1. Field of the Invention
The invention pertains to the field of electric power distribution. More particularly, the invention pertains to analysis of large-scale interconnected power systems.
2. Description of Related Art
The Federal Energy Regulatory Commission's (FERC) open-access NOPR has created far-reaching changes in the wholesale electric industry in the United States. To enforce the open-access transmission policy, FERC further defined a term “Available Transfer Capacity” (ATC) to inform all energy market participants regarding the maximum power transfer capability of a system. Hence, the development of a real-time method for accurately determine available transfer capability is essential in power systems within the open access environment. One main challenge is to quickly and accurately compute the real-time available transfer capability under varying loading conditions, taking into account the static as well as dynamic security constraints of a large number of contingencies.
The de-regulated electricity market has resulted in rather rapid changes in operating conditions. System operators now face more new, unknown power flow patterns than ever before. At the same time, economic pressure on the electricity market and on grid operators, coupled with limited investment in new generation and transmission networks, push power systems close to their stability limits. The uncertainty and variability brought about by renewable energies may further push power systems ever close to or beyond their stability limits.
Available Transfer Capability (ATC) has been used to guide power system operations for setting transfer limits on transmission corridors and key tie-lines. Currently, ATC is mostly calculated using off-line, worst-case scenarios and it results in very conservative calculations of power transfer limits. This traditional tool of off-line ATC calculation is inadequate. Hence, there is a need to calculate the ATC based on actual operating conditions.
Power transfer capability (PTC) refers to the capacity and ability of a transmission network to allow for the reliable transfer of electric power from an area of supply to an area of need by way of all transmission lines (or paths) between two areas under assumed system conditions. In this invention, the terminologies of power transfer capability (PTC) and the power transfer limit (PTL), i.e. (PTC under a specified control scheme) will be used interchangeably. The assumed (current and near-term) operating conditions include several projected factors such as the expected load demands, near-term real power dispatch, the system configuration, and the scheduled power transfers among the interconnected systems.
The power transfer capabilities proposed by NERC are generally the first contingency incremental transfer capability (FCITC) or first contingency total transfer capability (FCTTC) for predicted peak load conditions. FCITC is the amount of electric power incremental above a normal base power that can be transferred in a reliable manner based on all of the following conditions:
Note that condition (1) is related to the static security constraints under the first contingency of the pre-contingency operating conditions while condition (3) is concerned with the static security constraints of the post-contingency operating conditions. Condition (2) is the typical (angle) transient stability constraint and may not include the voltage dip problem during transients as constraints.
A set of interface tie-lines can be defined between a sending area and a receiving area.
In
The system-wide PTC can be mapped into an interface tie-line PTC. Depending on the selection of interface tie-lines, the corresponding interface tie-line PTC will be different.
The Continuation Power Flow Method (or “CPFLOW”) is a method for tracing power system behavior described in a paper “CPFLOW: Tool for Tracing Power System Steady-State Stationary Behavior Due to Load and Generation Variations”, Chiang, Sha and Balu, IEEE Transactions on Power Systems, Vol. 10, No. 2, pages 623-634, May 1995, which is incorporated herein by reference.
A BCU method is a systematic method to find the controlling unstable equilibrium point, as disclosed in U.S. Pat. No. 5,483,462 “On-line method for determining power system transient stability” granted to Dr. Hsiao-Dong Chiang, one of the inventors herein, which is incorporated herein by reference.
A BCU Classifier is a method for ensuring that unstable contingencies are captured and reduced, as described in “Development of BCU Classifiers for On-Line Dynamic Contingency Screening of Electric Power Systems”, Chiang, Wang and Li, IEEE Transactions on Power Systems, Vol. 14, No. 2, pages 660-666, May 1999.
The invention describes a system for accurately determining real-time Available Transfer Capability (ATC) and the required ancillary service of large-scale interconnected power systems in an open-access transmission environment, subject to static and dynamic security constraints of a list of credible contingencies, including line thermal limits, bus voltage limits, voltage stability (steady-state stability) constraints, and transient stability constraints.
The Real-Time ATC system developed in this invention is designed to provide power system operators with critical information including the following:
The outputs of the real-time ATC system include the following:
PTC of an interconnected power system depends heavily on underlying power transactions. In fact, the PTC and its associated binding constraints of an interconnected power system can be very different for different proposed power transactions. Hence, it is important to specify the proposed power transaction in calculating the PTC with respect to the power transaction.
Given a set of proposed power transactions, the objective of a transfer capability computation is to determine the maximum transfer value for a proposed power transaction or simultaneous power transactions. The problem formulation upon which the calculation is based must have the following general characteristics:
The basic information required for the system-wide PTC evaluations includes the following:
In addition to the above basic information, the information of how to model the control actions during the process of step increases in loads and generations is required. These control actions include the static VAR compensator, TCSC, tap changer, synchronous condenser voltage/Mvar, LTC transformer voltage control, phase-shiftier controls, and capacitor/reactor voltage control, etc. . . . .
We present a method to represent a power transaction or a set of power transactions. We also discuss the notion of generation/load margin to a static security limit.
Given a load demand vector (i.e. real and reactive load demands at each load bus) and a real generation vector (i.e. real power generation at each generator bus), one can compute the state of the power system (the complex voltage at each bus) by solving the set of power flow equations.
Let P=P
−P
and Q
=Q
−Q
. The lowercase g represents generation and the lowercase d represents load demand. The set of power flow equations can be represented in compact form as
Now one can investigate the steady-state behavior of the power system under slowly varying loading conditions and real power redispatch. For example, if one needs to trace the power system state from the base-case generation/load condition [Pd, Qd
, Pg
] to a new generation/load condition [Pd1, Qd1, Pg1], then one can parameterize the set of power flow equations as such
F(x,λ)=f(x)−λb=0 (2)
where the generation/load vector b is
It follows that the parameterized power flow equations become the base-case power flow equations when λ=0,
And when λ=1, the power system is at the new generation/load condition [Pd1, Qd1, Pg1] and can be described by
As shown in the above procedure, one can investigate the effects of varying real power generations as well as varying load demands on power system steady-state behaviors. In fact, one can parameterize any change in PQ loads in conjunction with any change in P generations by selecting an appropriate vector b.
Applying the above general setting to the problem of computing PTC of interconnected power systems, the vector b can be used to represent one or several of the following power transactions and transmission service:
We shall call the vector b the proposed power transaction vector, and the scalar λ, the generation/load condition number. The proposed power transaction vector b can be used to represent a transaction involving simultaneous power transfers by summing each power transaction vector, i.e. b=Σbi, i=1, 2, . . . where the vector represents the ith power transaction.
The introduction of the power transaction vector and the load generation condition number enable one to rigorously evaluate available transfer capability of an interconnected system satisfying the general characteristics (C1), (C2) and (C3) stated above. For instance, one can compute the maximum value of the generation/load condition number so that the resultant interconnected power system satisfies all the constraints, which are required in the general characteristics (C2) and (C3).
Due to the nonlinear nature of interconnected electric systems, power transfer capabilities between two areas and their associated binding constraints depend on a set of system conditions. The power transfer capabilities and their associated binding constraints can be significantly different for any other set of system conditions, such as a different set of system load demands, a different network configuration, a different power transaction, or a different generation dispatch pattern. Hence, transfer capability computations must be sufficient in system modeling and scope to ensure that all equipment as well as system limits of the entire interconnected systems network are properly taken into account.
In general, power transfers cannot be forced through pre-determined transmission paths, unless the paths are physically controlled by control devices such as phase-shifters. Therefore, power transfers will be distributed among all parallel paths according to the laws of physics. As a result, simple bi-lateral contracts between neighboring areas may not be sufficient to describe the actual power flow. Detailed nonlinear power system models must be used for analysis.
In addition, given a set of proposed power transactions, the binding constraint which limits the system's PTC can be the physical operating limits of an equipment/facility, or the bus voltage constraint in the entire system including the sending, the receiving as well as all neighboring areas, or the steady-state stability limit. The limiting equipment/facility, or the bus with voltage violation, or even the binding contingency may not occur in the two areas involving power transfers. To address this issue, a comprehensive modeling of the interconnected power system is necessary for the development of an effective on-line PTC method.
We describe our invented method for computing real-time static security constrained power transfer limit (i.e. real-time static PTL) with respect to a specified generation/load variation vector, given a proposed power transaction or a proposed simultaneous power transactions such as (i) a point-to-point MW transaction, or (ii) a slice-of-the-system sale, or (iii) a network service, or (iv) a reactive ancillary service, and the following information:
The real-time method of the invention computes the static-security constrained PTC (i.e. static PTC) for the proposed power transaction of the interconnected system with the following control laws and satisfying all the constraints stated above.
The real-time method of the invention allows the participation of generators, loads, ULTC taps, phase-shifter settings, shunt capacitors, and DC links as controls to maximize available transfer capability. The control laws can be classified as active control and passive control, where active control laws are the control laws whose objective function is to maximize power transfer capability through their control actions while passive control laws are the control laws whose objective function is to remove various types of security violations through their control actions which can also increase power transfer capability.
The actions of active control laws can be formulated as a constrained optimization problem whose objective function is the transfer capability while the actions of passive control laws can be formulated as a constrained optimization problem whose objective function is not the transfer capability.
It is important for the process of computing available transfer capability to take into account all credible contingencies. A simultaneous transfer capability solution can be regarded as secure only if it can sustain all credible contingency cases. The strategy of using effective schemes to rank all credible contingencies and of applying detailed analysis programs only to critical contingencies is widely accepted.
Adopting this strategy, the real-time method employs three look-ahead ranking schemes for identifying critical contingencies in terms of three static security constraints; i.e. thermal limits, voltage limits and steady-state stability limits. With these ranking schemes, the real-time method has the ability to:
Three fast and yet accurate look-ahead estimators which can identify and rank critical contingencies in the context of static security assessments are incorporated into the real-time method. One look-ahead estimator serves to rank the set of all credible contingencies in terms of load (or generation/load) to their branch MVA violations (i.e. thermal limit violations) and to identify the top few critical contingencies for thermal limit violation. Another look-ahead estimator ranks the set of all credible contingencies in terms of their load margins to system collapse (i.e. steady-state stability limit) and identifies the top few critical contingencies for violating steady-state stability limit. The third estimator ranks all credible contingencies in terms of their load margins to bus voltage violation and identifies the few top critical contingencies for voltage violation. These three look-ahead estimators are briefly described in the next section.
Given (i) the current operating condition (obtained from the state estimator and the topological analyzer), (ii) a proposed power transaction or a proposed set of simultaneous power transactions, (iii) a base case power system model with control devices, reactive power generation limits, schemes of real power dispatches, say due to participation factor, etc. (iv) and voltage constraints, thermal-limit constraints, steady-state stability limits (v) a credible contingency from a contingency list, the three look-ahead estimators estimate the following three load margins to the three static security limits, along the proposed power transaction vector b for the parameterized power system (parameterized along the direction of the proposed power transaction) for the power system subject to the contingency.
Each of the above three load margins is then applied to rank the contingency list for the following three categories:
A list of top-ranked contingencies can thus be composed by selecting the top-ranked contingencies from each category.
Apply the continuation power flow (CPFLOW) method to each top-ranked contingency to obtain the so-called P-V curve, or P-Q-V curve and find the load margins to the steady-state limit, voltage violation point and the thermal violation point. The smallest one is the load margin of the top-ranked contingency.
The solution method for the real-time method of the invention to evaluate the static PTC of an interconnected power system with respect to a set of proposed power transactions subject to static security constraints is presented below.
A detailed description of the steps in each stage is described below.
We explain the physical meaning of the value
Physically, if
On the other hand, the transmission network is unable to transfer the proposed power transactions, should the contingency j occur, if
This (normalized) operating margin can be translated into operational guidelines as follows: the system can reliably transfer the proposed power transaction. In addition, the transmission network can transfer additional (
The static PTC can be expressed in several ways. It is sometimes useful to represent the static PTC in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit point. The calculated system-wide static PTC is then mapped into each interface static PTC.
We consider a 15005-bus interconnected power system containing about 2400 generators, 16,000 transmission lines, 8,000 loads, 4000 fixed transformers, 2400 fixed shunts, 3000 ULTC transformers, 800 switchable shunts, and other control devices such as fixed and ULTC phase shifters, etc.
Given a base case of the interconnected power system with a secure operating point, a proposed power transaction described by transmitting 1300 MW real power from area A to area B by decreasing all the real power generations of area B uniformly to zero (24 generators are scaled down to 0 MW) and increasing real power generations of area A uniformly to supply the loads of Area B (the area-wide generation of Area A is scaled properly), we apply the real-time method to evaluate the real power transfer capability from area A to area B of the interconnected power system subject to a contingency list which is a set of transmission line or generator outages.
Three cutsets of 500 KV transmission lines were selected and the corresponding sum of the line flows was defined as the interface line flows.
In this numerical study, the PTC is expressed in terms of either (i) power transfer capability between the sending area and the receiving area, or (ii) the pre-contingency power flow of the three interface flows.
The three fast look-ahead estimators were applied to the contingency list. The top five most serious contingencies captured by each look-ahead estimator and the corresponding estimated load margin are listed in Table 1, Table 2 and Table 3, respectively. In these three tables, the contingency with the sign * is a generator trip.
Since 4 of 15 contingencies are redundant, there are only 11 contingencies that require further study. A detailed analysis based on the continuation power flow (CPFLOW) was performed for each of these 11 contingencies to compute the PTC and to identify the corresponding binding constraint. Note that the participation of all control devices and the physical constraints of these control devices are taken into account in the process of continuation power flow study.
The final results of ATC, which is the difference between the PTC and the current power flow with respect to the proposed power transaction along with the corresponding binding contingency and the corresponding binding constraints are shown in Table 4.
The numerical simulation shows that the ATC for the proposed power transaction, under the assumed set of contingencies, is 234 MW between the sending area and the receiving area (instead of 1300 MW). The corresponding contingency (i.e. 89389-89392) is the binding contingency. Equivalently, the ATC of the proposed transaction is 5422 MW for the east interface, 2203 MW for the central interface, and 4445 MW for the west interface.
It is interesting to note that the constrained east interface line flow under this contingency is the smallest among the constrained east interface line flows of the contingencies considered. This is also true for the constrained central interface line flow and the constrained west interface line flow.
The real-time method of the invention can compute each ATC with the corresponding binding contingency as a by-product and the associated violated constraint in an ‘increasing’ order as shown in Table 4. This piece of information is useful for decision-making personnel to take a proactive approach to measure the transfer capability of the network.
For instance, the ATC of the study system without the consideration of the contingency (89389-89392) is 584 MW. If the probability of the occurrence of contingency 89389-89392 is low, then it may be reasonable to post the ATC as 584 MW and, in the meantime, a remedy control scheme can be prepared in advance should contingency 89389-89392 occur.
Likewise, the ATC of the study system without the consideration of contingencies 89389-89392 & 89394-104 is 820 MW. If the probability of the occurrence of either contingency 89389-89392 or 89394-104 is low, then it may be reasonable to post the ATC as 820 MW and, in the meantime, a remedy control scheme can be prepared in advance should contingencies 89389-89392 and/or 89394-104 occur.
It should be also pointed out that this real-time method also allows (via the establishment of Table 4) a probabilistic treatment of each contingency and the associated risk management. Economic factors can also be linked to Table 4.
A static PTC nomogram is a two-dimensional display of static PTC in terms of two interface flows. Nomograms provide vital information for power system operators to operate power systems within power transmission static security limits and with a ‘comfort zone’. A nomogram always involves two interface paths. In computing a nomogram, we first need to associate one interface path with the X axis and the other interface path with the Y axis. Then we separate all source generators involved in the stress pattern into two groups. The source group that is responsible for the flow change in the X axis path is classified as group X, which is denoted as G1. The source group that is responsible for the power flow change in the Y axis path is classified as group Y, which is denoted as G2.
We compute the static PTC nomogram in the following way. We at first create two independent base generation vectors for bg1, bg2 G1 and G2 respectively. Then, we create two independent coefficients for a1, a2 respectively. The overall generation vector considering both source groups will be:
b
g
=a
1
b
g1
+a
2
b
g2 (6)
By assigning a1, a2 different values, we create a family of generation/load stress patterns, which spans the entire feasible generation/load stress space. For each generation/load stress pattern, we use the CPFLOW to compute the voltage stability load margin (i.e. the boundary of the nomogram along the stress pattern).
The proposed solution method to compute the static PTC nomogram is as follows:
b
g
=a
1
b
g1
+a
2
b
g2 (6)
b
g
=a
1
b
g1
+a
g
b
g2 (6)
The static PTC nomogram can be expressed in several ways. It is sometimes useful to represent the static PTC nomogram in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit point. The calculated system-wide static PTC nomogram is then mapped into each interface static PTC nomogram.
The real-time ATC is the difference between the real-time PTC and the current actual power flow. To provide a real-time static ATC (i.e. ATC subject to static security constraints and voltage security constraints), it is necessary to have some real-time information regarding a system's operating conditions This invention proposes to apply a wide-area measurement system (WAMS) such as phasor measurement units (PMUs) installed at selected tie-lines and buses to obtain the required real-time real power and reactive power information.
One central topic in the area of wide-area measurement is the utilization of this new type of measurement (as opposed to traditional SCADA measurements). Phasor data, precisely time-synchronized data at a high data rate, provide a wide-area view of current power system conditions. To fill the gap between real-time phasor measurements and real-time operation applications, we propose to develop an integrated system which contains a wide-area measurement system and the real-time PTC system for an accurate determination of real-time PTC. This real-time PTC determination ensures power system security and reliability while offers better power system asset utilization and economic benefits.
Given an operating point (derived from a state estimator), a network topology, a set of pre-determined interfaces and a contingency list associated with each interface, we develop a PMU-assisted, real-time static ATC determination system for each interface. The output of this system can be expressed as the following:
The architecture of the invented method for determining the real-time static ATC is shown in
There are four key components in this real-time static ATC determination system:
It should be pointed out that the solution methods of the invented system can also determine the top-ranked interface static power transfer limit of each selected interface under the contingency list associated with each interface.
This real-time static ATC determination system has the following features:
In the following discussion, we define the real-time dynamic power transfer capability of a power system.
The transient-stability-limit power transfer capability (PTC), or termed dynamic PTC is defined as the (minimum) distance (i.e. load margin in terms of MW and/or MVAR) from the current real-time operating point to the state vector of the base-case P-V curve, along a stress pattern (or a given power transaction) on which at least one contingency, from a contingency list, would result in transient instability.
We note that the dynamic PTC should be smaller than the nose-point load margin of the base-case power system since the transient-stability-limit load margin is not defined when its value is greater than the nose-point load margin of the base-case power system. The task of computing the transient-stability-limit load margin with respect to a set of credible contingencies is rather challenging.
In this invention, we develop a methodology, termed the BCU-limiter, which can quickly and accurately compute the PTC limited by the transient stability of credible contingencies (i.e. the real-time dynamic PTC). This BCU-limiter computes, given a proposed power transaction, the amount of power transfers a power system can withstand before its transient stability limit is reached.
In addition, the BCU-limiter can rank a given list of contingencies, in terms of their load margins, to transient stability limits and compute the corresponding PTC. This BCU-limiter is an integration of the BCU methods, the BCU classifiers, the continuation power flow (CPFLOW) method and a time-domain simulation method.
Given an operating point, the BCU-limiter not only performs power system dynamic security assessments and ranking but also computes the PTC limited by the transient stability of credible contingencies.
The amount of required calculation is huge and the following requirements are important for computing transient stability constrained PTC under a list of contingencies.
This invention designs an effective search algorithm that enables one to fast determine real-time dynamic PTC. The operating points chosen from the P-V curves on which the transient stability analysis of a contingency list is to be performed has a huge influence on the efficiency of the overall computation engine. We next propose an energy-margin-based search method to select the next operating point between two known operating points on a P-V curve.
Bracketing and Bisection algorithms, secant algorithms, Ridder's algorithm etc. to identify the PTL subject to contingency i. Here, we illustrate the Ridder's algorithm to find the root of the following equation
W
i(λ)=0, with Wi(λ1)<0 and Wi(λ1)>0 and λε[λ0, λ1]
Another one-dimensional search method for implementing Step 4 of the above algorithm is the golden bisection method, which is an one dimensional search method used for finding the optimal solution of a real-valued unimodal function. A unimodal function F(x) has the property that there is an unique x* on a given interval [a,b] such that F(x*) is the only minimum of F(x) on the interval, and F(x) is strictly decreasing for x≦x* and strictly increasing for x≧x*. The significance of this property is that it enables us to refine an interval containing a solution by computing sample values of the solution within the interval and discarding portions of the interval according to the function values obtained.
We now describe a real-time methodology, termed BCU-limiter, to compute real-time dynamic PTC.
We note that the TEPCO-BCU method is the method described in the following patents, which are incorporated herein by reference:
The TEPCO-BCU engine is composed of two major functions:
The dynamic PTC can be expressed in several ways. It is sometimes useful to represent the dynamic PTC in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit operating point. The system-wide dynamic PTC is then mapped into each interface dynamic PTC.
The 65-generator system represents a subsystem of a major interconnected grid in the North America. This subsystem is composed of nine areas with 1135 buses and 2216 transmission lines. The base-case area interchange power flows are graphically displayed in
There are seven tie lines between area 1 and area 2 with interchange power flow of 1207.67 MW and −217.47 MVar from Area 1 and Area 2. One good of this study is to find the real power transfer limit (i.e. PTC) from area 1 to area 2 under the transient stability constraint with the following operating scenario:
Area 2 generators decreases from the base-case value 17030.79 MW to 12091 MW; uniformly among all the generators in Area while Area 1 generation uniformly increases from 19365.88 MW to 24400 MW to compensate the power deficit in Area 2. The transmission losses incurred from this power transfer from Area 1 to Area 2 are compensated by the Area slack buses in Area 1 and Area 2.
The system-wide dynamic PTC and the interface-flow dynamic PTC between Area 1 and Area 2 are to be computed. The interface-flow between Area 1 and Area 2 is defined as the sum of the power flows on the seven tie lines. The treatment of reactive power limits, real power generations due to participation factors, switchable capacitors and transformer tap adjustment are handled by the Continuation Power Flow. The contingency list contains fourteen contingencies related to the seven tie lines between Area 1 and Area 2. The faults are 3-phase balanced faults occurring at both end buses of the transmission line.
The P-V curve traced by Continuation Power Flow along the direction of power transfers between Area 1 and Area 2 reaches the corresponding nose point at which the real interface-flow is 3263 MW. While this nose point is often referred to as the maximum power transfer point or maximum loading point, it is evident that this maximum power transfer point is not a feasible operating point from the static viewpoints of voltage-limit, thermal-limit or the dynamic viewpoint of transient stability. In other words, the maximum power transfer point usually does not represent the static PTC or the dynamic PTC.
A dynamic PTC nomogram is a two-dimensional display of dynamic PTC in terms of two interface flows. Nomograms provide vital information for power system operators to operate power systems within power transmission dynamic security limits and with a ‘comfort zone’.
A nomogram always involves two interface paths. In computing a nomogram, we first need to associate one interface path with the X axis and the other interface path with the Y axis. Then we separate all source generators involved in the stress pattern into two groups. The source group that is responsible for the flow change in the X axis path is classified as group X, which is denoted as G1. The source group that is responsible for the power flow change in the Y axis path is classified as group Y, which is denoted as G2.
We compute the dynamic PTC nomogram in the following way. We at first create two independent base generation vectors bg1, bg2 for G1 and G2 respectively. Then, we create two independent coefficients for a1, a2 respectively. The overall generation vector considering both source groups will be the same as equation (6). By assigning at, a1, a2 different values, we can create a family of generation/load stress patterns, which spans the entire feasible generation/load stress space.
For each generation/load stress pattern, we will use the invented TEPCO-BCU-Limiter to compute the dynamic PTC (i.e. the boundary of the nomogram along the stress pattern). The invented solution algorithm to compute the dynamic PTC nomogram is as follows:
b
g
=a
1
b
g1
+a
g
b
g2 (6)
b
g
=a
1
b
g1
+a
2
b
g2 (6)
It is sometimes useful to represent the dynamic PTC nomogram in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit point. The system-wide dynamic PTC nomogram is then mapped into each interface dynamic PTC nomogram.
The real-time ATC is the difference between the real-time PTC and the current (i.e. real-time) power flow. To provide a real-time dynamic ATC (i.e. ATC subject to transient stability constraints), it is necessary to have some real-time information regarding a system's operating conditions.
This invention proposes to apply wide-area measurement system (WAMS) such as phasor measurement units (PMUs) installed at selected tie-lines and buses to obtain required real-time real power and reactive power information. The task of determining real-time dynamic ATC subject to dynamic security constraints is very challenging due to the nonlinear nature of interconnected power systems and the tremendous computation requirements of the transient stability analysis of credible contingencies.
Given an operating point (derived from a state estimator), a network topology, a set of pre-determined interfaces and a contingency list associated with each interface, we develop a PMU-assisted, real-time dynamic ATC determination system. There are four key components in the invented PMU-assisted, real-time dynamic ATC determination system:
The output of the PMU-assisted, real-time dynamic ATC determination system can be expressed as the one-dimensional dynamic PTC (see
The proposed architecture of the Real-time dynamic ATC nomogram (i.e. in Two-dimensional maps) is shown in
It should be pointed out that the solution methods of the invented system can also determine the top-ranked interface dynamic power transfer limit of each selected interface under the contingency list associated with each interface.
This real-time dynamic ATC determination system has the following features:
We now describe the invented real-time methodology to compute real-time PTC subject to static and dynamic security constraints, which is described as follows:
The static and dynamic PTC load margin can be expressed in several ways. It is sometimes useful to represent the static and dynamic PTC load margin in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit point. The system-wide static and dynamic PTC load margin is then mapped into each interface static and dynamic PTC load margin.
We compute the static and dynamic PTC nomogram in the following way. We at first create two independent base generation vectors) bg1, bg2 for G1 and G2 respectively. Then, we create two independent coefficients for a1, a2 respectively. The overall generation vector considering both source groups will be the same as equation (6), below. By assigning a1, a2 different values, we can create a family of generation/load stress patterns, which spans the entire feasible generation/load stress space.
For each generation/load stress pattern, we will use the invented TEPCO-BCU-Limiter to compute the static and dynamic PTC nomogram (i.e. the boundary of the nomogram along the stress pattern). We continue this procedure for a family of generation/load stress patterns to obtain the static and dynamic PTC nomogram. The invented solution algorithm to compute the static and dynamic PTC nomogram is as follows
b
g
=a
1
b
g1
+a
2
b
g2 (6)
b
g
=a
1
b
g1
+a
2
b
g2 (6)
The static and dynamic PTC nomogram can be expressed in several ways. It is sometimes useful to represent the static and dynamic PTC nomogram in terms of pre-contingency interface power flow (i.e. the base-case interface power flow) at the limit point. The system-wide static and dynamic PTC nomogram is then mapped into each interface static and dynamic PTC nomogram.
The task of determining real-time static and dynamic ATC is very challenging due to the nonlinear nature of interconnected power systems and the tremendous computation requirements of the line thermal limits, bus voltage limits, voltage stability constraints and transient stability constraints of credible contingencies. Given an operating point (derived from a state estimator), a network topology, a set of pre-determined interfaces and a contingency list associated with each interface, we develop a PMU-assisted, real-time static and dynamic ATC determination system.
The output of the PMU-assisted, real-time static and dynamic ATC determination system can be expressed as an one-dimensional meter (see
There are four key components in the invented PMU-assisted, real-time static and dynamic ATC determination system:
It should be pointed out that the solution methods of the invented system can also determine the top-ranked interface static and dynamic power transfer limit of each selected interface under the contingency list associated with each interface.
This real-time dynamic ATC determination system has the following features:
Accordingly, it is to be understood that the embodiments of the invention herein described are merely illustrative of the application of the principles of the invention. Reference herein to details of the illustrated embodiments is not intended to limit the scope of the claims, which themselves recite those features regarded as essential to the invention.
This application claims one or more inventions which were disclosed in Provisional Application No. 61/545,682, filed Oct. 11, 2011, entitled “Systems for Real-Time Available Transfer Capability Determination of Large Scale Power Systems”. The benefit under 35 USC §119(e) of the United States provisional application is hereby claimed, and the aforementioned application is hereby incorporated herein by reference.
Number | Date | Country | |
---|---|---|---|
61545682 | Oct 2011 | US |