. or more on couplings of the upper pipes. This is many times the weight of the pile cap


112


to be lifted. As discussed above, at least two lifting rods are releasably connected to the lifting points on the cap


112


. Thus, the internal threads of two pipes


190


are adequately capable of sustaining the approximately 30,000-lbs. load of the pile cap


12


when coupled to at least two lifting rods.




Preferably, the pile cap


112


has a reinforcement bar


188


extending through the threaded oil well drilling pipes


190


. Prior to the pile cap


112


being cast with concrete, holes are drilled in the oil well drilling pipes


190


for interconnecting the reinforcement bar


188


with the pipes


190


. The reinforcement bar


188


is preferably steel re-bar and is preferably disposed through the holes in the pipes


190


and not welded to them. The reinforcement bar


188


helps to retain the pipes


190


in the pile cap


112


when lifted. As at the tops of the pipes, the lower ends of the pipes


190


are flush with the bottom of the pile cap


112


. In addition, the bottom ends of the pipes


190


are open, and the pipes


190


are able to drain rain water.




While the invention has been described with reference to the preferred embodiments, obvious modifications and alterations are possible by those skilled in the related art. Therefore, it is intended that the invention include all such modifications and alterations to the full extent that they come within the scope of the following claims or the equivalents thereof.



Claims
  • 1. A system for upgrading an existing bridge assembly with new structures using a crane with a cable, system comprising:a pile cap for supporting a portion of the new structures having a plurality of lifting points formed therein, wherein the plurality of lifting points formed in the pile cap comprises a plurality of pipes cast in the pile cap, each pipe having internal threads at an end adjacent a load-bearing surface of the pile cap; an intermediate member having a plurality of support locations being substantially equally spaced as the lifting points; and a first interconnecting member disposed at one of the support locations and being connectable to the cable, the first interconnecting member capable of supporting the intermediate member and capable of releasably connecting to one of the lifting points; and a plurality of second interconnecting members disposed at the other support locations, the second interconnecting members each being capable of interconnecting the intermediate member with one of the plurality of other lifting points.
  • 2. The system of claim 1, wherein the plurality of lifting points on the pile cap comprises:a first end point adjacent one end of the pile cap, a second end point adjacent another end of the pile cap, a central point between the first and second end points, and one or more third points being substantially spaced at predetermined distances between the central point and at least one of the end points.
  • 3. The system of claim 1, wherein the pipes each comprise an internally threaded end of an oil well drilling pipe.
  • 4. The system of claim 1, wherein the internal threads of at least two of the pipes are capable of sustaining a load of the pile cap when coupled to at least two of the interconnecting members.
  • 5. The system of claim 1, wherein the pile cap comprises a reinforcing member cast in the pile cap and interconnected with the plurality of pipes.
  • 6. The system of claim 1, wherein the intermediate member comprises a bar having a plurality of apertures defined therethrough at the support locations.
  • 7. The system of claim 1, wherein the first interconnected member comprises a central rod having first and second ends, the first end having a rotatable member connectable with the cable, the second end having a male member threadable in a centrally loaded lifting point.
  • 8. The system of claim 1, wherein the second interconnecting members each comprise a rod having first and second ends, the first end having a stop capable of engaging the intermediate member, the second end having a male member threadable in one of the lifting points.
  • 9. The system of claim 8, wherein the male members are capable of being housed in the intermediate member when in a retracted position.
  • 10. A system for handling components of a structure using a cable of a crane, the system comprising:a component of the structure, comprising: a body having a first surface, a first member in the body having a first threaded end exposed on the first surface, a reinforcing member cast in the body of the component and connected to the first member, wherein the reinforcing member comprises a bar passing though a hole drilled through the first member; and a device for moving the component, the device being connectable to the cable and comprising a second member having a second treaded end, the second threaded end capable of threading with the first threaded end of the first member.
  • 11. The system of claim 10, wherein the component is a concrete pile cap for upgrading the structure of an existing railroad bridge.
  • 12. The system of claim 10, wherein the first member comprises a portion of an oil well drilling pipe cast in the body and having a female thread formed at the first threaded end.
  • 13. The system of claim 10, wherein the first member has a second end exposed on a second surface of the body, the second end capable of draining water from the first threaded end exposed on the first surface.
  • 14. The system of claim 10, wherein the second member comprises a portion of an oil we drilling pipe having a male thread formed at the second threaded end.
  • 15. The system of claim 10, wherein the component comprises a plurality of first members in he body spaced at a plurality of lifting points on the component, each first member having a first threaded end exposed on the first surface.
  • 16. The system of claim 15, wherein the device comprises:a support member having a plurality of support locations being substantially equally spaced as the lifting points on the component; and a plurality of second members disposed on the support member at the lifting locations, each of the second members being movable between extended and retracted positions in the support member for handling the component in restrictive areas of the structure.
  • 17. The system of claim 16, wherein one of the plurality of second members has a second end connectable to the cable of the crane.
  • 18. A system using a cable for handling components of a structure having an obstruction, the system comprising:a component of the structure having a plurality of lifting points formed on a surface of the component; and a device for moving the component, comprising: a bar moved by the cable, and a plurality of rods disposed on the bar and movable between extended and retracted positions on the bar, each rod having a first end connecting to one of the lining points formed on the component when the rod is in the extended position, wherein the plurality of rods are alternatingly movable between the extended and retracted positions on the bar and the first ends of the rods are alternatingly connectable to the lifting points on the component for moving the component past the obstruction of the structure when interposed between the component and the bar.
  • 19. The system of claim 18, wherein the component is a concrete pile cap for upgrading the structure of an existing railroad bridge.
  • 20. The system of claim 18, wherein the lifting points of the component each comprise a threaded opening exposed on the surface of the component.
  • 21. The system of claim 18, wherein the lifting points of the component each comprise a fist portion of an oil well drilling pipe cast in the component and having a threaded opening exposed on the surface of the component.
  • 22. The system of claim 21, further comprising a reinforcing bar cast in the component and connected to the portions of the oil well drilling pipe.
  • 23. The system of claim 21, wherein the first ends of the rods each comprise a second portion of an oil well drilling pipe attached to the rod and having a male thread threading with the treaded opening.
  • 24. The system of claim 18, wherein the bar defines a plurality of holes being substantially equally spaced as the lifting points on the component and having the rods movably disposed therein.
  • 25. The system of claim 18, wherein the first ends of the rods are housed within a hollow of the bar when the rods are in the retracted position.
  • 26. The system of claim 18, wherein the plurality of rods comprises a central rod having a second end connecting to the cable and having a first stop for engaging the bar when the central first rod is in the retracted position.
  • 27. The system of claim 18, wherein the plurality of rods comprises a second rod having a second stop for engaging the bar when the second rod is in the extended position.
US Referenced Citations (7)
Number Name Date Kind
3448511 Suter Jun 1969 A
4103861 Buchler et al. Aug 1978 A
4301565 Weinbaum Nov 1981 A
4497153 Muller Feb 1985 A
4691399 Kim et al. Sep 1987 A
5048424 Madison et al. Sep 1991 A
5197389 Glomski et al. Mar 1993 A
Foreign Referenced Citations (1)
Number Date Country
2 653 144 Apr 1991 FR
Non-Patent Literature Citations (1)
Entry
English Abstract of FR 2 653 144-A1 entitled “Method for the construction of civil engineering constructions under railway tracks in use,” 1-page.