The present invention relates to the drilling, monitoring, placement and pre-tensioning of micropiles configured for use and deployment in an undersea environment.
In that regard, micropiles have been employed historically to withstand compressive and tensile loads in terrestial contexts. Where it is desired to secure an anchor to a seafloor bed, conventional approaches to appropriate design and proper application of an anchor or foundation system on a seafloor site are often based on expensive and time consuming geotechnical survey and analyses of survey results of the seafloor on which the anchor or foundation will be installed.
Also, without pre-stressing, a conventional marine micropile anchor installed on a seafloor, lake bed or river bed may be subjected to fatigue, corrosion, cracking, uplift and an inability to deal with lateral loading. Other conventional anchor systems used in a marine environment do not incorporate pre-stressed elements and thus may be subject to these same problems. The present systems and methodologies provide beneficial improvements to the prior art systems.
A significant portion of the geotechnical survey effort required for conventional approaches to planning seafloor anchors can be eliminated by measuring seabed properties in real-time, in-situ as part of the anchoring or foundation system micropile installation process. The system and method of the present application differs from what currently exists. During micropile anchor installation as described herein, seafloor properties may be measured and adjusted for in real-time during the drilling process, eliminating the need for geotechnical surveys in advance of the installation. A considerable amount of time and expense is required for current micropile anchor planning and installation and this time and expense may be reduced dramatically or eliminated with the system and method of the present disclosure. Further, the real-time measurement of seafloor properties during installation of anchors ensures the best anchor performance at a fraction of the time and expense.
A typical candidate anchoring site may have relatively homogeneous rock or other competent material covered with a sand/mud overburden of moderate thickness. In these cases, the holding capacity of a micropile may vary linearly with the embedment depth in the rock. Measured drilling parameters such as torque, push and rate of advance may be used to determine the transition point between sediment and rock. Therefore, the required drilling depth can be determined very accurately to maximize installation efficiency. Similarly, in the case where the overburden is extensive, additional micropile lengths can be installed so the full required embedment depth into competent material is met.
In addition, the drilling rate of advance in rock or any other material can be measured for a given set of conditions and yield information regarding seabed strength. Significant variations in the strength of the seabed could be identified during drilling and adjustments to the operations such as varying the total micropile embedment length to obtain the required holding capacity could be made. Measure-while-drilling modeling and simulation software will allow for installation planning that only depends on general seafloor parameters, not on detailed geotechnical survey results. Various seafloor parameters for modeling and simulation may dictate corresponding actions for micropile anchor installation planning. Sensor input to the measure-while-drilling software will determine the corresponding real-time control during drilling to install the micropile anchor.
A possible exemplary process for making the system of the present disclosure may be as follows: measure-while-drilling modeling and simulation software may be coded in cooperation with subject matter experts specifying the logic for the program. The suite of down-hole sensors may be selected to provide input to the real-time monitoring software that would be coded to effect adjustments to the drilling control accordingly. The modeling and simulation planning software would be optional to the real-time drilling sensors and monitoring software. It is not intended or required that the planning software must be integrated with the real time monitoring software but it is anticipated that such integration may be possible within the scope of the present disclosure.
The system of the present disclosure may be further operated in the following exemplary fashion: measure-while-drilling modeling and simulation software may allow for drilled and grouted seafloor micropile anchor installation planning. Micropile anchor installation may be controlled by the use of sensors placed within the hole being drilled and/or on the drill itself that measure real-time parameters of the drilling progress and the calculated drilling adjustments required to determine the required anchor holding capacity. Once installed, micropile strength also can be confirmed or verified as part of the installation process.
Pre-stressing the micropiles used to secure a sea anchor or marine mooring to the bed of a body of water may help to limit or restrict structural movement of the anchor due to anchor micropile elongation caused by cyclic and dynamic loads. Micropiles used for such anchors are typically made of steel that are driven into a position within the bed to provide resistance to movement of the anchor. When the anchor is subjected to forces being placed on the anchor by an object or structure that is connected to the anchor, these forces are transmitted to the micropiles, which can deform the micropiles or possibly shift them. This may compromise the integrity of the anchor, making it more likely to fail, or may permit an undesirable movement or displacement of the object or structure secured to the anchor.
In the context of the present application, pre-stressing means the intentional creation of permanent stresses in a structure for the purpose of improving the structure's performance under various service conditions. For marine applications of micropiles, it is desirable that each micropile in an anchor or other bottom fixing assembly be load tested to verify its capacity and that load be “locked in” to maintain a pre-stress to counteract the stresses resulting from the applied vertical and/or lateral mooring load to the assembly. Pre-stressing will help limit or restrict structural movement caused by cyclic and dynamic loads. Micropile pre-stressing for the purpose of achieving an anchor system capable of resisting vertical and lateral mooring loads is innovative and un-proven in the sub-sea environment; however, it is vital if micropiles are to be used efficiently for mooring systems.
Pre-stressing may provide the following benefits for a marine grouted micropile anchor system:
The system and method of the present disclosure differs from what currently exists. This system and method represent a new capability for micropiles or micropiles used in a marine environment.
A conventional non-pre-stressed system can allow movement of individual micropiles, which will lead to premature failure of the anchor and also will not help the anchor deal with any loads other than pure tension loads. The dynamic forces exerted on objects and structures secured to anchors in a marine environment are likely if not certain to place loads other than pure tension loads on the anchors to which they may be secured. Pre-stressing each individual micropile used as part of a sea anchor and locking that stress or load into each individual micropile will help maintain the compressive stress in each micropile and will serve to limit or restrict structural movement of the micropile and therefore the anchor.
The system and method of the present disclosure may incorporate the following elements, even though it is not intended to limit the scope of the present disclosure to just this set of exemplary elements: connecting a jacking or pre-stressing system to an anchor micropile; remotely operating the jacking system; applying a tension load to the micropile in increments with the jacking system while measuring the load and any elongation of the micropile; upon reaching a specified load or loading condition, lock load at that level; and disconnecting the jacking system from the micropile after locking the load and applying a similar process to any remaining unstressed micropiles.
The pre-tensioning device is attached to micropile. The pre-tension load is applied to the micropile. The pre-tensioned micropile is locked with a locking device. The system is moved to the next micropile. As pre-tension is applied, the micropile elongation and load will be measured using remote system controller until desired load is reached.
The most common and accurate way to pre-stress an anchor is direct pull, which may use a hydraulic jack that connects directly either at the anchor head or at a pulling head attached to the pre-stressing steel. Hydraulic jacks capable of developing 100 percent of the specified minimum tensile strength (SMTS) of available micropiles are available and can be adapted for sub-sea use. The jack frame typically bears against a steel plate while the hydraulic jack transfers a direct tension load to the anchor. When the pre-stress load is reached, a nut or other locking device may be turned against the anchor bearing plate, and the load from the jack may be released. The locking device or nut prevents the steel from relaxing back to its original length to maintain the pre-tension. Additional elongation in the anchor rod only occurs if the applied load exceeds the pre-stress load. The pre-stress load is typically 133% to 150% of the design load to allow for minor load relaxation, which may typically occur once the jack load is released.
A pressure gauge and dial gauge are used for terrestrial applications, but sub-sea pre-stressing may require a marinized load cell and a linear displacement transducer if the jacking device is to be controlled remotely. A remotely operated micropile pre-stressing system according to the present disclosure for use in a sub-sea setting may include the direct pull apparatus or jacking device, a load lock-off system, load-displacement measurement system and the mechanism and controller required to pre-stress multiple micropiles on a single template or anchor.
It is anticipated that commercially available conventional components may be marinized and integrated into the system of the present disclosure. A remote control and underwater operation capability will need to be developed for these conventional components to permit the system and method of the present disclosure to operate as described herein. Algorithms to account for different depths of water where the sea anchors may be positioned will need to be developed to ensure that the load measured accurately reflect the load that a micropile is being subjected to.
Thus, in one embodiment, a system is provided for more effectively deploying an undersea anchor, where the system comprises a controller programmed and configured to monitor the drilling and grouting of micropiles in real-time and compare the metrics detected by such monitoring against pre-determined design criteria to substantially ensure micropile deployment meets the design criteria upon completion of the drilling and grouting process during micropile deployment. In some embodiments, the system further comprises means for pre-tensioning the micropiles after deployment, where the controller is programmed and configured to determine whether the pre-tensioning process conforms to design criteria.
The aforementioned objects and advantages of the present invention, as well as additional objects and advantages thereof, will be more fully understood hereinafter as a result of a detailed description of a preferred embodiment when taken in conjunction with the following drawings in which:
By way of example, and referring to
The micropiles are secured to the bearing plate mechanically via a nut and washer arrangement 20, although other mechanical means may be employed. Each micropile is contemplated to comprise a length of threaded rod 22, one or more couplings 24 to join the rods 22 together to extend the length of the micropile as needed for depth of deployment, and a drill bit 26 at the distal tip of the micropile for creating the bore into which the micropile is deployed. Referring to
In the example shown in
With reference to
Referring to
It is contemplated that the systems and methods of the present invention may be applied to terrestrial micropile and anchor construction. There may be land-based micropile and anchor construction locations that do not permit the control and operation systems to be positioned at the anchor site. The systems of the present invention may permit the control of the jacking system to be handled remotely, whether the anchor location is underwater or in a difficult location above water. It is anticipated that embodiments of the present invention may preferably have a robust testing and calibration capability to ensure that micropiles are subjected to accurately measured loads.
Persons of ordinary skill in the art may appreciate that numerous design configurations may be possible to enjoy the functional benefits of the inventive systems. Thus, given the wide variety of configurations and arrangements of embodiments of the present invention the scope of the invention is reflected by the breadth of the claims below rather than narrowed by the embodiments described above.
The present application claims priority from provisional application Ser. Nos. 61/736,477 filed on Dec. 12, 2012, and 61/755,401 filed on Jan. 22, 2013, both of which are incorporated herein in their entirety by reference.
Number | Date | Country | |
---|---|---|---|
61736477 | Dec 2012 | US | |
61755401 | Jan 2013 | US |