This system is directed to a system tied to a construction site, provides for multiple party information verifications, and creates an immutable record for management and verification of project initiation associated with workers, constructions material and the construction process and stores the commencement and completion information on an immutable and/or distributed ledger.
For any construction project, there is are systematic and logical steps processes and materials that need to be in place for a project to initiate and be successful. Workers, materials, and the other individuals that are included in a successful project include approved architectural design, approved construction materials, availability of licensed, legal, qualified, and experienced workers or laborers, permits, insurance, financing, and inspections. Architectural designs can include a bill of materials representing construction materials to be used for the construction project that can be sent to suppliers or manufacturers so that the cost of the bill or materials is known prior to ordering the materials and finalizing the architectural plans. Each component of the materials can include a warranty that is from the manufacturer, distributor, installer, or any combination.
One disadvantage of the current construction process is the lack of accountability, verification and reliability of information related to the project commencement such as materials used, tasks performed and workers that perform tasks. These items, when improperly executed, can affect the validity of insurance, increase risks, increase costs, and claims and therefore increase premiums. Further, the inability to verify correct materials, installation, workers, and other factors can results in losses, mistakes, injury, costs, and insurance claims. This weakness in the current process and system negatively impact the project and when occurring at commencement can flow throughout the project.
Building codes also impact the construction project and are a set of rules that specify the standards for a construction project. Codes impact the architectural design, constructions materials, worker's license and experience and the construction process. A building code may require that building materials be installed in accordance with manufacturer's specifications and warranty regulations. Failure to follow these requirements can results in delays and error throughout the project. Proper planning and information managed prior to commencement can ensure regulatory code compliance and proper installation according to the specifications. Historically, tracking these initial tasks and materials can be difficult because of a lack of third-party verifications and a system that is tied to the construction site. Because current systems have no established verification processes mistakes, error and even fraud, can occur without detecting until much later in the project, if at all.
It would be an advantage to have a system that can receive designs from architects, labor resources, regulatory compliance, project locations, environmental conditions and other information that can provide for approvals to initiate the project and deploy resources to the project. For example, deploying workers prematurely can be costly and wasteful. It would be an advantage to have a system that can determine if commencement requirements are met prior the construction process initiation and provide notifications if there is a risk of non-compliance or delays in the project. It would be an advantage to have a system that can receive commencement information, provide such information to the construction site and associate the commencement information with the physical site.
Verification that workers are available and authorized, proper materials are delivered and used and installation procedures are followed is important because suppliers and contractors are known to substitute lesser quality materials, out of code materials, unlicensed or unauthorized workers, or take short cuts for financial reasons. Further, without third party verifications, inspectors can provide false or misleading information to sign off on a project when in fact the inspection preformed and that recorded are not consistent. When an inspection is preformed, the record of the inception is not consistently maintained. Recordation ranges from physical forms to smart phone images to proprietary inspection system such as a computerized system offered by Inspection Support Network®. The data is stored and maintained by the system provider so that data security is dependent upon the system provider. It would be advantageous to have a permanent verified record of code compliance that can be referenced by third parties prior, during, and after commencement of the construction project and for future verification of aspects of the project.
There have been since attempts to improve the construction process such as U.S. Pat. No. 7,898,403 that is directed to a method and system for detecting construction equipment process failures. A database is populated from information from a third-party source and a process failure report is provided for processes that are outside a norm assigned to the construction equipment asset. U.S. Pat. No. 7,031,930 is directed to a method and system for managing complex construction projects by monitoring subcontractors in real time, against a system after commencement of the project. U.S. Pat. No. 8,004,397 is directed to a mountable reporting source comprising a controller coupled with an interrogating component configured for automatically receiving an identifier which is unique to an asset having a position determining component. Again, this is directed to the construction process itself, not management, and verification of code compliance.
To ensure that proper materials, installation, and workers are ready for use, verifications of materials, confirmation of deliveries at construction sites, and obtaining sign offs are beneficial. Further, deliveries may be made regardless of weather conditions, resulting in some materials being subject to rain and other weather conditions that may negatively affect the materials that are delivered. This can result in legacy issues for warranties and quality. At large sites, errors may occur with deliveries to the wrong location or wrong contractor as different trades may use common materials. When materials are delivered, installed, or otherwise used in weather conditions that are contrary to the manufacturer specifications, significant damage and liability can be introduced to the construction project. For example, when moisture gets trapped behind the building material stucco, the moisture can produce “stucco tears,” which result in discoloration of the stucco beneath windows or cause the formation of mold and mildew, which can escalate into an infestation of black mold. Manufacturers have certain requirements for stucco and its installation and can require certain humidity ranges and temperature ranges. It would be advantageous for a system to record the weather of the installation for this and other materials.
In accordance with an exemplary embodiment, a computerized system for commencement of a construction project comprising is provided that can include a kiosk having a kiosk computer readable medium and configured to be affixed to a construction site prior to an initiation of a construction project, the kiosk in communication with a distributed ledger; a set of non-transitory computer readable instructions included in the kiosk computer readable medium for: creating a commencement record, detecting a physical location of the kiosk, determining then confirming if the physical location of the kiosk is within a construction site boundary included in a building information model stored on the kiosk computer readable medium, appending the commencement record with a physical location verification data representing that the kiosk is physically present at the construction site, determining if construction materials needed for the construction project are available according to a materials information received from a supplier computer system and a bill of materials, appending the commencement record with a materials verification data representing that the construction materials are available for the construction project, determining if a labor force needed for the construction project is available from a labor information received from a labor supplier computer system, appending the commencement record with a labor verification data representing that the labor force is available and properly authorized for the construction project, determining if sufficient insurance coverage is available from insurance information received from an insurance provider computer system, appending the commencement record with an insurance verification data representing that sufficient insurance is available for the construction project, determining if a sufficient financial commitment exists from a financing information received from a financing company computer system, appending the commencement record with a financial verification data representing that sufficient financing is available for the construction project, creating a completion record; retrieving worker activity information from the kiosk computer readable medium, determining if all worker tasks are completed and appending the completion record with a worker activity completion data representing that all worker tasks are completed, determining that no liens are associated with the construction project and that financing is complete for the construction project from the financing information received from the financing company, appending the completion record with a financing complete verification data representing that no liens are associated with the construction project; determining if the insurance coverage is closed from the insurance information received from the insurance provider computer system, appending the completion record with an insurance closed data representing that the insurance coverage on the construction project is closed, receiving a set of on-site inspection information at the kiosk representing that the construction site has passed an internal inspection from an internal inspector, appending the completion record with the set of on-site inspection information, receiving a permit of occupancy from a regulatory entity computer system representing that the construction project has passed an external inspection from an external inspector and is in compliance with a set of applicable codes and regulations associated with the construction project, appending the completion record with the permit of occupancy and, storing the commencement record and completion record on the distributed ledger.
The kiosk can be configured to be removed from the construction site after the completion record has been stored on the distributed ledger, can include a display and the set of non-transitory computer readable instructions include instructions for receiving a construction project schedule from the distributed ledger and displaying the constructions project schedule at the physical location of the construction site. A soil moisture sensor can be included and the set of non-transitory computer readable instructions include instructions for detecting an actual soil moisture value, determining if the actual soil moisture value is above a minimal soil moisture value and appending the commencement record with the actual soil moisture value The system can include a temperature sensor in communications with the kiosk; a minimal temperature value associated with the construction materials; and, the set of non-transitory computer readable instructions include instructions for detecting an ambient temperature, determining if the ambient temperature is above the minimal temperature value and appending the commencement record with the ambient temperature.
The set of non-transitory computer readable instructions can include instructions for determining if the construction materials are scheduled to be delivered in advance of an installation worker. Insurance coverage information can include an insurance binder stored on the kiosk computer readable medium. Insurance closed data can represent that construction insurance is closed, worker compensation insurance is closed, an owner of the construction project has secured property and casualty insurance, no gap in insurance are present, or any combination thereof.
The financing complete verification data can represent a termination of a construction loan from a first financing company and the securing of a permanent loan associated with the construction project from a second financing company. The set of non-transitory computer readable instructions can include instruction for receiving a set of regulatory requirements from the regulatory entity computer system and determining if the set of regulatory requirements are satisfied. The set of non-transitory computer readable instructions include instructions for receiving a building permit from a regulatory entity and displaying the building permit on a display included on the kiosk. The set of non-transitory computer readable instructions can include instructions for receiving a set of inspection information entered into the kiosk by the inspector and representing that a physical inspection of the construction site has occurred and appending the commencement record with an inspection data representing that the construction site has passed an inspection. The set of inspection information can represent a physical inspection of the construction site prior to a set of construction stages taken from a group of commencement requirements, excavation stage, foundation stage, drain installation, insulation installation, roof construction and completion.
The computerized system for commencement of a construction project comprising can include a unique identifier disposed at a construction site associated with the constriction project, a kiosk adapted to be uniquely and physically attached to a construction site prior an initiation of the construction project, removed from the construction site upon receipt of a certificate of occupancy and in communications with a distributed ledger; a kiosk computer readable medium included in the kiosk; a building information model stored on a computer readable medium included in the kiosk; a set of non-transitory computer readable instructions included in the computer readable medium for: determining if a physical location of the kiosk is within a construction site area, creating a commencement record if the kiosk is within the construction site area; detecting a set of construction materials physically delivered to the construction site, determining if the set of construction materials are a complete set for a stage of the construction project according to the building information model, appending the commencement record with a material data representing that a complete set of materials are available at the construction site for the stage of the construction project, detecting a worker physically present at the construction site, determining if the worker is authorized to perform an installation action directed to the set of construction materials, appending the commencement record with an installation action data representing that the worker is authorized to perform the installation action, storing the commencement record on the distributed ledger, determining when the installation action is completed; and, whereas the kiosk is configured to only be removed from the construction site after the installation action has been is completed.
The set of non-transitory computer readable instructions can include instructions for determining if insurance coverage is available according to the building information model and the commencement record, determining if insurance coverage is available according to a set of insurance information received from an insurance computer system, determining if sufficient financing is available according to the building information model and the commencement record, determining if sufficient financing is available according to a set of financial information received from a financing computer system, creating a completion record according to receiving a permit of occupancy from a regulatory entity and storing the permit of occupancy and completion record on the distributed ledger. The system can include a wearable device uniquely associated with the worker and the set of non-transitory computer readable instructions include instructions for tracking a movement of the worker according to the wearable device. The system can include a tracking tag attached to an item in the set of construction materials configured to be detected by the kiosk when the item is within a predetermined distance of the kiosk. The set of non-transitory computer readable instructions can include instructions for requesting a certificate of occupancy from a regulatory computer system, receiving the certificate of occupancy and displaying the certificate of occupancy on a display included in the kiosk, receiving inspection information from an inspector representing completion of the construction project and regulatory compliance and transmitting the inspection information to the regulatory computer system.
A computerized system for commencement of a construction project comprising can include a kiosk configured to be affixed to a construction site prior to the commencement of the construction project and removed from the construction site upon completion of the construction project, the kiosk is in communications with a distributed ledger; a unique identifier affixed to the construction site readable by a sensor on the kiosk to associate the kiosk with a physical location associated with the construction site, a set of non-transitory computer readable instructions included in the kiosk for: retrieving a building information model from the distributed ledger, determining if a physically location of the kiosk is within the construction site, creating a commencement record, wherein the physically location is included in the commencement record, detecting an actual set of construction materials physically present at the construction site, determining if the actual set of construction materials matches a design set of construction materials, creating a material data if the actual set of construction materials matches the design set of construction materials, appending the material data to the commencement record, detecting a worker physically present at the construction site, determining if the worker is authorized to perform an installation action directed to the set of actual construction materials, appending the commencement record with an installation action data representing that the worker is present at the construction site and authorized to perform the installation action, creating a completion record, retrieving worker activity information from the kiosk, determining if all worker tasks are completed and appending the completion record with a worker activity completion data representing that all worker tasks are completed, determining that financing is complete for the construction project from a financing information received from a financing company, appending the completion record with a financing complete verification data representing that financing is complete for the construction project, receiving a permit of occupancy from a regulatory entity computer system representing that the construction project has passed an external inspection from an external inspector and is in compliance with a set of applicable codes and regulations associated with the construction project, appending the completion record with the permit of occupancy and, storing the commencement record and completion record on the distributed ledger.
The set of non-transitory computer readable instructions can include instructions for detecting when the installation action is completed, creating a completion record representing that the installation action is completed and transmitting completion record to the regulatory computer system and transmitting a kiosk removal request to a project manager when the completion record is stored on the distributed ledger.
Systems at nearby construction sites may be interconnected using image capture devices, such as still cameras or video cameras, to provide security not only to the site on which it is stationed, but nearby sites as well. The processing of images from the multiple interconnected systems may be performed via processing logic to identify security issues.
A system utilizing biometrics for verification of actual workers on the construction site to correspond with professional licenses and work certifications for verified payroll and insurance coverage would optimize processes and ensure coverage. Onsite verification of processes, inspections, completions and deliveries with automated adjustments and notifications with confirmation would ensure increased productivity. Further such a system would improve efficiency as well as optimize cost savings, especially if information is accessible in real time at the construction site. Real time construction plans with corresponding training and construction manual tracking and management would improve quality control and efficiency that rarely exist today.
Automated verification of quantities, quality, and correct product deliveries along with after delivery tracking of materials with accountability is seldom used. Designated delivery areas with geofenced control and tracking of materials once delivered would help prevent loss. Confirmation of products integrated at a construction site provides transparency regarding sourcing, warranties, as well as future reference during the structure and individual products life of use.
The system seeks to identify all individuals entering or leaving the construction site and persistently records this information in a storage, such as in a database. Such records may be useful in a number of different contexts. The biometric-based identification device may be a camera or other image capture device. Facial recognition may be performed on the captured facial image to attempt to identify the individual. Alternative biometric-based identification devices, such as voice recognition systems, retinal scans, fingerprint scanners, hand scanners, voice print devices and the like may be utilized in the alternative or in addition to other biometric devices. As a last resort, the computing logic may allow authorized individuals to manually enter the presence of another authorized individual.
The system may record the date and time of events such as the arrival and departure of individuals, supplies, third parties, inspections, and the like to and from the construction site. The system may also record the date and current weather conditions. The weather information may be used to modify the schedule for workers so that workers are not working during inclement weather and to record the weather conditions at the time that the worker worked, and materials are delivered and installed. Additionally, the processing logic may prevent work from being performed if said work would violate manufacturer guidelines for installation/application. The recorded information may also be useful in identifying issues that can negatively affect the construction process, invalidate insurance coverage, and increase risk. Further, there is no system that can verify that the environmental conditions are adequate for the project initiation.
If the system determines that the environmental conditions are not suitable for project initiation, or some portion of the project to be initiated, the system may take the appropriate responses, such as sending notifications, triggering alarms, and/or contacting managers. The decision as to the appropriate response may be determined by, the date, the time current weather conditions, or related factor. For example, if the ground is frozen, initiation construction of the foundation may not be appropriate as frozen ground expands and changes the support conditions so that when the ground thaws, the grade can change, and settlement can occur. Further, concrete should not be subjected to freeze/thaw cycles until certain physical properties of the concrete are reached, such as a 500 psi benchmark. Further, the water:material ratio can be changed adversely as water, being an important component of the concrete hydration process, also causes undesirable freezing.
The system may also control access to tools, equipment, materials, and areas of the construction site so that project, or stages of the project, cannot be initiated unless the proper conditions are met. As to tools, equipment and materials, the system may confirm the identity of an individual and grant access to certain tools and equipment using smart locks and/or other technology. The system may limit the dates and duration of access to the tools/equipment such that the tools/equipment must be returned within the specified date/time window. An onsite scanner can be used to identify workers, environmental conditions, tools, equipment, materials, and areas of the construction site such as by using barcode or other identifying information to track items, associate them with a worker or area of the construction site.
The smart locks may also be used to limit access to certain portions of the project under construction. An individual's right to a portion of the construction site may be dictated by permissions that are stored through each party involved in the construction process. This may eliminate keyed entry during the process and provide further verifications of individual or group access.
The individuals on the construction site may be prompted to wear certain wearables that provide useful information to the system. For instance, individuals may be prompted to wear location tracking devices, such as GPS devices, Bluetooth, radio frequency identification (RFID) devices, ultra-high frequency (UHF) and/or beacon-based devices. The use of the wearables helps to perform geofencing within the construction site. The location tracking provided by the wearable helps the system to monitor the location of individuals on the construction site on an ongoing basis. The permissions may define what portions of the construction site an individual may access. Ongoing monitoring may indicate that an individual is attempting to enter a location where the individual is not permitted. This may trigger a response as described herein. A signal may be sent to the vest or wearable to trigger a visual or audio cue that the individual is not in a permitted area. In addition, individuals may be requested to wear wearables that track biometric information, such as heart rate, body temperature, respiration rate and blood pressure. This information may be tracked and stored on an ongoing basis. When the biometric data gathered from these wearables are outside an acceptable range, potentially indicating physical danger or injury, appropriate response actions may be taken such as notifying the individual, notifying a supervisor, and/or contacting medical personnel. Collected data may be used to verify a multitude of factors such as reported accidents, incidents of theft, hours worked, and the like. In the event that an accident occurs, the system can record information about the accident such as the worker involved, the equipment being used, physical location, other workers in the area, video capture from cameras in the area, material involved, tools and equipment involved and record the information for reporting and future study.
The system may track materials using a tracking tag. When a delivery is made, the delivery person may enter delivery notes and the delivered materials may be scanned or read to confirm the quantity and nature of what has been delivered and current weather conditions. The system can record weather information at the location and time where the materials are received, stored, and installed. Recording weather information at the construction site allows for autonomous confirmation of weather conditions that do not rely solely on third party sources. The system may track the movement of materials, tools, and equipment at the construction site. Scanning technology such as RFID readers, UHF readers and/or the like may be utilized to assist the location tracking for tools, equipment, and materials. The tracking of materials helps reduce the risk of theft. For example, the tracking solution may indicate instances of possible theft, such as when the materials are leaving the construction site when the removal of the materials is not appropriate.
The system may allow for the establishment of one or more geofenced zone areas. These areas could be monitored and established with additional access restrictions to individuals, material and equipment to further prevent loss or damage to the construction project. The system can determine the area where the materials are stored to assist in insuring that the materials are received and stored in compliance with the warranty specifications for the materials.
The system may control access to power by individuals of the construction site. The system may provide several power outlets and may grant access to the power outlets as warranted. The use of power may be recorded by the system. Different levels of voltage may be provided as required. The system can also restrict power usage during predetermined events including warranty confirmatory, safety situations and the like.
The system, including the kiosk, may also interface with the inspectors such that an inspector may enter notes and related details of an inspection. The system may allow the inspector to capture images of notes, forms, and the like using various solutions. The system can receive a set of internal inspection information entered into the kiosk from an internal inspector representing an internal physical inspection of the construction project at predetermined stages of the construction project. As components of the construction project are completed, an internal inspector can provide inspection information representing the component or stage of the construction project has been properly completed. This allows for inspections to be performed and recorded on the distributed ledger or other form of persistent storage (including block chain) prior and any correction, if needed, to be performed prior to an inspection. The system can also receive a set of external inspection information from an external inspector and an external inspection computer device representing a third-party physical inspection of the construction project at predetermined stages of the construction project. Based upon the internal inspection, external inspection, or both a certificate of inspection can be created and stored on the distributed ledger.
Exemplary embodiments may reference a record of a construction project on persistent storage. The process of maintaining the record for the construction project may begin by the development of a Building Information Model (BIM) that contains 3D plans for the construction with full details. Based on the BIM, a Bill of Materials (BOM) may be determined. The BOM may contain a complete itemization of materials needed for the construction project. The BOM includes information such as make, model, quantity, warranty information, hazardous material information or other safety details. The BOM may be updated as actual materials arrive to the site that includes serial numbers, bar codes, QR codes, RFID values or other component or product identifications. Materials arriving to the site may be recorded, as well as the BIM and BOM, on the persistent storage.
The exemplary embodiments may receive or determine a construction schedule that contains full project details and sequencing, including the specification of dependencies. Smart contracts may be provided that use the persistent storage for each step or task of the construction schedule. This information and the schedule may be augmented with worker or employee lists for each task. The smart contracts may set forth acceptance or inspection requirements for confirmation of completion and payment.
The exemplary embodiments may confirm conditions at the construction site and may record weather conditions at the time certain tasks are started, stopped, and/or marked as complete. The exemplary embodiments may record the weather conditions related to the materials on site.
The exemplary embodiments may build a complete record of plans, the actual “as built” including make, model, serial number, or other identification of for every component in the home resulting from the construction project. The record may include a complete record of who completed the work, who inspected the work and how the project was insured and funded. This record may be updated as any property management adds information like maintenance requests, maintenance completions, utility usage, rental history, etc.
When the kiosk is placed at the construction site, the kiosk can create a commencement record and store the commencement record on a distributed ledger. The commencement record can be created representing that kiosk is uniquely associated with the construction site and the kiosk is prepared to gather information and manage the construction project, process materials and labor. As the construction project progresses, various stages of the construction project occur. For example, the foundation can be a concrete slab and can be poured. Prior to pouring the concrete foundations, certain pre-requisites need to be met such as the proper environmental conditions, available materials, and proper site preparation and available of workers and labor. The kiosk can receive information from vendors, workers, sensors and like to determine of the pre-requisites for each stage are met and that stage can commence. The commencement record can be appended with information representing that the various stages of the construction project are ready for commencement and have commenced. These information for these various stages can be included in the commencement record.
For example, in one stage of the construction certain materials may be required. In the framing stage, the lumber or other materials need to be available and present at the construction site, authorized workers and labor need to be present and the site preparation needs to be completed for this stage. The kiosk can determine if the stage pre-requisites are met and append this information to the commencement record. The kiosk can also determine if there is sufficient insurance coverage and if there is a sufficient financial commitment to commence construction or a stage of construction.
Referring to
The kiosk can be removably attached to the construction site so that it is stationary during a first construction project but can be moved to a second construction project once the first construction project is completed.
The system 130 may be implemented in a distributed fashion and may include an alternative energy source 140. For example, solar panels, wind turbine(s), a battery or the like may be used. In a kiosk implementation, the alternative energy source may be physically affixed to the kiosk. For example, solar panels or a cable to a wind power source could be affixed to the kiosk. Alternatively, a power line leading to the alternative energy source may be connected to the kiosk to provide power for the kiosk.
The system 130 may include various scanners and readers 142, such as those described above relative to kiosk. The system 130 may include a utility supply and control 144 and a mechanism for turning the utilities, such as power, gas and/or water, on and off under a programmatic control. The system 130 may include an internet data supply control 145 and a mechanism for turning the access to this service on and off under a programmatic control. Programmatic control may be provided to grant or deny access to such resources. The system 130 may include an antenna 146 for wireless communications signals to receive and transmit. The system 130 may include a gyroscope 148 to monitor any moving of the system. The gyroscope 148 may indicate motion indicative of whether someone is trying to move or tilt the kiosk. Logic may be provided to send a notification in such an event where the gyroscope indicates substantial enough movement. The system 130 may include a weather station 150 to measure current weather conditions, such as temperature, air movement, humidity, precipitation, barometric pressure, direct sunlight, and the like. Input from the weather station 150 may be used to inform decision making by the system in some instances. Alternatively, the weather may be collected via software, such as from a weather service or other weather source. Similarly, the system 130 may include a weather sensor 141. The sensor can be a wet bulb globe temperature adapted to measure, among other things, heat stress in direct sunlight, which accounts for temperature, humidity, air movement (direction and speed), sun angle and cloud cover (solar radiation). The kiosk can also be in communications with one or more ground sensors that can detect moisture, temperature, or both. The ground sensors can be disposed around the construction site and can be associated with a specific aspect of the project. For example, a subset of moisture sensors can be disposed at or near the location of the foundation so that in the event of a concrete foundation, the moisture content of the soil can be in a desired range, else the creation of the foundation can be postponed. Therefore, the negative impact of undesirable soil moisture on the integrity of the foundation can be reduced or eliminated.
A list of hazardous materials at the site may be activated by activating element 232. This list is updated as hazardous materials are delivered, removed or consumed. Access to hazardous materials may also be controlled via the system 130.
The user interface on display 206 (
The system 130 may include coding software which allows each tool to be assigned to authorized personnel. Utilizing this coding along with smart locks as previously mentioned, the system 130 either unlocks or prevents access. Selection of the worker's compensation activation element 238 may be required at the end of each workday or when an injury occurs.
Delivery personnel may activate the delivery activatable element 226 (
As shown in
Referring to
Building material manufacturing specifications, which may be needed for compliance with warranty requirements, can be received from a supply computer device 376 and a regulatory code can be received from a regulatory computer device 378. The kiosk can include non-transitory computer readable instructions that when executed by a processor, provide the structure and function as described herein. Kiosk can receive a set of regulatory requirements associated with the construction site or project. The regulatory requirements can include approved construction materials that are approved by regulatory entities, such as governments, or designers, such as architects. Regulatory requirements can include building codes, fire codes, labor standards, building permit requirements, building and labor licenses, and the like. The regulatory requirements can include building and construction processes and procedures. For example, during construction, opening for windows and doors on second floors or higher should have safety railing installed. The type and quality of materials required for the construction project can be determined by the regulatory requirements. Compliance with the regulatory requirements can also be needed for a warranty to be honored. In some cases, when regulatory requirements are not followed, the warranty can be voided.
The various computer devices, including the server and site computer device (e.g. kiosk), can be in communications with persistent storage 380. The persistent storage can include a distributed ledger, immutable database, block-chain structure, and the like. The communications between the various computer device, including the server and the site computer device and immutable distributed ledger can be a global communications network, wide area network, local area network, deliver to a computer readable medium from one device to another (e.g. USB drive, CD, DVD) and can be wired or wireless.
The server can include a set of server computer readable instructions that can include a set of server computer readable instructions stored on the server computer readable medium that, when executed by a processer included in the server, can be configured to: receive a building information model from a design computing device in communications with the server including an architectural design in compliance with regulatory code associated with a construction site and a bill of materials representing a set of materials to be used at the construction site according to the architectural design and a building material manufacturing specifications, store the building information model on the distributed ledger, transmit to the bill of material to a supply computer device informing a third-party supplier, distributor of reseller to deliver the materials to the construction site, receive a material delivery information representing that the set of materials to be used at the construction site has been physically delivered to the construction site, receive material installation information representing that the set of materials at the construction site has been installed at the construction site in compliance with a regulatory code and the building material manufacturing specifications, receive an internal inspection information from a site computer device in communications with the server representing that the installation of the set of material is in compliance with at least one of the architectural design, the bill of materials, the regulatory code and the manufacturing specifications, transmit an external inspection information request to an external inspection computer device in communications with the server; receive an external inspection information from a site computer device representing that the installation of a set of material as installed is in compliance with at least one of the architectural design, the bill of materials, the regulatory code and the manufacturing specifications, transmit the external inspection information confirmation to an external inspection computer device in communications with the server; debit a first account associated with the construction site and credit a second account associated with an external inspector, create a certification of code compliance according to the building information model, the material delivery information, the material delivery information, the internal inspection report and the external inspection report, and, store the certification of code compliance on the immutable distributed ledger.
The kiosk can be physically associated with the construction site and includes a computer readable medium and input interface. A set of computer readable instructions that, when executed by a site processor can be configured to: receive the bill of materials, receive the material delivery information, receive the material installation information, receive internal inspection information from a first inspector, receive external inspection information from a second inspector, and, transmit the material delivery information, the material installation information, the internal inspection information and the external inspection information to the server or to the persistent storage.
A set of computer readable instructions can be configured to store the bill of materials on the distributed ledger; and the supply computer device can be configured to retrieve the bill of materials from the distributed ledger or a designer, such as an architect. The kiosk can be in communications with the distributed ledger; and, the set of computer readable instructions can be configured to store the material delivery information, the material installation information, the internal inspection information and the external inspection information on the immutable distributed ledger. A reader can be in communications with the kiosk and configured to receive information from a tracking device; and, the set of computer readable instructions can be configured to receive material delivery information from the tracking device associated with the set of materials.
The reader can be selected from the group consisting of: radio frequency identification (RFID) detector, ultra-high frequency (UHF) detector, a bar code scanner, a QR code scanner, near frequency communication (NFC) device; an optical character recognition (OCR) device and any combination thereof. A environmental sensor, such as a weather sensor or weather station, can be in communications with the or included in the kiosk and configured to record the weather at the construction site, the computer readable instructions can be configured to capture installation weather conditions at the construction site at a time that the set of materials is installed and associate installation weather with the installation of the set of materials and transmit the installation weather to the server. The computer readable instructions of the server of kiosk can be configured to create the certification of warranty according to the installation weather following the manufacturing specifications for the installed material. The construction site can be associated with or identified by a physical location information such as global position (e.g. GPS) information. The kiosk can be on a movable platform including a cart, pallet, vehicle, trailer and the like.
The system can control access to the construction site.
If there is not a match 406, a manual process may be executed, or an alternative authentication process may be deployed 416. If this alternative authentication fails to produce a match 406, access to the construction site may be denied 408. In addition, a notification may be sent to a responsible party and/or an event may be triggered, such as contacting security or law enforcement officials 410. If the alternative authentication process produces a match, the process proceeds to 412.
The system may store permissions for each individual accessing the construction site. These permissions may identify the dates and times where the individual is given access to the construction site. In addition, the permissions may specify what tools, equipment or materials the individual is allowed to access. The permissions may specify whether the individual is allowed to use a power supply and may specify what portions of the construction site the individual is permitted to access. These permissions may be accessed to determine the permissions for the identified individual 412. If the permissions indicate that access is permitted 414, the individual may be granted access to the construction site 418.
As was mentioned above, when individuals attempt to access the construction site and are not granted access, certain events may be triggered (see 410 in
One type of individual is a contractor.
The wearables may include safety gear, such as hard hats, gloves, goggles, vests and the like, as well as wearables for tracking and obtaining biometric data. The identity of the individual is confirmed 1002, and the permissions for the individual are accessed 1004 and a determination is made based on the permissions if the individual should be granted access to the wearables 1012. The system may offer an alternative touchscreen option to place a call to the appropriate party should the software fail to verify an otherwise authorized individual. If it is determined that the individual should be granted access, the smart lock for the storage location of the wearables is unlocked 1006. The individual may then be prompted to scan information regarding the wearables so as to register the wearables and associate the wearables with the individual 1008. In one embodiment, the system may use one or more images of an individual to determine if the individual has the necessary safety equipment. For example, an image of the individual taken by the kiosk can be used to determine if the individual is wearing a hardhat and generate a warning if no hardhat is present.
The system may require that an individual wear certain safety equipment in the form of wearables. The system may record what wearable the individual scans. The system tracks and records the location and biometric data gathered by the wearables 1010. The wearables may include smart vests, bracelets, badges, sensors and the like that provide location information and biometric data, such as heart rate, body temperature, blood pressure breathing rate, gyroscopic informatic and/or other information. These wearables assist the system in tracking the location of individuals of the construction site. These wearables also help to track the biometric data of individuals. The biometric data may be helpful in identifying that an individual is experiencing an accident, a health event or is idle. The biometric data is stored so that a record of the biometric data can be kept. If in 1005, it is determined based on the permissions that the individual should not be granted access, then access to the wearables is denied 1014.
The use of the wearable to track location helps to facilitate use and installation of material to determine warranty requirement compliance. The wearable information can be combined with geofencing in an exemplary embodiment. The geofencing enables the system to track and limit access to locations of individuals at the construction site. The construction site may be partitioned into areas where different permission rights are given for the various areas. For example, a plumber may be given access to the kitchen and the bathrooms of a project under construction but may be prohibited from being in the living room or the roof. As shown in
To help illustrate an example of geofencing,
When a worker enters an unauthorized area, an audio or video response can occur on the wearable device. For example, a smart vest may include lights that may flash or may be continuously illuminated in response to a party being outside the permitted areas on the construction site. Another option is for an audio alarm or a video alarm to be triggered at the construction site rather than on a wearable. A further option is to send a notification, such as a phone call, a text message, an email message or other notification to a supervisor on or off the construction site. Yet another option is to take disabling measures relative to the individual. The disabling measures could entail triggering locks or disabling equipment by shutting off power or the like. The geofencing can also be used to determine where material delivered, stored, and installed. The geofencing, along with date and time information, can assist with the determination whether the materials were handled or installed by a licensed, experience, approved, authorized or otherwise preferred worker.
The computer readable instruction of the kiosk can include instruction for the determination that a worker schedule is consistent with the set of construction stages. For example, if the construction site needs to be cleared of naturally occurring features such as trees, the initiation of the clearing process can be dependent upon the authorized worker being present with the proper equipment at the construction site. When the foundation is to be created, for example and concrete foundation, the kiosk can determine if an authorized worker and the proper equipment are present at the construction site prior to initiation of the foundation creation.
The system can assist with the timing and deliveries to the site according to initiation of aspects of stages of the construction project.
The deliveries may utilize various scanning and reader technology. In
The delivery person may interface with kiosk via display 106A and 1900 to provide delivery information. Flowchart 2100 of
The inspector may interface with the system.
The system may include a still camera(s) or a video camera(s) that can be included in the kiosk.
Systems at adjacent locations may be used in conjunction with each other.
The environmental conditions, including weather conditions, may trigger different protocols that are performed by the system. For example, inclement weather, very cold weather or very hot weather may trigger protocols to ensure worker safety and productivity as well as the protection of structures, materials, and equipment at the construction site.
As mentioned above, a great deal of information may be stored prior to and during the construction project for reference during the project and after the project is completed.
When the construction project is complete, information referenced on the distributed ledger may be extracted and encapsulated into a certification of materials and completion record 2604. The completion record can be a certificate of completion and can be created based upon the kiosk receiving a set of completion criteria from the regulatory entity, financial entity, insurance entity, internal inspector, and any others who can alone or in combination determine whether the set of compliance criteria has been met.
The construction project can be divided into stages and each stage can have a commencement record associated with the stage beginning and a completion. The construction project can include a completion record that can be an aggregation of completion criteria for the various stages of the construction project. The criteria for a construction project to be completed can include multiple elements such as a determination that there are no liens on the construction site or project, that all the workers tasks have been satisfactorily completed, the financing has been completed, the stages that have been commenced are completed, that there are no warranties or warranty claims outstanding, internal and external inspections have been performed and satisfactorily passed, insurance has been removed for a particular stages or for the construction project as that stage has been completed, the regulatory agencies have issued the necessary permits such as an occupancy permit and any combination.
When the construction project is completed, the completion record can be used, such as being retrieved by an insurance entity, close the construction insurance and worker compensation insurance as the construction project is completed. Once completed, there are no workers on site and therefore no need for further worker competition insurance. The property owner can secure property and casualty insurance as the construction insurance is no longer needed. This can reduce the overall costs of insurance as coverage is in place for the appropriate stage and does not run into stages where the specific insurance is not needed. The property owner can secure permanent financing in lieu of the construction financing. The certificate of completion can be stored on the persistent storage.
By detecting and storing activity, materials, labor and the like as various stages of the construction is completed, record of the various stages is contained in the commencement and completion records. Therefore, a specific time in the construction project can be retrieved for further review even after the construction project and stage are completed.
The commencement and completion record and certificate may hold information such as the BIM, the final BOM, worker sequence information, warranties for items in the completed home, confirmation of conditions and qualifications at the time of installation for warranty, punch list completion information, lender information, information regarding the contractors and workers, insurance policy information, inspection history information, ownership history, history of localized events like weather and records of trespassing (such as images) and bills of lading for items delivered during the project. The certificate may be delivered in electronic form and preferably in an immutable format. Alternatively, the certificate may be delivered in paper form. The certificate may be delivered to the owner of the property or to a property manager. In addition, the certificate may be passed to other interested parties, such as an insurance provider or financial institution.
A few examples help to illustrate the value of the certificate. The certificate acts as a complete record of the project. Suppose that an oven in a home fails 3 months after an owner occupies the premises. Since the certificate has complete warranty information, the owner can reference the warranty information and get the oven fixed under warranty. As another example, suppose that gutters on the home leak 6 months after an owner occupies the premises. The owner can reference the certificate to contact the contractor, construction company or manufacturer. The construction company might also have a remedy against the installation contractor based on evidence that materials were not installed properly or the manufacturer if the condition precedent were not confirmed or not met. Further, the bills of lading (BOLs) may indicate that the materials delivered were different from those specified in the BIM and BOM. The certificate may also assist in obtaining a lower insurance premium from a provider because be reducing or eliminating unknowns about the project.
The information referenced in the persistent storage may also be passed to a computing device of the owner 2606. The computing device may be, for example, part of a home supervisor system that manages and controls home systems, such as heating, air conditioning, lighting, an alarm system, or the like. The computing device may be part of a smart home controller and may interface with appliances and other items that are interconnected via a home control network. The computing device may include a document management system for securely storing the transferred information.
In exemplary embodiments, information may be gathered from and sent to multiple parties including a managing company responsible for the management and oversight of the construction project, a design company responsible for developing a design for the home and develops the BIM for the project, a supply company analyzes the BIM and develops a BOM for the construction project, and a construction company is responsible for constructing and assembling the home.
The supply company database 2810 may also store inventory management information 2830, such as quantity and the particulars of material inventory and material warranty information for such materials 2832. The warranty information for materials used in the project may be hashed 2834 and the resulting hash value may be stored in storage in the supply company database 2810. The hashed value 2834 may be passed to the management company database 2804 and then referenced on the persistent storage 2802. The supply company database 2810 may also store shipping management information 2836. This may include bill of lading histories 2838 and barcode, RFID values, UHF values and/or QR code scan histories 2840. The BOLs for the project and the barcode/QR scan codes for delivered items for the projects may be hashed 2842 and the resulting hash value(s) passed to the management company database 2804 for reference on the persistent storage 2802. Further, confirmation of what was specified by designers was delivered to the construction site and installed according to the manufacturer's specifications so that a construction project can be placed under warranty.
A construction company database 2812 may store project information 2846, such as TMS #'s, GPS data and addresses for projects. The construction company database may also hold scheduling information 2848 for the project. This may include detail regarding workflow and timing. A hash value of the construction project schedule or project schedule 2850 may be stored on the construction company database 2812, passed to the management company database 2804 and referenced on the persistent storage 2802. The construction company database 2812 may store worker information 2852. The worker information 2852 may include employee information 2854 for workers involved in projects. This employee information 2854 may include information regarding licenses for workers 2856, hire dates for workers 2858, employment end dates for workers 2860 and other information, such as names, photos, etc. The worker or labor information can include information that the worker or laborer is in compliance with applicable laws (including federal and state), in compliance with contractual obligations, properly licensed, of legal status, of sufficient experience, within application restrictions such as a limit on hours worked during a 24 hours period, authorized for the construction site or any combination. The worker or laborer information may be sortable by keys such as TMS # to identify workers for a project. The construction company database 2812 may also store scheduling information 2864 for workers. This information may be used to develop a worker/sequencing proposal that is hashed 2866 and the resulting hash value stored in the construction company database 2812. The hash value 2866 may be passed to the management company database 2804 and referenced on the persistent storage 2802. Worker sequencing data once the labor is completed 2868 may be hashed and the resulting hash value stored in the construction company database 2812 for a project. This hash value 2868 may be passed to the management company database 2804 and referenced on the persistent storage 2802.
Punch list management information 2870 may also be stored in the construction company database 2812. The punch list management information 2870 may include a hash of the punch list for a project 2871 and a hash of punch list releases for a project 2872. These hash values 2871 and 2872 may be passed to the management company database 2804 and referenced on the persistent storage 2802. The punch list information can be used for a determination of warranty requirement compliance.
Inspection management information 2874 may be stored in the construction company database 2812. Hashes of scheduled dates of inspections 2876, dates of actual inspections and results 2877 and failed inspection reports 2878 for a project may be stored in the construction company database. The hash values 2876, 2877 and 2878 may be passed to the management company database 2804 and referenced on the persistent storage 2802.
Hash values gathered and stored in the site supervisor database 2814 may be passed to the management company database 2804 and referenced on the persistent storage 2802. This may include hash values of information regarding dates and times of deliveries for a project 2880, delivery details for the project 2881 and delivery notes and delivery photos for the project 2882. The hash values may include hash values resulting from passing GPS information for wearables used in the project 2883, heart rate information gathered by wearables for the project 2884, failure reports from the wearables for the project 2885 through hash functions. Additionally hash values resulting from passing RFID tool usage information for the project 2886, security camera footage gathered by the site supervisor for the project 2887, weather data recorded by the site supervisor for the project 2888, hours information for when the site supervisor was active for the project through hash algorithms may be stored in the site supervisor database 2814, passed to the management company database 2804 and referenced on the persistent storage 2802. The values may also result from passing GPS location information for the system 2890, tracking information for delivery trucks 2892 and contractor power usage information 2894 through a hash function. Hash values 2890, 2892 and 2894 may be passed to the management company database 2804 and referenced on the persistent storage 2802.
Information referenced on the distributed ledger may originate from third parties.
Information may originate from an insurance company database 2908. A hash of an insurance policy for the project 2918, a hash of any insurance policy changes for the project 2920, a hash of policy start date 2922, a hash of policy cancellation date 2924 and a hash of policy change dates 2926 may be stored in the insurance company database 2908. The resulting hash values 2918, 2920, 2922, 2924 and 2926 may be transferred to the management company database 2904 and referenced on the persistent storage 2902.
Information may also originate from a property management database 2910. Hashes of a current rental agreement 2928, rental agreement particulars 2930 (such as agreement number, dates and amount paid) and notice(s) of missed payments 2932 may be stored therein. Information can include utility consumption and expenses such as insurance, taxes, maintenance, and the like. This hash values 2928, 2930 and 2932 may be added to the management company database 2904 and ultimately referenced on the persistent storage 2902.
The supply company 3110 is responsible for the intake of materials specified in the BOM that are needed for the construction project.
As shown in the diagram of
Much of the interactions among the parties shown in
The payment may be made electronically, such as through crypto currencies, like Bitcoin or Ether, or via a stable coin whose value is pinned to an item like a paper currency or the like. A cryptocurrency is a digital currency built with cryptographic protocols that make transactions secure and difficult to forge. Other Suitable forms of electronic payment includes Automated Clearing House (ACH) payment, Electronic Funds Transfer (EFT), card payments, other types of bank transfers or other types of electronic wallet transfer. In the case where crypto-currency is used, the crypto-currency may be delivered to the digital wallet of the supply company at a specified wallet address or account 3412. The ledger may be updated to show that the contract is complete 3414. Payment requires that the lender has sufficient funding in their digital wallet 3416. If not, the smart contract will not be written on the persistent storage 3418. If there is sufficient funding, payment is made, and the contract is written onto the persistence storage as complete at 3420.
A second illustrative smart contract shown in
A third illustrative smart contract shown in
There can be a relationship between the smart contracts and the project schedule.
Smart contracts may also play a role with deliveries.
The delivery information is hashed, and the resulting hash value is referenced on the blockchain-based persistent storage 3804. A smart contract is provided that uses the immutable distributed ledger 3806. A determination is made whether the conditions specified in the smart contract are satisfied 3808. If the conditions are satisfied, electronic payment for the delivery is realized 3810. If the conditions are not satisfied, notice of outstanding issues are sent and the delivery contractor may attempt to remedy the issues 3814. The process may then repeat beginning with step 3808 until the conditions are satisfied.
One of the benefits of the approach adopted by the exemplary embodiments described herein is that a complete record of materials used in the home of the construction project is maintained.
As has been discussed above, worker's compensation insurance may be adjusted as workers are added and removed from the workforce for the construction project with the assistance of smart contracts.
Liens are often used in construction. The exemplary embodiments enable the triggering and releasing of such liens to be automated.
Because of the tracking of construction progress and the automated scheduling, exemplary embodiments may provide for just in time (JIT) delivery. JIT delivery ensures that items are delivered when needed and are not delivered late causing delays. Moreover, JIT delivery ensures that items are not delivered too early and thus unnecessarily exposed to the elements, be susceptible to theft or occupy needed storage space.
The exemplary embodiments also support JIT labor where the laborer arrives on site when they are needed.
The present application is a continuation in part of U.S. patent application Ser. No. 16/991,916 entitled “System For Management Of Warranty Information For Projects And Materials” filed on Aug. 12, 2020 which in turn is a continuation in part of U.S. patent application Ser. No. 16/876,080 entitles “Digital Asset System For Management Of Projects And Materials”, filed May 17, 2020 which in turn is a continuation in part of U.S. patent application Ser. No. 16/810,782, entitled “System For Management And Verification of Code Compliance,” filed on Mar. 5, 2020 which in turn is a continuation in part of U.S. patent application Ser. No. 16/410,634, entitled “Use of A Persistent Storage Reference Construction Metadata and to Use Smart Contracts for a Construction Project,” filed on Jul. 12, 2019, U.S. patent application Ser. No. 16/510,642 entitled “Use of a Blockchain-Based Distributed Ledger and Smart Contracts for a Construction Project” filed on Jul. 12, 2019 both of which are continuations of U.S. patent application Ser. No. 16/452,076, entitled “Site Super System For Construction Sites”, filed Jun. 25, 2019 which all are incorporated reference.
Number | Name | Date | Kind |
---|---|---|---|
10338913 | Franchitti | Jul 2019 | B2 |
20170031676 | Cecchetti | Feb 2017 | A1 |
Number | Date | Country | |
---|---|---|---|
20210035383 A1 | Feb 2021 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16991916 | Aug 2020 | US |
Child | 16994585 | US | |
Parent | 16876080 | May 2020 | US |
Child | 16991916 | US | |
Parent | 16810782 | Mar 2020 | US |
Child | 16876080 | US | |
Parent | 16510642 | Jul 2019 | US |
Child | 16810782 | US | |
Parent | 16510634 | Jul 2019 | US |
Child | 16510642 | US | |
Parent | 16452076 | Jun 2019 | US |
Child | 16510634 | US | |
Parent | 16452076 | Jun 2019 | US |
Child | 16510642 | US |