The present disclosure relates to a tie rod for structural projects, which ensures protection of structures from wind and earthquake.
Up to now, the efforts of structural sciences were focused on antiseismic protection of buildings and their protection from the wind.
Efforts are focused on improvement of the ground, improvement of construction materials and improvement of concrete and iron under the American and German structural regulation. All these are good for structures but they lack a basic element. And that is that structures are not glued to the ground and therefore they can move during an earthquake, they can break and they can fall because of the wind. With the side forces applied by an earthquake or the wind the building is raised from the one side and tilts towards the other.
This means that the front sections of the building that are tilted cannot carry the weight of the back side of the building and support the whole weight. The result is that girders are caused to break and the building collapses. The other problem is that concrete that is used as the main structural material in the construction of frames cannot withstand the tension even though it withstands compression well.
Therefore, as the back side of the building is raised, strong tension and torque forces are formed which result in collapse. In frame buildings, torque depends on two other forces: tension and compression. During an earthquake, on multiple-story buildings the last slab, the middle one and the first one suffer different torque forces and forces in the shape of an ‘S’ are applied on the building, which are reverse and opposite to one another. There is a staged resonance increase of these forces and the building collapses.
This invention aims to the maximum and even zero minimization of these problems so that structures do not collapse.
According to the invention: this is achieved by applying a prestress force. Prestress is achieved by applying a tensioning force on the building performed from the top of the column to the ground. The tie rod for structural projects undertakes to apply this tensioning force on vertical support elements. Thus, we fix the whole building on the ground. In order to achieve this pull we must first drill holes at the main construction points, such as the bed plates of the frame.
Later we plunge the tie rod with the help of a steel cable connected to its end. By pulling the cable upwards, a mechanism opens the blades of the tie rod and therefore the one side is fixed to the ground. The other side we pass through a plastic pipe so that the cable does get not fixed when the concrete is poured.
When construction of the frame is finished, we connect the protruding cable to the tensioning bolt. As we turn the bolt a compression force is exerted towards the ground since the other end of the cable is fixed to the ground. The result is that the bed plates get fixed to the ground. In this way, during an earthquake or side wind forces the bed plates do not jump up or move. And thus, the reason they usually break is avoided. Second, the concrete tensioning strength is increased due to the compression applied on the column by the tie rod. And thus, the second reason that columns break is avoided. Third, if the construction has a single base, which is supported on rubber on individual bed plates and the help of the tie rod, then the building has a vertical micro-movement and at an axis equal to the ground surface with no change on the building's horizontal axis. Because the change in the shape of the straight line of the vertical and horizontal axis of the building and change of the vertical 90° relation of the two axis are responsible for the dual forces and tensions that cause buildings to collapse: and the construction relation above is decreased. The rubber between the single base and the individual bed plates contribute against shocks and absorb ground movement as well as the impact of columns on the ground.
Various objects, features, aspects and advantages of the present invention will become more apparent from the following detailed description of preferred embodiments of the invention, along with the accompanying drawings in which like numerals represent like components.
The word “exemplary” is used herein to mean “serving as an example, instance, or illustration.” Any embodiment described herein as “exemplary” is not necessarily to be construed as preferred or advantageous over other embodiments. It is to be understood that the terminology used herein is for purposes of describing particular embodiments only, and is not intended to be limiting. The defined terms are in addition to the technical and scientific meanings of the defined terms as commonly understood and accepted in the technical field of the present teachings.
As used in the specification and appended claims, the terms “a”, “an” and “the” include both singular and plural referents, unless the context clearly dictates otherwise. Thus, for example, “an apparatus” or “a device” includes one apparatus or device as well as plural apparatuses or devices.
The following description is intended to convey a thorough understanding of the embodiments described by providing a number of specific embodiments and details involving methods and systems for managing content submission and publication of content. It should be appreciated, however, that the present invention is not limited to these specific embodiments and details, which are exemplary only. It is further understood that one possessing ordinary skill in the art, in light of known systems and methods, would appreciate the use of the invention for its intended purposes and benefits in any number of alternative embodiments, depending upon specific design and other needs.
The invention is described below with the use of an example and reference to the attached designs:
Design 1 shows a 3-D rendition of the tie rod, its top and bottom part connected with a cable.
Design 2 shows the frame of a building with bed plates (13) and an elevator (11).
For the construction of a concrete frame with tie rods, we follow this procedure: we level the ground horizontally. We drill holes at the location of the columns to be constructed, right on the center of their placement on the existing construction, design 2. Drill holes must be perpendicular to the horizontal building axis. The depth of the holes must be ½ the building height. The diameter of the holes must be larger by ⅓ of the tie rod diameter (15). We plunge the tie rod (15) with the help of a cable (9) inside the hole. The tie rod and the cable size varies according to the size of the project. We repeat plunging of the other tie rods in the other locations and leave a length of cable protruding out of them.
In all cases, during pouring of concrete we pass the cable through a plastic pipe so that we can later pull it. We also pay attention that the plastic pipes are placed at the center of the column and are vertical before they are covered with the concrete. After the frame is constructed (10), we pull the cable (18) with the help of a bolt (3). As we pull, the blades of the tie rod (22) open and exert a force on the sides of the hole with the help of bars (11). These blades are equipped with pointed ends (13), design 1, for better grip on the ground. Since during an earthquake the ground creates a wave shaped impact, there is a danger that girders and slabs will break. This can be avoided in two ways. We construct the single base because during an earthquake the columns are maintained on the same horizontal or slightly slanted axis of the bed plates (design 2).
The second way is only one single base. But in this case, the tie rods are not placed on the columns but on the corners of the elevator (design 2) on locations (5), (6), (7) and (8) and pull on the elevator. It would be good if it is located in the center of the building. We pay attention to leave an elastic contraction joint (9) with enough tolerance so that the building can shake around it so as not to break but maintains its axis on a straight line.
Other points where the tie rod can be applied we find in design 3, where the pylons of a suspended cable bridge are fixed to the ground for antiseismic and wind protection reasons. In design 4, we see the wood construction of a home fixed to the ground for protection from tornado winds. Even if we suppose in design 4 that the structure is made of bricks and we place the tie rods in points (1), (2), (3), (4) and (5), we increase its seismic strength. The tie rods can also be used for shoring up loose ground with the help of an iron net.
The structural tie rod is comprised of a stainless steel member (17) which has eight stainless steel bars (11) which are connected to the member on the one end with a pin and on the other end the bars are connected to four blades located on the perimeter of the member (12), (13), (14), (10) in design 1. The exterior side of the blades is covered with pointed edges (13) which aid the blades to grip. The extension of the member is comprised of a steel cable (9) with a rubber jacket for protection from rust. This cable is fixed inside the member. Its length extends along the whole length of the hole drilled and along height of the whole building.
At its other end, it passes through the hole of a bolt (4), design 1, and comes out of the hole. The bolt (4) passes through a cast iron base plate (7) and moves vertically up-and-down on the base with the help of a threaded ring (5) with the same threading as the bolt and touches the top of the base plate (7). This threaded ring has four turning handles (6) for screwing. The bolt (4) has a base plate at its top (2) with a hole (1) so the steel cable can pass through it (9). The base plate has bolts along its perimeter at a different height in order to achieve fixing of the cable.
This base plate (2) ensures turning of the threaded ring (5) without turning of the cable (9) because it sits on the bolt (4) with and exterior ball bearing. As the threaded ring turns (5), the bolt (4) rises and as the cable is fixed, it rises with the resistance. As it rises, it pulls the member (17). Then, the bars open (11) around the member (17) forcing the blades against the sides of the hole.
Since the diameter of the opened tie rod is greater than the hole drilled, it presses the blades and the pointed edges, it grips and causes the cable to rise. Then, the whole system presses the structure towards the ground with the help of the cast iron base plate (7).
The previous description of the disclosed exemplary embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these exemplary embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Number | Date | Country | Kind |
---|---|---|---|
20080100105 | Feb 2008 | GR | national |
This application is a continuation of allowed, currently co-pending application Ser. No. 15/377,055 (Attorney Docket No. LYMBERIS001-US1C1), filed on Dec. 13, 2016, which is a continuation of U.S. Pat. No. 9,549,783, which was filed on May 14, 2012, and which was a National Stage Application of WO2009101454, filed on Feb. 5, 2009, and claims priority to Greek Patent Application 20080100105, filed on Feb. 14, 2008. All the applications herein mentioned are commonly owned and assigned to the Applicant of the present application.
Number | Date | Country | |
---|---|---|---|
Parent | 15377055 | Dec 2016 | US |
Child | 16125725 | US | |
Parent | 12866894 | May 2012 | US |
Child | 15377055 | US |