Production rate and resource capacity planning may be described as an inter-related set of processes used to answer key questions necessary for planning efficient production operations, where the goal is to plan the performance of some repetitive body of work subject to a combination of constraints on duration, rate, and resources. This type of planning may be applicable to any operational context involving repetitive work which may result in the delivery of finished products or completed services, and/or applicable to other types of non-operation contexts. The following four basic questions may be asked in the context of Production Rate and Capacity Planning:
Together, these questions (and other questions itemized in Section 6 of the Description below) may characterize the objectives of production rate and resource capacity planning.
In current practice, only one of these four questions, question Q3, may be easily answered, and only when a number of simplifying assumptions may be satisfied. The remainder of these questions often go unanswered, or are often answered only by ad-hoc, trial and error exercises. Using current practice there may be no assurance that suitable answers may be obtained or that the answers will prove valid in production operations. Often the most effective, but most expensive and time-consuming method used to answer these questions may be to implement a decision in production operations and to incrementally adjust resource quantities, target durations, and target rates until performance goals are achieved.
In current practice, questions Q1 and Q3 may be answered by constructing a finite capacity schedule for the planned work, limited by the fixed quantity of resources provided, using simulation or other conventional means. Each time a new quantity of resources is considered, the process may be repeated.
In current practice, questions Q2 and Q4 may not be so easily answered. For instance, often several different resource plans are constructed, and for each constructed resource plan a schedule may also be constructed (such as answers to question Q1 or Q3). If a schedule is produced that is near the target duration, small changes may be made to the corresponding resource plan and further trials may be run. Even when a suitable schedule is found, there may be no assurance that the best resource plan has been found because there may be so many ways that the quantity of required resources can be varied. Current practice often relies upon ad-hoc, trial and error exercises, and even when an answer is obtained, the quality of that answer may be uncertain.
One or more methods of production rate and resource capacity planning are needed to efficiently answer questions Q1, Q2, Q3, and/or Q4.
In one aspect of the invention, a method for production rate and capacity planning is provided. In one step, a resource quantity, unit duration, and production interval is determined for Category 1 resources. Category 1 resources comprise resources that are not shared between production units, which effect concurrency between the production units, which have no effect on the unit duration, and which have no effect on degree of concurrency within the production units. In another step, a resource quantity and unit duration is determined for Category 2 resources. Category 2 resources comprise resources that are not shared between the production units, which do not effect the concurrency between the production units, and which effect the unit duration by enabling the concurrency within the production units. In an additional step, a resource utilization is determined for Category 1 and Category 2 resources.
In another aspect of the invention, a method is provided for determining resource quantity, unit duration, and production interval for Category 1 resources. In one step, a minimum acceptable quantity of Category 1 resources is determined using at least one of fixed and target values for unit duration and production interval. Category 1 resources comprise resources that are not shared between production units, which effect concurrency between the production units, which have no effect on the unit duration, and which have no effect on degree of concurrency within the production units. In another step, a maximum acceptable unit duration is determined using at least one of fixed and target values for quantity of Category 1 resources and production interval. In yet another step, a minimum acceptable production interval is determined using at least one of fixed and target values for quantity of Category 1 resources and unit duration.
In still another aspect of the invention, a method is provided for determining resource quantity and unit duration for Category 2 resources. In one step, coefficients of a Parametric Model of Unit Duration are determined. In another step, a minimum unit duration that can be achieved with a given quantity of dedicated resources is determined. In still another step, a quantity of dedicated resources required to achieve a given unit duration is determined. Category 2 resources comprise resources that are not shared between the production units, which do not effect the concurrency between the production units, and which effect the unit duration by enabling the concurrency within the production units.
In yet another aspect of the invention, a method is provided for determining resource utilization. In one step, a utilization of Category 1 resources is determined using known quantities for at least one of unit duration, production interval, and quantity of dedicated resources. Category 1 resources comprise resources that are not shared between production units, which effect concurrency between the production units, which have no effect on the unit duration, and which have no effect on degree of concurrency within the production units. In another step, a utilization of Category 2 resources is determined using known quantities for at least one of unit duration and quantity of dedicated resources. Category 2 resources comprise resources that are not shared between the production units, which do not effect the concurrency between the production units, and which effect the unit duration by enabling the concurrency within the production units.
These and other features, aspects and advantages of the present invention will become better understood with reference to the following drawings, description and claims.
The following detailed description is of the best currently contemplated modes of carrying out the invention. The description is not to be taken in a limiting sense, but is made merely for the purpose of illustrating the general principles of the invention, since the scope of the invention is best defined by the appended claims.
In one embodiment, a method for production rate and resource capacity planning is disclosed which may be applied in any context where the goal is to plan the performance of some repetitive body of work subject to a combination of constraints on duration, rate, and resources.
The instant invention may be applicable to any operational context involving repetitive work which may result in the delivery of finished products or completed services. The invention may be applicable to manufacturing (both fabrication and assembly), maintenance repair and overhaul, training, flight operations, and other contexts which entail the repetitive performance of work.
The invention may be used to make decisions in staffing, asset management, capital investment, production rates, supply contracts, sales, and others areas where it is necessary to determine the quantity of resources required to meet a target duration or rate, or where it is necessary to determine what duration or rate may be achieved with the available resources.
Using one or more methods of the below disclosed invention, a single specific resource plan may be constructed. A set of derivative resource plans may be created and schedules may be constructed for each. The durations of these schedules may be analyzed and the results may be converted to an equational form and to an equivalent inverse form. Thereafter, any instance of questions Q1, Q2, Q3, and/or Q4 (as disclosed in the background section) for this body of work may be answered by application of the derived equation or its equivalent inverse form, without need to construct additional schedules. In many cases, this process may yield consistent, high quality answers based upon analysis of only three schedules.
In one embodiment of the invention, structured, systematic methods are provided to answer questions Q1, Q2, Q3, and/or Q4 (and others central to the processes of production rate and resource capacity planning). A discussion of key concepts and mathematical relationships is provided in this specification in order for the reader to understand the methods of the invention. The instant invention may unify the collection of processes required to perform production rate and capacity planning into a single decision process, which may contain the computational steps necessary for planning efficient production operations.
The instant invention discloses multiple method embodiments which allows one of ordinary skill in the art to practice one or more of the following:
Several of the mathematical relationships that may occur in the study of schedules and scheduling may have a common mathematical representation. These may include, but may not be limited to the following: the relationship between work content, duration, and resource quantity; the relationship between degree of concurrency, unit duration, and production interval; the relationship between resource capacity and unit duration; and the relationship between resource capacity and production rate.
To avoid redundantly presenting and deriving some of the key equational forms, the following basic discussion will be presented once, and then referenced as appropriate.
Several of the mathematical relationships that may occur in the study of schedules and scheduling may be characterized as a common mathematical relationship illustrated in
The graph for Eq. 1 is asymptotic to the lines x=0 and y=0, and may contain the point x=1, y=1 as illustrated in
The simple relationship between two variables x and y may be further generalized by an equation of the form (including its various equivalent forms):
The graph for Eq. 2 may be asymptotic to the lines x=c and y=a, and may contain the point
(x=c+√{square root over (b)}y=a+√{square root over (b)})
The coefficients a, b, and c may influence the shape and placement of the graph as illustrated in
Estimating the coefficients a, b, and c in Eq. 2 from empirical data may be based upon the assumption that the basic relationship defined in Eq. 1 may hold between the two variables x and y as modified by the additional parameters a, b, and c in Eq. 2. The simplest method for computing these coefficients may use two selected data points and may determine values for the coefficients which yield an equation going through those points. Other methods may analyze all data points and may determine values for the coefficients which may yield an equation which is the best fit to the data points using distance measures such as least squares.
In order to provide a suitably complete presentation of a method for production rate and resource capacity planning the following mathematical analysis derives a simple method which may determine values for the coefficients using two selected data points. Equivalent and related methods may be obtained from standard mathematics, statistics, or engineering textbooks and will not be presented here.
For purposes of the analysis, assume that two data points x1, y1, and x2, y2 are given, and that they each lie on the line defined by Eq 2. Also assume that these equations are used in a context where the value of coefficient a can be estimated or determined independently. This assumption may be satisfied in the methods described below.
The value of c may be determined by first incorporating known values for two data points x1, y1 and x2, y2, inserting the coefficient a into the equations, and rewriting the equations through a series of steps comprising the following:
To simplify the necessary computations the following substitution may be introduced:
Eq. 3.4 may be rewritten as follows:
This may yield the following equation for the coefficient c:
Using either part of Eq. 3.1, the value for coefficient b may be determined by incorporating known values for one data point, (e.g. x1,y1), inserting the coefficients a and c into the equations, and rewriting the equations through the following steps:
This may yield the following equation for the coefficient b:
b=(y1−a)·(x1c) Eq. 3.14
Using similar analysis, an equation that determines the value of x, given the value for y, and the coefficients a, b, and c, may be derived by the following transformations:
This may yield the following equation for the variable x as a function of y:
The instant disclosure includes the following inter-related set of concepts, definitions, and formulae that together provide necessary background for a complete description of the method for production rate and resource capacity planning:
Concepts of Production (Section 4.1);
Concepts and Measures of Resources (Section 4.2);
Concepts and Measures of Work (Section 4.3);
Concepts and Measures of Production Rate (Section 4.4);
Concepts and Measures of Concurrency (Section 4.5); and
Concepts and Measures of Duration (Section 4.6).
In the context of production rate and resource capacity planning, the concept of production may be defined to be delivery of a finished product or completed service. The delivery of a single instance of a product or service may constitute a single production unit, while the delivery of multiple similar instances of a product or service may constitute repetitive production.
A resource may be defined as any physical asset required for production, or as defined below, any physical asset required for the performance of work.
In any given production context there may be some resources that are limited and fixed in quantity. Because the performance of work depends upon the availability of necessary resources, any resources that are limited and fixed in quantity may, in turn, constrain or limit the performance in work and its associated duration and rate.
In any given production context there may be some resources that are flexible where the quantity available may be increased or decreased to satisfy production demands, cost of operation, and other factors. Because the performance of work may depend upon the availability of necessary resources, any resources that are flexible, may be adjusted to enable the performance of work and its associated duration, and rate.
Dedicated resources may be those that are assigned to a single production unit, from start until finish, without being assigned or applied to any other concurrent production unit. When one production unit is complete, dedicated resources may be assigned to a successive production unit, again dedicated from start until finish.
An example of a dedicated resource may be a pilot assigned to an aircraft to fly a commercial flight. Clearly, a pilot cannot time-share between two aircraft. A pilot may be dedicated to one aircraft and one flight from start until finish and when that flight is complete, may be assigned to another aircraft.
Shared resources may be those that are assigned to concurrent production units. During the period of time in which the concurrent production units are in work, shared resources may be alternately applied to one production unit, then to another, or to both simultaneously. When one production unit is complete, shared resources may be assigned to a successive production unit, while continuing to support those that have not yet been completed.
If a resource is or can be used to support more than one concurrent production unit at the very same moment of time, that usage may be said to be simultaneous. If a resource is or can be used to support more than one concurrent production unit by successively switching between them, that usage may be said to be interleaved.
An example of a shared resource and simultaneous usage may be an auxiliary power unit that can concurrently supply electricity to multiple pieces of equipment, up to the limit of its power rating and the availability of power connectors. Another example of a shared resource may be an instructor in a lab concurrently assisting multiple students, where general assistance may be simultaneous (advice or instructions to more than one student) and specific assistance may be interleaved (advice or instruction to only one student at a time).
Both dedicated and shared resources may be utilized in the same context of work. For example, a maintenance crew may be assigned to a flight line expected to support multiple aircraft at one time. Upon landing, an aircraft may be assigned a fixed gate (as a dedicated resource) until departure, while the crew (as a shared resource) may be expected to divide its support among all aircraft on the ground. While it may be feasible to assign a fixed crew to each gate as a dedicated resource, assigning a fixed crew at each gate of sufficient size to address all possible maintenance requirements may be excessive. At the same time, assigning a smaller crew at each gate may create risks that one aircraft may be delayed because of greater than average maintenance requirements while crew at another gate may be underutilized. Using a maintenance crew as a shared resource may require fewer total individuals while providing sufficient capacity to respond to variation in maintenance requirements on a case-by-case basis.
There are four basic effects that activities may have on resources. Two effects may be temporary. For instance, an activity may reserve and use a resource for a finite period of time (precluding use by other activities), or an activity may provide and make available a resource for a finite period of time (enabling use by this same or other activities). Two other effects may be permanent. For instance, an activity may consume a resource and permanently decrease the quantity available (preventing further use by any activity), or an activity may produce a resource and permanently increase the quantity available (enabling use by this same or subsequent activities).
This discussion of production rate and resource capacity planning may be concerned primarily with temporary reservation and use of resources over finite periods of time. The mathematics which relate the quantity of reserved resources to the overall rate of production for a given product or service may not be immediately obvious, yet when applied correctly may be powerful.
The occurrence of activities that provide resources over finite periods of time may be exceptional, and will be excluded from further discussion, although the mathematical models provided below may, to a certain extent, be equally applied to this category of usage and effects.
The mathematics which relates the quantity of resources permanently consumed or produced to the overall rate of production for a given finished product or completed service may be comparatively simple, and intuitive, and will be excluded from further discussion.
Focusing on temporary reservation and use of resources over finite periods of time, resource reservation and use may have two dimensions: (1) the quantity, and (2) the duration of time that the resource is required or provided.
The quantity of a resource, required or provided for the performance of some body of work, may be measured in some units such as: number of individuals; watts of electricity; number of tools; fixtures; or jigs, etc. Some measures of quantity may be clearly quantized such as number of tools or individuals, while other quantities may have a finer granularity such as watts of electricity that may be measured in both whole units and fractional parts.
In general, the quantity of resources required or provided for the performance of work (over a suitable period of time) may be represented by a vector, where each element of the vector may represent the quantity of resources required or provided within a single, distinct resource category. Systematic analysis of how the quantity of resources provided affects unit duration or production interval may require systematic exploration of the entire multidimensional vector space.
Such analysis may be simplified by focusing on a parametric model of resource availability defined using a proportional resource vector and a parametric series of quantized resource vectors (both are defined below). The basis for this concept may be simple but may require reflection on how resource availability affects unit duration (and equivalently production interval).
If only one category of resource is required for completion of one production unit, it may be reasonable to assume that the unit duration will be affected by the quantity of that resource. If only a small quantity is provided, the duration may be long. If a larger quantity is provided, the duration may be shorter. After a certain point, increase in the quantity provided may produce no further decrease in unit duration (see discussion of Minimum Duration and Resource Dependent Duration provided below).
If two categories of resources are required for completion of one production unit, it may also be reasonable to assume that the unit duration will be affected by the separate quantities of the resources provided. If a small quantity of the first resource is provided and a very large quantity of the second resource is provided, then the quantity of the first resource may have the most effect and the duration may be long. Likewise, if a very large quantity of the first resource is provided and a small quantity of the second resource is provided, then the quantity of the second resource may have the most effect and the duration, again, may be long. Separately exercising the quantity of each resource across a range of values may be wasted effort because the result may be largely determined by the resource that has the smallest proportional value.
The alternative may be to exercise the quantity of resources through a series of cases. In each case, the quantity of each resource may have an equal and balanced effect on unit duration. Analysis of the effect of resource availability on unit duration and production interval may require three things. First, it may require a means for determining the correct proportion between resources so that each resource has an equal and balanced effect. Second, it may require some means to represent that proportion. Third, it may require some means to construct a parametric series of individual cases, which may vary across a range of values while still preserving the desired proportions.
As will be described below, the correct proportion between resources may be derived from the Basis Work Content Vector. Construction of the parametric model of resource availability and resource vectors for individual cases of the analysis may begin with construction of a Proportional Resource Vector and may follow with construction of a parametric series of Quantized Resource Vectors.
In general, large complex bodies of work may require a mixture of differentiated resources in their performance, and even individual tasks may require resources from two or more distinct resource categories. The resources may include specific tools, pieces of equipment, human labor categorized by skill (e.g. electrician or mechanic) or qualification, and fluid resources of finer granularity such as electricity or thermal capacity.
In general, the quantity of resources required or provided for the performance of work (over a suitable period of time) may be represented by a vector where each element of the vector may represent the quantity of resources required or provided within a single, distinct resource category. Where useful or necessary, the quantity of resources provided for the performance of work may be divided into two or more vectors representing the separate allocation of shared and dedicated resources as follows:
R=[r1,r2, . . . rm], where Eq. 5.1
rj=the quantity of resource category j required or provided Eq. 5.2
The total quantity of resources T required or provided for the performance of some activity or body of work may, in some cases, be usefully computed as the sum of the elements within a Resource Vector. For example, this may be useful when considering the total number of individuals within a mixed pool of labor divided between specific skill sets. This quantity may also be useful in the definition of other concepts such as a Proportional Resource Vector.
A Proportional Resource Vector may be defined to be a resource vector where each element represents the percentage of the total resources contained within the corresponding resource category. By definition, this may imply that the sum of all elements within a Proportional Resource Vector equals one.
Clearly, any resource vector (R) may be reduced to a proportional resource vector (P) by dividing each element of (R) by (T).
A Quantized Resource Vector (Ps) may be defined to be a proportional resource vector (P) multiplied by a scalar quantity (s) as defined in the following:
Ps=s·P=[s·p1,s·p2, . . . s·pm], where (s) is a scalar value and Eq. 9.1
P=[p1,p2, . . . pm] is a proportional resource vector. Eq. 9.2
A Parametric Series of Quantized Resource Vectors may be defined to be a set of resource vectors:
P1,P2, . . . Pn Eq. 10
wherein each Quantized Resource Vector (Pi) may be constructed from a common Proportional Resource Vector (P), and scalar values s=1, 2, 3, . . . n.
A Modified Resource may be defined as a quantized proportional resource vector where the quantity of resources in each category has been rounded up and modified as necessary to satisfy the minimum resource requirements for performance of the given activity or production unit.
U=[u1,u2, . . . um], where Eq. 11.1
R=[r1,r2, . . . rm] is a quantized proportional resource vector and Eq. 11.2
ui=[ri], where use of [ ] indicates rounded and modified as necessary. Eq. 11.3
The mathematical relationship between resource quantity and unit duration, and the mathematical relationship between resource quantity and production interval, may be reduced to a common mathematical relationship as discussed in multiple sections below. Derivation and use of these mathematical relationships may depend upon a means to represent the quantity of resources required or provided as single scalar value. Clearly, the total quantity of resources, computed as the sum of elements within a resource vector, may be a candidate. Without additional restrictions this may be a poor choice. Many different resources vectors may yield the same total quantity of resources yet yield different unit durations or production intervals when used to generate schedules.
The mathematical relationship may depend upon more than total quantity. The mathematical relationship may be best derived and may be best employed in the context of a family of resource vectors where all resource vectors in the family can be reduced to one common proportional resource vector, and where each element of each resource vector has an equal and balanced effect on unit duration or production interval. Construction of a suitable family of resource vectors, based upon analysis of total work content, is described below.
Within a suitably constructed family of resource vectors, each resource vector (R) may be equivalent to a common proportional resource vector (P), multiplied by some scalar value (S).
R=S·P=[S·p1,S·p2, . . . S·pm], where (S) is a scalar value. Eq. 12.1
As a result, the total quantity of resources may equal (S):
Restricting focus to a suitable family of resource vectors, the total quantity of resources, or equivalently the scalar multiplier of the proportional resource vector, may serve as a suitable scalar representation of resource quantity and basis for deriving the desired mathematical relationships.
In practice, schedules may be constructed only from resource vectors that have been modified to satisfy the minimum resource requirements for performance of the given production unit. In practice then, the total quantity of resources within the quantized resource vector may be less than the total quantity of resources within the modified resource vector. Experience may show that either may be used within the methods described below, but use of the total quantity of resources within the modified resource vector may yield slightly more accurate results.
In the remainder of this application, the variable Q will be used to denote the quantity of resources required or provided for the performance of work. In all contexts, it is assumed that Q represents the total quantity of resources contained within a modified resource vector within a suitable family of resource vectors with a common proportional basis.
It may be impossible to provide a single definition of work that will serve equally in all contexts for production rate and resource capacity planning. Nevertheless, for this discussion, work may be defined to be performance of a set of activities, making use of a set of resources, contributing to the delivery of a finished product or completed service.
For example, the activity of manufacturing and assembling component parts to create a finished product qualifies as work. In maintenance, the activity of removing a failed component and replacing it with a new component to restore a product to an operational condition qualifies as work. Less obvious, the activity of inspecting aircraft structure to ensure that no fatigue or corrosion is present qualifies as work. In teaching, the activity of creating, delivering, and grading a test to certify the capabilities of the students qualifies as work.
Other examples are less clear but still qualify as work. For example, baking carbon-fiber epoxy composite materials in an oven to cure the plastics and bond the materials adds value to the finished product but does not immediately appear to be an activity. Other examples include processes of annealing, tempering, fermentation, drying, and curing which do not immediately appear to be activities yet all add value to manufactured goods.
Some might argue that activities or periods of time that do not add value to a product or service should not be interpreted as work. Nevertheless, activities or periods of time that require resources (for storage, for example) are relevant to this discussion and there will be no attempt in the following to distinguish between value-added and non-value-added activities, resource assignments, or periods of time.
Repetitive work may be accomplished by repetitive performance of a set of activities, making use of a set of resources, resulting in the delivery of multiple units of a finished product or completed service.
By convention, the work content of one activity may be defined as the product obtained by multiplying the quantity of resources required to perform the activity by the duration of the activity, each measured in relevant units. The most common measure of work content may be man-hours, or equivalently labor-hours, used in those cases where people may be required for the performance of work. Equally common may be references to man-months or man-years. This definition of work content may apply whether or not the resources are flexible and whether or not the duration is resource dependent.
Given a duration d, and a quantity of undifferentiated resources q, the work content w of one activity may be defined by the three equivalent equations (instances of the common mathematical relation defined by Eq 1) as follows:
When the work required to complete one production unit may be accomplished by performing a collection of individual activities by a pool of undifferentiated resources, the work content w may be defined as the sum of the work content of n individual activities as follows:
In general, large complex bodies of work may require a mixture of differentiated resources in their performance, and even individual tasks may require resources from two or more distinct resource categories. The resources may include specific tools, pieces of equipment, and human labor categorized by skill (e.g. electrician or mechanic) or qualification.
In general, the quantity of resources required for the performance of work may be represented by vector where each element of the vector may represent the quantity of resources required within a single, distinct resource category. In some cases, the quantity of resources required for the performance of work may be divided into two or more vectors representing the separate allocation of shared and dedicated resources.
The Basis Work Content Vector (Wbasis) for one production unit may be defined to be a vector where each element represents the work content within the corresponding resource category as follows:
Given this definition, the Basis Work Content Vector (Wbasis) may contain only those resources which are directly associated with the performance of individual activities (Eq 15.2 & Eq 15.3). It may not contain and may not account for the quantity of resources associated with the completion of one production unit as a whole (rather than completion of individual tasks).
For example, completion of a major assembly may require the performance of hundreds of individual tasks by individuals within specific labor categories and each task may explicitly require other supporting resources (such as test equipment, cranes, or hand tools). These requirements may be contained within the Basis Work Content Vector.
At the same time, this assembly may require dedicated use of an assembly jig for the full duration of work performed by those individuals. There may be no basis for computing the work content associated with the assembly jig as the product of a quantity and duration. While the quantity required may be easily stated (quantity one) the duration required may depend entirely upon quantity of other resources provided and the way that the work is organized and managed. Simple application of Eq 15.2 may lead to an equally questionable result. If use of the jig is associated with every constituent task then the work content computed for the jig may be equal to one times the sum of all task durations. This value may have reasonable interpretation if the tasks are performed serially, one after the other (one jig multiplied by the net duration), but may have no reasonable interpretation when the tasks are organized and managed to be performed with some degree of concurrency or a parallelism (the real requirement for the jig will then be one jig multiplied by the resulting duration). (See also discussion of Resource Requirements, Allocation, and Usage).
The total work content W for one production unit may be computed as the sum of the elements within the Basis Work Content Vector as follows:
The Proportional Work Content Vector V for one production unit may be defined to be a vector, where each element represents the percentage of the total work content contained within the corresponding resource category (computed by dividing each element of the basis work content vector by the total work content (W) (Eq. 16)) as follows:
In later discussion of the detailed methods for production rate and capacity planning, the Proportional Work Content vector may be used to derive a Proportional Resource Vector and a Parametric Series of Resource Vectors.
The interval between start of production units, in the performance of repetitive work, may be the duration of time between start of successive production units.
The interval between finish of production units, in the performance of repetitive work, may be the duration of time between finish of success production units.
The production interval I, in the performance of repetitive work, may be synonymous with the interval between finish. In a steady state condition for production, the interval between start and the interval between finish may be constant and equal and may be used synonymously with production interval.
Production interval may be further qualified with key words and phrases such as actual production interval, target production interval, minimum production interval, maximum production interval, etc. that may be defined separately, as necessary.
The production rate R, in the performance of repetitive work, may be the ratio between the number of finished production units and the duration of time required for their completion. Production rate may be further qualified with key words and phrases such as actual production rate, target production rate, minimum production rate, and maximum production rate, that will be defined separately, as necessary.
In practice, the word rate may be most commonly used in discussions of production but it is sometimes problematic to represent rate as a useful ratio. To be useful, the timeframe for this ratio should be long enough to contain at least one completed production unit and preferably several. Moreover, production rate may have many equivalent forms that can only be compared by conversion to a common denominator (e.g. 1 unit per month is equivalent to 12 units per year). Worse, common time units may have inconsistent boundaries leading to mathematical discrepancies (4 units per month is equivalent to 48 units per year, but 1 unit per week is equivalent to 52 units per year).
Within this methodology and its associated equations and algorithms, production interval I may be a more useful parameter and will be used most often.
Given the previous definitions of production interval I and production rate R, the relationship between production interval I and production rate R may be given by three equivalent equations (instances of the common mathematical relation defined by Eq. 1) as follows:
Concurrent production may occur when, during the performance of repetitive work, two or more production units are simultaneously in work for some measurable period of time in their performance. In the following discussion,
The degree of concurrency, within the performance of repetitive work, may be the measure of how much of the work is performed concurrently.
Given the previous definitions of unit duration D, production interval I, and degree of concurrency C, the Parametric Model of Production Concurrency may be given by following three equivalent equations (instances of the common mathematical relation defined by Eq. 1):
The derivative forms of Eq. 19 may form a family of equations, as shown in
When values of both D and C are known, Eq. 19.2 may be used to compute the value of I. Moreover, if only D is known or C is known, this equation may define the functional relationship between I and the remaining free variable, as shown in the following derivative equations where DF and CF are known fixed values.
When values of both I and C are known, Eq. 19.3 may be used to compute the value of D. Moreover, if only D is known or C is known, this equation may define the functional relationship between I and the remaining free variable, as shown in the following derivative equations where IF and CF are known fixed values.
D=CF·I Eq. 19.3a
D=C·IF Eq. 19.3b
Given the previous definition of degree of production concurrency C, the degree of maximum production concurrency Kmax and the corresponding degree of minimum production concurrency, Kmin may be defined by the following.
Kmax=┌C┐, defined to be the least integer greater than or equal to C Eq. 20.1
Kmin=└C┘, defined to be the greatest integer less than or equal to C Eq. 20.2
Given any two values for unit duration D and production interval I, the degree of production concurrency C may yield a value which provides an intuitive measure of how much work is performed concurrently. Given any two values for unit duration D and production interval I, the degree of maximum production concurrency Kmax may yield a value which is an upper bound on how much work is performed concurrently, and correspondingly Kmin may be a lower bound on how much work is performed concurrently.
When, as illustrated in
When the degree of concurrency is less than or equal to 1 (C←1), no more than one production unit may be in work at any one time. In such cases, the resources applied to each production unit may be effectively dedicated to exactly one production unit at a time. When the degree of production concurrency is greater than 1 (C>1), then for at least some short period of time, more than one production unit may be in work. In such cases the resources applied to each production unit may be dedicated, shared, or a combination of both.
The degree of maximum concurrency Kmax may be used to determine the quantity of dedicated Category 1 resources required in a given production context. Specific details are provided below.
Unit duration D may be the duration of time required to complete one production unit, accomplished by the performance of a set of activities, making use of a set of resources. Unit duration D may be measured by the difference between the start time and the finish time of the set of activities required to complete one production unit. Duration may be measured in any conventional units, such as seconds, days, or years. However, use of a common fine granularity measure (such as seconds or minutes) may yield more accurate and more usable results than use of large granularity measures and fractional units (such as years and decimal parts). Unit duration may be further qualified with keywords and phrases such actual duration, target unit duration, predicted unit duration, estimated unit duration, minimum feasible unit duration, maximum unit duration, average unit duration, etc. that are defined separately, as necessary.
When the duration of time required to complete one production unit may be unaffected and cannot be controlled by sequencing the constituent activities, by supply resources, and by other factors, the unit duration may be said to be fixed.
When the duration of time required to complete one production unit may be affected and can be controlled by sequencing the constituent activities, by supply of resources, and by other factors, the unit duration may be said to be flexible.
The minimum unit duration (Dmin) may be the minimum duration of time required to complete one production unit, when all constraints have been applied and when all means to reduce that duration have been exercised including sequencing of the constituent activities and supply of additional resources. In general, the minimum unit duration may be conveniently computed by constructing a schedule where all required constraints are enforced and all flexible resources are modeled as “infinite”.
The maximum unit duration Dmax may be the maximum duration of time required to complete one production unit without introducing artificial gaps in the performance of work where no activity is underway. In general, the maximum unit duration may be conveniently computed by constructing a schedule where all required constraints are enforced and the activities are further constrained to be performed serially, without overlap. In cases where there are no extraordinary timing constraints, the maximum unit duration may be exactly the sum of the durations of the constituent activities.
Depending upon the nature of the work and the way that it is organized, the supply of resources may affect both unit duration and production interval. This application includes the following inter-related set of concepts, definitions, and formulae that together establish the mathematical foundation required to implement the methods of production rate and resource capacity planning:
Resource Dependent Production (Section 5.1);
Key Categories of Resource Requirements (Section 5.2);
Resource Dependent Production Interval (Section 5.3);
Resource Dependent Unit Duration (Section 5.4);
Shared Resources and Production Interdependence (Section 5.5); and
Concepts and Measures of Resource Utilization (Section 5.6).
All work may be accelerated by decreasing the interval of time between start of successive production units (or equivalently by increasing the production rate). However, as the production interval decreases to a value less than or equal to the unit duration, concurrency may be introduced into production operations requiring an increase in dedicated and shared resources. When the production interval (or equivalently the production rate) of some body of repetitive work is affected and can be controlled by the quantity of resources supplied, it may be said to have a resource dependent production interval.
Generally, all work may have a resource dependent production interval. There are some circumstances where key resources (such as number of aircraft, number of assembly tools, or number of classrooms) may be fixed and it may be infeasible to exercise flexibility by increasing or decreasing those assets.
Some work, by its very nature, requires specific fixed resources for its performance and there may be no benefit if more resources are available. An example is the crew for an airline flight. An international flight may require a primary crew of one pilot and one co-pilot plus a relief crew of one additional pilot and one additional co-pilot. If all four individuals are available, the flight may proceed. If even one individual is missing, the flight may be held up, but the duration of the flight may be unaffected by and cannot be reduced by supplying additional crew.
Other work, by its very nature, requires some minimum resources for its performance but its duration depends upon the quantity provided. An example is large scale aircraft assembly. Given a few individuals of specific skill codes (electricians, mechanics, etc.), work proceeds very slowly resulting in long unit duration. Given larger number of individuals within those skill codes, work proceeds more rapidly resulting in short unit duration.
When the unit duration of some body of repetitive work may be affected and can be controlled by the quantity of resources supplied, it may be said to have resource dependent unit duration.
When the production interval (or equivalently the production rate) of some body of repetitive work may be affected and may be controlled by the quantity of one category of resources available to dedicate to each production unit (such as assembly tooling), and when the unit duration may be affected and may be controlled by the quantity of a separate category of resources available to dedicate to each production unit (such as labor), production interval and unit duration may be effectively independent. In such cases, the quantity of resources in each category may be exercised separately to separately control production interval and unit duration.
When the production interval (or equivalently the production rate) of some body of repetitive work may be affected and may be controlled by the quantity of one category of resources available to dedicate to each production unit (such as assembly tooling), and when the unit duration may be affected and may be controlled by the quantity of a separate category of resources shared across multiple concurrent production units (such as labor), production interval and unit duration may be effectively interdependent. Changes in quantity of the shared resources may affect both unit duration and the minimum feasible production interval (or equivalently the maximum feasible production rate).
Production operations of any scale may present complex combinations of resource requirements, allocation, and usage. For example, in large scale assembly a single production unit may require exclusive, dedicated use of special tooling (e.g. jig or fixture) for the duration of time required to complete the production unit, yet the quantity available may have no direct effect on the duration. Instead, the quantity available may simply determine how many production units may proceed concurrently, which may fall in Category 1.
In this same context, a single production unit may require use of labor in order to perform the work, and the quantity available may have direct effect on the time required to complete the production unit by enabling concurrency within the work required to complete one production unit. Here there may be two sub-cases. In one case, labor may be divided into segregated pools, where each pool is assigned exclusively to a single production unit for the duration, which may fall in Category 2. In the other case, labor may be managed within a single pool and shared across all production units, which may fall in Category 3.
Division of resource requirements, allocation, and usage into such categories may be necessary for systematic rate and capacity planning. However, within a single operational setting, the quantities provided must satisfy certain mathematical relationships described below, and the inter-relationships between them. For example, the quantity of Category 1 resources required may determined by the equations provided in Section 5.3, while the duration in that equation may be determined by the quantity of Category 2 resources provided and the equations in section 5.4. In other circumstances, the equations provided in Section 5.3 may determine the necessary or target duration and the equations of Section 5.4 may be used to determine the necessary quantity of Category 2 resources. In the same operational setting, there may be resources of Category 3, subject to the relationships defined in Section 5.5, while the overall degree of concurrency may be determined by the equations in Section 5.3.
Resources of CategoryC 1 may comprise the following resources: (1) not-shared (and potentially not sharable) between production units; (2) with direct effect on concurrency between production units; and (3) with no effect on unit duration and degree of concurrency within the production unit.
Resources of CategoryC 2 may comprise the following resources: (1) not-shared (although potentially sharable) between production units; (2) with no direct effect on concurrency between production units; (3) with direct effect on unit duration, by enabling concurrency within work required to complete one production unit.
Resources of CategoryC 3 may comprise the following resources: (1) shared between production units; (2) with direct effect on the concurrency between production units, by enabling concurrent work on multiple production units; (3) with direct effect on unit duration, by enabling concurrency within work required to complete individual production units. Methods related to rate and capacity planning for shared resources, which fall under Category 3, will be addressed in a separate application.
The following discussion may only apply to work where the degree of concurrency of some body of repetitive work may be affected and may be controlled by the quantity of resources supplied (resource dependent production interval), and where the quantity available may be increased or decreased to satisfy production demands (flexible resources). This discussion may be applicable to work where the key resources are dedicated to individual production units (not shared) and have no direct effect on unit duration. This may be relevant to manufacturing that is dependent upon the availability of dedicated tooling or machine tools, training that is dependent upon dedicated classrooms, flight operations that is dependent upon pilots or aircraft, etc.
Recall that Eq. 19.1 defines the degree of concurrency C as the ratio between unit duration D and production interval I. Also recall that Eq. 20.1 defines the degree of maximum production concurrency Kmax as simply the least integer greater than or equal to C. In practice the quantity of dedicated Category 1 resources supplied for the performance of some repetitive work must be greater than or equal to Kmax. If fewer resources are available, less work will be able to be performed concurrently, and target production rates (or equivalently interval) may not be met. Hence the relationship between the quantity of resources available Q1 and the three parameters degree of concurrency, unit duration, and production interval is defined by the following:
The following discussion may only apply to work where the unit duration of some body of repetitive work may be affected and may be controlled by the quantity of dedicated resources supplied (resource dependent duration) and where the quantity available may be increased or decreased to satisfy production demands (flexible resources). This may be most applicable to work which may be decomposed into a large number of individual activities which may be flexibly rearranged to take advantage of the availability of the dedicated Category 2 resources. This may be relevant to large scale assembly that is dependent upon the availability of a labor pool of flexible size, maintenance that is dependent upon a labor pool of flexible size, or cleaning service that is dependent upon a labor pool of flexible size, etc.
Consider a case where the work required to complete one production unit has been quantified as 210 labor-hours. It is imaginable that this work might be complete by 1 person working 210 hours in duration, 2 people working 105 hours, 3 people working 70 hours, 5 people working 42 hours, 7 people working 30 hours, or other combinations where the product of the number of people and the unit duration, measured in hours, yields 210. Yet it is equally clear, because of physical constraints on the performance of work, that duration and resources may never be perfectly exchanged one for the other.
When the work to be performed is accomplished by performing a collection of individual activities there are likely to be constraints on the performance of the individual activities. Without elaborating on all of the possibilities, assume at a minimum that the constituent tasks have documented resource requirements and may be subject to inter-task precedence constraints.
If one activity A is constrained to occur before another activity B, then it may be prohibited for B to occur before A or to be performed concurrent with A even for some short period of time. The net effect may be that the effective duration of performing activities A and B is at least the duration of A plus the duration of B. If the work required to complete one production unit is accomplished by performing a collection of individual activities which are subject to some specified precedence constraints, then there may be some minimum duration for that work that results from enforcing those constraints. If a collection of activities is subject to precedence constraints, then the minimum duration for that work may not be less than the duration of the critical path (computed using conventional algorithms).
If the work required to complete one production unit is accomplished by performing a collection of individual activities it is likely that some activities themselves may have a minimum resource requirement and cannot be performed unless that minimum quantity of resources is available.
Eq. 13.3 defines the work content w for one activity as the product of unit duration d and quantity of resources q. Eq. 14.1 further refines that definition for those cases where the work to be performed is accomplished by a collection of individual activities, each of which has a specified duration and quantity of resources required.
Using these equations as a guide, the functional relationship between Resource Availability and Unit Duration may be clear and simple. For a body of work with fixed work content W, the unit duration D may be decreased by increasing the quantity of resources provided Q.
While Eq. 13 may be commonly used in industry to perform rate and capacity planning, the actual relationship between resource availability and unit duration may be more complex. Use of these equations may lead to erroneous results, which then must be adjusted based upon actual operational performance. These equations may be inadequate because unit duration may be affected by the constraints between the constituent activities, the minimum feasible duration, per activity minimum resource requirements, the degree of concurrency between activities, and other factors.
A more general, parametric equation is required which can be instantiated with parametric values derived from analytic studies and empirical data which take these effects into consideration. Using Eqs. 1, 2, and 13 as a basis, the simplest parametric formulae that relate Category 2 resource availability (Q2) to unit duration (D), given fixed work content, comprises the following pair of equations:
Work that is composed of many small, loosely constrained activities may fit this equation well, while work that is compose of only a few, tightly constrained activities may fit this equation poorly.
Methods for estimating values for the parameters a, b, and c were provided in Section 2. Methods for performing the necessary empirical trials will be discussed below. Reflection on Eq 22.1 and
Resource utilization may be measured as the percentage of provided resources that are used in the performance of work. It is generally computed as a ratio where the numerator is the quantity of resources used and the denominator is the quantity of resources provided and then presented as a decimal, fraction, or percentage.
As discussed above, it may be difficult to relate use of Category 1 resources to work content or work accomplished. Nevertheless the utilization of Category 1 resources may be easily determined by consideration of concurrency between production units.
For repetitive production of a body of work with production interval I and unit duration D, the degree of concurrency C may be an average measure of how many production units are concurrently in work. At the same time Kmax may be the minimum number of Category 1 resources required to sustain the target rate and production interval. Assuming that the quantity of Category 1 resources provided Q1 is equal to Kmax, the maximum utilization of Category 1 resources U1 may be determined by the following:
The resource content (where appropriate, also referred to as labor content) over some duration of time d as performed by a dedicated pool of resources may be simply the product of the quantity of resources provided Q and the duration of time d, as defined in the following:
L=Q·d Eq. 24
Based upon this definition, resource utilization over some period of time may be defined as the ratio of total work content accomplished T to resource content provided L, as defined in the following:
Hence for a given allocation of Category 2 resources the following may apply:
But since unit duration D may be determined by a function of the quantity of resources provided, utilization of a given quantity of resources may be in fact determine solely by the nature of the work and the quantity of resources provided. Making use of Eq. 22 for a single production unit with a dedicated quantity of Category 2 resources Q2, the net labor content L over the duration of one production unit can be determined using the following equation (as parameterized by a, b, and c):
Hence the corresponding resource utilization for a given quantity of Category 2 resources (Q2) may be estimated by:
The example questions first introduced in Section 2 can now be more precisely stated and expanded to include additional, naturally related, questions as follows:
In the following sections, MethodM 1 may be used to select the appropriate supporting method based upon information that is known, and the operational question to be answered. Method 2 may address questions Q1, Q2, and Q3. Method 3 may address questions Q4 and Q5. Method 4 may address Questions Q6 and Q7. Method 5 may define a process for creating a parametric model of unit duration. Method 6 may define a process for creating a family of quantized resource vectors. Method 7 may define a process for creating a work content vector and for determining total work content.
Successful use of the defined methods may require use of computerized scheduling software and construction of the necessary resource models, activity models, and production models. It may also require construction of schedules using the computerized software, analysis and interpretation of the results, etc.
A skilled practitioner in the art of production rate and resource capacity planning will readily recognize that one or more embodiments of the methods disclosed herein may provide simple systematic means to solve problems which previously may only have been solved with ad hoc, trial and error methods.
The below methods are presented as numbered steps to be performed in order, except as otherwise specified (e.g. use method x, or go to step y). In this form, they may be reasonably implemented as computer programs or rendered as flowcharts, paper workbooks or computerized spreadsheets. In other embodiments, derivative implementations of these methods may be utilized.
The below methods require construction of schedules, based upon input resource models, activity models, and production models. For the most part, any computerized scheduling system may be sufficient, but the preferred implementation may utilize an optimizing scheduler so that the resulting production plans generally minimize unit duration, maximize production rate, and minimize required resources. An optimizing scheduler, as described in U.S. Pat. No. 5,890,134 which is hereby incorporated by reference, may satisfy both of these requirements.
It should be recognized that derivative forms of the below methods, in addition to other types of methods, may be used which incorporate alternative combinations of the below methods. Methods related to rate and capacity planning for shared resources of type Category 3 will be covered in a separate patent application.
A flow chart of Method 1 is shown in
A flow chart of Method 2 is shown in
A flow chart of Method 2.1 is shown in
A flow chart of Method 2.2 is shown in
A flow chart of Method 2.3 is shown in
A flow chart of Method 3 is shown in
A flow chart of Method 3.1 is shown in
A flow chart of Method 3.2 is shown in
A flow chart of Method 4 is shown in
A flow chart of Method 4.1 is shown in
A flow chart of Method 4.2 is shown in
A flow chart of Method 5 is shown in
A flow chart of Method 6 is shown in
A flow chart of Method 7 is shown in
where di=the duration of task i and
where rji=the quantity of resource category j required by task i
Rate and Capacity planning comes in many forms, depending upon the circumstance and what information is known and what information is desired. The defined methods have been designed to support virtually every analysis that is mathematically feasible using Method 1 as a starting point. A planner, skilled in the art of rate and capacity planning, may use the defined methods flexibly, and possibly in different order, according to circumstance.
Two examples are provided below along with the background data necessary to illustrate use of the defined methods. In these examples, suppose that a business has introduced a new product that requires manufacture and that the rate of production must be balanced against market demands and manufacturing capacity. Each example will state what information is known and fixed, will identify what information is desired in the form of one or more questions, and will trace the steps required to answer those questions using the defined methods.
To establish the background for this example and to facilitate quick illustration of the defined methods, consider the data provided in the Table of
Using this data, 12 schedules have been constructed using the corresponding parametric resource vectors along with one additional schedule constructed using infinite capacity. The resource quantity and resulting unit duration are tabulated as shown in the Table of
The coefficients of the Parametric Model of Unit Duration, as determined by Method 5, are shown in the Table of
The functional relationship between the quantity of Category 2 resources provided and the resulting unit duration as determined by the Parametric Model of Unit Duration, with an overlay of the empirical data from the Table of
Beginning with Method 1, make use of Method 2 and then Method 2.2 to determine the necessary unit duration. According to Method 2.2 determine the unit duration as a result of performing the below recited steps. Given fixed or target values for the quantity of dedicated Category 1 resources Q1=2 and production interval I=8, determine the maximum acceptable unit duration D.
(where working days consist of two 7.5 hours shifts)
Continuing with Step 44 of Method 2.2 make use of Method 3 to determine the quantity of Category 2 resources required per unit. According to Step 1 of Method 3, determine coefficients of the Parametric Model of Unit Duration using Method 5. In the context of Method 5, assume that the Parametric Series of Resource Vectors has been constructed as shown in the Table of
According to Method 5, continue with Step 6 as follows:
Returning to Method 3, skip Step 2, continue with Step 3 and use Method 3.2 to determine the quantity of Category 2 resources required per unit. According to Method 3.2 determine the quantity of Category 2 resources required per unit as a result of performing the following step. Given a target unit duration D, determine quantity of dedicated resources Q2 required as follows:
Finally, in answer to the initial questions:
Beginning with Method 1 use Method 2, and then Method 2.3 to determine the minimum feasible unit duration. According to Method 2.3 determine the minimum feasible unit duration as a result of performing the following steps. Given fixed or target values for the quantity of dedicated Category 1 resources Q1 and unit duration D, determine the minimum acceptable production interval I using the following steps:
According to Step 2 of Method 2.3, use Method 3 to determine the minimum feasible unit duration. According to Method 3 determine the minimum feasible unit duration as a result of performing the following steps:
Since the coefficients of the Parametric Model of Unit Duration are known from provided background data and the analysis performed in example 1, continue the process with Step 2 of Method 3, where Method 3.1 is used to determine the minimum unit duration. According to Method 3.1 and the background data presented in the previous section, estimate the minimum feasible unit duration as a result of performing the following step. Given a quantity of dedicated resources Q2, determine the minimum unit duration D that can be achieved.
Use Method 4 to determine the effective Category 1 and Category 2 resource utilization, first using Method 4.1 and then Method 4.2. According to Method 4.1, determine the utilization of Category 1 resources as a result of performing the following steps. Determine utilization of dedicated Category 1 resources.
According to Method 4.2, determine the utilization of Category 22 resources as a result of performing the following steps. Since quantity, duration, and total work content have been previously determined, Step 6 is effectively the starting point. Determine utilization of dedicated Category 2 resources.
Finally in answer to the initial questions:
A production interval of 6 days between units can be sustained with the provided Category 1 and Category 2 resources. Utilization of Category 1 resources is nearly perfect at 99.47% while utilization of Category 2 resources is only 16.55%. This is largely because a few tasks require a large number of individuals, and staffing to satisfy the requirements of those few tasks creates inefficiency. (See Table 1).
It should be understood, of course, that the foregoing relates to exemplary embodiments of the invention and that modifications may be made without departing from the spirit and scope of the invention as set forth in the following claims.
This application is a utility application claiming priority to provisional U.S. application Ser. No. 60/734,905, titled System And Method For Rate And Capacity Planning, filed on Nov. 8, 2005.